Ore sorting device and ore sorting machine thereof

By designing detachable blowing components and ejection components in the ore sorting equipment, and arranging them in a stepped manner along the ore throwing path, the limitations of the existing equipment in sorting ores of different particle sizes are solved, and flexible adjustment and high efficiency are achieved. Sorting reduces costs and resource waste.

CN221908515UActive Publication Date: 2024-10-29BEIJING HONEST TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420164799.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-23
Publication Date
2024-10-29
Estimated Expiration
2034-01-23

AI Technical Summary

Technical Problem

When existing ore sorting equipment handles ores of different particle sizes, the ejection device and the injection device have their own limitations, resulting in high equipment costs and inability to adapt to different mining areas and screening conditions. Loading two devices at the same time can easily cause a waste of resources.

Method used

Design an ore sorting device, including a detachable blowing component and an ejection component, arranged in a stepped manner along the ore throwing path. By adjusting the gasket set and valve plate component, the components can be flexibly adjusted and independently installed to adapt to Different working conditions.

Benefits of technology

It reduces production and maintenance costs, improves sorting efficiency, avoids waste of resources, adapts to the needs of ore sorting of different particle sizes, and reduces equipment costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221908515U_ABST
    Figure CN221908515U_ABST
Patent Text Reader

Abstract

The present disclosure discloses an ore sorting apparatus and an ore sorting machine thereof, the ore sorting apparatus including: a frame including a plurality of mounting portions arranged in a stepped shape along an ore throwing path; the blowing assembly is detachably mounted on one of the mounting parts, the blowing assembly comprises an air injection part, and the air injection part is used for blowing airflow to the target ore so as to move the target ore out of the multiple ores; and the pushing assembly is detachably installed on the other one of the multiple installation parts, the pushing assembly comprises a pushing piece, and the pushing piece is used for pushing the target ore so as to move the target ore out of the multiple pieces of ore. According to the ore sorting device disclosed by the invention, the execution part is modularly designed, and the corresponding rack layout is arranged, so that the sorting device can adapt to different working conditions to quickly and conveniently carry out assembly adjustment, the production and maintenance cost is reduced, and meanwhile, the sorting efficiency is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure generally relates to the field of mining technology. More specifically, the present disclosure relates to an ore sorting device and an ore sorting machine thereof. Background Art

[0002] In the field of mining technology, ore sorting equipment is one of the key equipment, which classifies ores according to their composition. A common method is to predetermine the target ore that meets the sorting index among multiple ores on the conveying device by means of image recognition, and then drive the sorting execution component to perform sorting operations on the determined target ore. Common sorting execution components may include, for example, a push-up device or a blowing device. Among them, the push-up device and the blowing device each have their limitations. The push-up device has a large thrust and can sort large-particle ore, but its operation frequency is low, and the lower limit of the particle size of the sorted particles is high, which is not suitable for sorting smaller particles (for example, particle size below 80mm). The blowing device has a high operation frequency, but a small thrust, and is not suitable for sorting large-particle ore (for example, particle size above 300mm). To solve the above limitations, some sorting equipment is equipped with two kinds of executive components for use together. However, in actual applications, the particle size of the ore varies greatly depending on the conditions of the mining area itself and the ore screening conditions. When the ore particle size is generally large or small, equipping two kinds of executive components at the same time is likely to cause waste of resources and increase equipment costs.

[0003] In view of this, there is an urgent need to provide an ore sorting device that can switch and select the execution device according to the working conditions to reduce the equipment cost. Utility Model Content

[0004] In order to at least solve one or more of the technical problems mentioned above, the present disclosure proposes an ore sorting device and an ore sorting machine thereof in multiple aspects.

[0005] In a first aspect, the present disclosure provides an ore sorting device, which includes: a frame, which includes a plurality of mounting parts arranged in a stepped manner along an ore throwing path; a blowing assembly, which is detachably mounted on one of the plurality of mounting parts, the blowing assembly includes a jet part, the jet part is used to blow an airflow to a target ore to remove it from a plurality of ores; and a pushing assembly, which is detachably mounted on another of the plurality of mounting parts, the pushing assembly includes a pushing member, the pushing member is used to push the target ore to remove it from a plurality of ores.

[0006] In some embodiments, at least one spray assembly mounting member is provided on both lateral sides of the spray assembly, and the first mounting portion among the multiple mounting portions includes two side walls, and mounting holes corresponding to the spray assembly mounting members are respectively opened on the opposite sides of the two side walls to install the spray assembly mounting member on the corresponding side walls.

[0007] In some embodiments, the second mounting portion among the multiple mounting portions includes a push-pull assembly mounting piece, the push-pull assembly mounting piece includes a push-pull assembly mounting plate arranged with the front side facing the push-pull assembly and a loading and unloading groove formed on the back side of the push-pull assembly mounting plate, the loading and unloading groove is open to the side of the push-pull assembly mounting piece, the push-pull assembly mounting plate includes a fixing hole that passes through its plate surface vertically, and the fixing hole is connected to the loading and unloading groove.

[0008] In some embodiments, an adjusting shim group is also included. The adjusting shim group includes a plurality of shims of various thicknesses. The adjusting shim group is vertically disposed between the jet part of the jet assembly and the jet assembly mounting member to adjust the height of the jet part.

[0009] In some embodiments, the blowing assembly is arranged before the pushing assembly along the ore throwing path, and a leak-proof assembly for shielding the gap between the blowing assembly and the pushing assembly is fixedly mounted on the blowing assembly.

[0010] In some embodiments, a valve plate assembly is further included, the valve plate assembly includes a valve plate box and a valve plate unit disposed in the valve plate box, the valve plate box includes a valve plate box inclined surface parallel to the moving direction of the ore at the corresponding position of the valve plate box.

[0011] In some embodiments, the blowing assembly, the pushing assembly and the valve plate assembly are arranged in sequence in a stepped manner along the ore throwing path.

[0012] In some embodiments, the valve plate box further comprises a valve plate box cover which is laterally divided into a plurality of sections, and an upper surface of the valve plate box cover is defined as a valve plate box inclined surface.

[0013] In some embodiments, the bottom of the valve plate box is provided with an inclined base.

[0014] In a second aspect, the present disclosure provides an ore sorting machine comprising the ore sorting device described in accordance with the first aspect and its embodiments.

[0015] Through the ore sorting device and ore sorting machine provided above, the disclosed embodiment can quickly and conveniently adjust the components to adapt to different working conditions by setting a plurality of mounting parts arranged in a stepped manner on the frame, and detachably mounting the blowing assembly and the pushing assembly on the mounting parts, thereby reducing production and maintenance costs while ensuring sorting efficiency. Further, in some embodiments, by arranging the blowing assembly laterally on the side wall of the frame, the installation part of the blowing assembly can be prevented from being affected by ore debris and dust. Furthermore, in some embodiments, by providing a pushing member mounting plate and a loading and unloading groove, the pushing assembly can be easily disassembled and assembled, saving maintenance costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] By reading the detailed description below with reference to the accompanying drawings, the above and other objects, features and advantages of the exemplary embodiments of the present disclosure will become readily understood. In the accompanying drawings, several embodiments of the present disclosure are shown in an exemplary and non-limiting manner, and the same or corresponding reference numerals represent the same or corresponding parts, wherein:

[0017] Figure 1 A side cross-sectional view showing an ore sorting apparatus according to some embodiments of the present disclosure in use;

[0018] Figure 2 A perspective schematic diagram showing an ore sorting device according to some embodiments of the present disclosure;

[0019] Figure 3 A perspective schematic diagram showing a blowing assembly of an ore sorting device according to some embodiments of the present disclosure;

[0020] Figure 4 A three-dimensional schematic diagram showing an adjustment gasket group of an ore sorting device according to some embodiments of the present disclosure is shown;

[0021] Figure 5 A perspective schematic diagram showing a valve plate assembly of an ore sorting device according to some embodiments of the present disclosure;

[0022] Figure 6 A perspective schematic diagram showing a cable shield of an ore sorting device according to some embodiments of the present disclosure;

[0023] Figure 7 An exploded schematic diagram showing an ore sorting device according to some embodiments of the present disclosure;

[0024] Figure 8 A side cross-sectional view showing an ore sorting device according to some embodiments of the present disclosure in a state where a push-up assembly is provided separately;

[0025] Fig. 9 A side cross-sectional view showing an ore sorting device according to some embodiments of the present disclosure in a state where a blowing assembly is provided separately;

[0026] Fig.10 A schematic diagram of an ore sorting machine according to some embodiments of the present disclosure is shown. DETAILED DESCRIPTION

[0027] The following will be combined with the drawings in the embodiments of the present disclosure to clearly and completely describe the technical solutions in the embodiments of the present disclosure. Obviously, the described embodiments are part of the embodiments of the present disclosure, not all of the embodiments. Based on the embodiments in the present disclosure, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present disclosure.

[0028] It should be understood that the terms "include" and "comprising" used in the specification and claims of the present disclosure indicate the presence of described features, integers, steps, operations, elements and / or components, but do not exclude the presence or addition of one or more other features, integers, steps, operations, elements, components and / or collections thereof.

[0029] It should also be understood that the terms used in this disclosure are only for the purpose of describing specific embodiments and are not intended to limit the disclosure. As used in this disclosure and claims, the singular forms of "a", "an", and "the" are intended to include the plural forms unless the context clearly indicates otherwise. It should also be further understood that the term "and / or" used in this disclosure and claims refers to any combination of one or more of the associated listed items and all possible combinations, including these combinations.

[0030] As used in this specification and claims, the term "if" may be interpreted as "when" or "upon" or "in response to determining" or "in response to detecting," depending on the context. Similarly, the phrase "if it is determined" or "if [described condition or event] is detected" may be interpreted as meaning "upon determination" or "in response to determining" or "upon detection of [described condition or event]" or "in response to detecting [described condition or event]," depending on the context.

[0031] The specific implementation of the present disclosure is described in detail below with reference to the accompanying drawings.

[0032] For the convenience of description and understanding, the following will be Figure 2 The length direction of the device shown in the figure is called the transverse direction, the depth direction is called the longitudinal direction, and the side of the device along the longitudinal direction facing the ore falling direction is called the front side, and the side facing away from the ore falling direction is called the rear side.

[0033] Figure 1 The side cross-sectional view of the ore sorting device of some embodiments of the present disclosure when in use is shown. The ore sorting device 100 of this embodiment includes a frame 10 and a blowing assembly 20, a push assembly 30 and a valve plate assembly 40 arranged on the frame 10. In addition, Figure 1Also shown is a portion of a conveyor assembly 300 for conveying ore, wherein the conveyor assembly 300 may be an ore transport device such as a conveyor belt. In operation, ores of different sizes are transported by the conveyor assembly 300 at a certain speed in the longitudinal direction, and when being transported to the discharge point, they leave the conveyor assembly 300 at an initial velocity in the longitudinal direction and fall along a parabola. Here, the scheme disclosed herein defines the path along which multiple ores fall along the parabola as an ore throwing path 200. Based on this, the blowing assembly 20 and the pushing assembly 30 can be sequentially arranged on the frame 10 along the ore throwing path 200. In this embodiment, the blowing assembly 20 is arranged on the upper part of the frame 10 relative to the pushing assembly 30 and is closer to the discharge point of the conveyor assembly 300 in the horizontal direction. Here, it is defined that the blowing assembly 20 is located upstream of the pushing assembly 30 along the ore throwing path 200, that is, the ore falling from the discharge point first passes through the position corresponding to the blowing assembly 20, and then passes through the position corresponding to the pushing assembly 30.

[0034] In one embodiment, the above-mentioned blowing assembly 20 disclosed herein may include a gas jetting portion 22 capable of ejecting gas, and the gas jetting portion 22 may include components such as a nozzle 221, for ejecting gas toward the target ore falling along the ore throwing path 200, so that the target ore is blown by the gas and changes its movement path, thereby moving the target ore out. Similarly, the above-mentioned push-up assembly 30 may include a push-up member 31, and as an example, the push-up member 31 may be processed into a push plate that rotates relative to the hinge. In operation, the push plate is driven by an internal cylinder 32, so that it can swing out toward the ore throwing path 200 and contact the target ore, thereby pushing the target ore to change its movement path and achieve the purpose of moving the target ore out.

[0035] See also Figure 2, which shows a three-dimensional schematic diagram of an ore sorting device of some embodiments of the present disclosure, in which a part of the frame is represented by a dotted line to show the structure of the device. In this embodiment, the frame 10 can be configured to have two side panels 11 opposite to each other in the transverse direction, and a bottom plate 13 fixedly connected to the two side panels 11, and a push-up assembly mounting member 12 is also fixedly mounted on the bottom plate 13. Among them, a blowing assembly mounting member 26 is provided on both lateral sides of the blowing assembly 20, and the two blowing assembly mounting members 26 protrude from both sides of the blowing assembly 20 in the transverse direction, and the blowing assembly mounting member 26 is provided with a through hole in which bolts can be set in the transverse direction. Bolt holes 112 corresponding to the through holes of the blowing assembly mounting member 26 are formed on the opposite sides of the upper parts of the two side panels 11, and the blowing assembly mounting member 26 is fixedly mounted on the side panels 11 by means of the cooperation of bolts with the bolt holes, thereby fixing the blowing assembly 20 to the frame 10. This arrangement allows the threaded connection of the blowing assembly 20 to avoid the main working area of ​​the device, and ore debris and dust will not accumulate at the connection, which facilitates the overall disassembly and maintenance of the blowing assembly 20. The ejection assembly mounting member 12 is configured as a substantially rectangular frame, wherein the upper side thereof is provided with an ejection assembly mounting plate 121 for mounting the ejection assembly 30. The bottom of the ejection assembly 30 is provided with a mounting outer edge 33 protruding along the longitudinal front and rear sides, and the mounting outer edge 33 is provided with a vertically penetrating through hole, which is preferably formed as a countersunk hole 331 in this embodiment. The ejection assembly mounting plate 121 is provided with through holes corresponding to the countersunk holes 331 of the mounting outer edge 33, and a plurality of loading and unloading grooves 122 are formed on one side of the ejection assembly mounting plate 121 away from the ejection assembly 30. The plurality of loading and unloading grooves 122 therein are respectively opened toward the front and rear sides in the longitudinal direction, and are connected to the through holes of the ejection assembly mounting plate 121. Through the above arrangement, the bolts arranged in the countersunk holes 331 of the mounting outer edge 33 can extend through the countersunk holes 331 into the through holes of the ejection assembly mounting plate 121 and be exposed from the loading and unloading grooves 122. Thus, the bolts can be tightened in the loading and unloading grooves 122 by nuts, thereby fixing the ejection assembly 30 to the ejection assembly mounting member 12. This arrangement prevents environmental dust or ore debris from falling into the threaded connection in the vertical direction during the operation of the device, thereby causing installation inconvenience or even clogging failure.

[0036] Figure 3 A three-dimensional schematic diagram of a blowing assembly of an ore sorting device according to some embodiments of the present disclosure is shown. The blowing assembly 20 may include a nozzle shield 21, which is generally formed as a flat, long, hollow prism, and the inside of the nozzle shield is used to accommodate a pneumatic actuator for blowing. See also Figure 1In this embodiment, the pneumatic actuator includes a plurality of nozzles 221, each of which is connected to a valve plate assembly 40 arranged at the bottom of the ore sorting device through an air pipe 45. An inclined surface 211 facing the ore throwing path 200 is provided on the upper side of the nozzle shield 21 in the vertical direction, and a plurality of blowing holes 212 corresponding to the nozzles 221 are provided on the inclined surface 211, so that the airflow blown out of the nozzles 221 faces the ore throwing path 200. Ear plates 25 are also provided on both sides of the blowing assembly 20, each ear plate 25 is fixedly connected to the nozzle shield 21, and a lifting ring 29 for lifting the blowing assembly 20 is also fixed on the ear plate 25. In addition, the ear plate 25 is also provided with a vertical through hole, and the spray assembly mounting member 26 also includes a mounting support plate 261 that protrudes laterally toward the inner side of the device, and the mounting support plate 261 is provided with threaded holes corresponding to the through holes on the ear plate 25, so that the ear plate 25 can be fixed to the mounting support plate 261 in the vertical direction through threaded connection. Figure 4 , Figure 4 A three-dimensional schematic diagram of an adjustment gasket group of an ore sorting device of some embodiments of the present disclosure is shown. The adjustment gasket group 28 includes a plurality of U-shaped gaskets of different thicknesses. The adjustment gasket group 28 is arranged at the place where the mounting bolts pass between the mounting support plate 261 and the ear plate 25, and the groove in the middle of the U-shaped shape is used to accommodate the studs of the mounting bolts. The adjustment gasket group 28 may, for example, include a first gasket 281 with a thickness of 2 mm, a second gasket 282 with a thickness of 3 mm, and a third gasket 283 with a thickness of 5 mm, so that the adjustment gasket group 28 forms different adjustment heights through different combinations. The height of the jet part 22 of the blowing assembly 20 relative to the frame 10 can be flexibly adjusted according to actual needs, and the replacement is very convenient, and the blowing assembly 20 does not need to be disassembled. A leak-proof plate 24 is also fixedly provided on the front end surface of the nozzle guard 21. The leak-proof plate 24 can be made of flexible materials such as rubber. It is fixed to the lower side of the front end surface of the nozzle guard 21 by bolts, and its lower end in the vertical direction is close to the push-up assembly 30, thereby preventing ore debris and dust from falling into the gap between the two.

[0037] See also Figure 5 and Figure 1 , Figure 5A three-dimensional schematic diagram of a valve plate assembly of an ore sorting device according to some embodiments of the present disclosure is shown. The valve plate assembly 40 can be arranged downstream of the ejection assembly 30 along the ore ejection path 200, and the bottom of the valve plate assembly 40 is fixed to the mounting base plate of the ejection assembly mounting member by means of bolts. Among them, the valve plate assembly 40 includes a valve plate box 41 and a valve plate unit 43 accommodated inside the valve plate box 41. The valve plate box 41 includes a horizontally placed, upwardly open, long strip-shaped box body 411, and a cover plate 412 buckled on the vertical upper side of the box body 411. In this embodiment, a plurality of cover plates 412 are arranged to be buckled on the upper side of the box body 411 in multiple sections along the horizontal direction, and each cover plate 412 is provided with a handle 421 for operation. This allows each cover plate 412 to be manually lifted by a single operator, creating convenience for installation and maintenance. Furthermore, because the cover plate 412 is divided into multiple sections, the weight of a single piece is reduced, and thus the thickness of a single cover plate 412 can be appropriately increased, creating conditions for improving the protective capability of the cover plate 412 .

[0038] In order to achieve safe operation, the portion of each cover plate 412 close to the ore throwing path 200 can be set as a slope 423 parallel to the ore moving direction corresponding to the ore throwing path 200, that is, when the ore moves along the ore throwing path 200 to the closest position to the cover plate 412, its moving direction is parallel to the slope 423. This setting avoids accidental damage caused by large pieces of ore hitting the cover plate 412 to the greatest extent, and even if a collision occurs, the angle of the slope 423 can also alleviate the impact caused by the ore, preventing the components in the valve plate unit 43 from being damaged due to vibration and impact. In this embodiment, the valve plate assembly 40 also includes a tilted base 46, which tilts the valve plate box 41 as a whole toward the ore throwing path 200. Preferably, the base 46 makes the upper surface of the valve plate box 41 form an angle of 20° with the horizontal plane. On the one hand, this reduces the impact of the upper surface of the valve plate box 41 when it is accidentally hit by the ore. On the other hand, the valve plate unit 43 is also tilted toward the front of the device, which is convenient for the device maintenance personnel to open the cover 412 to maintain the valve plate unit or replace the solenoid valve 431. At the same time, the air pipe joint 47 of the valve plate unit 43 arranged behind the valve plate box 41 is tilted upward, which is convenient for piping operation and maintenance. The two lateral sides of the valve plate box 41 are also provided with multiple cable outlets 44, and the power cable and the control cable can be electrically connected to the valve plate unit 43 through the cable outlets 44. In this embodiment, a cable sheath is also provided on the cable outlet 44 to prevent the cable from rubbing against the outlet side wall and prevent debris from entering the valve plate box 41.

[0039] See also Figure 6 and Figure 7 , Figure 6 A perspective schematic diagram of a cable shield of an ore sorting device according to some embodiments of the present disclosure is shown. Figure 7The schematic diagram of the decomposition of the ore sorting device of some embodiments of the present disclosure is shown, in which part of the frame 10 is omitted. Two cable shields 15 are symmetrically arranged on both sides of the valve plate assembly 40 and fixedly connected to the push assembly mounting member 12 of the frame 10. The cable shield 15 is formed to be hollow, and its vertical upper side surface is formed to be an inclined surface inclined toward the falling direction of the ore to reduce the impact of accidental collision of the ore. The cable shield 15 is open to one side of the valve plate assembly 40 and is arranged adjacent to the lateral side of the valve plate box 41, so that the cable extending from the cable outlet 44 on the side of the valve plate box 41 can be shielded and protected by the cable shield 15. The vertical upper side of the cable shield 15 is provided with a mounting side plate 151 with a longitudinally penetrating through hole 152, and the push assembly mounting member 12 is provided with a corresponding threaded hole, so that the cable shield 15 can be fixed to the push assembly mounting member 12 by bolts in the longitudinal direction. In addition, a vertical positioning pin 152 is also provided on the bottom side of the cable guard 15, and the ejection assembly mounting member 12 includes a mounting base plate 123, and the mounting base plate 123 is provided with a pin hole 124 corresponding to the positioning pin 152, so that the cable guard 15 can be positioned with the mounting base plate 123 through the positioning pin 152. Through the cooperation of the positioning pin and the bolt, the cable guard 15 can be easily installed or removed, thereby reducing the time and difficulty required for installation and maintenance.

[0040] See also Figure 7, wherein the ore sorting device of this embodiment further includes a front protection assembly 14, which includes a flexible protection pad 141, a plurality of fastening plates and a protection pad mounting plate 142. The plurality of fastening plates 143 and the protection pad mounting plate 142 clamp the protection pad 141 from both sides in the longitudinal direction, and the stacked protection pad mounting plates 142, the protection pad 141 and the fastening plates 143 are fixed together by bolts. The protection pad mounting plate 142 is also provided with a mounting hole for the bolt to pass longitudinally, and the push-out assembly mounting member 12 is provided with a threaded hole corresponding to the mounting hole, so that the front protection assembly 14 can be fixedly mounted on the push-out assembly mounting member 12 by means of bolts. The protective pad 141 can be made of elastic materials such as rubber, and is roughly in the shape of a rectangular sheet. Its upper end in the vertical direction is fixed between the protective pad mounting plate 142 and the fastening plate 143, and the main part of the protective pad 141 hangs down from the mounting position and is laid on the valve plate assembly 40 and the cable shield 15. Its transverse width exceeds the distribution width of the ore transported by the conveying assembly 300 in the transverse direction. Therefore, the flexible protective pad 141 can effectively protect the valve plate assembly 40 and the cable shield 15, while preventing debris from entering the interior of the device. By lifting the flexible protective pad 141, the valve plate assembly 40 can be easily maintained, saving labor costs. In this embodiment, a rear protective member 16 is also included. The rear protective member 16 is roughly formed in the shape of a rectangular sheet, and its vertical upper end is fixed to the longitudinal rear end face of the blowing assembly 20 by bolts, and its main part is arranged vertically downward, so as to cover the rear side of the device and prevent debris from entering the rear part of the device where the air pipe and wire are arranged to cause pollution.

[0041] In addition, a connecting member 60 is also provided in this embodiment, and the connecting member 60 is used to fix and connect the ejection assembly mounting member 12 and the blowing assembly 20, so as to facilitate transportation. Among them, the connecting member 60 includes an upper connecting plate 61 arranged on the upper side, and a vertical through hole is arranged on the upper connecting plate 61. Similarly, the connecting member 60 also includes a lower connecting plate 62 arranged on the lower side, which is also provided with a vertical through hole. A connecting pillar is formed between the upper connecting plate 61 and the lower connecting plate 62. Thus, by connecting the upper connecting plate 61 to the bottom of the blowing assembly 20 from bottom to top by bolts, and connecting the lower connecting plate 62 to the upper surface of the ejection assembly mounting plate 121 of the ejection assembly mounting member 12 from top to bottom by bolts, the blowing assembly 20 can be fixed to the ejection assembly mounting member 12. The setting of the connecting member 60 makes it possible to transport the blowing assembly 20, the ejection assembly 30 and the ejection assembly mounting member 12 independently as a whole, saving transportation costs.

[0042] Refer again Figure 2In this embodiment, the blowing assembly 20 is installed on the upper side of the side plate 11 of the frame 10, and the push-up assembly 30 installed on the push-up assembly mounting member 12 is set at a position downward along the ore throwing path 200. The side plate 11 for mounting the blowing assembly 20 is defined as the first mounting part, and the push-up assembly mounting member 12 for mounting the push-up assembly 30 is defined as the second mounting part. The first mounting part is higher than the second mounting part in the vertical direction and is farther back than the first mounting part in the longitudinal direction, that is, the first mounting part and the second mounting part are arranged in a stepped shape. This positional relationship enables the blowing assembly 20 and the push-up assembly 30 respectively mounted on the first mounting part and the second mounting part to form a horizontal separation and a vertical drop on the frame 10, so that the actual action parts of the blowing assembly 20 and the push-up assembly 30 are separated in the vertical direction and the horizontal direction, so that the ore moving along the ore throwing path 200 can be removed without interfering with each other, and can cooperate with each other.

[0043] With the cooperation of the identification module that can distinguish the size of the ore, the blowing assembly 20 and the pushing assembly 30 can be connected to a control module, and the ore sorting rules can be set through the control module. For example, since the blowing assembly 20 uses a solenoid valve to control the nozzle 221 to spray air to blow the ore to move, its action speed is fast and the frequency is high, but the driving force is small, which is suitable for removing small-sized ores; while the pushing assembly 30 uses a cylinder to drive the pushing member 31 to push the target ore, its action frequency is relatively low, but the driving force is greater, which is suitable for removing large-sized target ores. Therefore, the screening rules can be set and the division of labor mode can be set: use the blowing assembly 20 to remove smaller target ores, and use the pushing assembly 30 to remove larger target ores, so that the sorting procedure can be refined and the sorting error can be reduced. Alternatively, a collaborative mode can also be set: it is stipulated that target ores below the first size are only removed using the blowing assembly 20, target ores between the first size and the second size are removed together by the blowing assembly 20 and the pushing assembly 30, and target ores larger than the third size are only removed by pushing the pushing assembly 30, wherein the first size < the second size < the third size. This rule setting can improve the sorting efficiency while reducing the sorting error. In addition, the above rule setting can also be numerically adjusted according to actual conditions, or more types of identification modules can be added to form more sophisticated screening rules, and the present disclosure is not limited in this regard. The first mounting portion and the second mounting portion are arranged in a stepped shape, which also creates conditions for the separate disassembly and assembly of the blowing assembly 20 and the pushing assembly 30. During disassembly and assembly, the blowing assembly 20 and the pushing assembly 30 can be moved out or moved in from the front side of the device, reducing the equipment maintenance and installation costs.

[0044] Since the blowing assembly 20 and the ejecting assembly 30 of this embodiment can be installed relatively independently, one of the two assemblies can be installed separately for use according to actual conditions.

[0045] See also Figure 8 , Figure 8 The side cross-sectional view of the ore sorting device of some embodiments of the present disclosure in the state where the push-up assembly is set alone is shown. Among them, only the push-up assembly 30 is installed on the frame 10, and the first protective cover 17 for preventing dust accumulation is installed on the first mounting part. At this time, the push-up assembly 30 can work alone. This setting is suitable for the situation where only large-sized target ores need to be sorted, or the situation where the number of large-sized target ores is large.

[0046] See also Fig. 9 , Fig. 9 A side cross-sectional view of an ore sorting device according to some embodiments of the present disclosure is shown in a state where a blowing assembly is set alone. Similarly, only a blowing assembly 20 is set on the frame 10, and a second shield 18 for preventing dust accumulation is installed on the second mounting portion. This arrangement, in which the blowing assembly 20 is set alone to sort the ore, is suitable for the case where only small-sized target ores need to be sorted, or the case where there are a large number of small-sized target ores.

[0047] Those skilled in the art can understand that the ore sorting device in the above-described embodiment only discloses a layout scheme including two mounting parts. However, according to actual conditions, more mounting parts can be set up to form more mounting parts along the ore throwing path, thereby setting more actuators for sorting ore, and further improving the sorting efficiency of the device. For example, on the basis of the above-mentioned installed blowing assembly and push-up assembly, additional mounting side plates can be set on both sides of the lateral direction below the ore throwing path. The additional mounting side plates have a lower height than the push-up assembly mounting parts and are closer to the front side of the device, thereby forming a third mounting part that forms a stepped arrangement with the first mounting part and the second mounting part. By fixing the additional actuator assembly to the third mounting part, the sorting efficiency can be further improved. In addition, in the above-mentioned embodiment, the side plates arranged on both sides of the device are defined as the first mounting part, and the push-up assembly mounting parts fixed to the bottom plate are defined as the second mounting part, but the present disclosure does not limit the specific composition of the mounting part. For example, a stepped frame can be directly set up, so that the blowing assembly and the pushing assembly are installed on different steps of the frame in the vertical direction, or two longer side walls can be set up, on which multiple groups of mounting holes are arranged in a stepped manner, and the blowing assembly and the pushing assembly are respectively installed horizontally on the side walls, etc. It is only necessary to ensure that the corresponding mounting parts have the characteristics of a stepped arrangement.

[0048] According to the ore sorting device of the embodiment disclosed in the present invention, each operating part in the device is modularly set, and the frame is laid out in a corresponding modular installation method, so that the blowing component and the pushing component can work independently or cooperate with each other, combining the advantages of the blowing and pushing methods, and achieving the effect of sorting large and small particles of ore at the same time through a suitable control method. According to the characteristics of large sorting output, high efficiency, good reliability of the blowing component and large particle size of the pushing component, the advantages of the two sorting structures are combined through reasonable workflow control, and the ore does not need to be screened by particle size in advance in the mining area, so that mixed flow sorting of large and small particle size ores is achieved. The labor cost, equipment cost and environmental protection cost caused by ore screening are reduced, the ore sorting efficiency and output are greatly improved, and greater economic benefits can be created for the mining area. The pushing component or the blowing component can also be separately set on the frame according to actual work needs, so that the ore sorting device can install different execution components according to the sorting requirements of different sites, thereby saving equipment costs. At the same time, it can flexibly adjust the sorting strategy to cope with different working conditions. When the sorting strategy changes, the corresponding execution components with low working efficiency can be removed to avoid unnecessary loss or pollution of seldom used blowing components or pushing components in the ore sorting working environment.

[0049] See also Fig.10 , Fig.10 A schematic diagram of an ore sorting machine according to some embodiments of the present disclosure is shown. The ore sorting machine includes a conveying assembly 80, an identification assembly 90, and an ore sorting device 100 provided with a blowing assembly 20 and a pushing assembly 30 according to the above embodiment. The identification assembly 80, the blowing assembly 20, and the pushing assembly 30 are electrically connected to a control module (not shown), and the control module is used to receive the ore information transmitted by the identification assembly 90, and control the blowing assembly 20 and / or the pushing assembly 30 to perform a sorting operation on the ore according to a preset ore sorting rule.

[0050] Although multiple embodiments of the present disclosure have been shown and described herein, it will be apparent to those skilled in the art that such embodiments are provided by way of example only. Those skilled in the art may think of many changes, modifications, and alternatives without departing from the thought and spirit of the present disclosure. It should be understood that in the process of practicing the present disclosure, various alternatives to the embodiments of the present disclosure described herein may be adopted. The attached claims are intended to define the scope of protection of the present disclosure, and therefore cover equivalents or alternatives within the scope of these claims.

Claims

1. An ore sorting device, characterized in that: include: A frame including a plurality of mounting portions arranged in a stepped manner along an ore throwing path; a blowing assembly, which is detachably mounted on one of the plurality of mounting portions, the blowing assembly comprising an air jet portion, the air jet portion being used to blow an air stream toward the target ore to remove it from the plurality of ores; and The pushing assembly is detachably mounted on another one of the plurality of mounting parts, and the pushing assembly comprises a pushing member, and the pushing member is used to push the target ore to remove it from the plurality of ores.

2. The ore separation device according to claim 1, characterized in that: At least one spray assembly mounting member is provided on both lateral sides of the spray assembly, and the first mounting portion among the multiple mounting portions includes two side walls, and mounting holes corresponding to the spray assembly mounting members are respectively opened on the opposite sides of the two side walls to install the spray assembly mounting member on the corresponding side walls.

3. The ore separation device according to claim 2, characterized in that: The second mounting portion among the multiple mounting portions includes a push-pull assembly mounting piece, the push-pull assembly mounting piece includes a push-pull assembly mounting plate arranged with the front side facing the push-pull assembly and a loading and unloading groove formed on the back side of the push-pull assembly mounting plate, the loading and unloading groove is open to the side of the push-pull assembly mounting piece, the push-pull assembly mounting plate includes a fixing hole that passes through the plate surface perpendicularly, and the fixing hole is connected to the loading and unloading groove.

4. The ore separation device according to claim 3, characterized in that: It also includes an adjusting gasket group, which includes a plurality of gaskets of various thicknesses. The adjusting gasket group is vertically arranged between the jet part of the jet assembly and the jet assembly mounting member to adjust the height of the jet part.

5. The ore separation device according to claim 4, characterized in that: The blowing assembly is arranged in front of the pushing assembly along the ore throwing path, and a leak-proof assembly for shielding the gap between the blowing assembly and the pushing assembly is fixedly mounted on the blowing assembly.

6. The ore separation device according to claim 1, characterized in that: It also includes a valve plate assembly, which includes a valve plate box and a valve plate unit arranged in the valve plate box. The valve plate box includes a valve plate box inclined surface parallel to the moving direction of the ore when the ore is in a corresponding position of the valve plate box.

7. The ore separation device according to claim 6, characterized in that: The blowing assembly, the pushing assembly and the valve plate assembly are sequentially arranged in a stepped manner along the ore throwing path.

8. The ore separation device according to claim 7, characterized in that: The valve plate box further comprises a valve plate box cover which is laterally divided into multiple sections, and an upper surface of the valve plate box cover is defined as the valve plate box inclined surface.

9. The ore separation device according to claim 8, characterized in that: The bottom of the valve plate box is provided with an inclined base.

10. An ore sorting machine, characterized in that: Comprising an ore sorting device according to any one of claims 1-9.