Anti-blocking device for steam purging ammonia hydrogen sulfate air pre-heater
By using a combination of furnace return air preheating and high-pressure steam purging in the air preheater, the clogging problem caused by the deposition of ammonia hydrogen sulfate is solved, achieving more efficient heat utilization and more thorough cleaning, and reducing energy consumption. and system resistance to ensure the continuous and safe operation of the air preheater.
Patent Information
- Application Number
- CN202323446785.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-18
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2033-12-18
AI Technical Summary
The rotary air preheater in the thermal power plant is clogged due to the deposition of ammonia hydrogen sulfate, which increases the operating resistance and power consumption, affecting the continuous and safe operation of the generating unit.
A steam-purged hydrogen sulfate ammonia air preheater anti-blocking device is designed, which uses furnace return air to preheat the steam-purged regenerative elements in the bin. Combined with high-pressure steam cleaning, the partition plates are arranged asymmetrically to reduce system resistance, and The air preheater resistance is overcome by the furnace return air booster fan.
Effectively preheats the ammonia hydrogen sulfate in the steam purge bin, reduces the furnace return air flow and steam purge volume, improves heat utilization, makes cleaning cleaner, reduces energy consumption and system resistance, and ensures the continuous operation of the air preheater run.
Smart Images

Figure CN221897819U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of air preheaters, in particular to a steam-purge ammonium bisulfate air preheater anti-blocking device. Background Art
[0002] The rotary air preheater is also referred to as the air preheater. It is an important auxiliary machine of the thermal power plant. It is a heat exchange device that uses the heat storage element installed on the rotor to absorb heat on the flue gas side and release heat on the air side. The thermal power plant is a coal-fired power plant. Coal contains a certain amount of sulfur. After combustion, in addition to a large amount of nitrogen oxides (NOX), it also produces some sulfur dioxide (SO2) and sulfur trioxide (SO3) in the flue gas. In recent years, the thermal power station has generally added a selective catalytic reduction flue gas denitrification (SCR) device upstream of the air preheater, and ammonia (NH3) is injected. Under the action of the catalyst, the nitrogen oxides (NOX) in the flue gas are reduced to pollution-free nitrogen (N2) and water (H2O). However, the vanadium in the denitrification catalyst will promote the oxidation of sulfur dioxide (SO2) in the flue gas to sulfur trioxide (SO3), resulting in an increase in sulfur trioxide (SO3). The concentration of sulfur trioxide (SO3) at the inlet of the air preheater can reach 35-55μL / L. Ammonia (NH3) needs to be sprayed during the operation of the selective catalytic reduction flue gas denitrification device. The unreacted ammonia (NH3) during operation will inevitably cause ammonia (NH3) to escape. The escaped ammonia (NH3) reacts with sulfur trioxide (SO3) and water (H2O) in the flue gas to generate ammonium bisulfate (NH4HSO4), which will flow with the flue gas in the form of aerosol. Ammonium bisulfate (NH4HSO4) will become a highly viscous liquid in the range of 147-205℃, and will be deposited in the heat storage element at the cold end of the air preheater within this temperature range, adhere to the fly ash in the flue gas, and cause the air preheater to be blocked. This will increase the operating resistance of the air preheater, increase the power consumption of the fan, and waste electricity. When the blockage is serious, the machine has to be shut down for high-pressure water flushing, which affects the continuous and safe operation of the generator set.
[0003] Therefore, there is an urgent need for a steam-purged ammonium bisulfate air preheater anti-blocking device to solve the above problems. Utility Model Content
[0004] The utility model aims to provide a steam-purged ammonium bisulfate air preheater anti-blocking device, which can effectively solve the problems in the background technology.
[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0006] A steam-purged ammonium bisulfate air preheater anti-blocking device comprises an air preheater, wherein the air preheater is divided into a flue gas bin, a secondary air heating bin and a primary air heating bin, a partition plate is fixedly installed at the bottom of the secondary air heating bin, and a steam purge bin is separated from the bottom of the secondary air heating bin by the partition plate, a steam purge device is installed at the bottom of the steam purge bin, and the steam source of the steam purge device refers to the steam of the air preheater soot blower mother pipe, that is, the steam purge device is connected to a steam purge device connecting pipe, and the steam purge device connecting pipe is connected to the air preheater soot blower steam mother pipe, the lower end of the secondary air heating bin is fixedly connected to a cold secondary air duct, and the upper end of the secondary air heating bin is fixedly connected to a hot secondary air Pipe, the hot secondary air duct is connected to the furnace secondary air box, the furnace secondary air box is arranged in the water-cooled wall burner area, a furnace return air duct is connected between the outer side of the furnace secondary air box and the steam purge bin, the furnace return air duct is fixedly connected to the front valve at one end away from the furnace secondary air box, a furnace return air booster fan is arranged at one end of the front valve, the pressure head of the fan is only used to overcome the air preheater resistance, the front valve and the furnace return air booster fan are connected by a pipeline, the other end of the furnace return air booster fan is provided with a rear valve, the rear valve and the furnace return air booster fan and the steam purge bin are respectively connected by pipelines, collectively referred to as furnace return air duct.
[0007] As a further optimization solution of the present invention, the partition plate is not arranged vertically symmetrically, that is, the partition plate is separately installed at the bottom entrance of the secondary air heating bin.
[0008] As a further optimization scheme of the utility model, the secondary air heating bin and the steam purge bin share the same chamber, the inlet is divided into a cold secondary air duct inlet and a furnace return air duct inlet, and the outlets share a hot secondary air duct outlet.
[0009] As a further optimization scheme of the utility model, the furnace return air booster fan arranged on the furnace return air duct, the pressure head of the furnace return air booster fan is only used to overcome the resistance of the air preheater.
[0010] As a further optimization solution of the utility model, the steam blower is arranged at the bottom of the steam blowing bin and blows along the flow direction of the furnace return air.
[0011] Beneficial Effects
[0012] Compared with the prior art, the utility model has the following beneficial effects:
[0013] 1. The utility model discloses a steam-purged ammonium bisulfate air preheater anti-blocking device, which uses furnace return air to preheat and decompose ammonium bisulfate. The furnace return air absorbs radiation heat at the furnace water-cooled wall and has a higher temperature than hot primary air and hot secondary air. It uses less air flow and reduces the power consumption of the furnace return air booster fan.
[0014] 2. The utility model describes a steam-purged ammonium bisulfate air preheater anti-blocking device, which, by setting a smaller steam purge bin, arranges the steam purge bin in the secondary air bin of the original air preheater away from the primary air side, where the heat storage element has just completed the heat absorption process and the wall temperature of the heat storage element is the highest, which can reduce the furnace return air flow and steam purge volume required for preheating, reduce energy consumption, and have a high heat utilization rate.
[0015] 3. The steam-purged ammonium bisulfate air preheater anti-blocking device described in the utility model isolates the furnace return air and the cold secondary air by setting a non-vertically asymmetrical single partition plate. The partition plate has a simple structure, does not occupy the total flow area of the secondary air bin, and does not increase the system resistance. Compared with other fan-shaped plate division schemes, it saves 4.34% of the secondary air bin flow area (the center angle of the minimum fan-shaped plate is 5°).
[0016] 4. The utility model describes a steam-purged ammonia bisulfate air preheater anti-blocking device, which utilizes the furnace return air to preheat the heat storage element in the steam purge bin. It does not extract hot primary air for heating, and does not divert the primary air volume, thereby ensuring the full-load air volume requirement of the primary air machine for powder making, and is more adaptable to units with insufficient primary air margin.
[0017] 5. The utility model discloses a steam-purged ammonium bisulfate air preheater anti-blocking device, which is provided with a steam purger. In the ammonium bisulfate heat gasification decomposition zone, high-pressure steam is used to purge and remove the ammonium bisulfate. The ammonium bisulfate is cleaned more thoroughly and the air preheater anti-blocking effect is better. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the principle flow of the utility model;
[0019] Figure 2 It is a schematic diagram of the arrangement of the steam purge device of the utility model;
[0020] Figure 3 It is a schematic diagram of the bottom compartment of the air preheater of the utility model.
[0021] In the figure: 1. Flue gas bin; 2. Steam purge bin; 3. Partition plate; 4. Secondary air heating bin; 5. Primary air heating bin; 6. Furnace return air duct; 7. Furnace return air booster fan; 8. Front valve; 9. Rear valve; 10. Cold secondary air duct; 11. Hot secondary air duct; 12. Air preheater; 13. Steam purge; 14. Furnace secondary air box; 15. Steam purge connecting pipe; 16. Cold end heat storage element; 17. Furnace. DETAILED DESCRIPTION
[0022] like Figure 1-Figure 3As shown, the utility model provides a steam-purged ammonium bisulfate air preheater anti-blocking device, including an air preheater 12, the air preheater 12 is divided into a flue gas bin 1, a secondary air heating bin 4 and a primary air heating bin 5, a partition plate 3 is fixedly installed at the bottom of the secondary air heating bin 4, the bottom of the secondary air heating bin 4 is separated into a steam purge bin 2 by the partition plate 3, a steam purge device 13 is installed at the bottom of the steam purge bin 2, the steam source of the steam purge device 13 refers to the steam of the soot blower mother pipe of the air preheater 12, the steam purge device 13 is connected to a steam purge connecting pipe 15, the steam purge connecting pipe 15 is connected to the steam mother pipe of the soot blower of the air preheater 12, the lower end of the secondary air heating bin 4 is fixedly connected to a cold secondary air duct 10, the upper end of the secondary air heating bin 4 is fixedly connected to There is a hot secondary air duct 11, which is connected to the furnace secondary air box 14 and sent into the furnace 17 to assist combustion. The outer side of the furnace secondary air box 14 is connected to the furnace return air duct 6, and the end of the furnace return air duct 6 away from the furnace secondary air box 14 is fixedly connected to the front valve 8, and a furnace return air booster fan 7 is arranged at one end of the front valve 8. The front valve 8 and the furnace return air booster fan 7 are connected by a pipeline, and the other end of the furnace return air booster fan 7 is provided with a rear valve 9. The rear valve 9 is connected to the furnace return air booster fan 7 and the air preheater 12 located below the steam purge bin 2 through pipelines respectively. This connecting pipeline is collectively referred to as the furnace return air duct 6, and the front valve 8 and the rear valve 9 are installed before and after the furnace return air booster fan 7 to facilitate the isolation of the fan for maintenance.
[0023] The partition plate 3 is not arranged symmetrically up and down, that is, the partition plate 3 is installed alone at the bottom entrance of the secondary air heating bin 4. The secondary air heating bin 4 and the steam purge bin 2 share a bin chamber. The entrance is divided into a cold secondary air duct 10 entrance and a furnace return air duct 6 entrance, and the outlet shares a hot secondary air duct 11 outlet.
[0024] It should be noted that the utility model is a steam-purged ammonium bisulfate air preheater anti-blocking device. When the air preheater 12 is running and rotating, the rotor sequentially absorbs heat from the smoke bin 1 and transfers to the steam purge bin 2 to release heat, then transfers to the secondary air heating bin 4 to release heat, then transfers to the primary air heating bin 5 to release heat, and finally transfers to the smoke bin 1 to absorb heat, completing a heat absorption and release cycle;
[0025] The process of furnace return air is as follows: a small portion of furnace return air is drawn out from the outside of the furnace secondary wind box 14, introduced into the air preheater 12 through the furnace return air duct 6 and enters the bottom of the steam purge bin 2. After releasing heat to the cold end heat storage element 16, the temperature of the cold end heat storage element is increased, and the ammonium bisulfate attached to it is gasified and decomposed, and then continues to flow into the upper hot end heat storage element to absorb heat and then flow out, mixed with the hot secondary air flowing out of the hot end of the secondary air heating bin 4, and flows out through the hot secondary air duct 11 at the outlet of the air preheater 12 into the furnace 17 for combustion. In order for the furnace return air to complete this cycle, it is necessary to overcome the resistance of the heat storage element of the air preheater 12, which is generally about 1000Pa. Therefore, a furnace return air booster fan 7 is added to the furnace return air duct 6. The pressure head of the furnace return air booster fan 7 is only used to overcome the resistance of the air preheater, so as to overcome this resistance and complete the cycle of the furnace return air. After pressurization, the furnace return air is basically the same as the pressure of the cold secondary air. Therefore, after the furnace return air duct 6 and the cold secondary air 10 are separated by the partition plate 3 in the secondary air heating chamber 4, there is basically no pressure difference between the two, and there is no air leakage. Therefore, the fan-shaped plate structure is not used to reduce the occupied air duct area.
[0026] This solution uses furnace return air as the heat source for preheating the steam purge bin. A more convenient and flexible heat source and interface position can also be selected based on actual site conditions.
[0027] The steam sweeper 13 is arranged at the bottom of the steam sweeping bin, and the steam flow direction of the nozzle is consistent with the return air flow direction of the furnace. The steam used is connected to the main pipe of the air preheater soot blower by the steam sweeper connecting pipe 15. The ammonium bisulfate pre-decomposed by the furnace return air cannot be completely cleaned up by the furnace return air, and most of it still remains on the surface of the heat storage element. After the steam sweeper is put into operation, the high-temperature and high-pressure steam sprayed out sweeps the ammonium bisulfate remaining attached to the surface of the cold end heat storage element 16, and is taken away with the furnace return air, completely removing the ammonium bisulfate. The steam sweeper is intermittently operated, and the operating time is adjusted according to the air preheater pressure difference.
[0028] The above shows and describes the basic principle and main features of the utility model and the advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.
Claims
1. A steam-purged ammonium bisulfate air preheater anti-blocking device, comprising an air preheater (12), wherein the air preheater (12) is divided into a flue gas bin (1), a secondary air heating bin (4) and a primary air heating bin (5), characterized in that: A partition plate (3) is fixedly installed at the bottom of the secondary air heating bin (4), and a steam purge bin (2) is separated from the bottom of the secondary air heating bin (4) by the partition plate (3). A steam purge device (13) is installed at the bottom of the steam purge bin (2), and the steam purge device (13) is connected to a steam purge device connecting pipe (15). A cold secondary air duct (10) is fixedly connected to the lower end of the secondary air heating bin (4), and a hot secondary air duct (11) is fixedly connected to the upper end of the secondary air heating bin (4). The hot secondary air duct (11) is connected to a furnace secondary air box (14). A furnace return air duct (6) is connected to the outside of the furnace secondary air box (14); one end of the furnace return air duct (6) away from the furnace secondary air box (14) is fixedly connected to a front valve (8); one end of the front valve (8) is provided with a furnace return air booster fan (7); the front valve (8) and the furnace return air booster fan (7) are connected via a pipeline; the other end of the furnace return air booster fan (7) is provided with a rear valve (9); the rear valve (9) and the furnace return air booster fan (7) and the steam purge bin (2) are respectively connected via pipelines, and are collectively referred to as a furnace return air duct (6).
2. The steam-purged ammonium bisulfate air preheater anti-blocking device according to claim 1 is characterized in that: The heating air for the steam purge bin (2) is taken from the secondary air box of the furnace.
3. The steam-purged ammonium bisulfate air preheater anti-blocking device according to claim 1 is characterized in that: The partition plate (3) is not arranged vertically symmetrically, that is, the partition plate (3) is installed alone at the lower entrance of the secondary air heating bin (4).
4. The steam-purged ammonium bisulfate air preheater anti-blocking device according to claim 1 is characterized in that: The secondary air heating chamber (4) and the steam purge chamber (2) share the same chamber, the inlet is divided into a cold secondary air duct (10) inlet and a furnace return air duct (6) inlet, and the outlet shares a hot secondary air duct (11) outlet.
5. The steam-purged ammonium bisulfate air preheater anti-blocking device according to claim 1 is characterized in that: The furnace return air booster fan (7) is arranged on the furnace return air duct (6), and the pressure head of the furnace return air booster fan (7) is only used to overcome the resistance of the air preheater.
6. The steam-purged ammonium bisulfate air preheater anti-blocking device according to claim 1, characterized in that: The steam purge device (13) is arranged in the ammonium bisulfate heat gasification decomposition zone, i.e., the cold end bottom of the steam purge bin (2), and the steam is blown upwards in the same direction as the furnace return air, i.e., the heating air.