By using a combination of a pulverized coal concentration separator and a variety of burners in the pulverized coal boiler of the power station, the problem of reduced pulverized coal concentration and temperature during low-load operation is solved, and the stability and economy of the combustion system are achieved.

CN221923455UActive Publication Date: 2024-10-29ZHONGJIE HUANLIWEI (WUHAN) ENERGY TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420216471.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-29
Publication Date
2024-10-29
Estimated Expiration
2034-01-29

AI Technical Summary

Technical Problem

When the power station's pulverized coal boiler is operating at low load, the pulverized coal concentration in the primary air flow decreases, and the furnace temperature decreases, causing the pulverized coal burner to be unable to burn stably, requiring the investment of combustion-supporting equipment, which increases operating costs.

Method used

A combustion system including a pulverized feed pipe, a pulverized coal density separator, a primary air exhaust gas duct and a rich primary air duct is designed. The pulverized coal is divided into rich pulverized coal and light pulverized coal through the pulverized coal density separator. The primary air exhaust gas burner and the rich primary air burner are respectively introduced into the boiler burner area to increase the furnace temperature and pulverized coal concentration.

Benefits of technology

Under low load conditions, the pulverized coal concentration and furnace temperature are increased, ensuring combustion stability, reducing dependence on combustion-supporting equipment, and reducing operating costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221923455U_ABST
    Figure CN221923455U_ABST
Patent Text Reader

Abstract

The low-load stable-combustion combustion system comprises a pulverized coal feeding pipeline, a pulverized coal rich-lean separator, a primary air exhaust pipeline and a rich primary air pipeline, and the pulverized coal rich-lean separator is arranged at the outlet end of the pulverized coal feeding pipeline; the primary air exhaust pipeline and the thick primary air pipeline are both connected with the pulverized coal feeding pipeline in series through a pulverized coal thick-thin separator, and the outlet end of the primary air exhaust pipeline is provided with a primary air exhaust combustor used for being communicated with the upper portion of the combustor area of the boiler body. And the outlet end of the concentrated primary air pipeline is provided with a concentrated primary air combustor communicated with the lower part in the combustor area of the boiler body. According to the utility model, after the concentration of thick pulverized coal airflow in the thick primary air pipeline is improved to the concentration of pulverized coal under the normal load working condition under the low load working condition, the thick pulverized coal airflow enters the boiler body for combustion, and primary air exhaust leads thin pulverized coal to the upper part in the boiler body through the primary air exhaust pipeline; and the temperature of the hearth in the boiler body in the dense pulverized coal burner area is increased.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of pulverized coal boilers in power plants, and in particular to a combustion system and a boiler thereof suitable for low-load stable combustion of pulverized coal boilers in power plants. Background Art

[0002] Due to the rapid development of wind and photovoltaic power generation in my country, traditional pulverized coal-fired power plant boilers have assumed more and more peak load-shaving functions. Boilers are required to operate stably at a 25% BMCR load. In traditional combustion systems, when the boiler load is lower than 40%, in order to maintain the stability of pulverized coal combustion in the furnace, expensive fuel oil needs to be added for combustion assistance, which puts heavy pressure on the economic operation of power plants.

[0003] When the pulverized coal boiler of a power station is operated at low load, in order to ensure the safety of boiler operation, at least two coal mills are usually used for operation. Due to the needs of coal mill operation and the need to prevent powder accumulation in the pulverized coal pipeline, the primary air volume of the pulverized coal burner put into operation when the boiler is operated at low load is limited. The amount of pulverized coal put into operation when the boiler is operated at low load decreases with the load, and the reduction is much greater than the reduction in air volume, resulting in the pulverized coal concentration of the primary air pulverized coal airflow entering the pulverized coal burner for combustion being less than 50% of the usual when the boiler is operated at low load. The boiler furnace temperature also decreases as the boiler load decreases. The reduction in furnace temperature and pulverized coal concentration in the primary air pulverized coal airflow means that the conventional combustion system of the boiler usually needs to use oil guns, plasma burners and other combustion-supporting equipment when the load is less than 40%. Utility Model Content

[0004] The present application provides a combustion system and a boiler suitable for low-load stable combustion of a pulverized coal boiler in a power station, which can solve the problem in the related art that the pulverized coal burner cannot burn stably when the pulverized coal concentration of the primary air flow decreases and the furnace temperature decreases during low-load operation of the boiler.

[0005] In the first aspect, an embodiment of the present application provides a combustion system suitable for low-load stable combustion of a pulverized coal boiler in a power station, comprising: a pulverized coal delivery pipeline, a pulverized coal concentration-lean separator, a primary air and exhaust gas pipeline, and a concentrated primary air pipeline, wherein the pulverized coal concentration-lean separator is arranged at the outlet end of the pulverized coal delivery pipeline; the primary air and exhaust gas pipeline and the concentrated primary air pipeline are both connected in series with the pulverized coal delivery pipeline through the pulverized coal concentration-lean separator, the outlet end of the primary air and exhaust gas pipeline is arranged for a primary air and exhaust gas burner connected to the upper position of the boiler body burner area, and the outlet end of the concentrated primary air pipeline is arranged for a concentrated primary air burner connected to the lower position within the boiler body burner area.

[0006] In some embodiments, the primary air exhaust gas burner is located above the concentrated primary air burner.

[0007] In some embodiments, the primary air exhaust gas pipeline is provided with an adjustable exhaust gas shrinkage hole.

[0008] In some embodiments, an exhaust gas regulating door is provided on the primary exhaust gas duct.

[0009] In some embodiments, an expansion joint is provided on the primary air exhaust gas pipeline.

[0010] In some embodiments, the combustion system further includes a coal mill connected to the inlet end of the powder delivery pipeline.

[0011] In a second aspect, an embodiment of the present application provides a boiler, which includes: a boiler body and a combustion system as described above, wherein the combustion system is connected to the boiler body.

[0012] In some embodiments, the primary air exhaust gas burner is located above the concentrated primary air burner.

[0013] In some embodiments, a main burner is provided on the boiler body.

[0014] In some embodiments, the concentrated primary air burner is located below the main burner, and the primary air exhaust gas burner is located above the main burner.

[0015] The beneficial effects brought by the technical solution provided in the embodiments of the present application include:

[0016] The embodiment of the present application provides a combustion system and a boiler suitable for low-load stable combustion of pulverized coal boilers in power stations. The pulverized coal is divided into thick pulverized coal and light pulverized coal by a pulverized coal concentration separator, so that the concentration of the thick pulverized coal airflow in the thick primary air duct can be increased to the pulverized coal concentration under normal load conditions under low load conditions before entering the boiler body for combustion. The primary air exhaust gas leads the light pulverized coal to the upper position of the burner area of ​​the boiler body through the primary air exhaust gas duct, which can increase the furnace temperature in the boiler body in the thick pulverized coal burner area. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0018] Figure 1 A schematic diagram of the overall structure provided for an embodiment of the present application.

[0019] In the figure: 1. Coal mill; 2. Coal powder delivery pipeline; 3. Coal powder thick and thin separator; 4. Primary air and exhaust gas pipeline; 5. Concentrated primary air pipeline; 6. Expansion joint; 7. Adjustable shrinkage hole for exhaust gas; 8. Exhaust gas regulating door; 9. Main burner; 91. Concentrated primary air burner; 92. Primary air and exhaust gas burner; 10. Boiler body. DETAILED DESCRIPTION

[0020] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0021] See also Figure 1 The embodiment of the present application provides a combustion system and a boiler suitable for low-load stable combustion of a pulverized coal boiler in a power station, which can solve the problem in the related art that the pulverized coal burner cannot burn stably when the pulverized coal concentration of the primary air flow decreases and the furnace temperature decreases during low-load operation of the boiler.

[0022] In the first aspect, an embodiment of the present application provides a combustion system suitable for low-load stable combustion of a pulverized coal boiler in a power station, which includes: a pulverized coal delivery pipeline 2, a pulverized coal concentration separator 3, a primary air exhaust gas pipeline 4, and a concentrated primary air pipeline 5, wherein the pulverized coal concentration separator 3 is arranged at the outlet end of the pulverized coal delivery pipeline 2; the primary air exhaust gas pipeline 4 and the concentrated primary air pipeline 5 are both connected in series with the pulverized coal delivery pipeline 2 through the pulverized coal concentration separator 3, and the outlet end of the primary air exhaust gas pipeline 4 is provided with a primary air exhaust gas burner 92 for connecting to the upper position of the burner area of ​​the boiler body 10, and the outlet end of the concentrated primary air pipeline 5 is provided with a concentrated primary air burner 91 for connecting to the lower position in the burner area of ​​the boiler body 10.

[0023] Among them, the upper position of the burner area of ​​the boiler body 10 refers to the area above the main burner 9 installed on the boiler body 10, that is, the upper position of the coal powder combustion area in the boiler body 10. Similarly, the lower position of the burner area of ​​the boiler body 10 refers to the lower position of the area where the main burner 9 is installed on the boiler body 10, that is, the lower position of the coal powder combustion area in the boiler body 10.

[0024] In the present application, the pulverized coal is divided into concentrated pulverized coal and light pulverized coal by a pulverized coal thick and thin separator 3, so that the concentrated pulverized coal airflow concentration in the concentrated primary air duct 5 can be increased to the pulverized coal concentration under normal load conditions under low load conditions and then enter the boiler body 10 for combustion. The primary air exhaust gas leads the light pulverized coal to the upper position of the burner area of ​​the boiler body 10 through the primary air exhaust gas duct 4, which can also increase the furnace temperature of the boiler body 10 in the concentrated pulverized coal burner area.

[0025] Among them, the combustion system also includes a coal mill 1, and the coal mill 1 is connected to the inlet end of the powder delivery pipeline 2, that is, the coal mill 1 delivers the coal powder into the powder delivery pipeline 2 through the inlet end of the powder delivery pipeline 2, and the coal powder and the primary air coal powder airflow pass through the powder delivery pipeline 2 and enter the coal powder thick and thin separator 3 for thick and thin separation, and then the primary air coal powder airflow is divided into a thick coal powder airflow and a thin coal powder airflow, wherein the light coal powder airflow passes through the primary air exhaust gas pipeline 4 and enters the primary air exhaust gas burner 92 and then burns in the furnace of the boiler body 10, and the thick coal powder airflow passes through the thick primary air pipeline 5 and enters the thick primary air burner 91 and then enters the furnace of the boiler body 10 for combustion.

[0026] In this application, Figure 1 In the drawings shown, the boiler body 10 shown on the left and right sides are respectively the front wall and the rear wall of the same boiler body 10. It should be noted that when the pulverized coal boiler of a power station is operated at a low load, in order to ensure the safety of the boiler operation, usually at least two coal mills 1 are used for operation, that is, on one boiler body 10, Figure 1 In the figure, two combustion systems are provided. In addition, different numbers of combustion systems can be provided on one boiler body 10 according to actual conditions, for example, three combustion systems, four combustion systems, etc. can be provided on the boiler body 10.

[0027] On the basis of the above embodiments, in this embodiment, the primary air exhaust gas burner 92 is arranged above the concentrated primary air burner 91. More specifically, a main burner 9 is arranged on the boiler body 10, the concentrated primary air burner 91 is arranged below the main burner 9, and the primary air exhaust gas burner 92 is arranged above the main burner 9. Therefore, when the concentrated pulverized coal gas flows through the concentrated primary air duct 5 and enters the concentrated primary air burner 91 and enters the furnace of the boiler body 10 for combustion, the pulverized coal concentration in the concentrated pulverized coal gas flow is greatly increased, which can increase the combustion temperature of the lower position in the pulverized coal combustion area in the boiler body 10, and the light pulverized coal gas flows through the primary air exhaust gas duct 4 and enters the primary air exhaust gas burner 92 and is sent to the upper space in the furnace of the boiler body 10, which is conducive to increasing the height of the furnace flame and increasing the combustion temperature of the lower part of the boiler body 10 when the boiler body 10 is stably burning at low load.

[0028] When the boiler body 10 is running at low load, the burners corresponding to the two coal mills 1 put into operation should be relatively concentrated, that is, the concentrated primary air burners 91 in one combustion system are arranged adjacent to the concentrated primary air burners 91 in another combustion system, and the primary air exhaust gas burners 92 in one combustion system are arranged adjacent to the primary air exhaust gas burners 92 in another combustion system, so that the heat load of the boiler body 10 is concentrated. The concentrated primary air burners 91 arranged on the front wall and the rear wall are all located below the main burner 9.

[0029] On the basis of the above embodiment, in this embodiment, an exhaust air adjustable shrinkage hole 7 is provided on the primary air exhaust air duct 4. Through the exhaust air adjustable shrinkage hole 7, the air volume inside the primary air exhaust air duct 4 and the concentrated primary air duct 5 can be adjusted. When the combustion system is running, the exhaust air adjustable shrinkage hole 7 on the exhaust air duct can be used to adjust the concentrated primary air volume and the lean primary air volume to be the same.

[0030] On the basis of the above embodiment, in this embodiment, an exhaust gas wind regulating door 8 is provided on the primary air exhaust gas pipeline 4. When the coal quality changes, the exhaust gas wind regulating door 8 provided on the primary exhaust gas pipeline can be used to adjust the wind speed of the concentrated primary air burner 91 and the primary air exhaust gas burner 92 to avoid the occurrence of coking of the primary air burner and the primary air exhaust gas burner 92.

[0031] On the basis of the above embodiment, in this embodiment, an expansion joint 6 is provided on the primary air exhaust gas pipeline 4 to solve the expansion difference between the primary air exhaust gas pipeline 4 and the boiler body 10. The expansion joint 6, the exhaust gas adjustable shrinkage hole 7 and the exhaust gas regulating door 8 are installed on the primary air exhaust gas pipeline 4 in sequence.

[0032] In a second aspect, an embodiment of the present application provides a boiler, which includes: a boiler body 10 and a combustion system provided by any of the above embodiments of the present application, wherein the combustion system is connected to the boiler body 10 .

[0033] In the present application, the combustion system is used on the boiler body 10, and the coal powder is divided into thick coal powder and light coal powder by the coal powder thick-lean separator 3, so that the thick coal powder airflow concentration in the thick primary air duct 5 can be increased to the coal powder concentration under normal load conditions under low load conditions and then enter the boiler body 10 for combustion. The primary air exhaust gas leads the light coal powder to the upper position of the burner area in the boiler body 10 through the primary air exhaust gas duct 4, which can also increase the furnace temperature in the boiler body 10 in the thick coal powder burner area.

[0034] Among them, the combustion system also includes a coal mill 1, which is connected to the inlet end of the powder delivery pipeline 2, that is, the coal mill 1 delivers the coal powder into the powder delivery pipeline 2 through the inlet end of the powder delivery pipeline 2, and the coal powder and the primary air coal powder airflow pass through the powder delivery pipeline 2 and enter the coal powder thick and thin separator 3 for thick and thin separation, and then the primary air coal powder airflow is divided into a thick coal powder airflow and a thin coal powder airflow, wherein the light coal powder airflow passes through the primary air exhaust gas pipeline 4 and enters the primary air exhaust gas burner 92 and then burns in the furnace of the boiler body 10, and the thick coal powder airflow passes through the thick primary air pipeline 5 and enters the thick primary air burner 91 and then enters the lower position of the coal powder combustion area in the boiler body 10 for combustion.

[0035] On the basis of the above embodiment, in this embodiment, the primary air exhaust gas burner 92 is arranged above the concentrated primary air burner 91. More specifically, a main burner 9 is arranged on the boiler body 10, the concentrated primary air burner 91 is arranged below the main burner 9, and the primary air exhaust gas burner 92 is arranged above the main burner 9. Therefore, when the boiler is operating at a load of less than 25%, after the lean coal powder airflow of the primary air pulverized coal airflow coming out of the pulverizer 1 is separated by the external coal powder thick-lean separator 3, the dense coal powder airflow enters the dense primary air burner 91 through the dense primary air duct 5 and then enters the lower position of the coal powder combustion area in the boiler body 10 for combustion. The coal powder concentration in the dense coal powder airflow is significantly increased and can be increased to the coal powder concentration under normal load conditions, thereby increasing the combustion temperature at the lower position of the coal powder combustion area in the boiler body 10. After the lean coal powder airflow enters the primary air exhaust gas burner 92 through the primary air exhaust gas duct 4, it is sent to the upper space in the furnace of the boiler body 10, that is, the top of the main burner 9, which is beneficial to increase the height of the furnace flame and increase the combustion temperature at the lower position of the coal powder combustion area in the boiler body 10 when the boiler body 10 is stably burning at low load.

[0036] In the description of the present application, it should be noted that the terms "upper", "lower", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application. Unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood according to the specific circumstances.

[0037] It should be noted that, in this application, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.

[0038] The above description is only a specific implementation of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest range consistent with the principles and novel features applied for herein.

Claims

1. A combustion system suitable for low-load stable combustion of pulverized coal boilers in power plants, characterized in that: It includes: Powder delivery pipeline (2); A coal powder thick-thin separator (3), wherein the coal powder thick-thin separator (3) is arranged at the outlet end of the coal powder delivery pipeline (2); A primary air exhaust gas pipeline (4) and a concentrated primary air pipeline (5), wherein the primary air exhaust gas pipeline (4) and the concentrated primary air pipeline (5) are both connected in series with the pulverized coal conveying pipeline (2) via a pulverized coal thick-thin separator (3), the outlet end of the primary air exhaust gas pipeline (4) is provided with a primary air exhaust gas burner (92) for communicating with an upper position of a burner area of ​​a boiler body (10), and the outlet end of the concentrated primary air pipeline (5) is provided with a concentrated primary air burner (91) for communicating with a lower position in the burner area of ​​the boiler body (10).

2. The combustion system suitable for low-load stable combustion of pulverized coal boilers in power plants as claimed in claim 1, characterized in that: The primary air exhaust gas burner (92) is located above the concentrated primary air burner (91).

3. The combustion system suitable for low-load stable combustion of pulverized coal boilers in power plants as claimed in claim 1, characterized in that: The primary air exhaust gas pipeline (4) is provided with an exhaust gas air adjustable shrinkage hole (7).

4. The combustion system suitable for low-load stable combustion of pulverized coal boilers in power plants as claimed in claim 1, characterized in that: The primary exhaust air pipeline (4) is provided with an exhaust air regulating door (8).

5. The combustion system suitable for low-load stable combustion of pulverized coal boilers in power plants as claimed in claim 1, characterized in that: An expansion joint (6) is provided on the primary air exhaust gas pipeline (4).

6. The combustion system suitable for low-load stable combustion of pulverized coal boilers in power plants as claimed in claim 1, characterized in that: The combustion system further comprises a coal mill (1), wherein the coal mill (1) is connected to the inlet end of the powder delivery pipeline (2).

7. A boiler, characterized in that: It includes: Boiler body(10) ; The combustion system according to any one of claims 1 to 6, wherein the combustion system is connected to a boiler body (10).

8. The boiler according to claim 7, characterized in that: The primary air exhaust gas burner (92) is located above the concentrated primary air burner (91).

9. The boiler according to claim 8, characterized in that: The boiler body (10) is provided with a main burner (9).