High-tightness jacketed pipeline for high-purity gas

Through the design of jacketed pipelines and the use of inflatable airbags, the problems of sealing and maintenance costs of high-purity gas pipelines are solved, higher sealing and insulation performance are achieved, costs are reduced, and maintenance is facilitated.

CN221922333UActive Publication Date: 2024-10-29WENZHOU IND DESIGN INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420215686.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-26
Publication Date
2024-10-29
Estimated Expiration
2034-01-26

AI Technical Summary

Technical Problem

Existing high-purity gas pipelines have deficiencies in terms of sealing performance and maintenance costs, and have high environmental temperature requirements, resulting in the need to improve thermal insulation performance.

Method used

It adopts a jacketed pipeline design, including an inner tube, an outer tube and an inflatable air bag. The inner wall of the inflatable air bag is equipped with raised parts and thermal insulation coating. It is inflated by an air pump to improve sealing and monitors the pressure through an air pressure sensor. The outer tube is connected in sections. to improve inflation efficiency.

Benefits of technology

It improves the sealing and insulation performance of the pipeline, reduces construction and maintenance costs, and ensures safe transportation and convenient maintenance of high-purity gas.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221922333U_ABST
    Figure CN221922333U_ABST
Patent Text Reader

Abstract

A high-tightness jacketed pipeline for high-purity gas comprises an inner pipe, an outer pipe, an inflatable air bag and an inflatable pipe connected to the inflatable air bag, the diameter of the outer pipe is larger than that of the inner pipe, the inner pipe and the outer pipe are sleeved to form a jacket, one end of the inflatable air bag is fixedly connected to the outer pipe, the inflatable air bag is connected between the inner pipe and the outer pipe, and the other end of the inflatable air bag is fixedly connected to the outer pipe. A through hole is formed in the outer tube, the inflation tube penetrates through the through hole, the inflation tube is matched with the through hole in diameter, and when the inflation air bag is in the maximum size, the inflation air bag is matched with the gap between the inner tube and the outer tube in size.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of pipelines, in particular to a high-seal jacket pipeline for high-purity gas. Background Art

[0002] In the chemical industry, the design of high-purity gas pipelines is very important. It is necessary to comprehensively consider gas characteristics, purification requirements, leakage risks, pipeline strength and stability, etc. to ensure the safety, high purity and performance of the pipeline. In order to ensure the sealing of the pipeline, high-intensity compaction is usually used to compact the pipeline to improve the sealing of the pipeline. However, the existing compaction method has a high cost, and it is inconvenient to remove the compacted material when the pipeline needs maintenance, resulting in increased maintenance costs. In addition, high-purity gas has high requirements for ambient temperature during transportation. Therefore, it is necessary to improve the thermal insulation performance of the pipeline. Summary of the invention

[0003] In order to solve the above problems, the utility model provides a high-seal jacket pipeline for high-purity gas, which can improve the thermal insulation and sealing properties of the pipeline and reduce the construction cost and maintenance cost of the pipeline.

[0004] The technical solution of the utility model is: a high-sealing jacket pipeline for high-purity gas, comprising an inner tube, an outer tube, an inflatable airbag and an inflatable tube connected to the inflatable airbag, the diameter of the outer tube is larger than the diameter of the inner tube, the inner tube and the outer tube are sleeved to form a jacket, one end of the inflatable airbag is fixedly connected to the outer tube, the inflatable airbag is connected between the inner tube and the outer tube, the outer tube is provided with a through hole, the inflatable tube passes through the through hole, the diameter of the inflatable tube is matched to that of the through hole, and when the inflatable airbag is at its maximum volume, the inflatable airbag is matched to the gap size between the inner tube and the outer tube.

[0005] By adopting the above technical scheme, first, the two ends of the inner tube and the outer tube are respectively connected to the high-purity gas production device and the high-purity gas storage device, and then the inflation tube is connected to the inflation pump. The inflatable airbag is inflated to the maximum volume by the inflation pump, and the inflatable airbag completely fills the gap between the inner tube and the outer tube. In addition, the inner wall of the inflatable airbag will continuously apply pressure to the inner tube, thereby improving the sealing of the inner tube and preventing leakage of high-purity gas. In addition, since one end of the inflatable airbag is fixedly connected to the outer tube, the inflatable airbag will not slide relative to each other, thereby ensuring that the pressure on the inner tube is stable. When the pipeline needs to be repaired, it is only necessary to discharge the gas in the inflatable airbag to clear the gap between the inner tube and the outer tube, which is convenient for the staff to carry out maintenance work and reduces maintenance costs.

[0006] The utility model is further configured as follows: the inner wall of the inflatable airbag is provided with a plurality of raised components evenly distributed on the inner wall of the inflatable airbag, the raised length of the raised components is 5 mm, and the spacing between two adjacent raised components is 1 cm.

[0007] By adopting the above technical solution, since the inner wall of the inflatable airbag is provided with a plurality of protruding parts evenly distributed on the inner wall of the inflatable airbag, the pressure on the outer surface of the inner tube when the inflatable airbag is at the maximum volume can be increased, and the sealing performance of the inner tube can be further improved.

[0008] The utility model is further configured as follows: the inner wall of the inflatable airbag is provided with a first thermal insulation coating, and the outer surface of the inner tube is provided with a second thermal insulation coating.

[0009] By adopting the above technical solution, since the inner wall of the inflatable airbag is provided with a first thermal insulation coating, and the outer surface of the inner tube is provided with a second thermal insulation coating, the double-layer thermal insulation coating can greatly improve the overall thermal insulation performance of the pipeline. Even if the second thermal insulation coating on the inner tube surface is damaged, the inflatable airbag can be replaced to ensure that the first thermal insulation coating on the inflatable airbag continues to be effective, thereby reducing maintenance costs while ensuring the thermal insulation performance of the pipeline.

[0010] A further configuration of the utility model is that an air pressure sensor connected to the air pressure tube is provided on the air inflation tube.

[0011] By adopting the above technical solution, since an air pressure sensor connected to the air pressure tube is provided on the air inflation tube, the staff can know the pressure value inside the inflatable airbag according to the value displayed by the air pressure sensor, thereby knowing whether the inflatable airbag is at the maximum volume, thereby ensuring that the inner tube is continuously subjected to pressure and ensuring the overall sealing of the pipeline.

[0012] The utility model is further configured as follows: the outer tube comprises a plurality of outer tube bodies, the outer tube bodies are provided with sealing baffles fixedly connected to the outer tube bodies, two adjacent sealing baffles are connected by fixing bolts, the ends of the inflatable airbags are fixedly connected to the sealing baffles, and the number of the inflatable airbags is the same as that of the outer tube bodies.

[0013] By adopting the above technical solution, since the outer tube includes several outer tube bodies, the number of inflatable airbags is the same as that of the outer tube bodies. Therefore, the inflation efficiency of the inflatable airbags and the pressure of the inflatable airbags on the inner tube are improved through segmented connection, thereby further improving the overall sealing of the pipeline. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Attached Figure 1 The utility model is a cross-sectional view of a high-seal jacket pipeline for high-purity gas according to a specific embodiment of the utility model.

[0015] Attached Figure 2The utility model is a structural schematic diagram of an inflatable airbag in a high-seal jacket pipeline for high-purity gas according to a specific embodiment of the utility model.

[0016] 1-inner tube, 2-outer tube, 3-inflatable airbag, 4-inflatable tube, 5-through hole, 6-raised component, 7-first thermal insulation coating, 8-second thermal insulation coating, 9-air pressure sensor, 10-outer tube body, 11-sealing partition, 12-fixing bolt. DETAILED DESCRIPTION

[0017] like Figure 1-2 As shown, a high-sealing jacket pipeline for high-purity gas includes an inner tube 1, an outer tube 2, an inflatable airbag 3 and an inflatable tube 4 connected to the inflatable airbag 3, the diameter of the outer tube 2 is larger than the diameter of the inner tube 1, the inner tube 1 and the outer tube 2 are fitted together to form a jacket, one end of the inflatable airbag 3 is fixedly connected to the outer tube 2, the inflatable airbag 3 is connected between the inner tube 1 and the outer tube 2, a through hole 5 is provided on the outer tube 2, the inflatable tube 4 passes through the through hole 5, the inflatable tube 4 is adapted to the diameter of the through hole 5, and when the inflatable airbag 3 is at its maximum volume, the inflatable airbag 3 is adapted to the gap size between the inner tube 1 and the outer tube 2.

[0018] First, the two ends of the inner tube 1 and the outer tube 2 are respectively connected to the high-purity gas production device and the high-purity gas storage device, and then the inflation tube 4 is connected to the inflation pump. The inflatable airbag 3 is inflated to the maximum volume by the inflation pump, and the inflatable airbag 3 completely fills the gap between the inner tube 1 and the outer tube 2. In addition, the inner wall of the inflatable airbag 3 will continue to apply pressure to the inner tube 1, thereby improving the sealing of the inner tube 1 and preventing leakage of high-purity gas. In addition, since one end of the inflatable airbag 3 is fixedly connected to the outer tube 2, the inflatable airbag 3 will not slide relative to each other, thereby ensuring that the pressure on the inner tube 1 is stable. When the pipeline needs to be repaired, it is only necessary to discharge the gas in the inflatable airbag 3 to clear the gap between the inner tube 1 and the outer tube 2, which is convenient for the staff to carry out maintenance work and reduces maintenance costs.

[0019] The inner wall of the inflatable airbag 3 is provided with a plurality of raised parts 6 evenly distributed on the inner wall of the inflatable airbag 3 , the raised length of the raised parts 6 is 5 mm, and the distance between two adjacent raised parts 6 is 1 cm.

[0020] Since the inner wall of the inflatable airbag 3 is provided with a plurality of protruding parts 6 evenly distributed on the inner wall of the inflatable airbag 3 , the pressure on the outer surface of the inner tube 1 when the inflatable airbag 3 is at the maximum volume can be increased, and the sealing performance of the inner tube 1 can be further improved.

[0021] The inner wall of the inflatable airbag 3 is provided with a first thermal insulation coating 7 , and the outer surface of the inner tube 1 is provided with a second thermal insulation coating 8 .

[0022] Since the inner wall of the inflatable airbag 3 is provided with a first thermal insulation coating 7, and the outer surface of the inner tube 1 is provided with a second thermal insulation coating 8, the double-layer thermal insulation coating can greatly improve the overall thermal insulation performance of the pipeline. Even if the second thermal insulation coating 8 on the surface of the inner tube 1 is damaged, the inflatable airbag 3 can be replaced to ensure that the first thermal insulation coating 7 on the inflatable airbag 3 continues to be effective, thereby reducing maintenance costs while ensuring the thermal insulation performance of the pipeline.

[0023] The inflation tube 4 is provided with an air pressure sensor 9 connected to the inflation tube 4 .

[0024] Since the inflation tube 4 is provided with an air pressure sensor 9 connected to the inflation tube 4, the staff can know the pressure value in the inflatable airbag 3 according to the value displayed by the air pressure sensor 9, and thus know whether the inflatable airbag 3 is at the maximum volume, thereby ensuring that the inner tube 1 is continuously subjected to pressure and ensuring the overall sealing of the pipeline.

[0025] The outer tube 2 includes a plurality of outer tube bodies 10, each of which is provided with a sealing baffle 11 fixedly connected to the outer tube body 10, two adjacent sealing baffles 11 are connected by a fixing bolt 12, and the end of the inflatable airbag 3 is fixedly connected to the sealing baffle 11, and the number of the inflatable airbag 3 is the same as that of the outer tube body 10.

[0026] Since the outer tube 2 includes a plurality of outer tube bodies 10, the number of the inflatable airbags 3 is the same as that of the outer tube bodies 10. Therefore, the inflation efficiency of the inflatable airbags 3 and the pressure of the inflatable airbags 3 on the inner tube 1 are improved through segmented connection, thereby further improving the overall sealing of the pipeline.

Claims

1. A high-sealing jacketed pipeline for high-purity gas, characterized in that: The invention comprises an inner tube, an outer tube, an inflatable airbag and an inflatable tube connected to the inflatable airbag, wherein the diameter of the outer tube is larger than the diameter of the inner tube, the inner tube and the outer tube are fitted together to form a jacket, one end of the inflatable airbag is fixedly connected to the outer tube, the inflatable airbag is connected between the inner tube and the outer tube, a through hole is provided on the outer tube, the inflatable tube passes through the through hole, the diameter of the inflatable tube is matched with that of the through hole, and when the inflatable airbag is at its maximum volume, the inflatable airbag is matched with the gap size between the inner tube and the outer tube.

2. A high-seal jacket pipeline for high-purity gas according to claim 1, characterized in that: The inner wall of the inflatable airbag is provided with a plurality of protruding parts evenly distributed on the inner wall of the inflatable airbag, the protruding length of the protruding parts is 5 mm, and the distance between two adjacent protruding parts is 1 cm.

3. A high-seal jacket pipeline for high-purity gas according to claim 1, characterized in that: The inner wall of the inflatable airbag is provided with a first thermal insulation coating, and the outer surface of the inner tube is provided with a second thermal insulation coating.

4. A high-seal jacket pipeline for high-purity gas according to claim 1, characterized in that: The inflation tube is provided with an air pressure sensor connected to the inflation tube.

5. A high-seal jacket pipeline for high-purity gas according to claim 1, characterized in that: The outer tube includes a plurality of outer tube bodies, on which a sealing baffle fixedly connected to the outer tube body is provided, two adjacent sealing baffles are connected by fixing bolts, the ends of the inflatable airbags are fixedly connected to the sealing baffles, and the number of the inflatable airbags is the same as that of the outer tube bodies.