High-speed railway pier padstone construction operation safety platform

By setting up positioning structures and adjustment components on the pier stone cushion construction platform, the problems of fence suspension and unfixed fixation are solved, and the safety and efficiency of pier stone cushion construction are improved.

CN221941138UActive Publication Date: 2024-11-01CHINA RAILWAY 24TH BUREAU GROUP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420458234.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-11
Publication Date
2024-11-01
Estimated Expiration
2034-03-11

AI Technical Summary

Technical Problem

In the prior art, there is a problem of high suspension risk during construction of the bridge pier fence and the inability to effectively fix the fence and the bridge pier, resulting in safety risks.

Method used

A high-speed railway pier mattress construction safety platform including positioning structure and adjustment components is designed. The positioning structure corresponds to the grooves of the bridge pier. By moving the adjustment components on the positioning frame to abut the side walls of the grooves, ensuring the fence is fixed, and Improve fixing effect with automatic locking and rubber pads.

Benefits of technology

The stable fixation of fences and piers is achieved, the construction risks are reduced, the installation and disassembly process is simplified, and the construction efficiency and safety are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221941138U_ABST
    Figure CN221941138U_ABST
Patent Text Reader

Abstract

The utility model provides a high-speed railway bridge pier padstone construction operation safety platform, relates to the technical field of railway bridge construction, and solves the technical problem that in the prior art, a fence and a bridge pier are not effectively fixed or safety risks exist through suspension fixing. The high-speed railway pier padstone construction operation safety platform comprises a fence and a positioning structure arranged at the bottom of the fence, and the positioning structure corresponds to a groove of a pier; the positioning structure comprises a positioning frame arranged towards the direction of the groove and an adjusting assembly arranged on the positioning frame, and the adjusting assembly can move towards the two sides of the positioning frame on the positioning frame so as to abut against the side wall of the groove. The high-speed railway pier padstone construction operation safety platform can improve construction safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of railway bridge construction, in particular to a safety platform for high-speed railway bridge pier pad stone construction operations. Background Art

[0002] High-speed railway bridge pier support pad stone (such as Figure 1 and Figure 3 Mark 7) The construction work is basically carried out at heights of more than 2m. During the construction, the pier formwork and its integrated safety working platform have been removed. The working surface on the pier top is narrow and the risk of the edge is high. Temporary safety protection measures need to be set up to ensure the safety of the work.

[0003] In the prior art, when installing the pier fence, multiple accessories are processed and then welded and assembled on site, and then suspended on the top of the pier. The lifting risk is high and there is a safety risk. Secondly, the pier fence cannot be effectively fixed to the pier, which poses a safety risk. Utility Model Content

[0004] The purpose of the utility model is to provide a safety platform for high-speed railway bridge pier pad stone construction operations to solve the technical problem that the fence and the bridge pier are not effectively fixed or there is a safety risk through suspension fixation in the prior art. The preferred technical solution among the many technical solutions provided by the utility model can produce many technical effects as described below.

[0005] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0006] The utility model provides a high-speed railway bridge pier pad stone construction work safety platform, comprising a fence and a positioning structure arranged at the bottom of the fence, wherein the positioning structure corresponds to the groove of the bridge pier;

[0007] The positioning structure comprises a positioning frame arranged in the direction of the groove and an adjusting component arranged on the positioning frame. The adjusting component can move on the positioning frame toward both sides of the positioning frame to abut against the side walls of the groove.

[0008] As a further improvement of the utility model, the adjustment assembly includes an adjustment screw rod threadedly connected to the positioning frame, a plum blossom-shaped knob is provided at the first end of the adjustment screw rod, and a rubber pad is provided at the second end of the adjustment screw rod.

[0009] As a further improvement of the present invention, the fence includes a fence body and a safety door, the fence body is a rectangular structure, one side of the safety door is hinged to the fence body, and the other side of the safety door is connected to the fence body through an automatic lock.

[0010] As a further improvement of the present invention, at least three groups of adjustment components are provided.

[0011] As a further improvement of the present invention, the fence body is welded from 2mm thick rectangular tubes.

[0012] As a further improvement of the present invention, the safety door is an inward opening door.

[0013] The beneficial effect of the utility model is that a positioning structure is arranged at the bottom of the fence, the positioning structure includes a positioning frame and an adjusting component, the adjusting component can move on the positioning frame toward both sides of the positioning frame to abut against the side walls of the groove, thereby fixing the fence on the pier, realizing the positioning of the fence and the pier, and the disassembly and installation is very convenient, which greatly improves work efficiency and can effectively ensure work safety and reduce risks. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0015] Figure 1 It is a structural schematic diagram of the utility model;

[0016] Figure 2 It is a partial enlarged structural schematic diagram of the utility model;

[0017] Figure 3 It is a side view of the utility model.

[0018] In the figure, 1 is a fence; 2 is a positioning structure; 3 is a positioning frame; 4 is an adjustment component; 5 is an adjustment screw; 6 is a rubber pad; 7 is a supporting pad stone; 11 is a fence body; 12 is a safety door. DETAILED DESCRIPTION

[0019] Please refer to the attached figure below Figure 1 to Figure 3And the text content understands the content of the utility model and the difference between the utility model and the prior art. The following is a further detailed description of the technical solution (including the preferred technical solution) of the utility model by means of the accompanying drawings and the enumeration of some optional embodiments of the utility model. It should be noted that: any technical feature and any technical solution in the present embodiment are one or more of a variety of optional technical features or optional technical solutions. In order to describe the need for brevity, it is impossible to exhaustively list all the alternative technical features and alternative technical solutions of the utility model in this document, and it is not convenient for the implementation of each technical feature to emphasize that it is one of the optional multiple implementations, so those skilled in the art should know that: any technical means provided by the utility model can be replaced or any two or more technical means or technical features provided by the utility model can be combined with each other to obtain a new technical solution. Any technical feature and any technical solution in this embodiment do not limit the scope of protection of the utility model. The scope of protection of the utility model should include any alternative technical solutions that can be thought of by those skilled in the art without creative labor and new technical solutions obtained by combining any two or more technical means or technical features provided by the utility model.

[0020] In the description of the present invention, it should be noted that, unless otherwise specified, "multiple" means two or more than two; the directions or positional relationships indicated by the terms "upper", "lower", "left", "right", "inner", "outer", "front end", "rear end", "head", "tail", etc. are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", "third", etc. are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.

[0021] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.

[0022] The utility model provides a high-speed railway bridge pier pad stone construction operation safety platform which improves construction safety.

[0023] Combine the following Figure 1 to Figure 3 The technical solution provided by the utility model is described in more detail.

[0024] The utility model provides a high-speed railway bridge pier pad stone construction work safety platform, comprising a fence 1 and a positioning structure 2 arranged at the bottom of the fence 1, wherein the positioning structure 2 corresponds to the groove of the bridge pier;

[0025] The positioning structure 2 includes a positioning frame 3 arranged toward the groove and an adjusting component 4 arranged on the positioning frame 3. The adjusting component 4 can move on the positioning frame 3 toward both sides of the positioning frame 3 to abut against the side walls of the groove.

[0026] Specifically, the adjustment assembly 4 includes an adjustment screw 5 threadedly connected to the positioning frame 3, a plum blossom-shaped knob is provided at the first end of the adjustment screw 5, and a rubber pad 6 is provided at the second end of the adjustment screw 5. The adjustment screw 5 is extended or contracted by turning the plum blossom-shaped knob, and the rubber pad 6 can increase friction to ensure the positioning effect.

[0027] The utility model provides a safe platform for high-speed railway pier pad stone construction operations, by arranging a positioning structure 2 at the bottom of the fence 1, the positioning structure 2 includes a positioning frame 3 and an adjustment component 4, the adjustment component 4 can move on the positioning frame 3 toward both sides of the positioning frame 3 to abut against the side walls of the groove, thereby fixing the fence 1 on the pier, realizing the positioning of the fence and the pier, and the disassembly and installation are very convenient, which greatly improves work efficiency and can effectively ensure work safety and reduce risks.

[0028] Optionally, the positioning frame 3 includes a plurality of columns, and the plurality of columns are welded to the fence 1 .

[0029] Furthermore, the adjusting components 4 are provided in multiple groups, and the multiple groups of adjusting components 4 can abut against the side wall of the groove to improve the positioning effect.

[0030] Furthermore, the fence 1 includes a fence body 11 and a safety door 12, the fence body 11 is a rectangular structure, one side of the safety door 12 is hinged to the fence body 11, and the other side of the safety door 12 is connected to the fence body 11 through an automatic lock.

[0031] The safety door 12 is connected to the fence body 11 through an automatic lock, and the safety door 12 can be locked on the fence body 11 to prevent people from falling; the automatic lock needs to be opened manually for entry and exit, which improves safety.

[0032] Optionally, the safety door 12 is an inwardly opening door. The safety door 12 opens inwardly, which can effectively protect the safety of personnel and avoid accidental falls.

[0033] The installation process of the high-speed railway bridge pier pad stone construction safety platform provided by the utility model is as follows: after the high-speed railway bridge pier pad stone construction safety platform of the present invention is hoisted in place on the pier top by a car crane, the operator takes a climbing vehicle to the large mileage or small mileage side of the top cap, opens the safety door 12, enters the platform from the climbing vehicle, closes the safety door 12, and rotates the plum blossom-shaped knob in sequence to adjust the screw rod 5 to extend outward, so that the rubber pad 6 is in full contact with the concrete of the side wall of the groove of the bridge pier top cap, generating friction resistance, and the platform is firmly fixed. The operator safely constructs the pad stone. After the construction is completed, the plum blossom-shaped knob is rotated in sequence to adjust the screw rod 5 to shrink inward, the rubber pad 6 is separated from the concrete of the side wall of the groove of the bridge pier top cap, and the platform is separated from the top cap. The operator returns to the climbing vehicle through the safety door and uses the car crane to lift the platform off the pier top. The safe operation of the bridge pier pad stone construction is completed.

[0034] The above is only a specific implementation of the utility model, but the protection scope of the utility model is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed by the utility model, which should be included in the protection scope of the utility model. Therefore, the protection scope of the utility model should be based on the protection scope of the claims.

Claims

1. A high-speed railway bridge pier pad stone construction work safety platform, characterized in that: It comprises a fence and a positioning structure arranged at the bottom of the fence, wherein the positioning structure corresponds to the groove of the pier; The positioning structure comprises a positioning frame arranged in the direction of the groove and an adjusting component arranged on the positioning frame. The adjusting component can move on the positioning frame toward both sides of the positioning frame to abut against the side walls of the groove.

2. The high-speed railway bridge pier pad stone construction safety platform according to claim 1 is characterized in that: The adjusting assembly comprises an adjusting screw rod threadedly connected to the positioning frame, a first end of the adjusting screw rod is provided with a plum blossom-shaped knob, and a second end of the adjusting screw rod is provided with a rubber pad.

3. The high-speed railway bridge pier pad stone construction safety platform according to claim 1 is characterized in that: The fence includes a fence body and a safety door. The fence body is a rectangular structure. One side of the safety door is hinged to the fence body, and the other side of the safety door is connected to the fence body through an automatic lock.

4. The high-speed railway bridge pier pad stone construction safety platform according to claim 1 is characterized in that: The adjusting components are provided in at least three groups.

5. The high-speed railway bridge pier pad stone construction safety platform according to claim 3 is characterized in that: The fence body is welded from 2mm thick rectangular tubes.

6. The high-speed railway bridge pier pad stone construction safety platform according to claim 3 is characterized in that: The safety door is an inward opening door.