Photovoltaic cement pier moving and placing device
By designing the photovoltaic cement pier mobile placement device of support frames, lifting devices and power source components, the inefficiency and safety risks of construction workers when handling and moving cement piers are solved, and efficient and safe placement of cement piers is achieved. Reduced noise interference.
Patent Information
- Application Number
- CN202420657772.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-01
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2034-04-01
AI Technical Summary
The high weight of photovoltaic cement piers leads to high consumption of construction personnel during handling and moving and placement, low efficiency, increasing construction costs and safety risks, and may lead to roof collision noise and affecting the environment.
A photovoltaic cement pier mobile placement device including a support frame, a lifting device and a power source component is designed. The support frame is equipped with a universal wheel at the bottom, and the lifting device is arranged on the top of the support frame. The power source component is connected to the lifting device to provide power. , the suspension, movement and precise placement of cement piers are achieved through universal wheel pushing support frame and lifting device.
It reduces labor consumption, improves construction efficiency, reduces construction costs, reduces safety risks, and reduces noise interference caused by collision between cement piers and roofs.
Smart Images

Figure CN221939913U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of photovoltaics, and in particular relates to a mobile placement device for photovoltaic cement piers. Background Art
[0002] Photovoltaic cement piers are used as counterweights for photovoltaic brackets and are key materials in distributed photovoltaic construction. They have wind resistance and pressure resistance. As supporting equipment for photovoltaic modules, photovoltaic cement piers have strong stability, strong impact resistance and strong tolerance, which can ensure that photovoltaic modules remain balanced and stable in harsh environments. Different roof building structures determine the design height of photovoltaic brackets, and the weight of photovoltaic cement piers will also increase with the height of photovoltaic brackets. The weight of cement piers made by molding technology can reach 400-500 kilograms, which greatly increases the difficulty of moving and placing cement piers. At present, the placement construction of photovoltaic cement piers mainly uses a crane to hoist the cement pier to the roof, and then the construction workers use ropes, iron bars and other items to move the cement pier to a handcart through the joint efforts of multiple people. After transporting it to the required location, the construction workers work together to unload the cement pier from the handcart and place it nearby. Finally, according to the requirements of the drawings, they work together to adjust and place the cement pier to the precise position. Due to the heavy weight of the cement pier, during the transportation and mobile placement process, the construction labor consumption is high, the long-term work efficiency is low, and the construction cost is increased. In addition, during the process of carrying and moving the concrete, construction workers are prone to joint sprains, muscle strains and other injuries, increasing safety risks. In addition, during rooftop construction, construction workers cannot control the concrete piers during the process of moving and placing them, which will cause the concrete piers to collide with the roof and generate noise, affecting the office and operating environment downstairs. Utility Model Content
[0003] Therefore, the technical problem to be solved by the present invention is to provide a mobile placement device for photovoltaic cement piers, which can reduce labor consumption, improve construction efficiency and reduce construction costs.
[0004] In order to solve the above problems, the utility model provides a photovoltaic cement pier mobile placement device, including: a support frame, a lifting device and a power source assembly. The bottom of the support frame is provided with a universal wheel. The lifting device is arranged on the top of the support frame. The lifting device can lift the cement pier. The power source assembly is arranged on the support frame. The power source assembly is connected to the lifting device and is used to provide power for the lifting device.
[0005] Optionally, the support frame includes: a top frame, a plurality of support legs, and a plurality of reinforcing beams. A cross beam is provided on the top frame. A lifting device is provided on the cross beam. The top ends of the plurality of support legs are connected to the top frame. A universal wheel is provided at the bottom of each support leg. Both ends of each reinforcing beam are respectively connected between the support leg and the top frame to form a triangular support.
[0006] Optionally, the top frame includes: four square steels. The four square steels are connected end to end to form a square frame. The crossbeam is arranged between the square steels on opposite sides of the square frame.
[0007] Optionally, the support feet can be raised and lowered.
[0008] Optionally, the support frame further comprises: a first connecting plate and a second connecting plate. The first connecting plate is arranged at the top end of the supporting foot. The first connecting plate is connected to the top frame. The second connecting plate is arranged at the bottom end of the supporting foot. The universal wheel is mounted on the second connecting plate.
[0009] Optionally, it also includes: a brake system, which is arranged on the universal wheel.
[0010] Optionally, the brake system includes: a double brake assembly or a side brake assembly.
[0011] Optionally, the lifting device includes: an electric winch and a control handle. The electric winch is connected to the power source assembly. A connecting piece is provided at the lifting end of the electric winch. The connecting piece is used to connect the cement pier. The control handle is connected to the electric winch. The control handle is used to control the lifting and lowering of the electric winch.
[0012] Optionally, the power source assembly includes: a battery. The battery is fixed to the top of the support frame. The lifting device is connected to the battery.
[0013] Optionally, the universal wheel is a heavy-duty universal wheel.
[0014] Beneficial Effects
[0015] The photovoltaic cement pier mobile placement device provided by the utility model includes: a support frame, a lifting device and a power source assembly. The bottom of the support frame is provided with a universal wheel. The lifting device is arranged on the top of the support frame. When in use, the support frame of the device is pushed by the universal wheel so that the lifting device on the support frame is located directly above the cement pier, and then the cement pier is lifted by the lifting device so that the cement pier is suspended on the support frame. Then, the support frame is pushed by the universal wheel to move the cement pier to the designated position, and then the cement pier is lowered by the lifting device to put the cement pier into the accurate position. The device has a simple structure and a low cost. Even a construction worker can use the device to easily place the cement pier in any position and can accurately control it, which improves the work efficiency of the construction workers, reduces the construction cost, reduces the physical exertion and workload of manual handling, and reduces the safety risk. In addition, it can also effectively reduce the noise caused by the collision between the manual handling of the cement pier and the roof, and avoid interfering with the normal production and living environment. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 A schematic diagram of the three-dimensional structure of a photovoltaic cement pier mobile placement device according to an embodiment of the present utility model;
[0017] Figure 2 A structural schematic diagram of a cement pier according to an embodiment of the utility model;
[0018] Figure 3 The present invention is a structural schematic diagram of a cement pier according to an embodiment of the present invention.
[0019] The reference numerals are as follows:
[0020] 1. Support frame; 2. Universal wheel; 3. Lifting device; 4. Power source assembly; 5. Cement pier; 6. Embedded parts;
[0021] 11. Top frame; 12. Crossbeam; 13. Support foot; 14. Reinforcement beam; 15. First connecting plate; 16. Second connecting plate;
[0022] 31. Electric winch; 32. Control handle. DETAILED DESCRIPTION
[0023] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0024] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0025] In the present invention, unless otherwise clearly specified and limited, the terms "install", "connect", "connect", "fix" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0026] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.
[0027] This embodiment provides a mobile placement device for photovoltaic cement piers. Figure 1 A schematic diagram of the three-dimensional structure of a photovoltaic cement pier mobile placement device provided in this embodiment.
[0028] like Figure 1 As shown, the photovoltaic cement pier mobile placement device of this embodiment includes: a support frame 1, a lifting device 3 and a power source assembly 4. A universal wheel 2 is provided at the bottom of the support frame 1. The lifting device 3 is arranged on the top of the support frame 1. The lifting device 3 can lift the cement pier 5. The power source assembly 4 is arranged on the support frame 1. The power source assembly 4 is connected to the lifting device 3 and is used to provide power for the lifting device 3.
[0029] In some examples, such as Figure 1 As shown, the height of the support frame 1 is 0.5-1.5 m. Such a setting can meet the use requirements, can not only lift the cement pier 5, but also have good stability. For example, the height of the support frame is 1 m.
[0030] It should be noted that the shapes of the cement piers 5 are different. Figure 2 and Figure 3 As shown, common cement piers 5 are generally rectangular or cylindrical. The top of the cement pier 5 is generally embedded with embedded parts 6 such as lifting rings for easy transportation. When the photovoltaic cement pier mobile placement device of this embodiment is used to transport the cement pier 5, the lifting device 3 can be connected to the embedded parts 6 on the top of the cement pier 5 to achieve the lifting of the cement pier 5.
[0031] The photovoltaic cement pier mobile placement device of the present embodiment includes a support frame 1, a lifting device 3 and a power source assembly 4. A universal wheel 2 is provided at the bottom of the support frame 1. The lifting device 3 is arranged on the top of the support frame 1. When in use, the support frame 1 is pushed so that the lifting device 3 on the support frame 1 is located directly above the cement pier 5, and then the cement pier 5 is lifted by the lifting device 3 so that the cement pier 5 is suspended on the support frame 1. Then the support frame 1 is pushed to drive the cement pier 5 to move, and the cement pier 5 is transported to the designated position, and then the cement pier 5 is lowered by the lifting device 3 to put the cement pier 5 in the correct position. The device has a simple structure and a low cost. Even a construction worker can use the device to easily place the cement pier 5 in any position and can accurately control it, which improves the work efficiency of the construction workers, reduces the construction cost, and reduces the physical exertion and workload of manual handling, reduces the safety risk, and can effectively reduce the noise caused by the collision between the manual handling of the cement pier 5 and the roof, avoiding interference with the normal production and living environment.
[0032] In some embodiments, Figure 1 As shown, the support frame 1 includes: a top frame 11, a plurality of support legs 13, and a plurality of reinforcing beams 14. A cross beam 12 is provided on the top frame 11. A lifting device 3 is provided on the cross beam 12. The top ends of the plurality of support legs 13 are connected to the top frame 11. A universal wheel 2 is provided at the bottom of each support leg 13. The two ends of each reinforcing beam 14 are respectively connected between the support leg 13 and the top frame 11 to form a triangular support.
[0033] In some examples, such as Figure 1 As shown, the top frame 11, the plurality of support legs 13, and the plurality of reinforcing beams 14 are connected by bolts. With such a configuration, the connection is reliable, and it is convenient to assemble and disassemble, and to store. It is understandable that in other embodiments, the top frame 11, the plurality of support legs 13, and the plurality of reinforcing beams 14 can also be connected by welding, and this embodiment does not impose too many restrictions on this.
[0034] In some examples, such as Figure 1 As shown, two cross beams 12 are arranged on the top frame 11. The two cross beams 12 are parallel to each other. The lifting device 3 is connected to the two cross beams 12. Such arrangement is conducive to improving the firmness and stability of the installation of the lifting device 3.
[0035] In some examples, such as Figure 1 As shown, a reinforcing beam 14 is connected between each supporting foot 13 and the top frame 11. And multiple reinforcing beams 14 are arranged on both sides of the top frame 11 parallel to the cross beam 12. Such arrangement can avoid interference between the reinforcing beams 14 and the cement pier 5 during use.
[0036] The support frame of this embodiment includes a top frame 11, a plurality of support legs 13, and a plurality of reinforcing beams 14. The plurality of support legs 13 are supported on the top frame 11, and a universal wheel 2 is provided at the bottom of the support legs 13, and a cross beam 12 is provided on the top frame 11. The lifting device 3 is provided on the cross beam 12, and can lift the cement pier 5. After lifting the cement pier 5, the top frame 11 and the plurality of support legs 13 bear the weight of the cement pier 5. Workers only need to push the support frame 1 to transport and move the cement pier 5, which saves time and effort, and is highly efficient. In addition, by providing a reinforcing beam 14 between the support legs 14 and the top frame 11, it is beneficial to improve the structural strength of the support legs 13, thereby improving the bearing capacity of the support frame 1.
[0037] In some embodiments, Figure 1 As shown, the top frame 11 includes four square steels. The four square steels are connected end to end to form a square frame. The cross beam 12 is set between the square steels on opposite sides of the square frame.
[0038] In some examples, such as Figure 1 As shown, the top frame 11 includes four square steels connected end to end to form a square frame, and there are four supporting legs 13, which are arranged at the four corners of the square frame. Such an arrangement is conducive to improving the structural strength of the support frame 1.
[0039] In some examples, such as Figure 1 As shown, the four square steels are connected by welding to form a square frame. Such a configuration can make the structure of the square frame more stable. However, it is understandable that in other embodiments, the four square steels can also be connected by connecting members such as bolts, and this embodiment does not impose too many restrictions on this.
[0040] It should be noted that, in other embodiments, the shape of the top frame 11 is not limited to a quadrilateral, but may be a hexagon, a circle or other shapes, and may be specifically set according to the use requirements.
[0041] The top frame 11 of the present embodiment is formed by square steel, which has a firm structure and low cost, and is conducive to reducing the manufacturing difficulty and cost of the device.
[0042] In some embodiments, see Figure 1 , the supporting foot 13 can be raised and lowered.
[0043] For some examples, see Figure 1 The supporting foot 13 is a hydraulic telescopic rod. With such arrangement, the load-bearing capacity is strong and the adjustment is convenient.
[0044] For some examples, see Figure 1 The support foot 13 can also be formed by splicing or plugging multiple sections of pipes. When multiple sections of pipes are spliced to form the support foot 13, the connecting pieces between the multiple sections of pipes can be bolts. When multiple sections of pipes are plugged to form the support foot 13, the positioning pin can be used to limit the height of the support foot.
[0045] The support legs 13 of this embodiment can be raised and lowered, and the height of the support legs 13 can be adjusted according to the height of the installation space or the height of the cement pier 5, thereby expanding the application scope of the device and making it more flexible to use.
[0046] In some embodiments, Figure 1 As shown, the support frame 1 further includes: a first connecting plate 15 and a second connecting plate 16. The first connecting plate 15 is arranged at the top end of the supporting foot 13. The first connecting plate 15 is connected to the top frame 11. The second connecting plate 16 is arranged at the bottom end of the supporting foot 13. The universal wheel 2 is mounted on the second connecting plate 16.
[0047] In some examples, such as Figure 1As shown, there are two first connecting plates 15 between each supporting foot 13 and the top frame 11, one of which is welded to the top of the supporting foot 13, and the other is welded to the bottom of the top frame 11. The two first connecting plates 15 are fastened and connected by bolts. Such an arrangement can make the connection between the supporting foot 13 and the top frame 11 more reliable.
[0048] In some examples, such as Figure 1 As shown, there are two second connecting plates 16 between each supporting foot 13 and the universal wheel 2, one of which is welded to the bottom end of the supporting foot 13, and the other is welded to the top of the wheel frame of the universal wheel 2. The two second connecting plates 16 are fastened and connected by bolts. Such an arrangement can make the connection between the supporting foot 13 and the universal wheel 2 more reliable.
[0049] In this embodiment, the support leg 13 is connected to the top frame 11 via a first connecting plate 15 , and the support leg 13 is connected to the universal wheel 2 via a second connecting plate 16 , which is beneficial to improving the overall structural strength, stability and load-bearing capacity of the support frame 1 .
[0050] In some embodiments, see Figure 1 , also includes: a brake system, which is arranged on the universal wheel 2.
[0051] In this embodiment, a brake system is arranged on the universal wheel 2 to facilitate the braking and positioning of the support frame 1 and reduce the difficulty of moving and placing the cement pier 5.
[0052] In some embodiments, see Figure 1 , the brake system includes: a double brake assembly or a side brake assembly.
[0053] The dual brake of the universal wheel 2 is a relatively advanced braking system, which is locked by installing brakes on both sides at the same time. The advantage of this braking system is that it can provide a more uniform braking force, making the support frame 1 more stable when stationary and moving. In addition, the dual brake can also improve the braking performance and safety by achieving synchronous braking.
[0054] The side brake of the universal wheel 2 is a common braking system, which is locked by a brake installed on the side or the tail. The advantage of this braking system is that it can provide a strong braking force, so that the support frame 1 can remain stable when it is stationary and moving. In addition, the side brake can also adapt to different roof conditions and load conditions by adjusting the tightness of the brake.
[0055] Universal caster 2 side brake and double brake are two different brake systems, they have certain differences in design and function. In the double brake state, both the wheel rotation and the bead plate rotation must be locked, and the object cannot be moved or the rotation direction adjusted in the double brake state. The side brake only locks the rotation but not the bead plate rotation direction, so the caster can be adjusted in this state.
[0056] In some embodiments, Figure 1 As shown, the lifting device 3 includes: an electric winch 31 and a control handle 32. The electric winch 31 is connected to the power source assembly 4. A connecting piece is provided at the lifting end of the electric winch 31. The connecting piece is used to connect the cement pier 5. The control handle 32 is connected to the electric winch 31. The control handle 32 is used to control the lifting and lowering of the electric winch 31.
[0057] For some examples, see Figure 1 , the specification of the electric winch 31 is 12V, 4000 pounds. Such a setting can meet the use requirements. However, it can be understood that in other embodiments, electric winches 31 of other specifications can also be selected, which can be set according to the use requirements. This embodiment does not make too many restrictions on this.
[0058] For some examples, see Figure 1 The lifting device 3 may also include a slide rail and a crane, wherein the slide rail is arranged on the beam 12 along the length direction of the beam, and the crane is movably arranged on the slide rail. In this way, the crane can move along the beam 12, which is more convenient to use and has a higher degree of freedom.
[0059] In some examples, the connecting piece of the lifting end of the electric winch 31 includes a hook. The hook is used as a connecting piece to cooperate with the embedded part 6 on the cement pier 5, which is convenient for installation and disassembly.
[0060] The lifting device 3 of this embodiment includes an electric winch 31 and a control handle 32. The lifting and lowering of the electric winch 31 can be controlled by the control handle 32, which is convenient to use.
[0061] In some embodiments, Figure 1 As shown, the power source assembly 4 includes: a battery. The battery is fixed to the top of the support frame 1. The lifting device 3 is connected to the battery.
[0062] For some examples, see Figure 1 , the battery specifications are 12V, 32AH. Such a setting can meet the use requirements. However, it can be understood that in other embodiments, the battery specifications can be set according to actual use requirements, and this embodiment does not impose too many restrictions on this.
[0063] It should be noted that, in other embodiments, the battery may not be included, and the electric winch 31 may be directly plugged in for use.
[0064] In this embodiment, a battery is arranged on the support frame 1 to provide electric energy for the lifting device 3. When in use, there is no need to provide a power connection device such as a wire or a socket strip for plugging in. This is more flexible and convenient and has a wider range of use.
[0065] In some embodiments, see Figure 1 , the universal wheel 2 is a heavy-duty universal wheel.
[0066] The universal wheel 2 of this embodiment is a heavy-duty universal wheel, which can adapt to different roof conditions, has a strong load-bearing capacity and is durable.
[0067] The above is an introduction to the photovoltaic cement pier mobile placement device of this embodiment. Construction workers use the photovoltaic cement pier mobile placement device to move and transport cement piers on the roof, which can bring convenience to the construction. The device has a simple structure and low cost, and can be widely used in the distributed photovoltaic construction process.
[0068] It is easy for those skilled in the art to understand that, under the premise of no conflict, the above-mentioned advantageous methods can be freely combined and superimposed.
[0069] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention shall be included in the protection scope of the present invention. The above are only preferred implementations of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and variations can be made without departing from the technical principles of the present invention, and these improvements and variations should also be regarded as the protection scope of the present invention.
Claims
1. A photovoltaic cement pier mobile placement device, characterized in that: include: A support frame, wherein a universal wheel is provided at the bottom of the support frame; A lifting device, arranged on the top of the support frame; The lifting device is capable of lifting the cement pier; A power source assembly is arranged on the support frame; the power source assembly is connected to the lifting device to provide power for the lifting device.
2. The photovoltaic cement pier mobile placement device according to claim 1 is characterized in that: The support frame comprises: A top frame, wherein a crossbeam is disposed on the top frame; and the lifting device is disposed on the crossbeam; A plurality of supporting legs, the top ends of which are connected to the top frame; a universal wheel is provided at the bottom of each supporting leg; A plurality of reinforcing beams, both ends of each reinforcing beam are respectively connected between the supporting feet and the top frame to form a triangular support.
3. The photovoltaic cement pier mobile placement device according to claim 2 is characterized in that: The top frame comprises: Four square steels are connected end to end to form a square frame; the crossbeam is erected between the square steels on opposite sides of the square frame.
4. The photovoltaic cement pier mobile placement device according to claim 2, characterized in that: The supporting feet can be raised and lowered.
5. The photovoltaic cement pier mobile placement device according to claim 2, characterized in that: The support frame also includes: A first connecting plate is disposed on the top of the supporting leg; the first connecting plate is connected to the top frame; The second connecting plate is arranged at the bottom end of the supporting foot; the universal wheel is installed on the second connecting plate.
6. The photovoltaic cement pier mobile placement device according to claim 1 or 2, characterized in that: Also includes: The brake system is arranged on the universal wheel.
7. The photovoltaic cement pier mobile placement device according to claim 6, characterized in that: The brake system comprises: a double brake assembly or a side brake assembly.
8. The photovoltaic cement pier mobile placement device according to claim 1, characterized in that: The lifting device comprises: An electric winch, the electric winch is connected to the power source assembly; a connecting piece is provided at the lifting end of the electric winch; the connecting piece is used to connect to the cement pier; A control handle is connected to the electric winch; the control handle is used to control the lifting and lowering of the electric winch.
9. The photovoltaic cement pier mobile placement device according to claim 1, characterized in that: The power source assembly comprises: A storage battery is fixed to the top of the support frame; and the lifting device is connected to the storage battery.
10. The photovoltaic cement pier mobile placement device according to claim 1, characterized in that: The universal wheel is a heavy-duty universal wheel.