Workshop high formwork top connecting piece

By designing a shock-absorbing mechanism and a ferrule structure in the top connector of the high-support formwork, the problems of insufficient structural stability and poor seismic performance of traditional connectors are solved, and higher stability and seismic resistance are achieved.

CN221856195UActive Publication Date: 2024-10-18MCC NORTHEAST CONSTR SHENYANG ENGTECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323554583.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-26
Publication Date
2024-10-18
Estimated Expiration
2033-12-26

Smart Images

  • Figure CN221856195U_ABST
    Figure CN221856195U_ABST
Patent Text Reader

Abstract

The utility model relates to a factory building high formwork top connecting piece which comprises a first steel frame and a second steel frame arranged on the outer surface of the first steel frame, a damping mechanism is fixedly installed between the first steel frame and the second steel frame, a clamping sleeve is fixedly installed on the outer surface of the first steel frame and the outer surface of the second steel frame through bolts, and the clamping sleeve comprises a plate piece and a T-shaped sleeve piece. And a fixed triangular plate is welded and fixed between the plate piece and the T-shaped sleeve piece. The clamping sleeves are fixedly mounted on the outer surfaces of the first steel frame and the second steel frame through bolts, and the fixed triangular plates are welded and fixed between the plate pieces and the T-shaped sleeve pieces, so that the strength of the clamping sleeves is improved, and the top connecting piece of the factory building high formwork is more stable; through the damping mechanism fixedly installed between the first steel frame and the second steel frame, vibration of the second steel frame is buffered through the damping mechanism when the top connecting piece of the plant high formwork is connected, and the pressure borne by the top connecting piece of the plant high formwork is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of high-support formwork top connecting pieces, in particular to a high-support formwork top connecting piece for a factory building. Background Art

[0002] High formwork is a general term for the erection of steel pipes and formwork construction with a height of 5 meters or more in large-scale frame structures. The top connectors of traditional steel structure factory high formwork are completely fixed by high-strength bolts. Although it can improve the overall stability of the structure, the high-strength bolts have to withstand very high strength and require high stiffness. At the same time, in the existing factory high formwork top connectors, not only is the erection process complicated and labor-intensive, but the high formwork system of this structural form is also insufficiently stable, has weak bearing capacity, and has poor anti-seismic and energy-absorbing effects. In the event of an earthquake, the connectors cannot deform well in response to vibration, which can easily cause damage to the connectors. Summary of the invention

[0003] In view of the deficiencies in the prior art, the utility model provides a top connector for a high formwork of a factory building. The specific technical scheme is as follows: it comprises a first steel frame and a second steel frame is arranged on the outer surface of the first steel frame, a shock absorbing mechanism is fixedly installed between the first steel frame and the second steel frame, a clamping sleeve is fixedly installed on the outer surfaces of the first steel frame and the second steel frame by bolts, the clamping sleeve comprises a plate and a T-shaped kit, the plate and the T-shaped kit are integrally formed, the plate is fixed to the outer surface of the first steel frame by bolts, the T-shaped kit is fixedly sleeved on the outer surface of the second steel frame by bolts, and a fixed triangle plate is welded and fixed between the plate and the T-shaped kit.

[0004] Preferably, the lifting and shock absorbing mechanism includes a first damper and a first spring sleeved on the telescopic end of the first damper, the telescopic end of the first damper is fixed with a sleeve by a screw, the sleeve is rotatably connected to the first steel frame by a first hinge, and the lower end of the first damper is rotatably connected to the second steel frame by a second hinge.

[0005] Preferably, the supporting shock absorbing mechanism comprises a tripod fixed to the side surface of the first steel frame by bolts, a second damper is fixed between the tripod and the second steel frame, and a second spring is sleeved on the telescopic end of the second damper.

[0006] Preferably, two groups of shock absorbing mechanisms are provided, and the two groups of shock absorbing mechanisms are symmetrical about the first steel frame.

[0007] Beneficial effects of the utility model:

[0008] 1. The strength of the clamp is increased by fixing the clamp with bolts on the outer surfaces of the first steel frame and the second steel frame, and the fixing triangle is welded and fixed between the plate and the T-shaped kit. At the same time, the plate is fixed to the outer surface of the first steel frame by bolts, and the T-shaped kit is fixedly sleeved on the outer surface of the second steel frame by bolts, so that the top connector of the high formwork of the factory building is more stable; the shock-absorbing mechanism is fixedly installed between the first steel frame and the second steel frame, so that the top connector of the high formwork of the factory building can buffer the vibration of the second steel frame through the shock-absorbing mechanism when connected, slow down the elastic deformation of the connection between the first steel frame and the second steel frame, and reduce the pressure on the top connector of the high formwork of the factory building.

[0009] 2. Through the lifting and shock-absorbing mechanism fixedly installed between the first steel frame and the second steel frame, the second steel frame is lifted and shock-absorbing, so that the top connecting parts of the factory high formwork are subjected to the lifting force while being connected, and through the supporting and shock-absorbing mechanism fixedly installed between the first steel frame and the second steel frame, the second steel frame is supported and shock-absorbing. Through the supporting and shock-absorbing mechanism fixedly installed between the first steel frame and the second steel frame, the structural seismic resistance and the ability to resist collapse of the top connecting parts of the factory high formwork are enhanced. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] Figure 1 It is a three-dimensional right-side structural schematic diagram of the utility model;

[0011] Figure 2 It is a three-dimensional left-side structural schematic diagram of the utility model;

[0012] Figure 3 It is a schematic diagram of the ferrule structure in the utility model.

[0013] In the figure: 1, first steel frame; 2, first damper; 3, first hinge; 4, screw; 5, sleeve; 6, first spring; 7, ferrule; 71, plate 72, T-shaped kit 8, fixed triangle plate; 9, second hinge; 10, second steel frame; 11, second spring; 12, second damper; 13, tripod. DETAILED DESCRIPTION

[0014] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the utility model and are not used to limit the utility model.

[0015] like Figure 1-3The utility model provides a technical solution: a top connector of a high formwork for a factory building, comprising a first steel frame 1 and a second steel frame 10 provided on the outer surface of the first steel frame 1, a shock absorbing mechanism is fixedly installed between the first steel frame 1 and the second steel frame 10, and a clamping sleeve 7 is fixedly installed on the outer surfaces of the first steel frame 1 and the second steel frame 10 by bolts, the clamping sleeve 7 comprises a plate 71 and a T-shaped kit 72, the plate 71 and the T-shaped kit 72 are integrally formed, the plate 71 is fixed to the outer surface of the first steel frame 1 by bolts, the T-shaped kit 72 is fixedly sleeved on the outer surface of the second steel frame 10 by bolts, and a fixed triangle plate 8 is welded and fixed between the plate 71 and the T-shaped kit 72. In this embodiment, the strength of the sleeve 7 is increased by fixing the outer surfaces of the first steel frame 1 and the second steel frame 10 with bolts, and the fixed triangle plate 8 is welded and fixed between the plate 71 and the T-shaped kit 72. At the same time, the plate 71 is fixed to the outer surface of the first steel frame 1 by bolts, and the T-shaped kit 72 is fixedly sleeved on the outer surface of the second steel frame 10 by bolts, so that the top connector of the factory high formwork is more stable; through the shock-absorbing mechanism fixedly installed between the first steel frame 1 and the second steel frame 10, the top connector of the factory high formwork can buffer the vibration of the second steel frame 10 through the shock-absorbing mechanism when connected, so as to reduce the elastic deformation at the connection between the first steel frame 1 and the second steel frame 10, so that the pressure on the top connector of the factory high formwork is reduced.

[0016] Specifically, the shock absorbing mechanism includes a lifting shock absorbing mechanism and a supporting shock absorbing mechanism installed between the first steel frame 1 and the second steel frame 10. In this embodiment, the second steel frame 10 is lifted and damped by the lifting shock absorbing mechanism fixedly installed between the first steel frame 1 and the second steel frame 10, so that the top connecting piece of the high formwork of the factory building is subjected to a lifting force while being connected, and the second steel frame 10 is supported and damped by the supporting shock absorbing mechanism fixedly installed between the first steel frame 1 and the second steel frame 10. By means of the supporting shock absorbing mechanism fixedly installed between the first steel frame 1 and the second steel frame 10, the structural earthquake resistance and the ability to resist collapse of the top connecting piece of the high formwork of the factory building are enhanced.

[0017] Specifically, the lifting and shock absorbing mechanism includes a first damper 2 and a first spring 6 sleeved on the telescopic end of the first damper 2. The telescopic end of the first damper 2 is fixed with a sleeve 5 by a screw 4. The sleeve 5 is rotatably connected to the first steel frame 1 by a first hinge 3. The lower end of the first damper 2 is rotatably connected to the second steel frame 10 by a second hinge 9.

[0018] Specifically, the supporting shock absorbing mechanism includes a tripod 13 fixed to the side surface of the first steel frame 1 by bolts, a second damper 12 is fixed between the tripod 13 and the second steel frame 10, and a second spring 11 is sleeved on the telescopic end of the second damper 12.

[0019] Specifically, two groups of shock absorbing mechanisms are provided, and the two groups of shock absorbing mechanisms are symmetrical about the first steel frame 1 .

[0020] The working principle and use process of this utility model:

[0021] When in use, the clamping sleeve 7 is fixedly installed on the outer surface of the first steel frame 1 and the second steel frame 10 by bolts, at this time, the plate 71 is fixed to the outer surface of the first steel frame 1 by bolts, the T-shaped set 72 is sleeved on the outer surface of the second steel frame 10 and then fixed by bolts, and the triangular plate 8 is welded and fixed between the plate 71 and the T-shaped set 72; the lifting and pulling shock absorbing mechanism is installed between the first steel frame 1 and the second steel frame 10, the first spring 6 is sleeved on the telescopic end of the first damper 2, the telescopic end of the first damper 2 is fixed with the sleeve 5 by the screw 4, and the sleeve 5 is fixed by the first hinge The chain 3 is rotatably connected to the first steel frame 1, the lower end of the first damper 2 is rotatably connected to the second steel frame 10 via the second hinge 9, a shock absorbing mechanism is fixedly installed between the first steel frame 1 and the second steel frame 10, a tripod 13 is fixed to the side surface of the first steel frame 1 by bolts, a second damper 12 is fixed between the tripod 13 and the second steel frame 10, a telescopic end of the second damper 12 is sleeved with a second spring 11, and when the second steel frame 10 vibrates, the first damper 2 and the second damper 12 cooperate to reduce shock and are also used for resetting.

[0022] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A top connector for a high formwork for a factory building, characterized in that: The invention comprises a first steel frame (1) and a second steel frame (10) arranged on the outer surface of the first steel frame, a shock absorbing mechanism is fixedly installed between the first steel frame (1) and the second steel frame (10), a clamping sleeve (7) is fixedly installed on the outer surfaces of the first steel frame (1) and the second steel frame (10) by bolts, the clamping sleeve (7) comprises a plate (71) and a T-shaped set (72), the plate (71) and the T-shaped set (72) are integrally formed, the plate (71) is fixed to the outer surface of the first steel frame (1) by bolts, the T-shaped set (72) is fixedly sleeved on the outer surface of the second steel frame (10) by bolts, and a fixed triangle plate is welded and fixed between the plate (71) and the T-shaped set (72).

2. A top connector for a high formwork for a factory building according to claim 1, characterized in that: The shock absorbing mechanism comprises a first damper (2) and a first spring (6) sleeved on the telescopic end of the first damper (2); the telescopic end of the first damper (2) is fixed with a sleeve (5) by a screw (4); the sleeve (5) is rotatably connected to the first steel frame (1) by a first hinge (3); and the lower end of the first damper (2) is rotatably connected to the second steel frame (10) by a second hinge (9).

3. The top connector of a high formwork for a factory building according to claim 1, characterized in that: The shock absorbing mechanism comprises a tripod (13) fixed to the side surface of a first steel frame (1) by bolts, a second damper (12) is fixed between the tripod (13) and the second steel frame (10), and a second spring (11) is sleeved at the telescopic end of the second damper (12).

4. The top connector of a high formwork for a factory building according to claim 1, characterized in that: The shock absorbing mechanisms are provided in two groups, and the two groups of shock absorbing mechanisms are symmetrical with respect to the first steel frame (1).