Wall plastering equipment for constructional engineering

By designing wall plastering equipment with automatic stirring and recycling functions, the problems of low manual stirring efficiency and uneven plastering are solved, automatic stirring and ash recycling are realized, and construction efficiency and effect are improved.

CN221941852UActive Publication Date: 2024-11-01SHANDONG ZHENGU CONSTRUCTION TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420346631.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-26
Publication Date
2024-11-01
Estimated Expiration
2034-02-26

AI Technical Summary

Technical Problem

Existing wall plastering equipment requires manual mixing of raw materials, which is inefficient in work, wastes manpower, uneven plastering and excess ash are scattered, affecting the construction effect.

Method used

A wall plastering equipment including a mixing tank, storage box, plastering assembly and recycling component was designed. The mixing tank is equipped with a motor mixing rod, and the storage box is equipped with a pick-up tube. The plastering assembly is realized through leaking holes and uniform material plates. Evenly distributed, the recycling component uses a spring to push the plate to collect the falling ash and recycle it.

Benefits of technology

It realizes automatic stirring and recycling of raw materials, saves manpower, improves plastering efficiency, avoids mortar scattering, and ensures uniformity and effect of plastering.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221941852U_ABST
    Figure CN221941852U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of constructional engineering, and discloses a wall plastering device for constructional engineering, which comprises a base, a stirring tank arranged on the top of the base, a storage box arranged on one side of the stirring tank and arranged on the top of the base, a lifting cylinder movably arranged on the base on the front side of the storage box, and a push rod connected to the output end of the lifting cylinder. A movable block is arranged at the upper end of the push rod, a plastering assembly is arranged on the front side of the movable block, a recycling assembly is arranged below the plastering assembly, the plastering assembly comprises a material receiving hopper fixedly installed on the movable block, leakage holes are formed in the bottom of the material receiving hopper in a penetrating mode, and a material uniformizing plate is arranged below the material receiving hopper and is obliquely arranged; the upper end of the material uniformizing plate is fixedly connected to the moving block, the lower end of the material uniformizing plate is connected with the plastering plate, the plastering work is conducted on the wall through vertical movement of the plastering assembly, fallen ash is recycled through the recycling assembly, and the problem that after the wall surface is plastered, redundant ash is smeared and scattered to the ground, and consequently operation is inconvenient is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction engineering, in particular to a wall plastering device for construction engineering. Background Art

[0002] Wall plastering refers to the application of cement mortar, mixed mortar, or lime mortar on the wall surface. Indoor and outdoor wall plastering is a job that is done after the completion of the building structure construction. Scientific plastering can play a role in moisture-proofing, weathering-proofing, and heat-insulating, and prevent the walls of buildings from being eroded by wind, rain, snow, etc. The concrete walls constructed with large formwork are smooth and flat, but the walls constructed with large formwork need to be plastered and straightened at the junction of vertical and horizontal walls, the junction of upper and lower floors in the stairwell, and at door and window openings.

[0003] Chinese patent document CN205000608U discloses an automatic plastering machine for making a leveling layer on a wall. The utility model aims to solve the defects of the prior art, such as the low flatness of the leveling layer, the complex equipment structure, and the poor degree of automation. Key points of the technical solution: The features include a column, a vertical moving mechanism, a horizontal moving mechanism, a plastering mechanism, and a cement mortar delivery pipe. The column is installed on the outside of the wall. The vertical moving mechanism is composed of left and right vertical movers and a crossbeam. The left and right vertical movers are moved in coordination with the column. The horizontal moving mechanism is moved in coordination with the crossbeam. The plastering mechanism is composed of a plastering seat, a plastering drive motor, a plastering impeller, and a plastering transmission. The plastering transmission is fixed on the horizontal moving mechanism. The plastering impeller is installed on the power output end of the plastering transmission and is in the plastering seat cavity. There is a circular window with a diameter greater than the outer diameter of the plastering impeller on the front side of the plastering seat. A flattening ring is provided on the outside of the circular window. The feed port of the plastering seat is connected to the cement mortar delivery pipe. However, the device requires manual stirring of the raw materials, which has low work efficiency and wastes manpower. After the wall is plastered, excess dust is scattered on the ground, and the walking wheels are contaminated with dust on the ground when moving, causing the plastering device to be uneven in height, resulting in uneven plastering and inconvenient operation.

[0004] Therefore, in order to solve such problems, we propose a wall plastering equipment for construction engineering. Utility Model Content

[0005] The utility model aims to provide a wall plastering device for construction projects, aiming to solve the problem in the above-mentioned background technology that the existing wall plastering device needs manual stirring of raw materials, has low work efficiency and wastes manpower, and when the wall is plastered, excess dust is scattered on the ground, and the walking wheels are contaminated with dust on the ground when moving, causing the plastering device to be uneven in height, resulting in uneven plastering and inconvenient operation.

[0006] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a wall plastering device for construction engineering, comprising a base, a stirring tank is arranged on the top of the base, a connecting pipe is arranged through one side of the stirring tank, a valve is arranged on the connecting pipe, a storage box is connected to the end of the connecting pipe away from the stirring tank, the storage box is arranged on the top of the base, a lifting cylinder is movably arranged on the front side of the base of the storage box, a push rod is connected to the output end of the lifting cylinder, a moving block is arranged on the upper end of the push rod, a plastering assembly is arranged on the front side of the moving block, and a recycling assembly is arranged below the plastering assembly;

[0007] The plastering assembly includes a material receiving hopper fixedly mounted on a moving block, a leakage hole is opened through the bottom of the material receiving hopper, a material leveling plate is arranged below the material receiving hopper, the material leveling plate is arranged obliquely, the upper end of the material leveling plate is fixedly connected to the moving block, and the lower end of the material leveling plate is connected to a plastering plate.

[0008] Preferably, a rotating shaft is arranged inside the stirring tank, the lower end of the rotating shaft movably passes through the stirring tank and is connected to a motor, a stirring rod is arranged outside the rotating shaft, and a stirring paddle is installed on the stirring rod.

[0009] Preferably, a pumping pipe is provided inside the storage box, the upper end of the pumping pipe extends through the top of the storage box, the upper end of the pumping pipe is connected to a pump, the pump is installed on the top of the storage box, the pump is connected to a delivery pipe, the delivery pipe is fixed to the top of the moving block through a positioning block, and the outlet of the delivery pipe is provided above the receiving hopper.

[0010] Preferably, a mounting groove is provided on the top of the base, an electric guide rail is provided inside the mounting groove, a slider is movably provided outside the electric guide rail, and a lifting cylinder is fixedly installed on the top of the slider.

[0011] Preferably, the recovery component includes a telescopic short rod arranged on the front side of the base, the telescopic short rod is connected to a recovery bucket, the outer sleeve of the telescopic short rod is provided with a spring, a flat plate is provided on the side of the recovery bucket away from the base, and the recovery bucket is inclined, a baffle is provided at the higher end of the recovery bucket, and a placement groove is provided at the lower end of the recovery bucket, and the placement groove is provided at the end of the base close to the mixing tank.

[0012] Preferably, a slide rod is provided inside the movable block, a limit block is provided at the top of the slide rod, a movable clamping block is connected to the lower end of the slide rod, slide grooves are provided inside the base on both sides of the installation groove, and the movable clamping block is slidably provided inside the slide grooves.

[0013] The utility model has the following beneficial effects:

[0014] In the utility model, the raw materials are first mixed by a stirring tank, and the stirred raw materials enter a storage box through a connecting pipe for storage and then enter a plastering component, a recovery bucket is close to a wall, a spring pushes a flat plate on the recovery bucket to be close to the wall, and the fallen raw materials are caught, and the raw materials fall from the recovery bucket into a placement slot for recycling, and the device automatically stirs the raw materials, which saves manpower and improves work efficiency, and can collect excess ash after wall plastering, thereby preventing the mortar from scattering to the ground, and the walking wheels will be contaminated with ash on the ground when moving, causing the plastering device to be uneven in height and uneven in plastering, which not only reduces the loss but also ensures the plastering effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 This is a three-dimensional schematic diagram of a wall plastering device for construction engineering proposed by the utility model;

[0016] Figure 2 This is a schematic plan view of a wall plastering device for construction engineering proposed by the utility model;

[0017] Figure 3 This is a three-dimensional exploded view of a plastering component in a wall plastering device for construction engineering proposed by the utility model;

[0018] Figure 4 The utility model is a three-dimensional exploded diagram of a recycling component in a wall plastering device for construction engineering.

[0019] Legend:

[0020] 1. Base; 11. Mounting slot; 2. Mixing tank; 21. Rotating shaft; 22. Motor; 23. Stirring rod; 24. Stirring paddle; 3. Connecting pipe; 31. Valve; 4. Storage box; 41. Extraction pipe; 42. Pump; 43. Delivery pipe; 5. Electric guide rail; 51. Sliding block; 6. Lifting cylinder; 61. Push rod; 62. Moving block; 7. Plastering assembly; 71. Receiving hopper; 72. Leakage hole; 73. Material leveling plate; 74. Plastering plate; 8. Recovery assembly; 81. Telescopic short rod; 82. Recovery bucket; 83. Spring; 84. Flat plate; 85. Baffle; 86. Placement slot; 9. Sliding rod; 91. Limit block; 92. Movable card block; 93. Slide slot. DETAILED DESCRIPTION

[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0022] In the description of the present utility model, it should be noted that the orientation or position relationship indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. is based on the orientation or position relationship shown in the drawings, and is only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present utility model. The terms "first", "second", and "third" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance. In addition, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection. It can be a mechanical connection or an electrical connection. It can be directly connected, or indirectly connected through an intermediate medium, or it can be a communication between the two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present utility model can be understood according to specific circumstances.

[0023] Reference Figure 1-4 The utility model provides an embodiment: a wall plastering device for construction engineering, comprising a base 1, a running wheel is arranged at the bottom of the base 1, a stirring tank 2 is arranged at the top of the base 1, a connecting pipe 3 is arranged through one side of the stirring tank 2, a valve 31 is arranged on the connecting pipe 3, and an end of the connecting pipe 3 away from the stirring tank 2 is connected to a storage box 4, the storage box 4 is arranged on the top of the base 1 on one side of the stirring tank 2, and a lifting cylinder 6 is movably arranged on the base 1 on the front side of the storage box 4, a push rod 61 is connected to the output end of the lifting cylinder 6, a moving block 62 is arranged on the upper end of the push rod 61, and a plastering assembly 7 is arranged on the front side of the moving block 62, the raw materials are mixed by the stirring tank 2, and the mixed raw materials enter the storage box 4 through the connecting pipe 3 for storage, and the lifting cylinder 6 controls the push rod 61 to drive the moving block 62 to move vertically, so that the plastering assembly 7 moves up and down to plaster the wall;

[0024] The plastering assembly 7 includes a material receiving hopper 71 fixedly mounted on the moving block 62, a leakage hole 72 is penetrated through the bottom of the material receiving hopper 71, a material leveling plate 73 is arranged below the material receiving hopper 71, the outlet of the leakage hole 72 is opposite to the material leveling plate 73, the material leveling plate 73 is inclined, the upper end of the material leveling plate 73 is fixedly connected to the moving block 62, the lower end of the material leveling plate 73 is connected to a plastering plate 74, the plastering plate 74 is arranged on the front side of the material receiving hopper 71, the raw materials output from the storage box 4 are received by the material receiving hopper 71, the raw materials flow to the material leveling plate 73 through the leakage hole 72, the material receiving hopper 71 and the material leveling plate 73 make the plaster slurry evenly distributed, and finally the plaster slurry is applied to the wall using the plastering plate 74.

[0025] A rotating shaft 21 is provided inside the mixing tank 2, and the upper end of the rotating shaft 21 is rotatably arranged inside the top plate of the mixing tank 2, and the lower end of the rotating shaft 21 movably passes through the mixing tank 2 and is connected to a motor 22, which is fixedly installed at the bottom of the mixing tank 2 and arranged inside the base 1. A stirring rod 23 is provided outside the rotating shaft 21, and a stirring paddle 24 is installed on the stirring rod 23. The rotating shaft 21 is controlled to rotate by the motor 22, so that the stirring rod 23 and the stirring paddle 24 rotate to stir the raw materials, thereby quickly and fully mixing the raw materials.

[0026] A drawing pipe 41 is provided inside the storage box 4, and the upper end of the drawing pipe 41 extends through the top of the storage box 4. The upper end of the drawing pipe 41 is connected to a pump 42, which is installed on the top of the storage box 4. A delivery pipe 43 is connected to the pump 42, and the delivery pipe 43 is fixed to the top of the moving block 62 by a positioning block. The delivery pipe 43 is retractable, and the outlet of the delivery pipe 43 is arranged above the receiving hopper 71. Start the pump 42 to make the drawing pipe 41 draw the mixed raw materials in the storage box 4 into the delivery pipe 43, and the delivery pipe 43 transports the raw materials to the receiving hopper 71 for easy wall plastering.

[0027] A mounting groove 11 is provided at the top of the base 1, an electric guide rail 5 is provided inside the mounting groove 11, a slider 51 is movably provided outside the electric guide rail 5, a lifting cylinder 6 is fixedly installed on the top of the slider 51, and the movement of the slider 51 is controlled by the electric guide rail 5, so that the lifting cylinder 6 drives the moving block 62 to move forward and backward, so as to facilitate the adjustment of the plastering board 74 to fit the wall.

[0028] The recycling component 8 includes a telescopic short rod 81 arranged on the front side of the base 1, and a recycling bucket 82 is connected to the telescopic short rod 81. A spring 83 is sleeved on the outside of the telescopic short rod 81. A flat plate 84 is arranged on the side of the recycling bucket 82 away from the base 1, and a cushion is arranged on the side of the flat plate 84 close to the wall. The recycling bucket 82 is tilted to facilitate the recovery of raw materials. A baffle 85 is arranged on the higher end of the recycling bucket 82, and a placement groove 86 is arranged on the lower end of the recycling bucket 82. The placement groove 86 is arranged at the end of the base 1 close to the mixing tank 2. The recycling bucket 82 is placed close to the wall, and the spring 83 pushes the flat plate 84 on the recycling bucket 82 close to the wall to catch the fallen raw materials. The raw materials fall from the recycling bucket 82 into the placement groove 86 and can be recycled, which does not hinder the plastering work and can reduce losses.

[0029] Slide rods 9 are movably provided inside the two ends of the moving block 62, and a limit block 91 is provided at the top of the slide rod 9. When the moving block 62 moves vertically, the slide rod 9 limits and fixes it to ensure the smooth movement of the moving block 62. The lower end of the slide rod 9 is connected to a movable block 92, and a slide groove 93 is provided inside the base 1 on both sides of the mounting groove 11. The movable block 92 is slidably set inside the slide groove 93. When the slider 51 drives the moving block 62 on the lifting cylinder 6 to move forward and backward, the movable block 92 at the lower end of the slide rod 9 also moves in the slide groove 93.

[0030] Working principle: First, the receiving hopper 71 receives the raw materials output by the storage box 4, and the raw materials flow to the material leveling plate 73 through the leak hole 72. The receiving hopper 71 and the material leveling plate 73 make the plaster paddle evenly distributed. The lifting cylinder 6 controls the push rod 61 to drive the moving block 62 to move vertically, so that the plastering plate 74 moves up and down to plaster the wall. The recovery bucket 82 is close to the wall, and the spring 83 pushes the flat plate 84 on the recovery bucket 82 close to the wall to catch the fallen raw materials. The raw materials fall from the recovery bucket 82 into the placement groove 86 and can be recycled.

[0031] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A wall plastering device for construction engineering, comprising a base (1), Features: A stirring tank (2) is arranged on the top of the base (1), a connecting pipe (3) is arranged through one side of the stirring tank (2), a valve (31) is arranged on the connecting pipe (3), an end of the connecting pipe (3) away from the stirring tank (2) is connected to a storage box (4), the storage box (4) is arranged on the top of the base (1), a lifting cylinder (6) is movably arranged on the base (1) in front of the storage box (4), the output end of the lifting cylinder (6) is connected to a push rod (61), a moving block (62) is arranged on the upper end of the push rod (61), a plastering assembly (7) is arranged on the front side of the moving block (62), and a recovery assembly (8) is arranged below the plastering assembly (7); The plastering assembly (7) comprises a material receiving hopper (71) fixedly mounted on the moving block (62), a leak hole (72) penetrating the bottom of the material receiving hopper (71), a material leveling plate (73) arranged below the material receiving hopper (71), the material leveling plate (73) being arranged in an inclined manner, the upper end of the material leveling plate (73) being fixedly connected to the moving block (62), and the lower end of the material leveling plate (73) being connected to a plastering plate (74).

2. A wall plastering equipment for construction engineering according to claim 1, Features: A rotating shaft (21) is arranged inside the stirring tank (2), the lower end of the rotating shaft (21) movably passes through the stirring tank (2) and is connected to a motor (22), a stirring rod (23) is arranged outside the rotating shaft (21), and a stirring paddle (24) is installed on the stirring rod (23).

3. A wall plastering equipment for construction engineering according to claim 1, Features: A material extraction pipe (41) is arranged inside the storage box (4), the upper end of the material extraction pipe (41) extends through the top of the storage box (4), the upper end of the material extraction pipe (41) is connected to a pump (42), the pump (42) is installed on the top of the storage box (4), the pump (42) is connected to a delivery pipe (43), the delivery pipe (43) is fixed to the top of the moving block (62) through a positioning block, and the outlet of the delivery pipe (43) is arranged above the receiving hopper (71).

4. A wall plastering equipment for construction engineering according to claim 1, Features: The top of the base (1) is provided with a mounting groove (11), an electric guide rail (5) is arranged inside the mounting groove (11), a slider (51) is movably arranged outside the electric guide rail (5), and a lifting cylinder (6) is fixedly installed on the top of the slider (51).

5. A wall plastering equipment for construction engineering according to claim 1, Features: The recovery assembly (8) comprises a telescopic short rod (81) arranged at the front side of the base (1), the telescopic short rod (81) being connected to a recovery bucket (82), a spring (83) being sleeved on the outside of the telescopic short rod (81), a flat plate (84) being arranged on the side of the recovery bucket (82) away from the base (1), and the recovery bucket (82) being arranged obliquely, a baffle (85) being arranged at the higher end of the recovery bucket (82), and a placement groove (86) being arranged at the lower end of the recovery bucket (82), and the placement groove (86) being arranged at one end of the base (1) close to the stirring tank (2).

6. A wall plastering equipment for construction engineering according to claim 1, Features: The movable block (62) is provided with a slide rod (9) running through the inside thereof, a limit block (91) is provided at the top end of the slide rod (9), a movable clamping block (92) is connected to the lower end of the slide rod (9), and slide grooves (93) are provided inside the base (1) on both sides of the mounting groove (11), and the movable clamping block (92) is slidably provided inside the slide grooves (93).