Crack pouring structure for highway lane pavement and hardened road shoulder
By setting a sealing structure of polyurethane material and waterproof membrane between the highway shoulders, the problems of prone to cracking and poor durability of traditional shoulders are solved, and higher water protection and crack resistance are achieved, and the service life of the shoulders is extended.
Patent Information
- Application Number
- CN202420272025.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-04
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2034-02-04
AI Technical Summary
The traditional highway shoulder filling structure is prone to rupture and has poor durability. The inflow of rainwater damages the stability of the pavement surface and base layer, resulting in more serious pavement diseases.
A strip groove is set between the asphalt concrete pavement and the hardened shoulder, filled with polyurethane material, fiber layer and waterproof membrane to form a closed sealing structure to adapt to the expansion and contraction of the pavement and add flexible connections on the shoulders.
Effectively prevent moisture penetration, reduce aging and damage to the shoulder, improve water penetration ability, extend maintenance cycle, reduce maintenance costs, and enhance the durability and crack resistance of the shoulder.
Smart Images

Figure CN221941001U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of road engineering, in particular to a high-speed road lane pavement and hardened shoulder grouting structure. Background Art
[0002] Highways are fast and safe means of transportation, but in daily use, the shoulders are often damaged by factors such as vehicle load, weather and environment. In order to ensure the stability of the road and driving safety, the shoulders need to be regularly maintained and repaired. The traditional highway shoulder caulking structure has some problems, such as easy to crack and poor durability, which need to be improved.
[0003] In a certain project, cracks occurred on the asphalt pavement and hardened shoulder due to high altitude frost heave, and rainwater flowed into the road surface, destroying the stability of the pavement surface and base layer, which may cause more serious pavement diseases. By using this technology to fill the cracks in the asphalt concrete pavement and hardened shoulder, the road surface is in good working condition, ensuring that vehicles passing on the highway can run quickly, safely and comfortably. Utility Model Content
[0004] The purpose of the utility model is to provide a structure for grouting the road surface and hardened shoulders of highway lanes, so as to solve some problems existing in the traditional structure for grouting the road shoulders of highways, such as easy rupture, poor durability and the technical problems that rainwater flows into the road surface and destroys the stability of the road surface layer and the base layer.
[0005] To achieve the above purpose, the utility model adopts the following technical solutions.
[0006] A structure for grouting a lane pavement and a hardened shoulder of a highway, comprising a lane pavement and a hardened shoulder; the lane pavement and the hardened shoulder are both paved with asphalt concrete, and a crushed soil roadbed, a gravel layer and a heat insulation layer are sequentially laid from bottom to top below the lane pavement and the hardened shoulder; a strip groove is provided along the crack between the lane pavement and the hardened shoulder; the bottom surface of the strip groove is located above the heat insulation layer, and the side surface of the strip groove is an uneven rough surface; a lower layer of grouting material, a fiber layer, an upper layer of grouting material and a waterproof membrane are arranged from bottom to top in the strip groove; the fiber layer extends into the uneven gap on the side surface of the strip groove; the top surface of the waterproof membrane is adapted to the top surface of the lane pavement and the hardened shoulder.
[0007] Preferably, the width of the strip groove is at least 12 mm, the depth of the strip groove is 12 mm to 25 mm, and the depth-to-width ratio of the strip groove is less than 2:1.
[0008] Preferably, the upper caulking material and the lower caulking material are both made of polyurethane material, and the sum of the thicknesses of the upper caulking material, the fiber layer and the lower caulking material is 11 mm to 27 mm.
[0009] Preferably, the top surface of the waterproof membrane is flush with the top surface of the roadway pavement or the top surface of the waterproof membrane is 2 to 3 mm higher than the roadway pavement.
[0010] Preferably, the waterproof membrane has a thickness of 0.1 mm to 1.0 mm.
[0011] Preferably, the hardened shoulder has a slope of 2%, and the slope gradually slopes downward from the inside to the outside.
[0012] Preferably, flexible connections are formed between the upper caulking material and the hardened shoulder and lane pavement, between the lower caulking material and the hardened shoulder and lane pavement, and between the waterproof membrane and the hardened shoulder and lane pavement to adapt to the expansion and contraction deformation of the road surface.
[0013] Compared with the prior art, the utility model has the following characteristics and beneficial effects.
[0014] 1. The utility model provides a caulking material between the lane pavement and the hardened shoulder of the highway, and covers the caulking material with a layer of waterproof membrane. This design can effectively prevent moisture penetration between the pavement and the shoulder, reduce aging and damage of the shoulder structure, and the caulking material is made of polyurethane material, which has good elasticity and crack resistance. The waterproof membrane is made of polyethylene material, which has good water resistance and corrosion resistance. A closed sealing structure is formed between the caulking material, the waterproof membrane and the shoulder, which can effectively prevent moisture from entering and form a flexible connection to adapt to the expansion and contraction of the road surface.
[0015] 2. The utility model of the grouting structure between the highway lane pavement and the hardened shoulder increases the water penetration resistance of the shoulder, preventing the accumulation of water inside the shoulder and causing the shoulder to sink; improves the design of the grouting material so that it is tightly bonded between the shoulder and the base layer, reducing the risk of cracking and falling off; improves the durability of the shoulder, extends the maintenance cycle, and reduces the maintenance cost.
[0016] 3. The highway lane pavement and hardened shoulder grouting structure of the utility model is suitable for the maintenance and repair of highway shoulders and can be widely used in the field of road construction and maintenance.
[0017] 4. The utility model provides a fiber layer between the upper caulking material and the lower caulking material for the caulking structure of the highway lane pavement and the hardened shoulder, thereby increasing the crack resistance of the caulking structure and improving the durability and service life of the pavement. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The utility model is further described in detail below in conjunction with the accompanying drawings.
[0019] Figure 1It is a schematic cross-sectional structure diagram of a highway lane pavement and hardened shoulder grouting structure of the utility model.
[0020] Figure 2 yes Figure 1 Schematic diagram of the enlarged structure of point A.
[0021] Figure symbols: 1-lane pavement, 2-hardened shoulder, 3-gravel roadbed, 4-gravel layer, 5-insulation layer, 6-strip groove, 7-lower layer caulking material, 8-fiber layer, 9-upper layer caulking material, 10-waterproof membrane, 11-central dividing strip, 12-railing. DETAILED DESCRIPTION
[0022] like Figure 1-2 As shown, this highway lane pavement and hardened shoulder grouting structure includes a lane pavement 1 and a hardened shoulder 2; the lane pavement 1 and the hardened shoulder 2 are both paved with asphalt concrete, and below the lane pavement 1 and the hardened shoulder 2, from bottom to top, a crushed stone roadbed 3, a gravel layer 4 and a heat insulation layer 5 are laid in sequence; the heat insulation layer 5 is paved with heat insulation asphalt concrete; a strip groove 6 is provided between the lane pavement 1 and the hardened shoulder 2 and along the crack; the bottom surface of the strip groove 6 is located above the heat insulation layer 5, and the side surface of the strip groove 6 is an uneven rough surface; a lower layer grouting material 7, a fiber layer 8, an upper layer grouting material 9 and a waterproof membrane 10 are arranged in the strip groove 6 from bottom to top; the fiber layer 8 extends into the uneven gap on the side of the strip groove 6; the top surface of the waterproof membrane 10 is adapted to the top surfaces of the lane pavement 1 and the hardened shoulder 2.
[0023] In this embodiment, the width of the strip groove 6 is at least 12 mm, the depth of the strip groove 6 is 12 mm to 25 mm, and the depth-to-width ratio of the strip groove 6 is less than 2:1; when the crack width is greater than 10 mm, the strip groove 6 is formed after cleaning the debris in the crack; when the crack width is less than 10 mm, the strip groove 6 is formed by a slotting machine expanding the crack along the crack.
[0024] In this embodiment, the upper sealing material 9 and the lower sealing material 7 are both made of polyurethane material, and the sum of the thicknesses of the upper sealing material 9, the fiber layer 8 and the lower sealing material 7 is 11 mm to 27 mm.
[0025] In this embodiment, the top surface of the waterproof membrane 10 is flush with the top surface of the road surface 1 or the top surface of the waterproof membrane 10 is 2 to 3 mm higher than the road surface.
[0026] In this embodiment, the waterproof membrane 10 is made of polyethylene material, and the thickness of the waterproof membrane 10 is 0.1 mm to 1.0 mm.
[0027] In this embodiment, the slope of the hardened shoulder 2 is 2%, and the slope gradually slopes downward from the inside to the outside.
[0028] In this embodiment, flexible connections are formed between the upper caulking material 9 and the hardened shoulder 2 and lane pavement 1, between the lower caulking material 7 and the hardened shoulder 2 and lane pavement 1, and between the waterproof membrane 10 and the hardened shoulder 2 and lane pavement 1 to adapt to the expansion and contraction deformation of the road surface.
[0029] In this embodiment, guardrails 12 are provided on the side of the road surface 1 close to the central dividing strip 11 and on the outer side of the hardened shoulder 2 .
[0030] In this embodiment, in spring, the top surface of the waterproof membrane 10 is flush with the top surface of the roadway pavement 1 ; in autumn and winter, the top surface of the waterproof membrane 10 is 2 to 3 mm higher than the top surface of the roadway pavement 1 .
[0031] In this embodiment, the upper caulking material 9 and the lower caulking material 7 are both made of polyurethane material; a closed sealing structure is formed between the upper caulking material 9, the lower caulking material 7 and the waterproof membrane and the lane pavement 1 and the hardened shoulder 2.
[0032] The above embodiments are not exhaustive of specific implementation methods, and there may be other embodiments. The purpose of the above embodiments is to illustrate the utility model rather than to limit the protection scope of the utility model. All applications derived from simple changes of the utility model fall within the protection scope of the utility model.
Claims
1. A highway lane pavement and hardened shoulder caulking structure, comprising a lane pavement (1) and a hardened shoulder (2); characterized in that: The lane pavement (1) and the hardened shoulder (2) are both paved with asphalt concrete, and a crushed stone roadbed (3), a gravel layer (4) and a heat insulation layer (5) are laid in sequence from bottom to top below the lane pavement (1) and the hardened shoulder (2); a strip groove (6) is provided along the crack between the lane pavement (1) and the hardened shoulder (2); the bottom surface of the strip groove (6) is located above the heat insulation layer (5), and the side surface of the strip groove (6) is an uneven rough surface; a lower layer of caulking material (7), a fiber layer (8), an upper layer of caulking material (9) and a waterproof membrane (10) are provided in the strip groove (6) from bottom to top; the fiber layer (8) extends into the uneven gap on the side surface of the strip groove (6); the top surface of the waterproof membrane (10) is adapted to the top surfaces of the lane pavement (1) and the hardened shoulder (2).
2. The highway lane pavement and hardened shoulder caulking structure according to claim 1 is characterized by: The width of the strip groove (6) is at least 12 mm, the depth of the strip groove (6) is 12 mm to 25 mm, and the depth-to-width ratio of the strip groove (6) is less than 2:
1.
3. The highway lane pavement and hardened shoulder caulking structure according to claim 1 is characterized by: The upper layer caulking material (9) and the lower layer caulking material (7) are both made of polyurethane material, and the sum of the thicknesses of the upper layer caulking material (9), the fiber layer (8) and the lower layer caulking material (7) is 11 mm to 27 mm.
4. The highway lane pavement and hardened shoulder caulking structure according to claim 1 is characterized by: The top surface of the waterproof membrane (10) is flush with the top surface of the roadway pavement (1), or the top surface of the waterproof membrane (10) is 2 to 3 mm higher than the roadway pavement (1).
5. The highway lane pavement and hardened shoulder caulking structure according to claim 1 is characterized by: The thickness of the waterproof membrane (10) is 0.1 mm to 1.0 mm.
6. The highway lane pavement and hardened shoulder caulking structure according to claim 1 is characterized by: The slope of the hardened shoulder (2) is 2%, and the slope surface gradually slopes downward from the inside to the outside.
7. The highway lane pavement and hardened shoulder caulking structure according to claim 1 is characterized by: Flexible connections are formed between the upper caulking material (9) and the hardened shoulder (2) and the roadway pavement (1), between the lower caulking material (7) and the hardened shoulder (2) and the roadway pavement (1), and between the waterproof membrane (10) and the hardened shoulder (2) and the roadway pavement (1) to adapt to the expansion and contraction deformation of the road surface.