Large-span steel truss girder bridge double-sliding-block incremental launching construction structure

By introducing bracket components, cross-connection seat components and guardrail components into the double-slider push construction structure of the long-span steel truss bridge, the problems of increased weight and friction are solved, and better sliding effects and Material push adjustment extends service life.

CN221919026UActive Publication Date: 2024-10-29CCCC INFRASTRUCTURE MAINTENANCE GRP ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420536127.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-19
Publication Date
2024-10-29
Estimated Expiration
2034-03-19

AI Technical Summary

Technical Problem

In the existing double-slider push construction structure of the long-span steel truss girder bridge, the weight and friction increase, which affects the service life.

Method used

A double-slide push construction structure including a bracket component, a cross-connection seat component and a guardrail component is designed. The sliding effect is achieved through the fitting connection of the fitting groove and the pulley. The cross-connection seat component and the bottom connection seat component are used for Material pushing and conditioning, guardrail components provide material protection.

Benefits of technology

It improves the sliding connection effect, reduces the friction coefficient, enhances wear resistance, provides convenient material pushing and protection functions, and extends the service life of the device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221919026U_ABST
    Figure CN221919026U_ABST
Patent Text Reader

Abstract

The utility model discloses a large-span steel truss girder bridge double-sliding-block pushing construction structure which comprises a main base, a bracket assembly is arranged on the inner wall of the main base and comprises a bracket, the two sides of the bracket are provided with wedging grooves, and the inner walls of the wedging grooves are connected with the outer wall of the main base in an attached mode. A pulley is arranged on the inner wall of the bracket; through the arrangement of the bracket assembly, in the use process, the inner wall of the wedging groove is connected with the outer wall of the main base in an attached mode, the good sliding connection effect can be achieved, and the friction coefficient can be reduced through the arrangement of the sliding wheels; according to the double-sliding-block pushing construction structure of the large-span steel truss girder bridge, through the arrangement of the bracket assembly, in the using process, the inner wall of the wedging groove is connected with the outer wall of the main base in an attached mode, the good sliding connection effect can be achieved, the friction coefficient can be reduced through the arrangement of the pulleys, and the good protection and wear-resisting effect can be achieved; the use effect of the device is improved, and convenience is provided for a user.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of construction engineering, in particular to a double-slider top-pushing construction structure of a large-span steel truss bridge. Background Art

[0002] Construction projects refer to the planning, investigation, design, construction, completion and other technical work for the construction, renovation or expansion of buildings and ancillary facilities, as well as the installation of supporting lines, pipelines and equipment. It also refers to the construction of various houses and buildings, also known as construction workload. This part of the investment must be started and materials must be moved, and it can only be realized through construction activities.

[0003] The existing technology has the following problems:

[0004] In the prior art, the weight of the double-slider jacking construction structure of the beam bridge increases during use, the friction increases, and the service life is affected. Therefore, it is necessary to design a double-slider jacking construction structure for a large-span steel truss bridge with good performance. Utility Model Content

[0005] In view of the problems in the related technology, the utility model proposes a double-slider jacking construction structure for a large-span steel truss bridge to overcome the above-mentioned technical problems existing in the existing related technology.

[0006] To this end, the specific technical solution adopted by the utility model is as follows: a double-slider top-pushing construction structure of a large-span steel truss bridge, comprising a main seat, the inner wall of the main seat is provided with a bracket assembly, the bracket assembly comprises a bracket, both sides of the bracket are provided with a fitting groove, the inner wall of the fitting groove is fitted and connected with the outer wall of the main seat;

[0007] The inner wall of the bracket is provided with a pulley; through the setting of the bracket assembly, during use, the setting in which the inner wall of the fitting groove is fitted and connected with the outer wall of the main seat can achieve a better sliding connection effect, and the setting of the pulley can reduce the friction coefficient and achieve a better protective and wear-resistant effect, thereby improving the use effect of the device and providing convenience for the user.

[0008] Preferably, transverse connecting seat assemblies are provided at both ends of the bracket assembly, and the transverse connecting seat assembly includes a limit seat, the outer wall of the limit seat is fixedly connected to a side seat, one side of the side seat is provided with a connecting groove, and the inner wall of the limit seat is clamped with the outer wall of the bracket; through the setting of the transverse connecting seat assembly, during use, it can be connected and installed with the transverse pushing mechanism of the bracket assembly so that the material in the main seat can be pushed laterally, which improves the use effect of the device and provides convenience for the user.

[0009] Preferably, a bottom connecting seat assembly is provided at the bottom of the main seat, and the bottom connecting seat assembly includes a connecting plate, and a base is provided at the bottom of the connecting plate; through the setting of the bottom connecting seat assembly, it can be connected and installed with the longitudinal pushing mechanism of the main seat, so as to adjust the height of the material in the main seat, thereby improving the use effect of the device and providing convenience for the user.

[0010] Preferably, mounting holes are arranged in a circle on the outer wall of the connecting plate, and the connecting plate and the main seat are fixedly connected with bolts through the mounting holes.

[0011] Preferably, there are two bottom connecting seat assemblies, and a bottom mounting groove is provided at the bottom of the base.

[0012] Preferably, a guardrail assembly is provided on the outer wall of the main seat, and the guardrail assembly includes a mounting frame, a guard rod is provided on the outer wall of the mounting frame, and a connecting tube is provided on the outer wall of the guard rod.

[0013] Preferably, there are multiple protection rods, and the multiple protection rods are threadedly connected through a connecting tube.

[0014] Preferably, the outer wall of the mounting frame is clamped with the bracket, and the mounting frame and the bracket are fixedly connected by bolts; through the provision of the guardrail assembly, during use, a better protection effect can be achieved for the materials stored in the main seat, thereby improving the use effect of the device and providing convenience for the user.

[0015] The beneficial effects of the utility model are as follows: 1. The double-slider jacking construction structure of the large-span steel truss bridge, through the setting of the bracket assembly, can achieve a better sliding connection effect during use, wherein the setting of the inner wall of the fitting groove and the outer wall of the main seat are fitted and connected, wherein the setting of the pulley can reduce the friction coefficient, achieve a better protective and wear-resistant effect, improve the use effect of the device, and provide convenience for users.

[0016] 2. The double-slider jacking construction structure of the large-span steel truss bridge can be connected and installed with the horizontal pushing mechanism of the bracket assembly through the setting of the horizontal connecting seat assembly during use, so that the material in the main seat can be pushed horizontally, which improves the use effect of the device and provides convenience for users; through the setting of the bottom connecting seat assembly, it can be connected and installed with the longitudinal pushing mechanism of the main seat, so that the height of the material in the main seat can be raised and lowered, which improves the use effect of the device and provides convenience for users.

[0017] 3. The double-slider jacking construction structure of the large-span steel truss bridge can achieve better protection for the materials stored in the main seat through the setting of the guardrail assembly during use, thereby improving the use effect of the device and providing convenience for users. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0019] Figure 1 It is a front view of the double-slider jacking construction structure of a large-span steel truss bridge according to an embodiment of the utility model;

[0020] Figure 2 It is a bottom view of the double-slider jacking construction structure of a large-span steel truss bridge according to an embodiment of the utility model;

[0021] Figure 3 It is a structural schematic diagram of a bracket assembly of a double-slider jacking construction structure of a large-span steel truss bridge according to an embodiment of the utility model;

[0022] Figure 4 It is a structural schematic diagram of a transverse connection seat assembly of a double-slider top-pushing construction structure of a large-span steel truss bridge according to an embodiment of the utility model;

[0023] Figure 5 It is a structural schematic diagram of a bottom connection seat assembly of a double-slider top-pushing construction structure of a large-span steel truss bridge according to an embodiment of the utility model;

[0024] Figure 6 It is a schematic structural diagram of a guardrail assembly of a double-slider jacking construction structure for a large-span steel truss bridge according to an embodiment of the utility model.

[0025] In the figure: 1. main seat; 2. bracket assembly; 201. bracket; 202. fitting groove; 203. pulley; 3. horizontal connecting seat assembly; 301. limit seat; 302. side seat; 4. bottom connecting seat assembly; 401. base; 402. connecting plate; 403. mounting hole; 5. guardrail assembly; 501. mounting frame; 502. guardrail rod; 503. connecting tube. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0027] According to an embodiment of the utility model, a double-slider jacking construction structure for a large-span steel truss bridge is provided.

[0028] Embodiment 1;

[0029] like Figure 1-Figure 6 As shown, the double-slider jacking construction structure of a large-span steel truss bridge according to an embodiment of the utility model comprises a main seat 1, the inner wall of the main seat 1 is provided with a bracket assembly 2, the bracket assembly 2 comprises a bracket 201, and fitting grooves 202 are provided on both sides of the bracket 201, and the inner wall of the fitting groove 202 is fitted and connected with the outer wall of the main seat 1;

[0030] A pulley 203 is provided on the inner wall of the bracket 201 .

[0031] In this embodiment, through the setting of the bracket assembly 2, during use, the setting in which the inner wall of the fitting groove 202 is fitted and connected with the outer wall of the main seat 1 can achieve a better sliding connection effect, and the setting of the pulley 203 can reduce the friction coefficient and achieve a better protective and wear-resistant effect, thereby improving the use effect of the device and providing convenience for the user.

[0032] Embodiment 2:

[0033] On the basis of the first embodiment, the preferred embodiment of the double slider top-pushing construction structure of the large-span steel truss bridge provided by the utility model is as follows: Figure 1-Figure 6 As shown: both ends of the bracket assembly 2 are provided with a transverse connecting seat assembly 3, the transverse connecting seat assembly 3 includes a limit seat 301, the outer wall of the limit seat 301 is fixedly connected with a side seat 302, one side of the side seat 302 is provided with a connecting groove, and the inner wall of the limit seat 301 is clamped with the outer wall of the bracket 201;.

[0034] A bottom connecting seat assembly 4 is provided at the bottom of the main seat 1, and the bottom connecting seat assembly 4 includes a connecting plate 402, and a base 401 is provided at the bottom of the connecting plate 402;

[0035] The outer wall of the connecting plate 402 is provided with mounting holes 403 in a circle, and the connecting plate 402 and the main seat 1 are fixedly connected with bolts through the mounting holes 403;

[0036] There are two bottom connection seat assemblies 4 , and a bottom installation groove is formed at the bottom of the base 401 .

[0037] In this embodiment, through the setting of the transverse connecting seat assembly 3, during use, it can be connected and installed with the transverse pushing mechanism of the bracket assembly 2, so that the material in the main seat 1 can be pushed laterally, which improves the use effect of the device and provides convenience for the user.

[0038] In this embodiment, by setting the bottom connecting seat assembly 4, it can be connected and installed with the longitudinal pushing mechanism of the main seat 1, so as to adjust the height of the material in the main seat 1, thereby improving the use effect of the device and providing convenience for the user.

[0039] Embodiment three;

[0040] On the basis of the first embodiment, the preferred embodiment of the double slider top-pushing construction structure of the large-span steel truss bridge provided by the utility model is as follows: Figure 1 one Figure 6 As shown: the outer wall of the main seat 1 is provided with a guardrail assembly 5, the guardrail assembly 5 includes a mounting frame 501, the outer wall of the mounting frame 501 is provided with a guard rod 502, and the outer wall of the guard rod 502 is provided with a connecting tube 503;

[0041] There are multiple protection rods 502, and the multiple protection rods 502 are threadedly connected through the connecting tube 503;

[0042] The outer wall of the mounting frame 501 is clamped with the bracket 201, and the mounting frame 501 and the bracket 201 are fixedly connected by bolts.

[0043] In this embodiment, by providing the guardrail assembly 5, a better protection effect can be achieved for materials stored in the main seat 1 during use, thereby improving the use effect of the device and providing convenience for the user.

[0044] In order to facilitate understanding of the above technical solution of the present invention, the working principle or operation method of the present invention in the actual process is described in detail below.

[0045] In actual application, first, the device is connected through the transverse connecting seat assembly 3 and the bottom connecting seat assembly 4, and the material to be transported is placed in the bracket assembly 2, and the transverse pushing mechanism and the longitudinal lifting mechanism are started for use.

[0046] In summary, with the aid of the above-mentioned technical scheme of the utility model, the double-slider top-pushing construction structure of the large-span steel truss bridge, through the setting of the bracket assembly 2, in use, the setting in which the inner wall of the fitting groove 202 is fitted and connected with the outer wall of the main seat 1 can achieve a better sliding connection effect, wherein the setting of the pulley 203 can reduce the friction coefficient, can achieve a better protective and wear-resistant effect, improve the use effect of the device, and provide convenience for users; through the setting of the horizontal connecting seat assembly 3, in use, it can be connected and installed with the horizontal pushing mechanism of the bracket assembly 2, so that the material in the main seat 1 can be pushed horizontally, which improves the use effect of the device and provides convenience for users; through the setting of the bottom connecting seat assembly 4, it can be connected and installed with the longitudinal pushing mechanism of the main seat 1, so that the height of the material in the main seat 1 can be raised and lowered, which improves the use effect of the device and provides convenience for users; through the setting of the guardrail assembly 5, in use, it can achieve a better protection effect on the materials stored in the main seat 1, improve the use effect of the device, and provide convenience for users.

[0047] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A double-slider push-up construction structure for a long-span steel truss bridge, comprising a main seat (1), characterized in that: The inner wall of the main seat (1) is provided with a bracket assembly (2), the bracket assembly (2) comprises a bracket (201), both sides of the bracket (201) are provided with fitting grooves (202), the inner wall of the fitting groove (202) is fitted and connected with the outer wall of the main seat (1); The inner wall of the bracket (201) is provided with a pulley (203).

2. The double-slider jacking construction structure for a long-span steel truss bridge according to claim 1 is characterized in that: A transverse connecting seat assembly (3) is provided at both ends of the bracket assembly (2), and the transverse connecting seat assembly (3) comprises a limit seat (301), the outer wall of the limit seat (301) is fixedly connected to a side seat (302), a connecting groove is provided on one side of the side seat (302), and the inner wall of the limit seat (301) is clamped with the outer wall of the bracket (201).

3. The double-slider jacking construction structure for a long-span steel truss bridge according to claim 1 is characterized in that: A bottom connecting seat assembly (4) is arranged at the bottom of the main seat (1), and the bottom connecting seat assembly (4) comprises a connecting plate (402), and a base (401) is arranged at the bottom of the connecting plate (402).

4. The double-slider jacking construction structure for a long-span steel truss bridge according to claim 3 is characterized in that: The outer wall of the connection plate (402) is provided with mounting holes (403) in a circle, and the connection plate (402) and the main seat (1) are fixedly connected by bolts via the mounting holes (403).

5. The double-slider jacking construction structure for a large-span steel truss bridge according to claim 3 is characterized in that: The number of the bottom connecting seat components (4) is two, and a bottom mounting groove is provided at the bottom of the base (401).

6. The double-slider jacking construction structure for a long-span steel truss bridge according to claim 1 is characterized in that: The outer wall of the main seat (1) is provided with a guardrail assembly (5), the guardrail assembly (5) comprises a mounting frame (501), the outer wall of the mounting frame (501) is provided with a guardrail rod (502), and the outer wall of the guardrail rod (502) is provided with a connecting tube (503).

7. The double-slider jacking construction structure for a long-span steel truss bridge according to claim 6 is characterized in that: There are multiple protection rods (502), and the multiple protection rods (502) are threadedly connected via a connecting tube (503).

8. The double-slider jacking construction structure for a large-span steel truss bridge according to claim 6 is characterized in that: The outer wall of the mounting frame (501) is clamped with the bracket (201), and the mounting frame (501) and the bracket (201) are fixedly connected by bolts.