Monitoring system for pipe jacking under-pressure bin opening and tool changing

By designing a monitoring system for pipe jacking and opening the warehouse under pressure during pipe jacking construction, the toxic and harmful gases and pressure in the pressure warehouse are monitored in real time, and the dual network structure is used to ensure stable data transmission and solve the problem of unsafe construction environment. , realizing the safety monitoring of opening positions under pressure.

CN221840484UActive Publication Date: 2024-10-15SINOHYDRO BUREAU 5
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420504636.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-15
Publication Date
2024-10-15
Estimated Expiration
2034-03-15

AI Technical Summary

Technical Problem

During pipe jacking construction, it is difficult to ensure safety monitoring during pressure silo opening operations, especially under complex geological conditions. The content and pressure of toxic and harmful gases in the pressure silo cannot be effectively monitored, resulting in an unsafe construction environment.

Method used

Design a monitoring system, including gas content monitoring parts, pressure monitoring parts, microprocessors, communication modules and servers, by real-time monitoring of the gas content and pressure of oxygen, carbon dioxide, carbon monoxide, methane, and hydrogen sulfide in the pressure chamber, and utilize The dual network structure of zigbee and 4G networks ensures the stability of data transmission and provides a safe construction environment.

Benefits of technology

It achieves real-time and accurate monitoring of the content and pressure of toxic and harmful gases in the pressure chamber, provides a safe construction environment for construction workers, reduces the data loss rate, and ensures the safety of opening the chamber and changing tools under pressure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221840484U_ABST
    Figure CN221840484U_ABST
Patent Text Reader

Abstract

The utility model discloses a monitoring system for pipe jacking under-pressure bin opening and tool changing, and belongs to the technical field of pipe jacking construction. The system comprises a gas pressure bin, a gas content monitoring piece, a pressure monitoring piece, a microprocessor, a communication module and a server, the gas content monitoring part, the pressure monitoring part and the communication module are respectively connected with the microprocessor, and the microprocessor is connected with the server through the communication module. According to the monitoring system for pipe jacking under-pressure bin opening and tool changing, the content of poisonous and harmful gas in the air pressure bin is monitored in real time through the gas content monitoring part, the pressure index in the air pressure bin is monitored in real time through the pressure detection part, and the content and pressure of the poisonous and harmful gas are accurately monitored in real time; a safe construction environment is provided for constructors, and under-pressure bin opening and tool changing are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of pipe jacking construction, in particular to a monitoring system for opening and changing cutters of pipe jacking under pressure. Background Art

[0002] The buried depth of the jacking section is 15.7m to 17.50m. The jacking pipe is generally pushed in the strong weathering layer of mud gravel and bedrock, and the weak weathering layer is partially. The rock layer is soft and hard, and there is a soft top and a hard bottom. It is easy to deviate when pushing at the interface. There may be isolated rocks in the mud gravel layer. It is recommended that the designer consider the ability to handle isolated rocks when selecting jacking equipment.

[0003] When encountering moderately weathered, strongly weathered, mud gravel, and granite strata, the saturated compressive strength of tuff is 67MPa~98.7MPa, and the saturated compressive strength of granite is 35MPa~51MPa. The upper part is soft and the lower part is hard. The actual soil conditions are more complicated than those shown in geological survey data, and geological mutations occur every few meters.

[0004] According to the geological conditions of the section, the tool inspection is carried out once every 200m of composite special soil layer and 100m of rock soil layer, and the "normal pressure tool change" method is preferred. However, when the formation conditions are poor, the face is unstable, and it is impossible to handle under normal pressure conditions, the gas pressure method is used to open the warehouse (pressure opening operation). How to ensure the safety of pressure opening requires monitoring during the opening and tool change operation, which has become a new problem to be solved. Utility Model Content

[0005] The utility model aims to provide a monitoring system for opening and changing cutters of a jacking pipe under pressure, so as to solve the problem of maintaining safety monitoring in the existing opening operation under pressure.

[0006] The technical solution of the utility model to solve the above technical problems is as follows:

[0007] A monitoring system for opening and changing tools for pipe jacking under pressure, comprising: a pressure chamber, a gas content monitoring component, a pressure monitoring component, a microprocessor, a communication module and a server;

[0008] The gas content monitoring component, the pressure monitoring component and the communication module are respectively connected to the microprocessor, and the microprocessor is connected to the server via the communication module;

[0009] The gas content monitoring component is arranged at the port of the air pressure chamber, and is used to monitor the gas content of oxygen, carbon dioxide, carbon monoxide, methane and hydrogen sulfide in the air pressure chamber;

[0010] The pressure detection component is arranged on the outer wall surface of the air pressure chamber, and the pressure detection component is used to detect the pressure inside the air pressure chamber.

[0011] Furthermore, in the monitoring system for opening the warehouse and changing the tool under pressure during pipe jacking, the gas content monitoring component is a multi-gas detector.

[0012] Furthermore, in the monitoring system for opening the chamber and changing tools during pipe jacking under pressure, the monitoring system also includes a camera, which is arranged at the chamber opening of the pneumatic chamber, and is connected to the microprocessor, and is used to monitor and record the tool changing operation in real time.

[0013] Furthermore, in the monitoring system for opening and changing tools under pressure during pipe jacking, the communication module includes a zigbee node module and a 4G communication module, and the zigbee node module and the 4G communication module are respectively connected to the microprocessor.

[0014] Furthermore, in the monitoring system for opening and changing tools under pressure during pipe jacking, the monitoring system also includes a local host and a zigbee coordinator, the microprocessor is connected to the zigbee coordinator through the zigbee node module, the zigbee coordinator is connected to the local host, the local host is arranged in a monitoring room, and the local host is connected to the server through Ethernet communication.

[0015] Furthermore, in the monitoring system for opening the chamber and changing the tool under pressure during pipe jacking, the pneumatic chamber (10) comprises: a main chamber and an auxiliary chamber, and the main chamber and the auxiliary chamber are connected.

[0016] Furthermore, in the monitoring system for opening the chamber and changing the tool during pipe jacking under pressure, the volume of the main chamber is 1.5-2.5 times that of the auxiliary chamber.

[0017] Furthermore, in the monitoring system for opening the chamber and changing the tool during pipe jacking under pressure, both the main chamber and the auxiliary chamber are provided with doors.

[0018] Furthermore, in the monitoring system for opening the warehouse and changing tools under pressure during jacking, a pressurizing pipeline and a decompressing pipeline are connected to the outside of the pneumatic warehouse, and safety solenoid valves are provided on both the pressurizing pipeline and the decompressing pipeline, and the safety solenoid valves are connected to the communication module.

[0019] Furthermore, in the monitoring system for opening the chamber and changing the tool during pipe jacking under pressure, a manhole cabin is provided outside the air pressure chamber.

[0020] The utility model has the following beneficial effects:

[0021] The utility model provides a monitoring system for opening and changing cutters under pressure for pipe jacking. It monitors the toxic and harmful gas content in the pressure chamber in real time through a gas content monitoring component, and monitors the pressure index in the pressure chamber in real time through a pressure detection component, thereby achieving real-time and accurate monitoring of the toxic and harmful gas content and pressure, providing a safe construction environment for construction personnel, and achieving opening and changing cutters under pressure.

[0022] The monitoring system for opening and changing cutters under pressure in pipe jacking provided by the utility model effectively ensures the stability of data transmission and reduces the data loss rate through the dual network structure of zigbee and 4G network. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] The drawings described herein are used to provide a further understanding of the embodiments of the present utility model, constitute a part of this application, and do not constitute a limitation of the embodiments of the present utility model. In the drawings:

[0024] Figure 1 It is a structural explosion diagram of the monitoring system for opening and changing cutters under pressure for pipe jacking according to the utility model;

[0025] Figure 2 It is a structural schematic diagram of the air pressure chamber in the monitoring system for opening the chamber and changing the tool under pressure for jacking pipes according to the utility model;

[0026] Marks and corresponding parts names in the attached drawings:

[0027] In the figure: 10-pressure chamber, 101-main cabin, 102-auxiliary cabin, 103-manhole cabin, 11-gas content monitoring component, 12-pressure monitoring component. DETAILED DESCRIPTION

[0028] This section will describe in detail the specific embodiments of the utility model. The preferred embodiments of the utility model are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the utility model, but it cannot be understood as a limitation on the protection scope of the utility model.

[0029] In the description of the present invention, it should be understood that descriptions involving orientation, such as up, down, front, back, left, right, etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0030] In the description of the present utility model, "several" means one or more, "more" means more than two, "greater than", "less than", "exceed" etc. are understood to exclude the number itself, and "above", "below", "within" etc. are understood to include the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.

[0031] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.

[0032] Example

[0033] Please refer to Figure 1 and 2 The embodiment of the utility model provides a monitoring system for opening and changing tools of a jacking pipe under pressure, including: a gas pressure chamber 10, a gas content monitoring component 11, a pressure monitoring component 12, a microprocessor, a communication module and a server;

[0034] The gas content monitoring component, the pressure monitoring component and the communication module are respectively connected to the microprocessor, and the microprocessor is connected to the server via the communication module;

[0035] The gas content monitoring component is arranged at the port of the air pressure chamber, and is used to monitor the gas content of oxygen, carbon dioxide, carbon monoxide, methane and hydrogen sulfide in the air pressure chamber;

[0036] The pressure detection component is arranged on the outer wall surface of the air pressure chamber, and the pressure detection component is used to detect the pressure inside the air pressure chamber.

[0037] The working principle of the pressurized opening and cutting tool change is: when the ground cannot be reinforced by grouting, the ground water inflow is large and does not meet the precipitation conditions or the precipitation is not ideal, the air compressor is used to pressurize the air and inject it into the soil bin, and the water and soil pressure in front of the cutter disc is balanced by establishing a reasonable air pressure in the soil bin to prevent groundwater infiltration and collapse of the excavation surface. Under air pressure conditions, construction personnel enter the soil bin to safely carry out inspections, maintenance and tool replacement.

[0038] The utility model provides a monitoring system for pipe jacking under pressure to open the warehouse and change the cutter. It monitors the toxic and harmful gas content in the pressure warehouse in real time through a gas content monitoring component, and monitors the pressure index in the pressure warehouse in real time through a pressure detection component, thereby realizing real-time and accurate monitoring of the toxic and harmful gas content and pressure, providing a safe construction environment for construction personnel, and realizing pressure opening under pressure.

[0039] In some feasible solutions, the gas content monitoring device is a multi-gas detector. The multi-gas detector can realize the simultaneous detection of the gas contents of oxygen, carbon dioxide, carbon monoxide, methane and hydrogen sulfide in the pressure chamber.

[0040] In some feasible solutions, the monitoring system further includes a camera 13, which is arranged at the port of the air pressure chamber, connected to the microprocessor, and used to monitor and record the tool changing operation in real time. In order to observe the working conditions in the air pressure chamber more clearly, a camera is also arranged to monitor and record the tool changing operation in real time.

[0041] In some feasible solutions, the communication module includes a zigbee node module and a 4G communication module, and the zigbee node module and the 4G communication module are respectively connected to the microprocessor. When the 4G network cannot be connected, the microprocessor can send data to the local host for storage through the zigbee network, and the local host can upload it to the server. The dual network setting effectively reduces the risk of data loss due to network problems.

[0042] In some feasible schemes, the monitoring system also includes a local host and a zigbee coordinator, the microprocessor is connected to the zigbee coordinator through the zigbee node module, the zigbee coordinator is connected to the local host, the local host is set in the monitoring room, and the local host is connected to the server via Ethernet communication.

[0043] In some feasible solutions, the air pressure chamber includes: a main chamber 101 and an auxiliary chamber 102, and the main chamber and the auxiliary chamber are connected. The auxiliary chamber is reserved for backup, and when a special situation occurs in the main chamber, the construction workers can run to the auxiliary chamber for temporary stay.

[0044] In some feasible solutions, the volume of the main cabin is 1.5-2.5 times that of the auxiliary cabin. The area of ​​the auxiliary cabin is slightly smaller than that of the main cabin.

[0045] In some feasible solutions, the main cabin and the auxiliary cabin are both provided with cabin doors. Each cabin has an independent cabin door, which is independent of each other.

[0046] In some feasible solutions, the pressure chamber is connected to the outside with a pressurizing pipeline and a decompression pipeline, and both the pressurizing pipeline and the decompression pipeline are provided with a safety solenoid valve, which is connected to the communication module. The pressurizing pipeline is connected to an air compressor for pressurizing the pressure chamber, and the decompression pipeline is connected to the atmosphere for decompressing the pressure chamber, and the pipeline is connected or closed through the safety solenoid valve via the communication module.

[0047] In some feasible solutions, a manhole cabin 103 is provided outside the air pressure chamber. The manhole cabin can also be used to observe the guide change operation in the air pressure chamber.

[0048] In a pipe jacking project, the air pressure chamber has a length of 2.8m and a diameter of 1.632m. The structure is a double-cabin structure with a main cabin volume of 3.1m 3 , auxiliary cabin volume 1.8m 3 ; Full occupancy: 2 persons in the main cabin and 1 person in the auxiliary cabin; Design pressure 5.5 bar, total weight 5.17 KG, maximum working pressure 5 bar, 2 cabin doors, size φ600.

[0049] The specific implementation methods described above further illustrate the purpose, technical solutions and beneficial effects of the utility model in detail. It should be understood that the above description is only the specific implementation method of the utility model and is not used to limit the protection scope of the utility model. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the utility model should be included in the protection scope of the utility model.

Claims

1. A monitoring system for opening and changing cutters during pipe jacking. It is characterized in that include: A gas pressure chamber (10), a gas content monitoring component, a pressure monitoring component, a microprocessor, a communication module and a server; The gas content monitoring component, the pressure monitoring component and the communication module are respectively connected to the microprocessor, and the microprocessor is connected to the server via the communication module; The gas content monitoring component is arranged at the port of the air pressure chamber, and is used to monitor the gas content of oxygen, carbon dioxide, carbon monoxide, methane and hydrogen sulfide in the air pressure chamber; The pressure monitoring component is arranged on the outer wall surface of the air pressure chamber, and the pressure monitoring component is used to detect the pressure inside the air pressure chamber.

2. The monitoring system for opening and changing tools during pipe jacking under pressure according to claim 1, It is characterized in that The gas content monitoring component is a multi-gas detector.

3. The monitoring system for opening and changing tools during pipe jacking under pressure according to claim 1, It is characterized in that The monitoring system also includes a camera, which is arranged at the port of the air pressure chamber, and is connected to the microprocessor. The camera is used to monitor and record the tool changing operation in real time.

4. The monitoring system for opening and changing tools during pipe jacking under pressure according to claim 1, It is characterized in that The communication module includes a zigbee node module and a 4G communication module, and the zigbee node module and the 4G communication module are respectively connected to the microprocessor.

5. The monitoring system for opening and changing tools during pipe jacking under pressure according to claim 4, It is characterized in that The monitoring system also includes a local host and a zigbee coordinator. The microprocessor is connected to the zigbee coordinator through the zigbee node module. The zigbee coordinator is connected to the local host. The local host is arranged in a monitoring room. The local host is connected to the server through Ethernet communication.

6. The monitoring system for opening and changing tools during pipe jacking under pressure according to claim 1, It is characterized in that The air pressure chamber comprises a main chamber and an auxiliary chamber, and the main chamber and the auxiliary chamber are connected.

7. The monitoring system for opening and changing tools during pipe jacking under pressure according to claim 6, It is characterized in that The volume of the main compartment is 1.5-2.5 times that of the auxiliary compartment.

8. The monitoring system for opening and changing tools during pipe jacking under pressure according to claim 6, It is characterized in that The main cabin and the auxiliary cabin are both provided with cabin doors.

9. The monitoring system for opening and changing tools during pipe jacking under pressure according to claim 1, It is characterized in that A pressurizing pipeline and a decompressing pipeline are connected to the outside of the air pressure chamber. Safety solenoid valves are arranged on both the pressurizing pipeline and the decompressing pipeline. The safety solenoid valves are connected to the communication module.

10. The monitoring system for opening and changing tools during pipe jacking under pressure according to claim 4, It is characterized in that A manhole cabin is arranged outside the air pressure chamber.