Hanging basket for constructional engineering

By adopting a splicing structure and a placement structure on the hanging basket, the problem that the existing hanging basket cannot be flexibly disassembled and assembled is solved, the stability and safety of the hanging basket are improved, and it can adapt to the needs of different construction workers.

CN221920226UActive Publication Date: 2024-10-29SHANDONG LUYING CONSTR PROJECT MANAGEMENT CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420169244.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-23
Publication Date
2024-10-29
Estimated Expiration
2034-01-23

AI Technical Summary

Technical Problem

The existing hanging basket is assembled through welding and the structure is solidified. It cannot be disassembled and assembled reasonably according to the number of people and the situation. As a result, the hanging basket is unstable when the number of people is small. It is necessary to replace the hanging basket with a shorter length. When there are more people, multiple hanging baskets need to be hoisted. Hanging basket is very inconvenient.

Method used

It adopts a splicing structure, including slots, blocks, limit holes and limit rods. The hanging basket is disassembled and spliced ​​through adjusting rods and fixed rods. It is combined with a placement structure to prevent tools from falling and ensure safety.

Benefits of technology

It realizes the flexible assembly of the hanging basket to adapt to different construction number conditions, improves the stability and safety of the hanging basket, and avoids the hidden danger of tools falling.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221920226U_ABST
    Figure CN221920226U_ABST
Patent Text Reader

Abstract

The utility model provides a hanging basket for constructional engineering, and relates to the technical field of hanging baskets, the hanging basket comprises a hanging basket and a splicing structure, the upper surface of the hanging basket is fixedly connected with a connector, the surface of the connector is provided with a hook, the top of the hook is fixedly connected with a hanging rope, the surface of the hanging basket is provided with the splicing structure, and the splicing structure is fixedly connected with the hanging basket. A placement structure is arranged in the hanging basket, the splicing structure comprises a clamping groove and a clamping block, the clamping groove is formed in the side face of the hanging basket, the clamping block is clamped to the surface of the clamping groove, the clamping block is fixedly connected to the face, away from the clamping groove, of the hanging basket, limiting holes are formed in the surfaces of the clamping block and the clamping groove, and limiting rods are slidably inserted into the limiting holes. A limiting rod is arranged in the middle of the hanging basket body, a pull ring is fixedly connected to the surface of the limiting rod, a fixing hole is formed in the surface of the limiting rod, and a fixing rod is inserted into the fixing hole in a sliding mode. And the hanging basket cannot be reasonably disassembled, assembled and spliced according to the specific number of constructors and construction conditions.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of hanging baskets, in particular to a hanging basket for construction engineering. Background Art

[0002] The hanging basket is a construction tool for high-altitude operations in construction projects. It is used for curtain wall installation, exterior wall cleaning, and other construction facilities that run up and down along the facade of a building or structure via a steel wire rope. It is also a working platform for operators.

[0003] Most of the existing hanging baskets on the market are assembled by welding, and the structure is relatively rigid. It is impossible to reasonably disassemble and assemble the hanging basket according to the specific number of construction workers and construction conditions. When there are fewer people, it is necessary to replace the hanging basket with a shorter length to avoid the hanging basket being unstable during the hoisting process due to too long length and too few people. When there are more people, multiple hanging baskets need to be hoisted, which is very inconvenient. Utility Model Content

[0004] The utility model aims to solve the shortcomings in the prior art and provides a hanging basket for construction engineering.

[0005] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a hanging basket for construction engineering, comprising a hanging basket and a splicing structure, a connector is fixedly connected to the upper surface of the hanging basket, a hook is provided on the surface of the connector, a hanging rope is fixedly connected to the top of the hook, a splicing structure is provided on the surface of the hanging basket, a placement structure is provided inside the hanging basket, the splicing structure comprises a slot and a block, a slot is provided on the side of the hanging basket, a block is spliced ​​on the surface of the slot, a side of the hanging basket away from the slot is fixedly connected with a block, and limiting holes are provided on the surfaces of the block and the slot, and a limiting rod is slidably inserted in the limiting hole.

[0006] The effects achieved by the above-mentioned components are as follows: in the utility model, when using the hanging basket for construction projects, in order to avoid the fact that most of the existing hanging baskets are assembled through welding, the structure is relatively rigid and it is impossible to reasonably disassemble and assemble the hanging basket according to the specific number of construction workers and construction conditions. When the number of people is small, it is necessary to replace the hanging basket with a shorter length to avoid the hanging basket being unstable during the hoisting process due to the small number of people and the length of the hanging basket being too long. When the number of people is large, multiple hanging baskets need to be hoisted, which is a very inconvenient problem. The hanging basket can be assembled and disassembled through the splicing structure, so as to facilitate the adaptation to different construction workers. After the assembly is completed, the construction tools can be placed in it through the placement structure to avoid the tools falling and causing safety hazards. After preparation, the hook and connector can be driven by the lifting rope to achieve the effect of lifting the hanging basket, thereby completing the use of the entire hanging basket.

[0007] Preferably, a pull ring is fixedly connected to the surface of the limiting rod, a fixing hole is opened on the surface of the limiting rod, and a fixing rod is slidably inserted into the fixing hole.

[0008] The effect achieved by the above components is that the fixing rod passes through the limiting rod and is slidably inserted into the fixing hole, thereby fixing the limiting rod.

[0009] Preferably, an adjusting rod is rotatably connected to the surface of the fixing rod, and an insertion groove and an installation groove are clamped on the surface of the hanging basket.

[0010] The effect achieved by the above components is: the fixing rod rotates to move the adjusting rod out of the insertion groove, and then the adjusting rod is moved away from the fixing hole to drive the fixing rod out of the fixing hole.

[0011] Preferably, an adjusting rod is clamped on the surface of the insertion groove, and a fixing spring and a spring rod are fixedly connected to the surface of the installation groove.

[0012] The effect achieved by the above-mentioned components is that the insertion groove facilitates the clamping of the adjusting rod and prevents the adjusting rod from sliding due to external force.

[0013] Preferably, a fixing spring is sleeved on the surface of the spring rod, and the fixing spring and one end of the spring rod away from the mounting groove are fixedly connected with a fixing rod.

[0014] The effect achieved by the above components is that the fixing spring inside the installation slot drives the spring rod to extend and retract to squeeze the fixing rod, so as to facilitate pushing the fixing rod to fix.

[0015] Preferably, the placement structure comprises a placement box and a fixing plate, and the back side of the placement box is fixedly connected with the fixing plate.

[0016] The effect achieved by the above components is: the construction tools are placed therein through the placement structure to prevent the tools from falling and causing safety hazards and accidents. The placement box can be first installed and fixed on the railing on the surface of the hanging basket.

[0017] Preferably, a rubber block is fixedly connected to the surface of the fixing plate, a fixing groove is provided on the surface of the railing of the hanging basket, and a rubber block is clamped in the fixing groove.

[0018] The effect achieved by the above components is: the placement box is clamped on the surface of the hanging basket along the fixing plate on the back, and the rubber block on the surface of the fixing plate is clamped in the fixing groove. At this time, the rubber block has elasticity, so the effect of fixed clamping can be achieved.

[0019] Preferably, a limiting groove is provided on the surface of the fixing plate, and the inner wall of the limiting groove is clamped with the limiting plate.

[0020] The effect achieved by the above components is: the limiting plate is clamped along the limiting groove to limit the fixing plate, thereby preventing the fixing plate from being squeezed and causing the placement box to slide, thereby completing the fixation of the entire placement box, thereby achieving the effect of facilitating the storage of construction tools.

[0021] Compared with the prior art, the advantages and positive effects of the utility model are:

[0022] In the utility model, a splicing structure is set. When using the utility model, in order to avoid the fact that most of the existing hanging baskets are assembled by welding, the structure is relatively rigid and it is impossible to reasonably disassemble and assemble the hanging basket according to the specific number of construction workers and construction conditions. When the number of people is small, it is necessary to replace the hanging basket with a shorter length to avoid the hanging basket being unstable during the hoisting process due to too long length and too few people. When the number of people is large, it is necessary to hoist multiple hanging baskets, which is very inconvenient. The splicing structure can be used to assemble and disassemble the hanging basket. When the number of people is small, it is necessary to replace the hanging basket with a shorter length to avoid the hanging basket being unstable during the hoisting process due to too long length and too few people. When the number of people is large, it is necessary to hoist multiple hanging baskets, which is very inconvenient. The splicing structure can be used to assemble and disassemble the hanging basket, thereby achieving convenience. To adapt to the situations of different construction workers, when the hanging basket is used, when there are fewer construction workers, the hanging basket can be disassembled, the adjusting rod is first rotated along the fixing rod to move the adjusting rod out of the insertion slot, and then the adjusting rod is moved in the direction away from the fixing hole to drive the fixing rod to move out of the fixing hole, so as to facilitate the removal of the limit rod from the limit hole through the pull ring, and at this time the hanging basket can be moved out of the slot along the card block, thereby completing the disassembly of the two hanging baskets. When a large number of people need to be assembled, the card block on the side of the hanging basket can be first connected to the card slot, and then the limit rod can be slid and inserted into the limit hole, and the adjusting rod can be loosened at this time, so that the fixing spring inside the installation slot drives the spring rod to extend and retract to squeeze the fixing rod, so that the fixing rod passes through the limit rod and is slidably inserted into the fixing hole, thereby achieving the fixation of the limit rod, and then completing the splicing and fixation of the two hanging baskets. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 The utility model provides a three-dimensional structural schematic diagram of a hanging basket for construction engineering;

[0024] Figure 2 Another structural schematic diagram of a hanging basket for construction engineering proposed by the utility model;

[0025] Figure 3 A partial schematic diagram of a splicing structure of a hanging basket for construction engineering proposed by the utility model;

[0026] Figure 4 The utility model provides a partial schematic diagram of a placement structure of a hanging basket for construction engineering.

[0027] Legend: 1. Hanging basket; 2. Connector; 3. Hook; 4. Hanging rope; 5. Splicing structure; 501. Card slot; 502. Card block; 503. Limiting hole; 504. Limiting rod; 505. Pull ring; 506. Fixing hole; 507. Fixing rod; 508. Adjusting rod; 509. Inserting slot; 510. Installing slot; 511. Fixing spring; 512. Spring rod; 6. Placing structure; 601. Placing box; 602. Fixing plate; 603. Fixing slot; 604. Rubber block; 605. Limiting slot; 606. Limiting plate. DETAILED DESCRIPTION

[0028] Embodiment 1, as Figure 1-4 As shown, a hanging basket for construction engineering includes a hanging basket 1 and a splicing structure 5, a connector 2 is fixedly connected to the upper surface of the hanging basket 1, a hook 3 is provided on the surface of the connector 2, a hanging rope 4 is fixedly connected to the top of the hook 3, the splicing structure 5 is provided on the surface of the hanging basket 1, and a placement structure 6 is provided inside the hanging basket 1. In the utility model, when using the hanging basket for construction engineering, in order to avoid the existing hanging basket 1, most of which are assembled by welding, the structure is relatively rigid, and the hanging basket 1 cannot be reasonably disassembled and spliced ​​according to the specific number of construction workers and construction conditions. When the number of people is small, it is necessary to replace the hanging basket 1 with a shorter length to avoid the hanging basket 1 being unstable during the hoisting process due to the excessive length and too few people. When the number of people is large, multiple hanging baskets 1 need to be hoisted, which is very inconvenient. The hanging basket 1 can be assembled and disassembled through the splicing structure 5, so as to achieve the situation that is easy to adapt to different construction workers. After the assembly is completed, the construction tools are placed therein through the placement structure 6 to avoid the tools falling and causing safety hazards. After preparation, the hook 3 and the connector 2 can be driven by the lifting rope 4 to achieve the effect of lifting the hanging basket 1, thereby completing the use of the entire hanging basket 1.

[0029] Reference Figure 3The splicing structure 5 includes a slot 501 and a block 502. The side of the hanging basket 1 is provided with a slot 501, and the surface of the slot 501 is connected with the block 502. The side of the hanging basket 1 away from the slot 501 is fixedly connected with the block 502. The surfaces of the block 502 and the slot 501 are both provided with a limiting hole 503. A limiting rod 504 is slidably inserted in the limiting hole 503. A pull ring 505 is fixedly connected to the surface of the limiting rod 504. A fixing hole 506 is provided on the surface of the limiting rod 504. The fixing hole 506 is provided with a fixing hole 506. 06 is slidably inserted with a fixing rod 507, and the surface of the fixing rod 507 is rotatably connected with an adjusting rod 508, the surface of the hanging basket 1 is clamped with an insertion groove 509 and an installation groove 510, the surface of the insertion groove 509 is clamped with the adjusting rod 508, the surface of the installation groove 510 is fixedly connected with a fixing spring 511 and a spring rod 512, the surface of the spring rod 512 is sleeved with a fixing spring 511, and the fixing spring 511 and the spring rod 512 are fixedly connected to the fixing rod 507 at one end away from the installation groove 510. In the utility model, by setting a splicing structure 5, when using the utility model, in order to avoid the existing hanging basket 1, most of which are assembled by welding, the structure is relatively rigid, and the hanging basket 1 cannot be reasonably disassembled and spliced ​​according to the specific number of construction workers and construction conditions. When the number of people is small, it is necessary to replace the hanging basket 1 with a shorter length to avoid the hanging basket 1 being unstable during the hoisting process due to the length being too long and the number of people being too small. When the number of people is large, it is necessary to hoist multiple hanging baskets 1, which is very inconvenient. The splicing structure 5 can be used to assemble and disassemble the hanging basket 1, so as to achieve the situation that it is easy to adapt to different construction workers. When using the hanging basket 1, when there are few construction workers, the hanging basket 1 can be disassembled, and the adjusting rod 508 is first rotated along the fixing rod 507 to move the adjusting rod 508 out of the insertion groove 509. At this time, the adjusting rod 5 08 moves in the direction away from the fixing hole 506, driving the fixing rod 507 to move out of the fixing hole 506, thereby facilitating the removal of the limiting rod 504 from the limiting hole 503 through the pull ring 505. At this time, the hanging basket 1 can be moved out of the card slot 501 along the clamping block 502, thereby completing the disassembly of the two hanging baskets 1. When a large number of people need to be assembled, the clamping block 502 on the side of the hanging basket 1 can be first clamped in the card slot 501, and then the limiting rod 504 can be slidably inserted into the limiting hole 503. At this time, the adjusting rod 508 is loosened, so that the fixing spring 511 inside the mounting groove 510 drives the spring rod 512 to extend and squeeze the fixing rod 507, so that the fixing rod 507 passes through the limiting rod 504 and is slidably inserted into the fixing hole 506, thereby achieving the fixation of the limiting rod 504, and then completing the splicing and fixation of the two hanging baskets 1.

[0030] Reference Figure 4The placement structure 6 includes a placement box 601 and a fixing plate 602. The back of the placement box 601 is fixedly connected to the fixing plate 602. The surface of the fixing plate 602 is fixedly connected to the rubber block 604. The railing surface of the hanging basket 1 is provided with a fixing groove 603. The rubber block 604 is clamped in the fixing groove 603. The surface of the fixing plate 602 is provided with a limiting groove 605. The inner wall of the limiting groove 605 is clamped with the limiting plate 606. In the utility model, by setting a placement structure 6, when using the utility model, construction tools are placed therein through the placement structure 6 to prevent tools from falling and causing safety hazards. The placement box 601 can be first installed and fixed on the railing on the surface of the hanging basket 1, and the placement box 601 is first clamped on the surface of the hanging basket 1 along the fixed plate 602 on the back, so that the rubber block 604 on the surface of the fixed plate 602 is clamped in the fixed groove 603. At this time, since the rubber block 604 is elastic, the effect of fixed clamping can be achieved. Finally, the limiting plate 606 is clamped along the limiting groove 605, thereby limiting the fixing plate 602, preventing the fixing plate 602 from being squeezed and causing the placement box 601 to slide, thereby completing the fixation of the entire placement box 601, and thus achieving the effect of facilitating the storage of construction tools.

[0031] Working principle: in the utility model, when using the hanging basket for construction engineering, in order to avoid the existing hanging basket 1, most of which are assembled by welding, the structure is relatively rigid, and it is impossible to reasonably disassemble and assemble the hanging basket 1 according to the specific number of construction workers and construction conditions. When the number of people is small, it is necessary to replace the hanging basket 1 with a shorter length to avoid the hanging basket 1 being unstable during the hanging process due to too long length and too few people. When the number of people is large, it is necessary to hoist multiple hanging baskets 1, which is very inconvenient. The hanging basket 1 can be assembled and disassembled through the splicing structure 5, so as to achieve the situation that it is easy to adapt to different construction workers. When the number of people is small, it is necessary to replace the hanging basket 1 with a shorter length to avoid the hanging basket 1 being unstable during the hanging process due to too long length and too few people. The installation process is unstable. When there are many people, multiple hanging baskets 1 need to be hoisted, which is very inconvenient. The hanging basket 1 can be assembled and disassembled through the splicing structure 5, so as to facilitate the adaptation to different construction personnel. When using the hanging basket 1, when there are fewer construction personnel, the hanging basket 1 can be disassembled, and the adjusting rod 508 is first rotated along the fixing rod 507 to move the adjusting rod 508 out of the insertion groove 509. At this time, the adjusting rod 508 is moved in the direction away from the fixing hole 506, driving the fixing rod 507 to move out of the fixing hole 506, so as to facilitate the removal of the limiting rod 504 from the limiting hole 503 through the pull ring 505. At this time, the hanging basket 1 can be moved out of the card slot 501 along the card block 502. This completes the disassembly of the two hanging baskets 1. When a large number of people need to assemble, the block 502 on the side of the hanging basket 1 can be first engaged in the slot 501, and then the limit rod 504 can be slidably inserted into the limit hole 503. At this time, the adjusting rod 508 is loosened, so that the fixing spring 511 inside the installation slot 510 drives the spring rod 512 to extend and squeeze the fixing rod 507, so that the fixing rod 507 passes through the limit rod 504 and is slidably inserted into the fixing hole 506, thereby fixing the limit rod 504, and then completing the splicing and fixing of the two hanging baskets 1. After the assembly is completed, the construction tools can be placed in it through the placement structure 6 to prevent the tools from falling and causing safety hazards. The placement box 601 can be installed and fixed on the hanging basket 1 first. On the railing on the surface of the basket 1, first, the placement box 601 is clamped on the surface of the hanging basket 1 along the fixed plate 602 on the back, so that the rubber block 604 on the surface of the fixed plate 602 is clamped in the fixed groove 603. At this time, due to the elasticity of the rubber block 604, the fixed clamping effect can be achieved. Finally, the limiting plate 606 is clamped along the limiting groove 605 to limit the fixing plate 602, so as to prevent the fixing plate 602 from being squeezed and causing the placement box 601 to slide. In this way, the entire placement box 601 is fixed, so as to achieve the effect of facilitating the storage of construction tools. After preparation, the hook 3 and the connector 2 can be driven by the lifting rope 4 to achieve the effect of lifting the hanging basket 1, thereby completing the use of the entire hanging basket 1.

[0032] The above is only a preferred embodiment of the utility model, and does not limit the utility model in other forms. Any technician familiar with the profession may use the technical content disclosed above to change or modify it into an equivalent embodiment with equivalent changes and apply it to other fields. However, any simple modification, equivalent change and modification made to the above embodiment based on the technical essence of the utility model without departing from the technical solution of the utility model still belongs to the protection scope of the technical solution of the utility model. In the description of the utility model, it should be noted that unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected, or indirectly connected through an intermediate medium, or it can be the internal connection of two components. For ordinary technicians in this field, the specific meanings of the above terms in the utility model can be understood by specific circumstances.

Claims

1. A hanging basket for construction engineering, comprising a hanging basket (1) and a splicing structure (5), characterized in that: The upper surface of the hanging basket (1) is fixedly connected to a connector (2), the surface of the connector (2) is provided with a hook (3), the top of the hook (3) is fixedly connected to a hanging rope (4), the surface of the hanging basket (1) is provided with a splicing structure (5), the interior of the hanging basket (1) is provided with a placement structure (6), the splicing structure (5) comprises a slot (501) and a block (502), the side of the hanging basket (1) is provided with a slot (501), the surface of the slot (501) is snap-connected with the block (502), the side of the hanging basket (1) away from the slot (501) is fixedly connected with the block (502), the surfaces of the block (502) and the slot (501) are both provided with a limiting hole (503), and a limiting rod (504) is slidably inserted in the limiting hole (503).

2. The construction engineering hanging basket according to claim 1, characterized in that: A pull ring (505) is fixedly connected to the surface of the limiting rod (504), a fixing hole (506) is opened on the surface of the limiting rod (504), and a fixing rod (507) is slidably inserted into the fixing hole (506).

3. The construction engineering hanging basket according to claim 2, characterized in that: The surface of the fixing rod (507) is rotatably connected with an adjusting rod (508), and the surface of the hanging basket (1) is clamped with an insertion groove (509) and a mounting groove (510).

4. The construction engineering hanging basket according to claim 3, characterized in that: The surface of the insertion groove (509) is clamped with an adjustment rod (508), and the surface of the installation groove (510) is fixedly connected with a fixing spring (511) and a spring rod (512).

5. The construction engineering hanging basket according to claim 4, characterized in that: A fixing spring (511) is sleeved on the surface of the spring rod (512), and a fixing rod (507) is fixedly connected to one end of the fixing spring (511) and the spring rod (512) away from the mounting groove (510).

6. The construction engineering hanging basket according to claim 5, characterized in that: The placement structure (6) comprises a placement box (601) and a fixing plate (602), and the back side of the placement box (601) is fixedly connected to the fixing plate (602).

7. The construction engineering hanging basket according to claim 6, characterized in that: A rubber block (604) is fixedly connected to the surface of the fixing plate (602), a fixing groove (603) is provided on the surface of the railing of the hanging basket (1), and a rubber block (604) is clamped in the fixing groove (603).

8. The construction engineering hanging basket according to claim 7, characterized in that: A limiting groove (605) is provided on the surface of the fixing plate (602), and the inner wall of the limiting groove (605) is clamped with the limiting plate (606).

Citation Information

Cited By

  • Hanging basket for constructional engineering

    CN223608161U