Cable bent tower heavy load supporting bracket structure
By using a cable tower heavy-duty support corbel structure with pre-embedded keyboxes and bottom supports on the cable tower of the suspension bridge, spiral support steel bars are used to connect with the main bars of the cable tower to avoid bending moment transmission and solve the concrete cracking caused by the traditional corbel structure. problem, improving the convenience of construction and the stability and safety of the cable tower.
Patent Information
- Application Number
- CN202323524865.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-22
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2033-12-22
AI Technical Summary
The traditional corbel structure can easily cause bending moments to be transmitted to the cable tower during the construction of the suspension bridge cable tower, causing concrete cracking and affecting stability and safety.
The heavy-duty support corbel structure of the cable tower using pre-embedded key boxes and bottom supports is connected to the main bars of the cable tower through spiral support steel bars. The horizontal members and oblique members of the corbels are connected through plug-in and hinge joints to avoid welding installation and ensure bending. Moments are not transferred.
It achieves the convenience of installation and the safety of concrete stress, avoids the transmission of bending moments to the cable tower, and improves the overall stability and safety of the cable tower.
Smart Images

Figure CN221877763U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of road engineering, and in particular relates to a cable tower heavy-load supporting bracket structure. Background Art
[0002] At present, most of the cable towers of super-large suspension bridges in China are reinforced concrete frame structures with portal frames. In order to ensure the rigidity and stability of the cable towers of suspension bridges, upper and lower beams are usually designed to ensure the overall stability and safety of the towers. According to the statistics of the construction technology of super-large suspension bridges under construction and completed in China, more than 95% of the lower beams of the cable towers are constructed using the traditional ground-type large steel pipe bracket + bracket + Bailey beam method, and a small number of them use the large triangular steel pipe diagonal brace + bracket + Bailey beam method to construct the cable tower beams. The traditional bracket is usually installed on the cable tower through welding of the cable tower embedded parts, which is easy to transfer the bending moment to the cable tower, thereby causing problems such as cracking of the cable tower concrete. Utility Model Content
[0003] The main purpose of the utility model is to provide a heavy-load supporting bracket structure of a cable tower, aiming to effectively avoid the transmission of bending moment to the cable tower and ensure the stress safety of the cable tower concrete.
[0004] To this end, the utility model provides a heavy-load supporting corbel structure for a cable tower, in which a pre-embedded key box and a bottom support are respectively provided at the installation positions of the horizontal member and the diagonal member of the corbel on the cable tower, the pre-embedded key box is supported and installed on the cable tower through a first spiral support steel bar, the bottom support is supported and installed on the cable tower through a second spiral support steel bar, the first spiral support steel bar and the second spiral support steel bar are connected to the main reinforcement of the cable tower, the horizontal member is matched and inserted in the pre-embedded key box, and the lower end of the diagonal member is hinged to the bottom support.
[0005] Specifically, it also includes a first pull rod and a second pull rod, one end of the first pull rod passes through the horizontal member and is threadedly connected to a first sleeve pre-buried in the cable tower, and the other end is connected to a first locking nut;
[0006] One end of the second pull rod passes through the oblique member and is threadedly connected to a second sleeve pre-buried in the cable tower, and the other end is connected to a second locking nut.
[0007] Specifically, the first sleeve and the second sleeve are respectively connected to the main reinforcement of the cable tower through the third spiral support steel bar.
[0008] Specifically, the first spiral support steel bar is vertically embedded in the cable tower, and the top end is fixedly connected to the bottom of the embedded key box.
[0009] Specifically, the second spiral support steel bar is pre-buried in the cable tower at an angle, and the top end is fixedly connected to the bottom support, and the inclination direction of the second spiral support steel bar is parallel to or coincides with the extension direction of the diagonal member.
[0010] Specifically, a fourth spiral support steel bar fixedly connected to the side of the embedded key box is horizontally pre-embedded in the cable tower, and the fourth spiral support steel bar is connected to the main reinforcement of the cable tower.
[0011] Compared with the prior art, the utility model has the following beneficial effects: the horizontal component of the corbel is directly inserted into the pre-embedded key box of the cable tower, the oblique component is hingedly connected to the bottom support, the pre-embedded key box and the bottom support are effectively connected to the cable tower wall laterally through spiral support steel bars. Compared with the traditional corbel installed by welding the pre-embedded parts of the cable tower, the inserted corbel is more convenient in installation, and at the same time avoids the transmission of bending moment to the cable tower, thereby ensuring the stress safety of the cable tower concrete. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0013] Figure 1 It is a schematic diagram of the structure of the heavy-load supporting bracket of the cable tower provided by the embodiment of the utility model;
[0014] Among them: 1. Cable tower; 2. Horizontal member; 3. Diagonal member; 4. Embedded key box; 5. Bottom support; 6. First spiral support steel bar; 7. Second spiral support steel bar; 8. First tie rod; 9. Second tie rod; 10. First sleeve; 11. First locking nut; 12. Second sleeve; 13. Second locking nut; 14. Third spiral support steel bar; 15. Fourth spiral support steel bar. DETAILED DESCRIPTION
[0015] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0016] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0017] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0018] See also Figure 1 A heavy-load supporting corbel structure for a cable tower, wherein a pre-embedded key box 4 and a bottom support 5 are respectively provided at the installation positions of the horizontal member 2 and the diagonal member 3 of the corbel on the cable tower 1. The pre-embedded key box 4 is supported and installed on the cable tower 1 by a first spiral supporting steel bar 6, and the bottom support 5 is supported and installed on the cable tower 1 by a second spiral supporting steel bar 7. The first spiral supporting steel bar 6 and the second spiral supporting steel bar 7 are connected to the main reinforcement of the cable tower 1, the horizontal member 2 is matched and inserted in the pre-embedded key box 4, and the lower end of the diagonal member 3 is hinged to the bottom support 5.
[0019] In the present embodiment, the horizontal member 2 of the corbel is directly inserted into the embedded key box 4 of the cable tower 1, the inclined member 3 is hingedly connected to the bottom support 5, and the embedded key box 4 and the bottom support 5 are effectively connected to the tower wall of the cable tower 1 laterally through the spiral support steel bars. Compared with the traditional corbel installed by welding the embedded parts of the cable tower 1, the inserted corbel is more convenient in installation, and at the same time avoids the transmission of bending moment to the cable tower 1, thereby ensuring the stress safety of the concrete of the cable tower 1.
[0020] See also Figure 1It can be understood that in order to ensure the stability of the installation of the corbel, the corbel also includes a first pull rod 8 and a second pull rod 9. Channels for the first pull rod 8 to pass through are opened at the corresponding positions of the horizontal member 2 and the cable tower 1, and channels for the second pull rod 9 to pass through are opened at the corresponding positions of the inclined member 3 and the cable tower 1. One end of the first pull rod 8 passes through the horizontal member 2 and is threadedly connected to the first sleeve 10 embedded in the cable tower 1, and the other end is connected to the first locking nut 11, and the first pull rod 8 can be locked by screwing the first locking nut 11. One end of the second pull rod 9 passes through the inclined member 3 and is threadedly connected to the second sleeve 12 embedded in the cable tower 1, and the other end is connected to the second locking nut 13, and the second pull rod 9 can be locked by screwing the second locking nut 13.
[0021] See also Figure 1 It should be explained that, in actual design, in order to effectively prevent the concrete structure of the cable tower 1 from being damaged during the tightening process of the nut, the first sleeve 10 and the second sleeve 12 are respectively connected to the main reinforcement of the cable tower 1 through a third spiral support steel bar 14.
[0022] See also Figure 1 Specifically, the first spiral support steel bar 6 is vertically embedded in the cable tower 1, and the top end is fixedly connected to the bottom of the embedded key box 4. The second spiral support steel bar 7 is obliquely embedded in the cable tower 1, and the top end is fixedly connected to the bottom support 5. The inclination direction of the second spiral support steel bar 7 is parallel to or coincides with the extension direction of the oblique member 3. The cable tower 1 is also horizontally embedded with a fourth spiral support steel bar 15, and the two ends of the fourth spiral support steel bar 15 are respectively fixedly connected to the side of the embedded key box 4 and the main reinforcement of the cable tower 1.
[0023] Unless otherwise stated, any technical solution disclosed in the above utility model, if it discloses a numerical range, then the disclosed numerical range is a preferred numerical range, and any technician in the field should understand that the preferred numerical range is only a numerical value with a more obvious technical effect or representative value among many implementable numerical values. Since there are too many numerical values to be exhaustive, the utility model discloses only some numerical values to illustrate the technical solution of the present invention, and the numerical values listed above should not constitute a limitation on the scope of protection of the invention.
[0024] At the same time, if the above-mentioned utility model discloses or involves components or structural parts that are fixedly connected to each other, then, unless otherwise stated, the fixed connection can be understood as: a detachable fixed connection (for example, connected by bolts or screws), and can also be understood as: a non-detachable fixed connection (for example, riveting, welding). Of course, the mutual fixed connection can also be replaced by an integrated structure (for example, manufactured by one-piece molding using a casting process) (except when it is obviously impossible to use an one-piece molding process).
[0025] In addition, the terms used in any technical solution disclosed in the above utility model to indicate positional relationship or shape include the state or shape that is similar, similar or close to it unless otherwise stated. Any component provided by the utility model can be assembled from multiple separate components, or it can be a separate component manufactured by an integrated molding process.
[0026] The above embodiments are merely examples for clearly illustrating the present invention, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the embodiments here. The obvious changes or modifications derived from these are still within the scope of protection of the present invention.
Claims
1. The tower heavy-load support bracket structure is characterized by: A pre-embedded key box (4) and a bottom support (5) are respectively provided at the installation positions of the horizontal member (2) and the diagonal member (3) of the upper bracket of the cable tower (1); the pre-embedded key box (4) is supported and installed on the cable tower (1) by a first spiral support steel bar (6); the bottom support (5) is supported and installed on the cable tower (1) by a second spiral support steel bar (7); the horizontal member (2) is matched and plugged into the pre-embedded key box (4); the lower end of the diagonal member (3) is hinged to the bottom support (5); the first spiral support steel bar (6) and the second spiral support steel bar (7) are connected to the main reinforcement of the cable tower (1).
2. The cable tower heavy-load support bracket structure according to claim 1 is characterized in that: It also includes a first pull rod (8) and a second pull rod (9), one end of the first pull rod (8) passes through the horizontal member (2) and is threadedly connected to a first sleeve (10) pre-buried in the cable tower (1), and the other end is connected to a first locking nut (11); One end of the second pull rod (9) passes through the inclined member (3) and is threadedly connected to a second sleeve (12) pre-buried in the cable tower (1), and the other end is connected to a second locking nut (13).
3. The cable tower heavy-load support bracket structure according to claim 2 is characterized in that: The first sleeve (10) and the second sleeve (12) are respectively connected to the main reinforcement of the cable tower (1) via third spiral support reinforcement bars (14).
4. The cable tower heavy-load support bracket structure according to any one of claims 1 to 3, characterized in that: The first spiral support steel bar (6) is vertically pre-embedded in the cable tower (1), and the top end is fixedly connected to the bottom of the pre-embedded key box (4).
5. The cable tower heavy-load support bracket structure according to claim 4 is characterized in that: The second spiral support steel bar (7) is pre-buried obliquely in the cable tower (1), and the top end is fixedly connected to the bottom support (5), and the inclination direction of the second spiral support steel bar (7) is parallel to or coincides with the extension direction of the diagonal member (3).
6. The cable tower heavy-load support bracket structure according to claim 5 is characterized in that: A fourth spiral support steel bar (15) is also horizontally pre-buried in the cable tower (1) and fixedly connected to the side of the pre-buried key box (4); the fourth spiral support steel bar (15) is connected to the main reinforcement of the cable tower (1).