Water conservancy flood bank

By designing a water conservancy flood control embankment with a detachable support frame and baffle structure, the problem of time-consuming and labor-intensive increase in traditional flood control embankment is solved, convenient increase in height and rapid recovery is achieved, and flood control effect is improved.

CN221941223UActive Publication Date: 2024-11-01ZHEJIANG ZHIZHITIAN CONSTRUCTION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420215901.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-29
Publication Date
2024-11-01
Estimated Expiration
2034-01-29

AI Technical Summary

Technical Problem

The traditional method of increasing the flood control embankment is stacked with sandbags, which is time-consuming and labor-intensive, with large project volume and long construction period, making it difficult to quickly deal with water level changes.

Method used

A water conservancy flood control embankment is designed, adopting a detachable support frame and baffle structure. Through the installation of the support frame and the tight stacking of the baffle, combined with the locking component, convenient dam height increase and removable to restore the original appearance.

Benefits of technology

The ease and speed of the lifting process is achieved, the construction period is shortened, and the flood control effect is enhanced when the water level rises, making it easier to manage and maintain.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221941223U_ABST
    Figure CN221941223U_ABST
Patent Text Reader

Abstract

The utility model relates to a water conservancy flood bank which comprises a dam body and further comprises a plurality of supporting frames detachably installed on the top of the dam body, and the length of the supporting frames extends in the height direction of the dam body. The adjacent supporting frames are sequentially arranged at intervals in the length direction of the dam body, a plurality of baffles are horizontally erected between the adjacent supporting frames, and the baffles are sequentially and tightly stacked in the length direction of the supporting frames; the outer side wall of the supporting frame is provided with limiting grooves used for allowing the ends of the baffles opposite to each other to be inserted into the supporting frame from top to bottom, and the length of the limiting grooves extends in the length direction of the supporting frame. The limiting grooves are symmetrically formed in the outer side walls, deviating from each other, of the supporting frame, and locking assemblies used for locking the baffles in the corresponding limiting grooves are further arranged at the top of the supporting frame. The method has the advantages that the heightening process is easy to operate, convenient and fast, and the overall construction period is greatly shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of flood control levees, and in particular to a water conservancy flood control levee. Background Art

[0002] A flood dam refers to a dam built to prevent river flooding. A water conservancy flood dam is one of the water conservancy infrastructures that intercept water flows and is widely used in agricultural irrigation, fishery farming, hydropower stations, and urban river landscape projects.

[0003] At present, the water conservancy flood embankment in the relevant technology is mainly used to intercept the rising water level. Especially in the case of heavy rainfall, as the river water level continues to rise, in order to meet the requirements of flood control and prevention, the height of the flood embankment needs to be raised in advance, and the traditional way of raising the height of the flood embankment is usually to use sandbags to raise the height of the flood embankment. However, the method of raising the height by stacking sandbags is not only time-consuming and labor-intensive, but also has a large amount of engineering and requires a long construction period. Utility Model Content

[0004] The present application provides a water conservancy flood embankment, which is convenient for raising the height of the flood embankment, has a convenient raising process, is easy to operate, and shortens the construction period.

[0005] The present application provides a water conservancy flood embankment adopting the following technical solution:

[0006] A water conservancy flood control embankment includes a dam body and a plurality of support frames detachably mounted on the top of the dam body, wherein the length of the support frames extends along the height direction of the dam body; adjacent support frames are arranged in sequence along the length direction of the dam body, and a plurality of baffles are horizontally mounted between adjacent support frames, and the baffles are tightly stacked in sequence along the length direction of the support frames; the outer side walls of the support frames are provided with limiting grooves for the respective opposite ends of the baffles to be inserted into the support frames from top to bottom, and the length of the limiting grooves extends along the length direction of the support frames; the limiting grooves are symmetrically arranged on the outer side walls of the support frames that are away from each other, and the top of the support frames is also provided with locking components for locking the baffles in their respective limiting grooves.

[0007] By adopting the above technical scheme: when the dam body needs to be raised, the support frame is first fixedly installed in the designated installation position of the dam body in sequence along the length direction of the dam body, and then the end of each baffle is inserted from the limit groove of the support frame from top to bottom onto the support frame, and the baffles inserted between the support frames on the adjacent two sides will be tightly stacked in sequence along the length direction of the support frame. At this time, the overall height of the dam body can be raised under the blocking of the baffles, and finally the baffles are locked in their respective limit grooves by the locking assembly, thereby completing the raising of the dam body. The entire raising process is simple, convenient and fast to operate, and the overall construction period is greatly shortened; when the water level drops, the support frame can be removed from the dam body, so that the support frame and the baffles can be conveniently stored and managed, and the original appearance of the dam body can be restored.

[0008] Preferably, a plurality of groups of plug-in frames corresponding to the support frames are arranged on the outer wall of the dam body, and the plug-in frames in the same group are arranged in sequence along the height direction of the dam body. The support frames are respectively inserted into the plug-in frames in the same group from top to bottom, and the support frames are limited on the outer wall of the dam body by the plug-in frames; fasteners are threadedly connected to the plug-in frames, and the fasteners are used to tighten and fix the support frames on the plug-in frames.

[0009] Preferably, the locking assembly includes a locking plate arranged at the top of the support frame, and the locking plate is slidably arranged on the top of the support frame along a direction perpendicular to the insertion direction of the baffle into the limiting groove, and the locking plate is located on a sliding path where the baffle slides out from the top opening of the limiting groove where it is located, and the locking plate is used to cover the top opening of the limiting groove; a locking hole is passed through the locking plate, and the locking assembly also includes a latch rod slidably arranged on the support frame along the length direction of the support frame, the top of the latch rod is opposite to the locking hole, and the latch rod is used to be inserted into and locked in the locking hole.

[0010] Preferably, a guide plate is detachably mounted on a side of the baffle away from the plug-in frame, the width of the guide plate gradually decreases from top to bottom, and an arc-shaped guide arc surface is formed on the side of the guide plate away from the baffle.

[0011] Preferably, a hanging plate is provided on one side of the guide plate facing the baffle plate, and the hanging plate is used to be suspended from top to bottom on the baffle plate located at the top of the support frame.

[0012] Preferably, the upper surface of the dam body is provided with a plurality of screws arranged in sequence at intervals, the screws and the upper surface of the dam body are perpendicular to each other, the bottom of the guide plate is penetrated by a plurality of through holes for the respective relative screws to pass through from bottom to top, and the screws passing through the through holes are threadedly connected with fastening nuts, and the bottom of the guide plate is pressed against the upper surface of the dam body through the screws and the fastening nuts.

[0013] Preferably, a pressing plate is integrally formed at the bottom of the guide plate, the pressing plate is used to fit together with the upper surface of the dam body, and the perforations are arranged on the pressing plate.

[0014] In summary, the present application includes at least one of the following beneficial technical effects:

[0015] The whole heightening process is simple, convenient and fast to operate, which greatly shortens the overall construction period. By removing the support frame from the dam body, the support frame and the baffle can be easily stored and managed, thus restoring the original appearance of the dam body.

[0016] When locking the baffle in the limit slot, you only need to push the locking plate until the top opening of the limit slot is covered, and finally insert the top of the latch rod into the locking hole of the locking plate. At this time, the locking plate can cover the top opening of the limit slot under the locking of the latch rod, so that the baffle cannot be removed from the limit slot. At this time, the baffle is locked on the support frame, and the entire locking process is very convenient and quick.

[0017] When the rising water level is more turbulent, the drainage plate can further enhance the blocking effect on the water surface, making it difficult for the rising water level to cross the drainage plate, thereby improving the flood prevention effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application;

[0019] Figure 2 yes Figure 1 Schematic diagram of the local structure explosion;

[0020] Figure 3 yes Figure 2 Schematic diagram of the local structure behind the hidden drainage plate;

[0021] Figure 4 yes Figure 3 Schematic diagram of the local structure from another perspective.

[0022] Explanation of the reference numerals: 1. dam body; 2. support frame; 20. limit groove; 3. baffle; 4. locking assembly; 40. locking plate; 41. locking hole; 42. latch rod; 5. plug-in frame; 50. fastener; 6. drainage plate; 60. drainage arc surface; 61. hanging plate; 62. perforation; 63. pressure plate; 7. screw; 70. fastening nut. DETAILED DESCRIPTION

[0023] The present application is further described in detail below in conjunction with the accompanying drawings.

[0024] The embodiment of the present application discloses a hydraulic flood embankment.

[0025] Reference Figure 1 , Figure 2A water conservancy flood embankment includes a dam body 1 cast by concrete, and also includes a plurality of support frames 2 detachably mounted on the top of the dam body 1, the length of the support frames 2 extends along the height direction of the dam body 1, adjacent support frames 2 are parallel to each other, and are arranged in sequence along the length direction of the dam body 1. A plurality of groups of plug-in frames 5 corresponding to the number of the support frames 2 are fixedly mounted on the outer wall of the dam body 1, and each group of plug-in frames 5 corresponds to the support frames 2 one by one.

[0026] like Figure 2 , Figure 3 As shown, the plug-in racks 5 in the same group are arranged in sequence along the height direction of the dam body 1 at intervals on the outer wall of the dam body 1, and the lower ends of the support frames 2 are respectively and sequentially inserted into the plug-in racks 5 in the same group from top to bottom, and the inner wall of the plug-in rack 5 fits the outer wall of the support frame 2. Under the action of each group of plug-in racks 5, the support frame 2 is limited on the outer wall of the dam body 1. The outer wall of each plug-in rack 5 is threadedly connected with a fastener 50. In this embodiment, the fastener 50 is a bolt, and the fastener 50 is used to tighten and fix the respective relative support racks 2 in the plug-in rack 5.

[0027] like Figure 3 , Figure 4 As shown, a plurality of baffles 3 are horizontally arranged between two adjacent support frames 2, and the plurality of baffles 3 are stacked closely in sequence along the length direction of the support frame 2. The outer side wall of the support frame 2 facing the baffle 3 is provided with a limiting groove 20 for inserting the ends of the baffles 3 opposite to each other from top to bottom into the support frame 2, and the length of the limiting groove 20 extends along the length direction of the support frame 2. The limiting grooves 20 are symmetrically arranged on the outer side walls of the support frame 2 that are away from each other, and the top of the support frame 2 is also provided with a locking assembly 4 for locking the baffles 3 in the respective limiting grooves 20.

[0028] like Figure 3 , Figure 4 As shown, the locking assembly 4 includes a locking plate 40 disposed on the top of the support frame 2. The locking plate 40 is slidably disposed on the top of the support frame 2 in a direction perpendicular to the direction in which the baffle 3 is inserted into the limiting groove 20, and the locking plate 40 is located on the sliding path of the baffle 3 sliding out of the top opening of the limiting groove 20 where the baffle 3 is located. The locking plate 40 is used to cover the top opening of the limiting groove 20, and the locking plate 40 is pushed away from the plug-in frame 5 until the locking plate 40 covers the top opening of the limiting groove 20. At this time, the baffle 3 can be restricted from moving upward from the respective limiting groove 20 under the blocking of the locking plate 40.

[0029] like Figure 3 , Figure 4As shown, a locking hole 41 is formed through the locking plate 40, and the locking assembly 4 further includes a latch rod 42 slidably arranged on the support frame 2 along the length direction of the support frame 2, the latch rod 42 is used to be inserted from bottom to top and locked in the locking hole 41, and the sliding direction of the latch rod 42 outside the support frame 2 is perpendicular to the sliding direction of the locking plate 40 at the top of the support frame 2. When the locking plate 40 covers the top opening of the limiting groove 20, the top of the latch rod 42 is directly opposite to the locking hole 41.

[0030] like Figure 2 , Figure 3 As shown, a guide plate 6 is detachably mounted on the side of the baffle plate 3 facing away from the plug-in frame 5, the width of the guide plate 6 gradually decreases from top to bottom, and an arc-shaped guide arc surface 60 is formed on the side of the guide plate 6 facing away from the baffle plate 3. Two hanging plates 61 are fixedly mounted on the top side wall of the guide plate 6 facing the baffle plate 3, and the hanging plates 61 are symmetrically arranged on both sides of the guide plate 6. The hanging plates 61 are used to be suspended and fixed from top to bottom above the baffle plate 3 located on the top of the support frame 2.

[0031] like Figure 2 , Figure 3 As shown, the bottom of the guide plate 6 is integrally formed with a pressure plate 63. When the upper end of the guide plate 6 is suspended and fixed on the top of the baffle 3 by the hanging plate 61, the bottom wall of the pressure plate 63 will fit with the upper surface of the dam body 1. The pressure plate 63 is penetrated with a plurality of through holes 62 arranged in sequence along the length direction of the dam body 1. A plurality of screw rods 7 arranged in sequence are fixedly installed on the top side wall of the dam body 1 facing the pressure plate 63. The screw rods 7 are perpendicular to the upper surface of the dam body 1, and the screw rods 7 correspond to the through holes 62 one by one. The screw rods 7 are used to pass through the respective opposite through holes 62 from bottom to top. The screw rods 7 that pass through the through holes 62 are threadedly connected with the fastening nuts 70. The pressure plate 63 is fixed to the upper surface of the dam body 1 by the mutual cooperation between the screw rods 7 and the fastening nuts 70.

[0032] The implementation principle is:

[0033] When the dam body 1 needs to be raised, the support frame 2 is first fixedly installed in the designated installation position of the dam body 1 in sequence along the length direction of the dam body 1, and then the ends of each baffle 3 are inserted from the limit groove 20 of the support frame 2 from top to bottom into the support frame 2, and each baffle 3 inserted between the adjacent support frames 2 on both sides will be tightly stacked in sequence along the length direction of the support frame 2. At this time, the overall height of the dam body 1 can be raised under the blocking of the baffle 3, and finally the baffle 3 is locked in the respective limit groove 20 by the locking assembly 4, thereby completing the raising of the dam body 1. The entire raising process is simple, convenient and fast to operate, greatly shortening the overall construction period. When the water level drops, the support frame 2 can be removed from the dam body 1, so that the support frame 2 and the baffle 3 can be easily stored and managed, and the original appearance of the dam body 1 can be restored.

[0034] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A hydraulic flood embankment, comprising a dam body (1), characterized in that: It also comprises a plurality of support frames (2) detachably mounted on the top of the dam body (1), the length of the support frames (2) extending along the height direction of the dam body (1); adjacent support frames (2) are arranged in sequence at intervals along the length direction of the dam body (1), a plurality of baffles (3) are horizontally mounted between adjacent support frames (2), the baffles (3) are stacked in sequence and closely along the length direction of the support frames (2); the outer side walls of the support frames (2) are provided with limiting grooves (20) for allowing the ends of the respective opposite baffles (3) to be inserted from top to bottom into the support frames (2), the length of the limiting grooves (20) extending along the length direction of the support frames (2); the limiting grooves (20) are symmetrically arranged on the outer side walls of the support frames (2) which are away from each other, and the top of the support frames (2) is also provided with locking components (4) for locking the baffles (3) in their respective limiting grooves (20).

2. A hydraulic flood embankment according to claim 1, characterized in that: A plurality of groups of plug-in frames (5) having a number corresponding to the support frames (2) are arranged on the outer wall of the dam body (1); the plug-in frames (5) in the same group are arranged in sequence along the height direction of the dam body (1); the support frames (2) are respectively inserted into the plug-in frames (5) in the same group from top to bottom; the support frames (2) are limited on the outer wall of the dam body (1) by the plug-in frames (5); and fasteners (50) are threadedly connected to the plug-in frames (5); the fasteners (50) are used to screw the support frames (2) onto the plug-in frames (5).

3. A hydraulic flood embankment according to claim 2, characterized in that: The locking assembly (4) comprises a locking plate (40) arranged at the top of the support frame (2); the locking plate (40) is slidably arranged at the top of the support frame (2) in a direction perpendicular to the direction in which the baffle plate (3) is inserted into the limiting groove (20); and the locking plate (40) is located on a sliding path in which the baffle plate (3) slides out from the top opening of the limiting groove (20) where the baffle plate (3) is located; the locking plate (40) is used to cover the top opening of the limiting groove (20); a locking hole (41) is passed through the locking plate (40); the locking assembly (4) further comprises a latch rod (42) slidably arranged on the support frame (2) along the length direction of the support frame (2); the top of the latch rod (42) is opposite to the locking hole (41), and the latch rod (42) is used to be inserted into and locked in the locking hole (41).

4. A hydraulic flood embankment according to claim 2, characterized in that: A flow guide plate (6) is detachably mounted on a side of the baffle plate (3) facing away from the plug-in frame (5); the width of the flow guide plate (6) gradually decreases from top to bottom, and an arc-shaped flow guide arc surface (60) is formed on the side of the flow guide plate (6) facing away from the baffle plate (3).

5. A hydraulic flood embankment according to claim 4, characterized in that: A hanging plate (61) is provided on one side of the guide plate (6) facing the baffle plate (3), and the hanging plate (61) is used to be suspended from top to bottom on the baffle plate (3) located on the top of the support frame (2).

6. A hydraulic flood embankment according to claim 5, characterized in that: The upper surface of the dam body (1) is provided with a plurality of screw rods (7) arranged in a sequentially spaced relationship. The screw rods (7) and the upper surface of the dam body (1) are perpendicular to each other. The bottom of the guide plate (6) is penetrated by a plurality of through holes (62) for the respective opposite screw rods (7) to pass through from bottom to top. The screw rods (7) passing through the through holes (62) are threadedly connected with fastening nuts (70). The bottom of the guide plate (6) is pressed against the upper surface of the dam body (1) through the screw rods (7) and the fastening nuts (70).

7. A hydraulic flood embankment according to claim 6, characterized in that: A pressing plate (63) is integrally formed at the bottom of the guide plate (6), the pressing plate (63) being used to fit together with the upper surface of the dam body (1), and the through hole (62) is provided on the pressing plate (63).