Coal gangue slope protection cofferdam

Through the design of the coal gangue slope protection cofferdam, the structure of spliced ​​bricks and connecting rods does not require formwork support, which solves the problem of long construction time of the existing cofferdam and achieves rapid construction and efficient construction process.

CN221878140UActive Publication Date: 2024-10-22SINOHYRDO ENG BUREAU 3 CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420459487.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-11
Publication Date
2024-10-22
Estimated Expiration
2034-03-11

AI Technical Summary

Technical Problem

During the construction process of the existing cofferdam, formwork needs to be supported and removed, resulting in long construction time and affecting the construction speed.

Method used

The coal gangue slope protection cofferdam design does not require formwork support. The wall structure is formed by splicing multiple bricks and connecting rods. During the construction process, concrete is poured to fix the bricks to form a strong cofferdam structure.

Benefits of technology

It effectively shortens the construction time, increases the construction speed, and reduces the construction cost and environmental impact because there is no need for formwork support and removal.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221878140U_ABST
    Figure CN221878140U_ABST
Patent Text Reader

Abstract

The utility model belongs to the field of green utilization of coal gangue, and particularly relates to a coal gangue slope protection cofferdam which comprises a base. The number of the first wall bodies is two, the two first wall bodies are oppositely arranged on the base at intervals, each first wall body comprises a plurality of first bricks and first connecting rods, first round holes are formed in the first bricks, the first bricks are spliced and stacked to form the first wall bodies, the first connecting rods are arranged in the aligned first round holes in a penetrating mode, and the first connecting rods are fixedly connected with the base; the number of the second wall bodies is two, the two second wall bodies and the two first wall bodies define a cofferdam structure, each second wall body comprises a plurality of second bricks and second connecting rods, second round holes are formed in the second bricks, the second bricks are spliced and stacked to form the second wall bodies, and the second connecting rods penetrate through the aligned second round holes. And the second connecting rod is fixedly connected with the base. The cofferdam can be built without erecting a template, the consumed time is short, materials are easy to obtain, and the construction speed is effectively increased.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the field of green utilization of coal gangue, and in particular relates to a coal gangue slope protection cofferdam. Background Art

[0002] As a large-scale industrial solid waste, coal gangue has serious harm to the natural environment. The effective treatment and utilization of coal gangue can not only realize the green development of the coal industry, but also realize the recycling of secondary resources, which is in line with the concept of modern industrial development. Therefore, there is an urgent need for a recycling method that can effectively treat coal gangue. At present, the common cofferdams are to set up the formwork first, and then pour concrete inside the formwork to form the outer wall of the cofferdam. When building the cofferdam, it takes a long time to set up and remove the formwork, which affects the construction speed of the cofferdam. Utility Model Content

[0003] The embodiment of the present application provides a gangue slope protection cofferdam, the construction of which does not require the setting up of formwork, is time-saving, and is easy to obtain materials, thereby effectively improving the construction speed.

[0004] A gangue slope protection cofferdam, comprising:

[0005] Base;

[0006] A first wall, wherein the first wall is provided with two groups, and the two groups of the first walls are arranged on the base at a relative interval, the first wall comprises a plurality of first bricks and a first connecting rod, the first bricks are provided with first circular holes, the first bricks are spliced ​​and stacked to form the first wall, the first circular holes of the first bricks are aligned along the height direction of the first wall, the first connecting rod is passed through the aligned first circular holes, and the first connecting rod is fixedly connected to the base;

[0007] The second wall body is provided with two groups, and the two groups of the second walls are respectively arranged on both sides of the two groups of the first walls, and the two groups of the second walls and the two groups of the first walls are combined to form a cofferdam structure. The second wall comprises a plurality of second bricks and a second connecting rod, and the second bricks are provided with second circular holes. The second bricks are spliced ​​and stacked to form the second wall, and the second circular holes of the second bricks are aligned along the height direction of the second wall, and the second connecting rod is passed through each aligned second circular hole, and the second connecting rod is fixedly connected to the base.

[0008] According to some other embodiments of the utility model, the gangue slope protection cofferdam also includes a corner column, which connects the first wall and the second wall. The corner column includes a plurality of third bricks and a third connecting rod. The third bricks are provided with third circular holes, and each of the third circular holes is aligned along the height direction of the corner column. The third connecting rod is passed through each of the third circular holes and connected to the base.

[0009] According to some other embodiments of the coal gangue slope protection cofferdam of the utility model, connecting columns are provided on both sides of the third brick, and the side edges of the first brick and the second brick are provided with connecting holes, and the connecting columns are assembled in the connecting holes to connect the third brick with the first brick and the second brick adjacent thereto.

[0010] According to some other embodiments of the coal gangue slope protection cofferdam of the utility model, the first brick is provided with a first rectangular hole, and along the height direction of the first wall, each of the first rectangular holes is aligned, and concrete is poured into each of the aligned first rectangular holes.

[0011] According to some other embodiments of the coal gangue slope protection cofferdam of the utility model, the second bricks are provided with second rectangular holes, and along the height direction of the second wall, the second rectangular holes are aligned, and concrete is poured into the aligned second rectangular holes.

[0012] According to some other embodiments of the coal gangue slope protection cofferdam of the utility model, a cylindrical rod is provided on the inner side of the first brick, the first bricks on two groups of the first walls are aligned, and the cylindrical rods on the two aligned first bricks are connected by a connecting tube.

[0013] According to the gangue slope protection cofferdam of some other embodiments of the utility model, the cylindrical rods on each group of the first walls are connected by a fixing plate.

[0014] According to some other embodiments of the coal gangue slope protection cofferdam of the utility model, a connecting plate is provided on the inner side of the second brick, and the connecting plate is connected to the cylindrical rod on the first brick adjacent thereto.

[0015] According to the gangue slope protection cofferdam of some other embodiments of the utility model, two adjacent connecting plates on the inner side of the second wall are connected by a connecting rod.

[0016] According to some other embodiments of the coal gangue slope protection cofferdam of the utility model, a first small hole and a second small hole are provided on the connecting plate, the connecting rod is inserted into the first small hole, and the cylindrical rod is inserted into the second small hole.

[0017] The gangue slope protection cofferdam of the utility model embodiment has at least the following beneficial effects: during the construction process, multiple first bricks are spliced ​​and stacked, and the first circular holes on the first bricks are aligned one by one, and then the first connecting rod is inserted into the first circular hole and fixed to the base, so that the first bricks are connected to form a first wall. Similarly, multiple second bricks are spliced ​​and stacked, and the second through holes on the second bricks are aligned one by one, and then the second connecting rod is inserted into the second through hole and fixed to the base, so that the second bricks are connected to form a second wall. The two groups of first walls and the two groups of second walls are mutually enclosed to form a cofferdam. The construction of this cofferdam does not require the support of formwork, is time-saving, easy to obtain materials, and effectively improves the construction speed. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a top view of a gangue slope protection cofferdam provided in one embodiment of the present application;

[0019] Figure 2 yes Figure 1 A top view of a first brick, a second brick, and a third brick in the illustrated embodiment. DETAILED DESCRIPTION

[0020] In order to enable those skilled in the art to better understand the technical solutions in the present application, the technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work should fall within the scope of protection of the present application.

[0021] The following is a further detailed description of the implementation of the present application in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present application but cannot be used to limit the scope of the present application.

[0022] In the description of the embodiments of the present application, it should be noted that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, which are only for the convenience of describing the embodiments of the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the embodiments of the present application. In addition, the terms "first", "second", and "third" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0023] In the description of the embodiments of the present application, it should be noted that, unless otherwise clearly specified and limited, the terms "connected" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the embodiments of the present application can be understood according to specific circumstances.

[0024] In the embodiments of the present application, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or that the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" and "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0025] As a large-scale industrial solid waste, coal gangue has serious harm to the natural environment. The effective treatment and utilization of coal gangue can not only realize the green development of the coal industry, but also realize the recycling of secondary resources, which is in line with the concept of modern industrial development. Therefore, there is an urgent need for a recycling method that can effectively treat coal gangue. At present, the common cofferdams are to set up the formwork first, and then pour concrete inside the formwork to form the outer wall of the cofferdam. When building the cofferdam, it takes a long time to set up and remove the formwork, which affects the construction speed of the cofferdam.

[0026] See also Figure 1 , Figure 2The present application provides a gangue slope protection cofferdam, comprising a base, a first wall 1 and a second wall 2. The first wall 1 is provided with two groups, and the two groups of first walls 1 are arranged on the base at intervals. The first wall 1 comprises a plurality of first bricks 10 and a first connecting rod. The first bricks 10 are provided with first circular holes 10a. The first bricks 10 are spliced ​​and stacked to form the first wall 1. The first circular holes 10a of the first bricks 10 are aligned along the height direction of the first wall 1. The first connecting rods are inserted through the aligned first circular holes 10a for connection, and the first connecting rods are fixed to the base. The second wall 2 is fixedly connected, and two groups of second walls 2 are respectively arranged on both sides of the two groups of first walls 1. The two groups of second walls 2 and the two groups of first walls 1 are enclosed to form a cofferdam structure. The second wall 2 includes a plurality of second bricks 20 and a second connecting rod. The second bricks 20 are provided with second circular holes 20a. The second bricks 20 are spliced ​​and stacked to form the second wall 2. The second circular holes 20a of the second bricks 20 are aligned along the height direction of the second wall 2. Second connecting rods are passed through the aligned second circular holes 20a, and the second connecting rods are fixedly connected to the base.

[0027] During the construction process, multiple first bricks 10 are spliced ​​and stacked, and the first circular holes 10a on the first bricks 10 are aligned one by one, and then the first connecting rod is passed through the first circular hole 10a and fixed to the base, so that the first bricks 10 are connected to form a first wall 1. Similarly, multiple second bricks 20 are spliced ​​and stacked, and the second through holes on the second bricks 20 are aligned one by one, and then the second connecting rod is passed through the second through hole and fixed to the base, so that the second bricks 20 are connected to form a second wall 2. The two groups of first walls 1 and the two groups of second walls 2 are mutually enclosed to form a cofferdam. The construction of this cofferdam does not require the support of formwork, is time-saving, easy to obtain materials, and effectively improves the construction speed.

[0028] In order to improve the firmness of the cofferdam, in some embodiments, a first rectangular hole 10b is provided on the first brick 10, and each first rectangular hole 10b is aligned along the height direction of the first wall 1, and concrete is poured into each first rectangular hole 10b.

[0029] Specifically, the first rectangular hole 10b is arranged in the middle of the first brick 10, and two first circular holes 10a are arranged, and the two first circular holes 10a are respectively arranged on both sides of the first rectangular hole 10b, and the first rectangular hole 10b and the first circular hole 10a both penetrate the first brick 10 along the height direction of the first wall 1. After the first connecting rod is passed through the aligned first circular holes 10a to connect them, concrete is poured into each aligned first rectangular hole 10b, so that each first brick 10 is more firmly connected and the first wall 1 formed thereby is also more stable.

[0030] In some other embodiments, the second brick 20 is further provided with a second rectangular hole 20b, and along the height direction of the second wall 2, the second rectangular holes 20b are aligned, and concrete is poured into the aligned second rectangular holes 20b.

[0031] Specifically, the second rectangular hole 20b is provided in the middle of the second brick 20, and two second circular holes 20a are provided. The two second circular holes 20a are respectively provided on both sides of the second rectangular hole 20b, and the second rectangular hole 20b and the second circular hole 20a both penetrate the second brick 20 along the height direction of the second wall 2. After the second connecting rod is passed through the aligned second circular holes 20a to connect them, concrete is poured into each aligned second rectangular hole 20b, so that the connection between each second brick 20 is more firmly, and the second wall 2 formed thereby is also more stable.

[0032] In some embodiments, the coal gangue slope protection cofferdam also includes a corner column 3, which connects the first wall 1 and the second wall 2. The corner column 3 includes a plurality of third bricks 30 and a third connecting rod. The third bricks 30 are provided with a third circular hole 30a, and each third circular hole 30a is aligned along the height direction of the corner column 3. The third connecting rod is passed through each third circular hole 30a and connected to the base.

[0033] Specifically, the corner column 3 is arranged between the first wall 1 and the second wall 2, and the third circular hole 30a passes through the third brick 30 along the height direction of the corner column 3. After the third bricks 30 are stacked, the third connecting rod is passed through the aligned third circular hole 30a and fixed on the base, so that each third brick 30 is fixed to form a corner column 3.

[0034] In some embodiments, connecting columns 30b are provided on both sides of the third brick 30, and connecting holes are provided on the sides of the first brick 10 and the second brick 20. The connecting columns 30b are assembled in the connecting holes to connect the third brick 30 with the first brick 10 and the second brick 20 adjacent thereto.

[0035] Specifically, the third brick 30 has the same height as the first brick 10 and the second brick 20. A connecting column 30b is set on one side of the third brick 30 for connecting to the first brick 10. A connecting column 30b is set on one side of the third brick 30 for connecting to the second brick 20. The first brick 10 and the second brick 20 are provided with connecting holes corresponding to the connecting columns 30b. During the construction process, the connecting columns 30b on both sides of each third brick 30 are respectively embedded in the corresponding connecting holes on the first brick 10 and the second brick 20, thereby realizing the connection between the corner column 3 and the first wall 1 and the second wall 2.

[0036] In order to improve the connection performance between the two groups of first walls 1, in some embodiments, a cylindrical rod 10c is provided on the inner side of the first brick 10, the first bricks 10 on the two groups of first walls 1 are aligned, and the cylindrical rods 10c on the two aligned first bricks 10 are connected through a connecting tube 7.

[0037] Specifically, the cylindrical rod 10c is vertically installed on the inner side of the first brick 10. After the two groups of first walls 1 are installed, the cylindrical rods 10c in the two groups of first walls 1 are aligned one by one, and then the aligned cylindrical rods 10c are connected through the connecting tube 7, so that the two groups of first walls 1 are connected.

[0038] In the present application, the connecting cylinder 7 is threadedly connected to the cylindrical rod 10c.

[0039] In some other embodiments, the cylindrical rods 10c on each group of first walls 1 are connected by a fixing plate 4. In this way, the cylindrical rods 10c on the first bricks 10 are connected by the fixing plate 4, thereby improving the integrity of the first bricks 10 and further improving the stability and firmness of the first wall 1.

[0040] Of course, the fixing plate 4 can be a plate as large as the first wall 1, on which a plurality of through holes corresponding to the cylindrical rods 10c are arranged, and then directly sleeved on each cylindrical rod 10c to achieve connection.

[0041] In some embodiments, a connecting plate 20 c is provided on the inner side of the second brick 20 , and the connecting plate 20 c is connected to the cylindrical rod 10 c on the first brick 10 adjacent thereto.

[0042] Specifically, the connecting plate 20c is vertically fixed on the inner side of the second brick 20, and a connection relationship is established between the first wall 1 and the second wall 2 through the connection between the connecting plate 20c and the cylindrical rod 10c, thereby further improving the connection performance between the first wall 1 and the second wall 2.

[0043] In order to improve the integrity of the second wall 2 , in some embodiments, two adjacent connecting plates 20 c on the inner side of the second wall 2 are connected by a connecting rod 5 .

[0044] In some embodiments, a first small hole 200c and a second small hole 201c are provided on the connecting plate 20c, the connecting rod 5 is inserted into the first small hole 200c, and the cylindrical rod 10c is inserted into the second small hole 201c.

[0045] Specifically, the first small hole 200c and the second small hole 201c are arranged at intervals along the length direction of the connecting plate 20c, and the two ends of the connecting rod 5 are respectively connected to the first small hole 200c on the two connecting plates 20c, and the cylindrical rod 10c on the first brick 10 adjacent to it is passed through the second small hole 201c.

[0046] In addition, waterproof cloth is provided on the inner side of the first wall 1 and the second wall 2, and coal gangue crushed stones of different particle sizes are filled on the inner side of the waterproof cloth, wherein the waterproof cloth can further enhance the water blocking effect of the cofferdam, and the coal gangue crushed stones also enhance the stability of the cofferdam. At the same time, a soil pile 6 is provided on the outer side of the cofferdam to maintain the stability of the cofferdam.

[0047] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the embodiments of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

Claims

1. A gangue slope protection cofferdam, characterized in that: include: Base; A first wall, wherein the first wall is provided with two groups, and the two groups of the first walls are arranged on the base at a relative interval, the first wall comprises a plurality of first bricks and a first connecting rod, the first bricks are provided with first circular holes, the first bricks are spliced ​​and stacked to form the first wall, the first circular holes of the first bricks are aligned along the height direction of the first wall, the first connecting rod is passed through the aligned first circular holes, and the first connecting rod is fixedly connected to the base; The second wall body is provided with two groups, and the two groups of the second walls are respectively arranged on both sides of the two groups of the first walls, and the two groups of the second walls and the two groups of the first walls are combined to form a cofferdam structure. The second wall comprises a plurality of second bricks and a second connecting rod, and the second bricks are provided with second circular holes. The second bricks are spliced ​​and stacked to form the second wall, and the second circular holes of the second bricks are aligned along the height direction of the second wall, and the second connecting rod is passed through each aligned second circular hole, and the second connecting rod is fixedly connected to the base.

2. The gangue slope protection cofferdam according to claim 1 is characterized in that: It also includes a corner column, which connects the first wall and the second wall. The corner column includes a plurality of third bricks and a third connecting rod. The third bricks are provided with third circular holes, and each of the third circular holes is aligned along the height direction of the corner column. The third connecting rod is passed through each of the third circular holes and connected to the base.

3. The gangue slope protection cofferdam according to claim 2 is characterized in that: The third brick is provided with connecting columns on both sides, and the side edges of the first brick and the second brick are both provided with connecting holes, and the connecting columns are assembled in the connecting holes to connect the third brick with the first brick and the second brick adjacent thereto.

4. The gangue slope protection cofferdam according to claim 1, characterized in that: The first bricks are provided with first rectangular holes, and along the height direction of the first wall, the first rectangular holes are aligned, and concrete is poured into the aligned first rectangular holes.

5. The gangue slope protection cofferdam according to claim 1, characterized in that: The second bricks are provided with second rectangular holes, and along the height direction of the second wall, the second rectangular holes are aligned, and concrete is poured into the aligned second rectangular holes.

6. The gangue slope protection cofferdam according to claim 1, characterized in that: A cylindrical rod is provided on the inner side of the first brick, the first bricks on two groups of the first wall are aligned, and the cylindrical rods on the two aligned first bricks are connected via a connecting tube.

7. The gangue slope protection cofferdam according to claim 6, characterized in that: The cylindrical rods on each group of the first walls are connected via a fixing plate.

8. The gangue slope protection cofferdam according to claim 7, characterized in that: A connecting plate is provided on the inner side of the second brick, and the connecting plate is connected to the cylindrical rod on the first brick adjacent to the second brick.

9. The gangue slope protection cofferdam according to claim 8, characterized in that: Two adjacent connecting plates on the inner side of the second wall are connected by a connecting rod.