Fabricated factory enclosing wall

By adopting the socket connection technology and fully dry connection method of foundation and columns in the prefabricated fence, the problems of installation accuracy and difficulty in positioning of prefabricated columns are solved, efficient and convenient construction and installation are achieved, and the connection strength and Installation efficiency reduces cost and construction period.

CN221896392UActive Publication Date: 2024-10-25CENT SOUTHERN CHINA ELECTRIC POWER DESIGN INST CHINA POWER ENG CONSULTING GROUP CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420188581.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-26
Publication Date
2024-10-25
Estimated Expiration
2034-01-26

AI Technical Summary

Technical Problem

Existing prefabricated fences require high installation accuracy of prefabricated columns in UHV substation projects, and it is difficult to position and calibrate the foundation cup mouth, resulting in low installation efficiency and requiring a large amount of manual labor and machinery for positioning control.

Method used

The foundation and columns are prefabricated and connected through the load-bearing grooves and grouting grooves of the sockets. The foundation and columns are integrated using grouting sleeves and connecting steel bars, and the bending and shear resistance of the columns are increased through shear-resistant grooves and shear-resistant keys. performance, positioning steel bars are set to facilitate the installation and fixation of the mold, and full dry connection technology is adopted to reduce wet work on site.

Benefits of technology

It achieves convenient and efficient construction, improves installation accuracy and connection strength, reduces the degree and duration of on-site mechanized construction, and reduces costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221896392U_ABST
    Figure CN221896392U_ABST
Patent Text Reader

Abstract

A bearing groove and a grouting groove are formed in the top of a fence foundation, grouting sleeves are embedded in the bottoms of stand columns, the tops of the grouting sleeves are in mechanical threaded connection with longitudinal stressed steel bars in the stand columns, the bottoms of the grouting sleeves are flush with the bottom faces of the stand columns, and the grouting sleeves are used for being connected with reserved connecting steel bars at the top of the foundation. During installation, the stand columns are inserted into the bottoms of the bearing grooves, and the connecting steel bars are inserted into the grouting sleeves; after the bin sealing groove is filled with cement mortar for sealing, the grouting groove and the grouting sleeve are communicated through the stand column, and a sealed grouting space is formed. Grouting materials are injected into the grouting holes of the stand columns, the grouting grooves and the cavities of the grouting sleeves in the stand columns are filled with the grouting materials in sequence, and finally the grouting materials flow out along the grouting holes to connect the foundation and the stand columns into a whole. The enclosing wall stand columns, the ground beams, the wallboards, the top beams and the coping are connected in a prefabricated insertion mode. Construction is convenient and efficient, wet operation is avoided, scaffolds do not need to be erected, the mechanical construction degree is high, and installation precision is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of assembled fences, in particular to an assembled factory fence. Background Art

[0002] At present, prefabricated fences have been widely used in substation projects. Compared with traditional brickwork and cast-in-place frame fences, prefabricated fences are prefabricated in factories and assembled on site. They have the advantages of convenient and quick installation, shortening construction period, reducing the workload of on-site concrete formwork and pouring wet operations, and improving the image of safe and civilized construction on site.

[0003] Due to the high sound power level of the main transformer, high-voltage shunt reactor and other equipment in the UHV substation project, in order to meet the station boundary noise standard requirements, in noise-sensitive areas, the fence is generally raised to 5-6m as a noise reduction fence, and a sound barrier is added above the fence according to the noise reduction needs. The UHV substation fence structure has the characteristics of high height, large cross-section, and large column bottom bending moment. At present, some power projects have adopted conventional prefabricated fences to replace traditional cast-in-place concrete frame fences, realizing factory prefabrication, on-site assembly, convenient and fast installation, and shortening the construction period. However, conventional prefabricated fences still have the following problems: high installation accuracy requirements for prefabricated columns, difficult positioning and calibration of prefabricated columns in the foundation cup, requiring a lot of manpower and machinery for positioning control, and low installation efficiency. Utility Model Content

[0004] The purpose of the utility model is to provide an assembled factory enclosure to address the defects of the prior art.

[0005] In order to solve the above technical problems, the utility model provides an assembled factory fence, including a foundation and a column, both of which are prefabricated structures, a socket is opened at the top of the foundation, the socket includes a bearing groove and a grouting groove, the grouting groove is opened at the bottom of the bearing groove and is coaxially arranged with the bearing groove, connecting steel bars are pre-embedded in the foundation, the top of the connecting steel bars extend upward from the grouting groove, a grouting sleeve is pre-embedded at the bottom of the column, the bottom end of the grouting sleeve extends to the lower end surface of the column, the column is inserted into the bearing groove and supported at the bottom of the bearing groove, so that the connecting steel bars are inserted into the grouting sleeve and the grouting sleeve is connected with the grouting groove, the grouting sleeve is filled with grouting material to connect the foundation and the column as one, a sealing groove is set between the inner wall of the bearing groove and the column, and the sealing groove is filled with grouting material for closing the grouting groove.

[0006] Furthermore, the socket includes a shear groove, which is opened at the bottom of the grouting groove and arranged coaxially with the grouting groove. A shear key is arranged at the bottom of the column, and the shear key is inserted into the shear groove. A grouting space is arranged between the shear key and the inner wall and bottom of the shear groove, and the grouting space is connected to the grouting groove.

[0007] Furthermore, an upper extension tube and a lower extension tube are provided on the side wall of the grouting sleeve, one end of the upper extension tube and the lower extension tube are connected to the interior of the grouting sleeve, and the other end of the upper extension tube and the lower extension tube extend to the outer wall of the column, the upper extension tube and the lower extension tube are respectively close to the upper end and the lower end of the grouting sleeve, the lower extension tube is used for grouting, and the upper extension tube is used for grouting.

[0008] Furthermore, the upper end of the grouting sleeve is fixedly connected to the longitudinal steel bars embedded in the column.

[0009] Furthermore, positioning steel bars are embedded in the foundation, extending upward from the top of the foundation. The positioning steel bars are arranged outside the socket and are used to install a fixed mold to fix the column.

[0010] Furthermore, a plurality of grouting sleeves are evenly arranged around the outer circumference of the shear key.

[0011] Furthermore, it includes a ground beam and a wall panel, a first installation groove is vertically opened on both sides of the column, the ground beam and the wall panel are arranged between two adjacent columns, both ends of the ground beam and the wall panel are inserted into the first installation groove, both ends of the ground beam are supported on the foundation, and the wall panel is set on the ground beam.

[0012] Furthermore, the lower end of the ground beam is fixedly connected to the foundation through cement mortar.

[0013] Furthermore, it includes a pressure top and a top beam, the pressure top is detachably connected to the top of the column, the top beam is arranged on the top of the wall panel, the pressure top is pressed on one end of the top beam, second installation grooves are opened on both sides of the pressure top, and the two ends of the top beam are inserted into the second installation grooves.

[0014] Furthermore, the longitudinal steel bars embedded in the column extend upward out of the column and are threadedly connected with fixings, and the fixings are used to connect to the sound barrier on the top of the wall.

[0015] The beneficial effects of the utility model are:

[0016] 1. After the foundation and columns of the utility model are transported to the site, the columns can be inserted into the sockets of the foundation and then concrete can be injected into the sealing slot to seal the grouting slot to prevent the concrete in the grouting sleeve from flowing out. By injecting concrete into the grouting sleeve, the concrete flows into the grouting slot through the grouting sleeve. The concrete in the grouting slot connects the inner wall of the grouting slot and the column. The concrete in the grouting sleeve connects the grouting sleeve with the connecting steel bar, thereby connecting the foundation and the column as one. The assembled wall structure is convenient and efficient to construct, does not require wet work on site, does not require scaffolding, has a high degree of mechanized construction, and has high installation accuracy.

[0017] 2. The utility model can increase the bending and shearing resistance of the column by arranging the shear groove and the shear key, increase the connection strength between the column and the foundation, and improve the stability of the column and the integrity of the column and the foundation.

[0018] 3. The grouting sleeve of the utility model can be filled with concrete by arranging the upper extension pipe and the lower extension pipe, thereby preventing the occurrence of a weak strength area in the column.

[0019] 4. The utility model provides positioning steel bars, which can be used to install and fix the mold after the column is inserted into the socket of the foundation, thereby fixing the column during the grouting process.

[0020] 5. The ground beams, wall panels, top beams and top beams of the utility model as well as between them and the columns are all detachably connected, which is convenient for on-site construction and later maintenance and disassembly. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a schematic diagram of the structure of the utility model;

[0022] Figure 2 This is a schematic diagram of the connection structure between the foundation and the column of the utility model;

[0023] Figure 3 for Figure 2 Top view of the AA section;

[0024] Figure 4 It is a structural schematic diagram of the utility model when the column is installed and connected with the foundation;

[0025] Figure 5 for Figure 4 Top view of the middle BB section;

[0026] Figure 6 This is a schematic diagram of the structure of the grouting sleeve of the utility model;

[0027] Figure 7 This is a schematic diagram of the front elevation structure of the column of the utility model;

[0028] Figure 8 It is a schematic diagram of the side elevation structure of the column of the utility model;

[0029] Fig. 9 for Figure 7 Top view of the CC section;

[0030] Fig.10 for Figure 7 Top view of the middle DD section;

[0031] Fig.11 This is a schematic diagram of the ground beam connection structure of the utility model;

[0032] Fig.12 This is a schematic diagram of the front elevation structure of the ground beam of the utility model;

[0033] Fig.13 It is a top view of the ground beam of the utility model;

[0034] Fig.14 This is a schematic diagram of the connection structure between the wall panel and the column of the utility model;

[0035] Fig.15 It is a structural schematic diagram of the top pressure and top beam of the utility model.

[0036] Figure numerals: foundation 1; column 2; ground beam 3; wall panel 4; top 5; top beam 6; fixed mold 7; bearing groove 8; grouting groove 9; grouting sleeve 10; grouting material 11; shear groove 12; shear key 13; grouting space 14; sealing groove 15; connecting steel bar 16; longitudinal steel bar 17; positioning steel bar 18; positioning sleeve 19; first installation groove 20; second installation groove 21; fixing part 22; upper extension pipe 23; lower extension pipe 24; grouting hole 25; slurry outlet hole 26; cement mortar 27; angle steel 28. DETAILED DESCRIPTION

[0037] In order to make the technical problems, technical solutions and beneficial effects to be solved by the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0038] like Figure 1 As shown, this embodiment provides an assembled factory fence, including a foundation 1, columns 2, ground beams 3, wall panels 4, top pressure 5, and top beams 6. The foundation 1, columns 2, ground beams 3, wall panels 4, top pressure 5, and top beams 6 are all precast concrete structures.

[0039] like Figures 7 to 10 As shown, the column 2 is in the shape of a rectangular parallelepiped as a whole, and longitudinal steel bars 17, stirrups and grouting sleeves 10 are pre-embedded in the column 2. The longitudinal steel bars 17 and the grouting sleeves 10 are arranged along the length direction of the column 2. The grouting sleeves 10 are arranged near the lower end of the column 2. The upper end of the grouting sleeves 10 is connected to the longitudinal steel bars 17 by mechanical threads, and the lower end of the grouting sleeves 10 is flush with the lower end surface of the column 2. Figure 6As shown, an upper extension tube 23 and a lower extension tube 24 are integrally provided on the side wall of the grouting sleeve 10, and the upper extension tube 23 and the lower extension tube 24 are both perpendicular to the grouting sleeve 10, and the upper extension tube 23 and the lower extension tube 24 are respectively arranged close to the upper end and the lower end of the grouting sleeve 10, and the end of the upper extension tube 23 away from the grouting sleeve 10 is a grouting hole 26, and the end of the lower extension tube 24 away from the grouting sleeve 10 is a grouting hole 25.

[0040] First mounting grooves 20 for mounting the ground beam 3 and the wall panel 4 are provided on both sides of the column 2. The length direction of the first mounting groove 20 is parallel to the length direction of the column 2. The upper end of the first mounting groove 20 extends to the upper end surface of the column 2, and the lower end of the first mounting groove 20 extends to the upper end of the grouting sleeve 10.

[0041] A shear key 13 is provided at the bottom of the column 2. The cross section of the shear key 13 is semi-conical, the size of which matches the grouting groove and a grouting space 14 is reserved.

[0042] like Figure 2 , 3 As shown, the bottom of the foundation 1 is fixed on the ground, and a bearing groove 8 is provided at the top of the foundation 1. The cross section of the bearing groove 8 is larger than the cross section of the column 2. The column 2 can be inserted into the bearing groove 8, so that a sealing groove 15 is formed between the inner wall of the bearing groove 8 and the column 2. A grouting groove 9 is provided at the bottom of the bearing groove 8. The cross section of the grouting groove 9 is smaller than the cross section of the column 2, so that after the column 2 is inserted into the bearing groove 8, the grouting groove 9 is closed, and the lower end of the grouting sleeve 10 is connected to the grouting groove 9. Connecting steel bars 16 are pre-embedded in the foundation 1, and one end of the connecting steel bar 16 extends upward from the bottom of the grouting groove 9. The position of the connecting steel bar 16 corresponds to the grouting sleeve 10, so that after the column 2 is inserted into the bearing groove 8, the connecting steel bar 16 is inserted into the grouting sleeve 10. The cross section of the grouting sleeve 10 is larger than the cross section of the connecting steel bar 16, so that the grouting material 11 poured from the grouting hole 25 can smoothly flow into the grouting groove 9, as shown in FIG. Figure 6 shown.

[0043] A shear groove 12 is provided at the bottom of the grouting groove 9, and the cross section of the shear groove 12 is semi-conical, and the cross section of the shear groove 12 is larger than the shear key 13, so that after the column 2 is inserted into the bearing groove 8, the shear key 13 is inserted into the shear groove 12, and a grouting space 14 is formed between the inner wall of the shear groove 12 and the shear key 13, and the grouting space 14 is connected to the grouting groove 9, so that the grouting material 11 poured from the grouting hole 25 can smoothly flow into the grouting space 14, thereby fixing the column 2 and the foundation 1, and improving the connection strength between the column 2 and the foundation 1. In this embodiment, the grouting material 11 is a fine stone concrete grouting material.

[0044] The load-bearing groove 8, grouting groove 9 and shear groove 12 are all arranged coaxially with the column 2. The depths of the load-bearing groove 8, grouting groove 9 and shear groove 12 are designed according to the weight of the column 2 and the load-bearing capacity of the column 2. The greater the depths of the load-bearing groove 8 and the grouting groove 9, the more stable the column 2.

[0045] like Figure 4 , 5 As shown, four positioning sleeves 19 are embedded in the foundation 1, and the upper ends of the positioning sleeves 19 extend to the upper end surface of the foundation 1. The positioning sleeves 19 are threadedly connected with positioning steel bars 18, and one end of the positioning steel bars 18 extends upward from the foundation 1. The positioning steel bars 18 can be connected to a fixing mold 7 by bolts, so as to fix the column 2 inserted into the foundation 1. The fixing mold 7 is connected to the positioning steel bars 18 through waist-shaped holes, and the length direction of the waist-shaped holes is parallel to the wall panel 4. Even if there is a deviation between the grouting sleeve 10 and the axis of the connecting steel bars 16, the left and right positions of the fixing mold 7 can be adjusted to ensure that the fixing mold 7 clamps the column 2.

[0046] like Figures 11 to 13 As shown, the ground beam 3 is in the shape of a long strip, and protrusions that can be inserted into the first installation groove 20 are arranged at the left and right ends of the ground beam 3. The lower end of the ground beam 3 is fixedly connected to the foundation 1 through cast-in-place cement mortar 27.

[0047] like Figure 1 , 14 As shown, the wall panel 4 is in the shape of a long strip, and a plurality of wall panels 4 are horizontally arranged between two columns 2 , with both ends of the wall panel 4 inserted into the first installation groove 20 .

[0048] like Fig.15 As shown, the capping 5 is square and is sleeved on the top of the column 2. The longitudinal reinforcement 17 embedded in the column 2 extends upward out of the column 2 and is threadedly connected with a fixing member 22. The fixing member 22 is a column top anchor bolt, which is used to connect the sound barrier capping 5 at the top of the wall. The two ends of the capping 5 are provided with a second installation groove 21, and the two ends of the top beam 6 are inserted into the second installation groove 21 of the capping 5. In this embodiment, the two ends of the uppermost wall panel 4 are fixedly connected to the column 2 by angle steel 28 to improve the integrity of the structure.

[0049] The construction method of the prefabricated factory wall includes:

[0050] S1, fix the foundation 1 on the ground, align the grouting sleeve 10 of the column 2 with the connecting steel bar 16, and then insert the shear key 13 of the column 2 into the shear groove 12;

[0051] S2, installing fixed molds 7 on both sides of the column 2, inserting the positioning steel bars 18 into the waist-shaped holes of the fixed molds 7 and fixing the fixed molds 7 by bolts, so that the two fixed molds 7 clamp the column 2 in place through the waist-shaped holes of the fixed molds 7;

[0052] S3, injecting concrete slurry into the sealing groove 15, so that the shear groove 12 and the grouting space 14 form a continuous closed space, and pouring concrete slurry into the grouting hole 25 of the grouting sleeve 10 until the concrete slurry flows out of the grouting hole 26;

[0053] S4, after the grouting material reaches the designed strength, the fixed mold 7 is disassembled;

[0054] S5. Apply cement mortar 27 on the foundation 1, insert the two ends of the ground beam 3 into the first installation groove 20 of the column 2, and fix the bottom of the ground beam 3 to the foundation 1 through the cement mortar 27;

[0055] S6, inserting the two ends of the wall panel 4 into the first installation groove 20 of the column 2, and placing the lowermost wall panel 4 on the ground beam 3;

[0056] S7. Insert the two ends of the top beam 6 into the first installation groove 20 of the column 2. The top beam 6 and the column 2 can be further fixedly connected by the angle steel 28; install the pressure top 5 on the top of the column 2 so that the top beam 6 is inserted into the second installation groove 21 of the pressure top 5 and fixed.

[0057] The prefabricated factory fence has the following advantages:

[0058] Technical aspects: The column 2 and the foundation 1 are connected by the grouting sleeve 10, and the sealing process of the column 2 and the foundation 1 is innovatively proposed to achieve the rapid installation of the column 2. The full dry connection technology is adopted, and the first installation groove 20 is reserved on the column 2. The ground beam 3, the wall panel 4, the top 5, the top beam 6 and the column 2 are all connected by layer plug-in, realizing the full dry connection of the assembled fence, which greatly reduces the wet work on site.

[0059] Cost: According to calculations, this solution saves 12% of the overall cost compared to conventional prefabricated wall solutions. This is mainly due to the grouting sleeve 10 connection solution, which makes it easier to install the column 2, saving labor costs and machine shifts, and optimizing costs from the construction and installation levels.

[0060] In terms of construction period: According to calculations, compared with traditional cast-in-place walls, the use of fully dry connections brings the advantage of convenient installation, saving more than 48% of the construction period; compared with conventional prefabricated walls, the construction period is saved by 20%. This solution improves the installation efficiency of column 2; the use of fully dry connections eliminates the need for wet work on site, improving the efficiency of mechanized construction.

[0061] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.

Claims

1. An assembled factory wall, characterized by: The invention comprises a foundation (1) and a column (2), wherein the foundation (1) and the column (2) are both prefabricated structures, a socket is provided at the top of the foundation (1), the socket comprises a bearing groove (8) and a grouting groove (9), the grouting groove (9) is provided at the bottom of the bearing groove (8) and is arranged coaxially with the bearing groove (8), a connecting steel bar (16) is pre-embedded in the foundation (1), the top end of the connecting steel bar (16) extends upward from the grouting groove (9), a grouting sleeve (10) is pre-embedded at the bottom of the column (2), the bottom end of the grouting sleeve (10) extends upward from the grouting groove (9), and the grouting sleeve (10) is pre-embedded at the bottom of the column (2). The support (14) extends to the lower end surface of the column (2), the column (2) is inserted into the bearing groove (8) and supported on the bottom of the bearing groove (8), so that the connecting steel bar (16) is inserted into the grouting sleeve (10) and the grouting sleeve (10) is connected to the grouting groove (9), the grouting sleeve (10) is filled with grouting material (11) to connect the foundation (1) and the column (2) as a whole, and a sealing groove (15) is provided between the inner wall of the bearing groove (8) and the column (2), and the sealing groove (15) is filled with grouting material (11) for closing the grouting groove (9).

2. The assembled factory enclosure according to claim 1 is characterized by: The socket includes a shear groove (12), the shear groove (12) is provided at the bottom of the grouting groove (9) and is arranged coaxially with the grouting groove (9), a shear key (13) is provided at the bottom of the column (2), the shear key (13) is inserted into the shear groove (12), a grouting space (14) is provided between the shear key (13) and the inner wall and bottom of the shear groove (12), and the grouting space (14) is communicated with the grouting groove (9).

3. The assembled factory enclosure according to claim 2 is characterized by: An upper extension tube (23) and a lower extension tube (24) are provided on the side wall of the grouting sleeve (10); one end of the upper extension tube (23) and the lower extension tube (24) are both connected to the interior of the grouting sleeve (10); the other ends of the upper extension tube (23) and the lower extension tube (24) extend to the outer wall of the column (2); the upper extension tube (23) and the lower extension tube (24) are respectively close to the upper end and the lower end of the grouting sleeve (10); the lower extension tube (24) is used for grouting, and the upper extension tube (23) is used for grouting.

4. The assembled factory enclosure according to claim 3 is characterized by: The upper end of the grouting sleeve (10) is fixedly connected to the longitudinal steel bars (17) pre-buried in the column (2).

5. The assembled factory enclosure according to claim 1 is characterized by: Positioning steel bars (18) are pre-buried in the foundation (1), and the positioning steel bars (18) extend upward from the top of the foundation (1). The positioning steel bars (18) are arranged outside the socket and are used to install a fixed mold (7) so as to fix the column (2).

6. The assembled factory enclosure according to claim 2 is characterized by: A plurality of grouting sleeves (10) are evenly arranged around the outer circumference of the shear key (13).

7. The assembled factory enclosure according to any one of claims 1 to 6, characterized in that: The invention comprises a ground beam (3) and a wall panel (4), wherein first installation grooves (20) are vertically provided on both sides of the column (2), the ground beam (3) and the wall panel (4) are arranged between two adjacent columns (2), both ends of the ground beam (3) and the wall panel (4) are inserted into the first installation grooves (20), both ends of the ground beam (3) are supported on a foundation (1), and the wall panel (4) is arranged on the ground beam (3).

8. The assembled factory enclosure according to claim 7 is characterized by: The lower end of the ground beam (3) is fixedly connected to the foundation (1) via cement mortar (27).

9. The assembled factory enclosure according to claim 7 is characterized by: The invention comprises a pressure top (5) and a top beam (6), wherein the pressure top (5) is detachably connected to the top of the column (2), the top beam (6) is arranged on the top of the wall panel (4), the pressure top (5) is pressed on one end of the top beam (6), second installation grooves (21) are provided on both sides of the pressure top (5), and the two ends of the top beam (6) are inserted into the second installation grooves (21).

10. The assembled factory enclosure according to claim 7, characterized in that: The longitudinal steel bars (17) embedded in the column (2) extend upwards out of the column (2) and are threadedly connected to a fixing member (22), wherein the fixing member (22) is used to connect to the sound barrier at the top of the wall.