Staggered construction structure of parallel master-slave double-hole tunnel penetrating through water-rich section

By setting up the first support structure and the second support structure during tunnel construction, the connection between the main tunnel and the auxiliary tunnel is realized, the problem that the auxiliary tunnel cannot be used as a passage is solved, the construction efficiency and safety are improved, and the main tunnel can be used for multiple tasks construction at the same time.

CN221856728UActive Publication Date: 2024-10-18CHINA ROAD & BRIDGE
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420064007.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-11
Publication Date
2024-10-18
Estimated Expiration
2034-01-11

AI Technical Summary

Technical Problem

During tunnel construction, when the main tunnel and the auxiliary tunnel are constructed in parallel, the auxiliary tunnel cannot be used as a passage for machinery, personnel, ventilation, etc., and the working surface of the main tunnel cannot be increased. The construction technology is complex and the accuracy is difficult to control.

Method used

Design a staggered construction structure of parallel master-slave double-tunnels through water-rich areas. By setting up a first support structure and a second support structure in the main tunnel, the tunnel part and the main tunnel part are connected, and the second support structure is used as machinery and personnel. , ventilation channels, increase the working surface of the main tunnel, and improve the construction safety factor.

Benefits of technology

The function of the auxiliary tunnel as a mechanical, personnel and ventilation channel is realized, the working surface of the main tunnel is increased, the construction process is simplified, and the construction efficiency and safety are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221856728U_ABST
    Figure CN221856728U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of tunnel construction structures, in particular to a water-rich-section-crossing parallel master-slave double-hole tunnel staggered construction structure which comprises a first supporting structure located in a main tunnel part, and the first supporting structure is used for supporting the top, close to a communicating tunnel part, of the main tunnel part; the second supporting structure is used for supporting the top, close to the main tunnel part, of the communicating tunnel part; the end, close to the communicating tunnel part, of the first supporting structure is erected on the top of the second supporting structure. The tunnel can be used as a tunnel of a mechanical channel, a personnel channel, a ventilation channel and the like so as to increase the working face of the main tunnel part and achieve simultaneous construction of multiple working faces of the main tunnel part, the construction efficiency is improved, installation is convenient, the safety coefficient in the construction process is increased, and the far-reaching social value is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of tunnel construction structures, in particular to a staggered construction structure of parallel main-slave double-hole tunnels that cross a water-rich area. Background Art

[0002] During the construction and operation of tunnels, some longer highway tunnels often design auxiliary tunnels next to the main tunnel to achieve multiple purposes such as providing geological forecasts, slag discharge channels, material transportation, ventilation and maintenance for the main tunnel. However, the distance between the auxiliary tunnel and the main tunnel is small, and the parallel construction of the main tunnel and the auxiliary tunnel may affect each other. At the same time, the construction process of the connecting cross tunnel between the main and auxiliary tunnels is complex and the accuracy is difficult to control.

[0003] Chinese patent authorization announcement number: CN 218493607 U discloses a support structure for a small-clearance double-hole tunnel passing through a water-rich broken zone, including an advance support structure composed of multiple advance small pipes, a primary support layer, multiple grouting anchors, multiple tension anchors, a surface grouting layer and a secondary lining layer; the multiple advance small pipes and grouting anchors are all arranged in holes on the tunnel vault, the primary support layer and the secondary lining layer are placed on the tunnel body, and the primary support layer is between the secondary lining layer and the rock surface of the tunnel body; the surface grouting layer is parallel to the tunnel excavation surface, and multiple tension anchors are horizontally arranged in the middle rock column between the leading tunnel and the following tunnel.

[0004] In the double-tunnel structure with small clearance, the support structure is divided into a leading tunnel and a trailing tunnel. The leading tunnel represents the tunnel that is excavated first in the double-tunnel structure with small clearance, and the trailing tunnel represents the tunnel that is excavated later in the double-tunnel structure with small clearance. The support structure exists in both the leading tunnel and the trailing tunnel, and includes: surface grouting layer, advance support structure, primary support layer and secondary lining layer.

[0005] However, there is an intermediate rock pillar between the advance tunnel and the subsequent tunnel in the support structure, which are not connected. Moreover, the subsequent tunnel is constructed after the construction of the advance tunnel is completed. The advance tunnel cannot be used as a tunnel for machinery, personnel, ventilation, etc. of the subsequent tunnel, and the working surface of the subsequent tunnel cannot be increased. Utility Model Content

[0006] In response to the above-mentioned problems, the utility model aims to provide a staggered construction structure of parallel main and slave double-hole tunnels that crosses water-rich areas. The auxiliary tunnels and connecting tunnels can be used as passages for machinery, personnel, ventilation, etc., so as to increase the working surface of the main tunnel and realize simultaneous construction of multiple working surfaces of the main tunnel, which has far-reaching social value.

[0007] The main idea of ​​the technical solution adopted by the utility model is: a connecting tunnel part and an auxiliary tunnel part including a second supporting structure for connecting the main tunnel part and the auxiliary tunnel part, which can be used as a tunnel for passages for machinery, personnel, ventilation, etc., so as to increase the working surface of the main tunnel part and realize simultaneous construction of multiple working surfaces of the main tunnel part; the second supporting structure at which the connecting tunnel part intersects with the main tunnel part and the first supporting structure located in the main tunnel part increase the safety factor of the construction process.

[0008] In order to achieve the above purpose, the technical solution adopted by the utility model is as follows:

[0009] A staggered construction structure of parallel main and slave double tunnels crossing water-rich areas.

[0010] It includes: a first support structure located in the main tunnel portion, the first support structure is used to support the top of the main tunnel portion close to the connecting tunnel portion;

[0011] A second supporting structure at the intersection of the connecting tunnel portion and the main tunnel portion, wherein the second supporting structure is used to support the top of the connecting tunnel portion close to the main tunnel portion;

[0012] One end of the first supporting structure close to the connecting tunnel portion is mounted on the top of the second supporting structure.

[0013] As a preferred technical solution of the present utility model, the second supporting structure includes a first supporting beam assembly, a transverse hole arch frame and a second supporting column assembly, the second supporting column assembly is symmetrically installed on the left and right sides of the transverse hole arch frame, and the first supporting beam assembly is installed on the top of the second supporting column assembly.

[0014] As a preferred technical solution of the present utility model, the second support column assembly includes at least E group support columns and F group support columns, the first joist assembly includes at least G group joists and H group joists, the G group joists are installed on the E group support columns, and the H group joists are installed on the F group support columns.

[0015] As a preferred technical solution of the utility model, the first supporting structure includes a cross beam, a cantilevered arch frame, a first supporting column assembly, a third supporting column assembly and a temporary scaffolding, the cantilevered arch frame is connected to the first supporting beam assembly, the cross beam is installed at the top of the first supporting column assembly for connecting the temporary scaffolding, and the third supporting column assembly is used to support the temporary scaffolding.

[0016] As a preferred technical solution of the above scheme, the first support beam assembly is provided with a slot, and a protrusion matching the slot is provided at the connection between the cantilever arch frame and the first support beam assembly.

[0017] The beneficial effect of the utility model is that compared with the prior art, the improvement of the utility model lies in that, by setting the first supporting structure and the second supporting structure, installation is convenient, the safety factor of the construction process is increased, and the auxiliary tunnel part, including the tunnel part connected with the second supporting structure, can be used as a tunnel for machinery, personnel, ventilation and other passages, so as to increase the working surface of the main tunnel part, realize the simultaneous construction of multiple working surfaces of the main tunnel part, and improve the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the plan layout of the connecting tunnel part of the auxiliary tunnel part entering the main tunnel part of the utility model;

[0019] Figure 2 It is a cross-sectional schematic diagram of 1-1 of the utility model;

[0020] Figure 3 It is a cross-sectional schematic diagram of 2-2 of the utility model;

[0021] Figure 4 It is a cross-sectional schematic diagram of 3-3 of the utility model;

[0022] Figure 5 It is an enlarged schematic diagram of part A of the utility model;

[0023] Figure 6 It is a longitudinal construction diagram of the main tunnel section at the connecting tunnel section of the utility model;

[0024] Figure 7 It is a structural schematic diagram of the first support beam assembly and the second support column assembly of the utility model;

[0025] Figure 8 It is an enlarged schematic diagram of Part I of the utility model;

[0026] Fig. 9 It is an enlarged schematic diagram of the J part of the utility model;

[0027] Among them: 1. first supporting structure, 1-1. cross beam, 1-2. cantilever arch frame, 1-3. first supporting column assembly, 1-4. third supporting column assembly, 1-5. temporary scaffolding, 1-6. bump, 2. second supporting structure, 2-1. first supporting beam assembly, 2-2. cross hole arch frame, 2-3. second supporting column assembly, 2-4. E group supporting columns, 2-5. F group supporting columns, 2-6. G group supporting beams, 2-7. H group supporting beams, 2-8 slots. DETAILED DESCRIPTION

[0028] In order to enable those skilled in the art to better understand the technical solution of the present invention, the technical solution of the present invention is further described below in conjunction with the accompanying drawings and embodiments.

[0029] Example

[0030] See also Figure 1-Figure 9 , the present application discloses a staggered construction structure of parallel main-slave double-tunnels crossing a water-rich area, comprising: a first support structure 1 located in the main tunnel portion, the first support structure 1 is used to support the top of the main tunnel portion close to the connecting tunnel portion;

[0031] A second supporting structure 2 at the intersection of the connecting tunnel portion and the main tunnel portion, the second supporting structure 2 is used to support the top of the connecting tunnel portion close to the main tunnel portion;

[0032] One end of the first supporting structure 1 close to the connecting tunnel portion is mounted on the top of the second supporting structure 2 .

[0033] like Figure 2 As shown, the second support structure 2 includes a first support beam assembly 2-1, a transverse hole arch frame 2-2 and a second support column assembly 2-3, the second support column assembly 2-3 is symmetrically installed on the left and right sides of the transverse hole arch frame 2-2, and the first support beam assembly 2-1 is installed on the top of the second support column assembly 2-3. The transverse hole arch frame 2-2 adopts I20 steel.

[0034] like Figure 7 , Figure 8 As shown, the second support column assembly 2-3 includes at least the E group support columns 2-4 and the F group support columns 2-5, and the first joist assembly 2-1 includes at least the G group joists 2-6 and the H group joists 2-7, the G group joists 2-6 are installed on the E group support columns 2-4, and the H group joists 2-7 are installed on the F group support columns 2-5.

[0035] like Figure 3-Figure 5 As shown, the first supporting structure 1 includes a crossbeam 1-1, a cantilevered arch frame 1-2, a first supporting column assembly 1-3, a third supporting column assembly 1-4 and a temporary scaffolding 1-5. The cantilevered arch frame 1-2 is connected to the first supporting beam assembly 2-1, the crossbeam 1-1 is installed at the top of the first supporting column assembly 1-3, and is used to connect the temporary scaffolding 1-5. The third supporting column assembly 1-4 is used to support the temporary scaffolding 1-5.

[0036] The cantilever arch frame 1-2 is set in the reinforced section of the main tunnel using I20 steel frame with a spacing of 1.0m. The top is supported by I20 steel frame temporary scaffolding 1-5, and the spacing between temporary scaffolding 1-4 is 0.8m.

[0037] In order to ensure that the main tunnel cantilever arch frame 1-2 has a stable foothold, an I20 I-beam first beam assembly 2-1 is set at the intersection of the connecting tunnel and the main tunnel. The first beam assembly 2-1 is welded with 3 I20 steel frames. The main tunnel cantilever arch frame 1-2 falls on the first beam assembly 2-1 and is welded together with the first beam assembly 2-1. The arch frame spacing is 0.6m, and a total of 11 beams are processed.

[0038] like Fig. 9 As shown, the first joist assembly 2-1 is provided with a slot 2-8, and the connection between the cantilever arch frame 1-2 and the first joist assembly 2-1 is provided with a protrusion 1-6 matching the slot 2-8. When in use, the protrusion 1-6 is inserted into the slot 2-8, which facilitates the installation of the cantilever arch frame 1-2 and the first joist assembly 2-1, and can quickly place the cantilever arch frame 1-2 on the first joist assembly 2-1, which is convenient for installation and improves work efficiency.

[0039] like Figure 1 As shown, the upper part is a main tunnel part, the lower part is an auxiliary tunnel part, and at least one connecting tunnel part is used to connect the main tunnel part and the auxiliary tunnel part. The main tunnel part and the auxiliary tunnel part are parallel.

[0040] The main tunnel section includes the main tunnel face, and the auxiliary tunnel section includes the pilot tunnel face. The pilot tunnel face is farther than the main tunnel face in the excavation direction, and the connecting tunnel section is arranged between the pilot tunnel face and the main tunnel face.

[0041] When the auxiliary tunnel section is ahead of the main tunnel section entrance by more than 1000m, if it is necessary to increase the working face to improve the construction efficiency and shorten the construction period, it is necessary to construct a connecting cross tunnel 30m behind the auxiliary tunnel section heading face.

[0042] like Figure 6 As shown, the connecting tunnel portion includes an upper step and a lower step, the upper step is located near one end of the connecting tunnel portion, the lower step is located near one end of the main tunnel portion, and the upper step is connected to the lower step.

[0043] The specific application cases of the utility model are as follows:

[0044] First, the construction points of the auxiliary tunnel section

[0045] The excavation method for auxiliary tunnels is full-section excavation. The construction points are as follows:

[0046] (1) Measurement and layout: Use a total station and precision level to measure and layout the tunnel excavation profile.

[0047] (2) Excavation: Excavation is carried out by drilling and blasting method, and smooth blasting is adopted for construction.

[0048] (3) The ventilation adopts the pressure ventilation method to ensure the fresh air in the tunnel and improve the working environment in the tunnel.

[0049] (4) Mud removal and transportation: Mud removal by loaders is carried out in the early stage of the tunnel entrance section. Mud removal by scrapers is carried out after the construction reaches a certain position. Mud removal by loaders and dump trucks is carried out.

[0050] (5) Initial support: Use a wet spraying machine to apply wet spraying concrete, mortar anchor rods, hanging steel mesh and I-beam frames.

[0051] (6) The waterproof layer is constructed by a nail-free laying process, i.e., the pad welding method. The waterproof board is welded by heat sealing. The non-woven fabric is installed on the construction platform with nails with pads of the same material as the waterproof board. The waterproof membrane (waterproof layer) is then covered. The waterproof layer is then welded and fixed to the waterproof layer pad on the nails using a heat sealing machine.

[0052] (7) Secondary concrete lining: Use a steel mold lining trolley, a mixer truck to transport concrete to the working surface, and a delivery pump to pump concrete into the lining trolley formwork.

[0053] When the auxiliary tunnel face is advanced to a distance of more than 30m from the main tunnel entrance and out of the influence range of surrounding rock disturbance, the main tunnel will be constructed, and the auxiliary tunnel will continue to be constructed forward.

[0054] Second, key points in determining the excavation method for the main tunnel

[0055] According to the engineering geology, hydrogeology and ground environment conditions of the main tunnel, corresponding construction methods and auxiliary construction methods are selected for different surrounding rocks. For different surrounding rocks and different sections, excavation is carried out according to the following construction methods.

[0056] (1) The construction sections with surrounding rock hardness index f = 1.5 and f = 3 were excavated using the three-step seven-step method, first excavating the upper step, then the middle step, and finally the lower step, reserving the core soil. The tunnel was reinforced with advanced small-duct grouting at the face, and the initial support was #30 I-beam support and system anchor bolts + B25 shotcrete.

[0057] (2) For the construction section with a surrounding rock hardness index of f = 4-5, the step method is used for excavation. The upper step is excavated first, and then the lower step is excavated. The construction is carried out in the order of upper step first and lower step second. The initial support is system anchor rod + steel mesh + B25 shotcrete.

[0058] (3) For the construction section with a surrounding rock hardness index of f=6, full-section excavation and smooth surface controlled blasting are adopted, and the amount of explosives used is strictly controlled to reduce the disturbance of blasting vibration to the rock formation. The initial support is a system of anchor rods + steel mesh + B25 shotcrete.

[0059] (4) Mud is transported by trackless transport, loaded by excavators and transported by dump trucks to the slag dump outside the tunnel. Ventilation adopts forced ventilation to ensure fresh air in the tunnel and improve the working environment in the tunnel.

[0060] Third, the main tunnel construction points

[0061] According to the surrounding rock conditions and cross-section size, the tunnel is constructed using the three-bench seven-step method, the step method, and the full-section method.

[0062] (1) Measurement and layout: Use a total station and precision level to measure and layout the tunnel excavation profile.

[0063] (2) Excavation: Excavation is carried out by blasting using the drilling and blasting method. If the surrounding rock is poor and advance support is required according to design requirements, the advance support construction should be completed according to the design before excavation.

[0064] (3) Mud removal and transportation: Excavators or loaders are used to load mud in the tunnel, and loaders and dump trucks are used to transport mud out.

[0065] (4) Initial support: Use a wet spraying machine to apply wet spraying concrete, mortar anchor rods, hanging steel mesh and I-beam frames.

[0066] (5) The waterproof layer is constructed by a nail-free laying process, that is, the pad welding method. The waterproof board is welded by heat sealing, and the non-woven fabric is installed on the construction platform with nails with pads of the same material as the waterproof board. Then the waterproof membrane (waterproof layer) is covered, and the waterproof layer is welded and fixed to the waterproof layer pad on the nails with a heat welding machine.

[0067] (6) Secondary concrete lining: Use a steel formwork lining trolley, a mixer truck to transport concrete to the working surface, and a delivery pump to pump concrete into the lining trolley formwork.

[0068] When the auxiliary tunnel is ahead of the main tunnel entrance by more than 1000m, if it is necessary to increase the working face to improve construction efficiency and shorten the construction period, it is necessary to construct a connecting cross tunnel 30m behind the auxiliary tunnel face.

[0069] Fourth, key points for connecting tunnel construction

[0070] According to the actual surrounding rock conditions on site, the "small guide tunnel scaffolding climbing method" was used for the construction section where the connecting tunnel entered the main tunnel. After the connecting tunnel was constructed to the junction with the main tunnel, it entered the main tunnel in the form of an orthogonal trumpet, and at the same time excavated uphill to the elevation of the main tunnel vault, and continued to excavate a certain distance in the same direction; after forming the working space, it turned to the opposite direction for construction, and expanded the temporary support to reach the standard section of the main tunnel.

[0071] (1) Construction of connecting tunnel section adjacent to main tunnel section 1

[0072] The connecting tunnel part adjacent to the main tunnel part is designed to be f=4-5. In order to ensure construction safety and consider the bell mouth construction technology, the scheme adopts I20 I-beam frame with anchor rods, steel mesh and shotcrete reinforced support. The specific support parameters are:

[0073] ① The cross tunnel arch frame 2-2 within the connecting tunnel section is made of I20 steel, the spacing between the cross tunnel arch frames 2-2 is 1.0m, the cross tunnel arch frames 2-2 are longitudinally welded together with φ22 threaded steel bars, the circumferential spacing of the connecting bars is 1m, and φ42 locking foot anchor pipes are used for positioning.

[0074] ② The arch wall of the connecting tunnel is sprayed with C25 concrete with a thickness of 20cm. The arch is equipped with φ25 hollow grouting anchor rods, and the side walls are equipped with φ22 mortar anchor rods. The anchor rods are 3m long, with a spacing of 1.0m×1.0m, arranged in a plum blossom shape. φ6 steel mesh is hung on the arch wall with a spacing of 20cm×20cm, overlapping 1-2 grids and welded point by point.

[0075] (2) Construction of the intersection between the cross tunnel arch frame 2-2 of the connecting tunnel and the cantilever arch frame 1-2 of the main tunnel

[0076] The bell mouth at the junction of the connecting tunnel section and the main tunnel section is reinforced with three parallel I20 I-shaped gantries, and serves as the footing support for the main tunnel section's cantilever arch frame 1-2.

[0077] ① In order to ensure that the main tunnel cantilever arch frame 1-2 has a stable foothold, an I20 I-beam first beam assembly 2-1 is set at the intersection of the connecting tunnel and the main tunnel. The first beam assembly 2-1 is welded with 3 I20 steel frames. The main tunnel cantilever arch frame 1-2 falls on the first beam assembly 2-1 and is welded together with the first beam assembly 2-1. The spacing between the cantilever arch frames 1-2 is 0.6m, and a total of 11 beams are processed.

[0078] ②Add locking foot anchor pipes at the arch foot of the cantilever arch frame 1-2 of the main tunnel section, and install 4 φ42 locking foot anchor pipes with a length of 4m at the arch foot of the connection with the cross hole arch frame 2-2 of the connecting tunnel section to ensure the stability of the cantilever arch frame 1-2.

[0079] ③ The longitudinal tie rod of the connecting tunnel part extends 1m to the main tunnel part and is firmly welded to the main tunnel part top arch frame 1-2 or the longitudinal tie rod. The advance small duct extending from the connecting tunnel part into the main tunnel part is also welded to the main tunnel part top arch frame 1-2.

[0080] ④ The first joist assembly 2-1 at the intersection of the connecting tunnel section and the main tunnel section and the second support column assembly 2-3 made of I20 steel are welded together, and the spacing between the I20 steel second support column assembly 2-3 is 1.0m (consistent with the spacing between the main tunnel section cantilever arch frame 1-2), and the main tunnel section cantilever arch frame 1-2 falls on the first joist assembly 2-1 at the top of the second support column assembly 2-3. That is, the main tunnel section cantilever arch frame 1-2 falls on the G group joist 2-6 at the top of the E group support column 2-4, and on the H group joist 2-7 at the top of the F group support column 2-5.

[0081] (3) Construction of the reinforced section of the main tunnel

[0082] The reinforced section of the main tunnel section intersecting with the connecting tunnel section is within a range of 20m. The actual design surrounding rock f=6 is reduced by one level according to the design and the surrounding rock f=5 composite lining is used for support. In the intersection range between the connecting tunnel section and the main tunnel section, 1-2 cantilever arch supports are added on both sides. The support parameters are:

[0083] ① The cantilever arch frame 1-2 in the reinforced section of the main tunnel is made of I20 steel frame with a spacing of 1.0m. The cantilever arch frames 1-2 are welded together with φ22 longitudinal connecting bars, and the circumferential spacing of the tie rods is 1m. The nodes of the upper and lower step arch feet of the cantilever arch frame 1-2 are positioned with 4m long φ42 locking foot anchor pipes. Two locking foot anchor pipes are set at each node.

[0084] ② 15cm thick C25 concrete is sprayed on the arch wall (25cm thick C25 concrete is sprayed on the reinforcement section), the arch part is φ25 hollow grouting anchor, and the side wall is equipped with φ22 mortar anchor. Both anchors are 6m long, with a spacing of 1.0m×1.0m, arranged in a plum blossom shape. φ6 steel mesh is hung on the arch wall with a spacing of 20cm×20cm, overlapping at least 1 grid and welded point by point.

[0085] Fifth, key points for construction at the intersection of the connecting tunnel and the main tunnel

[0086] Due to many unfavorable factors such as the enlarged excavation clearance at the intersection, many construction processes, high construction difficulty, and long support closure time after excavation, this section was excavated using the step excavation method. According to the composite lining parameters designed for the connecting tunnel section and the main tunnel section, the initial support of the connecting tunnel section at the intersection section was strengthened to ensure support for the main tunnel section to cross the connecting tunnel section in the next step. The construction process at the intersection of the connecting tunnel section and the main tunnel section is as follows.

[0087] (1) When the connecting tunnel section approaches the intersection mileage of the main tunnel section, the arch elevation of the connecting tunnel section is gradually raised and the steel frame is extended.

[0088] (2) After the connecting tunnel section is excavated to the excavation contour line of the main tunnel section, the initial support reinforcement ring and the first joist assembly 2-1 are installed at the intersection. A longitudinal horizontal first joist assembly 2-1 is set on the arch of the steel frame of the lining support reinforcement ring of the connecting tunnel section 3 along the direction of the main tunnel section 3. The first joist assembly 2-1 is made of I20 steel (three beams are welded in parallel). The two ends of the first joist assembly 2-1 are connected to the I20 steel second support column assembly 2-3 to the bottom of the main tunnel wall. The first joist assembly 2-1 area is not sprayed for the time being, and it will be sprayed together after the main tunnel section steel frame is settled. The reinforced initial support of the connecting tunnel section should be implemented as soon as possible.

[0089] (3) At the intersection of the connecting tunnel and the main tunnel, a scaffolding is used to enter the main tunnel. After the scaffolding climbs up to the top of the tunnel, it is excavated forward with a flat slope to the arch foot of the outer step of the main tunnel. The main tunnel is excavated from the top. According to the stability of the surrounding rock, an I20 temporary scaffolding is used to support the top. The spacing between the scaffoldings is 0.8m. The scaffoldings are welded as a whole with φ22 steel bars, combined with 5cm of initial sprayed concrete to form a temporary support system. The scaffolding structure size is determined according to the on-site conditions and processed on-site.

[0090] ① Use a light small excavator to enter the arch of the main tunnel body horizontally and vertically in a small pilot pit manner, and excavate the top of the arch with the pilot pit arc surface, and use manual pneumatic picks and work platforms for trimming.

[0091] ② After entering the main tunnel section, the excavation and initial support need to be larger than the corresponding design elevation of the arch section of the main tunnel section to reserve temporary support thickness and sufficient deformation. During the excavation process, I20 I-beam temporary scaffolding 1-5 is used for timely support.

[0092] ③ When the temporary support of the upper pilot pit excavation surface of the main tunnel arch is qualified, remove the vertical support on one side of the temporary scaffolding 1-5, and carry out the initial support on this side (remove first and then support), and the longitudinal scaffolding crossbeam 1-1 at the arch will be used as permanent support, and the same method will be applied to the other side.

[0093] (4) After the initial support of the upper pilot pit of the arch is stable, the upper pilot pit of the arch is excavated in the main attack direction (the side of the small pile number of the entrance) using the work platform, with a depth of 1.0 to 1.5 m. After the excavation is qualified, the initial spraying is carried out immediately, and the initial support is applied in time.

[0094] (5) Turn around and use the work platform to excavate the upper pilot pit of the arch in the direction of the secondary attack (the side with the large pile number at the exit), with a depth of 1.0 to 1.5 m. After the excavation is qualified, the initial spraying is carried out immediately, and the initial support is applied in time, using the same method as above.

[0095] (6) After the excavation and support of the 6.0m range of the arch upper pilot pit is completed, the middle and upper rock mass is expanded section by section, and the initial support of the right half is extended to the arch line. The advance of each cycle is 1.0 to 1.5m.

[0096] (7) Under the initial support of the upper section, the step method is used to excavate and support in the main attack direction (small pile number side). To ensure safety, the upper step within the 140m range of the main tunnel section is excavated and supported twice to the maximum span (arch line).

[0097] (8) When the distance from the upper section to the face reaches 30m, the construction of the lower section side wall bottoming begins. The left and right side walls are staggered 3 to 5m forward and backward for bottom excavation support, with each cycle advancing 2m while moving forward.

[0098] The present application discloses a staggered construction structure of parallel main-slave double-hole tunnels that cross water-rich areas. The structure is simple and easy to install, which increases the safety factor of the construction process. The auxiliary tunnel part, including the tunnel part connected by the second supporting structure, can be used as a tunnel for machinery, personnel, ventilation, etc., to increase the working surface of the main tunnel part, realize the simultaneous construction of multiple working surfaces of the main tunnel part, and improve the construction efficiency.

[0099] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection of the utility model is defined by the attached claims and their equivalents.

Claims

1. A staggered construction structure of parallel main and slave double tunnels through water-rich areas, characterized in that: include: A first supporting structure (1) located in the main tunnel portion, the first supporting structure (1) being used to support the top of the main tunnel portion close to the connecting tunnel portion; a second supporting structure (2) at the intersection of the connecting tunnel portion and the main tunnel portion, wherein the second supporting structure (2) is used to support the top of the connecting tunnel portion close to the main tunnel portion; One end of the first supporting structure (1) close to the connecting tunnel portion is mounted on the top of the second supporting structure (2).

2. According to claim 1, a staggered construction structure of parallel main-slave double tunnels crossing a water-rich area is characterized in that: The second supporting structure (2) comprises a first support beam assembly (2-1), a transverse hole arch frame (2-2) and a second support column assembly (2-3); the second support column assembly (2-3) is symmetrically mounted on the left and right sides of the transverse hole arch frame (2-2); and the first support beam assembly (2-1) is mounted on the top end of the second support column assembly (2-3).

3. The staggered construction structure of a parallel main-slave double-tunnel through a water-rich area according to claim 2 is characterized in that: The second support column assembly (2-3) comprises at least an E group support column (2-4) and an F group support column (2-5), and the first joist assembly (2-1) comprises at least a G group joist (2-6) and an H group joist (2-7), wherein the G group joist (2-6) is installed on the E group support column (2-4), and the H group joist (2-7) is installed on the F group support column (2-5).

4. The staggered construction structure of a parallel main-slave double tunnel crossing a water-rich area according to claim 3 is characterized in that: The first supporting structure (1) comprises a crossbeam (1-1), a cantilevered arch frame (1-2), a first supporting column assembly (1-3), a third supporting column assembly (1-4) and a temporary scaffolding (1-5); the cantilevered arch frame (1-2) is connected to the first supporting beam assembly (2-1); the crossbeam (1-1) is installed at the top end of the first supporting column assembly (1-3) and is used to connect the temporary scaffolding (1-5); and the third supporting column assembly (1-4) is used to support the temporary scaffolding (1-5).

5. The staggered construction structure of parallel main-slave double tunnels crossing a water-rich area according to claim 4 is characterized in that: The first support beam assembly (2-1) is provided with a slot (2-8), and a protrusion (1-6) matching the slot (2-8) is provided at the connection between the cantilever arch frame (1-2) and the first support beam assembly (2-1).