Template for secondary structure pouring
By setting up a deflector and a sealing plate on the secondary structure formwork, the design of the drive assembly and spring fixing assembly is solved, and the construction quality and efficiency are improved.
Patent Information
- Application Number
- CN202323592478.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-27
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2033-12-27
AI Technical Summary
In secondary structure construction, concrete is prone to overflow at the pouring port, resulting in uneven cylinders after the formwork is removed, reducing construction efficiency and increasing costs.
Design a formwork for secondary structure casting. The top of the formwork is equipped with a deflector and a sealing plate. The sealing plate is driven by the drive component to slide the casting port, combining the design of the spring and fixed component to ensure the stability of the sealing plate. And convenient operation.
It effectively reduces concrete overflow, improves the flatness and construction efficiency of the cylinder, and improves the construction quality.
Smart Images

Figure CN221941924U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of secondary structure construction, and in particular to a formwork for casting a secondary structure. Background Art
[0002] Secondary structure refers to some non-load-bearing concrete structures, structural columns, lintels, etc. in frames, shear walls, frame-shear projects that need to be completed before decoration. They are called secondary structure.
[0003] During the secondary structure construction of the structural column, after the structural column formwork is built, it is usually necessary to open a pouring port on the top of the structural column formwork, install a guide plate at the pouring port, and pour concrete into the structural column. After the concrete is dry, the formwork can be removed.
[0004] Regarding the above-mentioned related technologies, there are the following defects: there will be some overflowed concrete at the pouring port. After the formwork is removed, the concrete at the pouring port will protrude from the surface of the structural column and need to be chiseled, which reduces the construction efficiency. Moreover, the appearance of the column after chiseling is poor and may require secondary processing, which increases the construction cost. Utility Model Content
[0005] In order to improve the problem that concrete easily overflows from the pouring port, the present application provides a formwork for casting a secondary structure.
[0006] The template for secondary structure casting provided in this application adopts the following technical solution:
[0007] A template for casting a secondary structure comprises: a template and a pouring port arranged on the top of the template, a guide plate is provided on the template at the pouring port, a sealing plate is slidably connected to the guide plate, and a driving component is provided on the guide plate for driving the sealing plate to slide so that the sealing plate seals the pouring port.
[0008] By adopting the above technical solution, after pouring is completed, the driving component drives the sealing plate to slide, and the sealing plate blocks the pouring port, thereby reducing the possibility of concrete overflow in the formwork, improving the flatness of the column surface, and improving the construction quality and efficiency.
[0009] Optionally: the driving assembly includes a support plate arranged on the guide plate, the support plate is threadedly connected with a screw rod, and the sealing plate is rotatably connected to the screw rod.
[0010] By adopting the above technical solution, the screw is rotated, and the screw moves along the guide plate, thereby driving the blocking plate to slide along the guide plate until the blocking plate blocks the pouring port. The operation is convenient and the fixation is stable.
[0011] Optionally: the support plate is rotatably connected to a side of the guide plate away from the template, and a fixing component for fixing the support plate is provided on the guide plate.
[0012] By adopting the above technical solution, during the pouring of concrete, the support plate is rotated to the bottom of the guide plate to avoid affecting the pouring; after the pouring is completed, the support plate is rotated to the top of the guide plate, and then the support plate is fixed using a fixing assembly.
[0013] Optionally: the fixing assembly includes an insertion rod passing through the guide plate, the guide plate is provided with a first insertion hole for the insertion rod to pass through, and the support plate is provided with a second insertion hole for the insertion rod to pass through.
[0014] By adopting the above technical solution, when the support plate is rotated to the top of the guide plate, the first socket is aligned with the second socket, and the insertion rod is inserted into the first socket and the second socket, the support plate is fixed, the operation is convenient, and the construction efficiency is improved.
[0015] Optionally: a spring is sleeved on the insertion rod, one end of the spring is connected to the insertion rod, and the other end of the spring is connected to the guide plate. The spring is in a stretched state, and the spring causes the insertion rod to tend to slide toward the support plate.
[0016] By adopting the above technical solution, on the one hand, when the first socket is aligned with the second socket, under the action of the spring restoring force, the insertion rod automatically rebounds into the first socket and the second socket, making the operation more convenient; on the other hand, under the action of the spring restoring force, the insertion rod is pressed tightly against the first socket and the second socket, making the fixation more stable and reducing the possibility of the insertion rod loosening.
[0017] Optionally, one end of the insertion rod close to the support plate is spherical.
[0018] By adopting the above technical solution, when the insertion rod slides into the first insertion hole, it plays a guiding role, making it easier for the insertion rod to slide into the first insertion hole.
[0019] Optionally: an anti-sticking layer is provided on one side of the sealing plate close to the pouring port.
[0020] By adopting the above technical solution, the possibility of concrete at the pouring port adhering to the sealing plate is reduced. On the one hand, it is convenient to remove the sealing plate; on the other hand, it further improves the flatness of the column surface and further improves the construction quality.
[0021] Optionally: a handle is provided on the screw rod.
[0022] By adopting the above technical solution, holding the handle makes it easier to rotate the screw, reducing the possibility of slipping.
[0023] In summary, this application has the following beneficial effects:
[0024] After pouring concrete, use a blocking plate to seal the pouring port, which reduces the possibility of concrete overflow, improves the flatness of the column surface, and improves construction quality and efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application.
[0026] Description of reference numerals:
[0027] 1. Template; 11. Pouring port; 12. Guide plate; 2. Sealing plate; 21. Anti-sticking layer; 3. Driving assembly; 31. Support plate; 32. Screw; 33. Handle; 4. Fixing assembly; 41. Insert rod; 42. First insertion hole; 43. Second insertion hole; 44. Spring; 51. Bottom plate; 52. Bearing. DETAILED DESCRIPTION
[0028] The present application is further described in detail below in conjunction with the accompanying drawings.
[0029] This embodiment: a template for secondary structure casting, referring to Figure 1 , including: a template 1 and a pouring port 11 opened at the top of the template 1, a guide plate 12 is fixedly connected to the bottom of the pouring port 11 on the template 1, and the guide plate 12 is inclined at 20 degrees.
[0030] A support plate 31 is rotatably connected to the side of the guide plate 12 away from the template 1 in the height direction of the template 1, and a fixing component 4 for fixing the support plate 31 is provided on the guide plate 12. A blocking plate 2 is slidably connected to the support plate 31, and a driving component 3 is provided on the support plate 31 for driving the blocking plate 2 to slide so that the blocking plate 2 blocks the pouring port 11.
[0031] It should be noted that a side of the blocking plate 2 close to the pouring port 11 is provided with an anti-sticking layer 21, which is a polymer coating. The advantage of such a setting is that the possibility of concrete adhering to the blocking plate 2 is reduced, and the flatness of the column surface is improved.
[0032] During the pouring of concrete, the support plate 31 is rotated to the bottom of the guide plate 12 to avoid affecting the pouring of concrete. After the pouring is completed, the support plate 31 is rotated to the top of the guide plate 12 and the support plate 31 is fixed using the fixing assembly 4. Under the driving action of the driving assembly 3, the blocking plate 2 moves toward the pouring port 11 until the pouring port 11 is blocked. After the concrete is dry, the formwork 1 and the blocking plate 2 can be removed. The possibility of concrete overflow is reduced, the flatness of the column surface is improved, and the construction quality and efficiency are improved.
[0033] Among them, the fixing component 4 includes a bottom plate 51 fixedly connected to the side of the guide plate 12 away from the template 1, the bottom plate 51 is perpendicular to the guide plate 12, a first plug hole 42 is opened on the bottom plate 51, an insertion rod 41 is slidably inserted into the first plug hole 42, the insertion rod 41 is perpendicular to the bottom plate 51, the end of the insertion rod 41 close to the support plate 31 is spherical, and a second plug hole 43 for the insertion rod 41 to pass through is opened on the support plate 31.
[0034] In addition, a spring 44 is sleeved on the insertion rod 41, one end of the spring 44 is fixedly connected to the insertion rod 41, and the other end of the spring 44 is fixedly connected to the guide plate 12. The spring 44 is in a stretched state, and the spring 44 causes the insertion rod 41 to have a tendency to slide toward the support plate 31.
[0035] During the rotation of the support plate 31, under the pushing action of the support plate 31, the end of the insertion rod 41 abuts against the support plate 31 and slides relatively along the support plate 31. At the same time, the insertion rod 41 slides along the first insertion hole 42. At this time, the spring 44 is in a stretched state. As the support plate 31 rotates, when the first insertion hole 42 is aligned with the second insertion hole 43, under the action of the restoring force of the spring 44, the insertion rod 41 rebounds into the first insertion hole 42 and the second insertion hole 43, and the support plate 31 is fixed.
[0036] The driving assembly 3 includes a screw rod 32 threadedly connected to the support plate 31, the screw rod 32 passes through the support plate 31, the screw rod 32 is perpendicular to the support plate 31, and a handle 33 is fixedly connected to the end of the screw rod 32 away from the template 1. The blocking plate 2 is rotatably connected to the end of the screw rod 32 away from the support plate 31 through a bearing 52, and the blocking plate 2 and the screw rod 32 are 20 degrees apart.
[0037] After the support plate 31 is fixed firmly, the handle 33 is held to rotate the screw rod 32, and the screw rod 32 moves along the guide plate 12, thereby driving the blocking plate 2 to move toward the pouring port 11 until the pouring port 11 is blocked. The operation is convenient and the fixation is firm.
[0038] The implementation principle of a formwork for secondary structure casting in an embodiment of the present application is as follows: during the pouring of concrete, the support plate 31 is rotated to the bottom of the guide plate 12 to avoid affecting the normal pouring of concrete. After the pouring is completed, the support plate 31 is rotated to the top of the guide plate 12. Under the action of the restoring force of the spring 44, the plug 41 rebounds to the first plug hole 42 and the second plug hole 43, and the support plate 31 is fixed. The screw 32 is rotated, and the screw 32 drives the sealing plate 2 to move toward the pouring port 11 until the pouring port 11 is blocked. The possibility of concrete overflow is reduced, the flatness of the column surface is improved, and the construction quality and efficiency are improved.
[0039] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A formwork for casting secondary structures, It is characterized in that include: A template (1) and a pouring port (11) provided at the top of the template (1); a guide plate (12) is provided on the template (1) at the pouring port (11); a blocking plate (2) is slidably connected to the guide plate (12); and a driving component (3) is provided on the guide plate (12) for driving the blocking plate (2) to slide so that the blocking plate (2) blocks the pouring port (11).
2. A formwork for secondary structure casting according to claim 1, Features: The driving assembly (3) comprises a support plate (31) arranged on the guide plate (12), a screw rod (32) being threadedly connected to the support plate (31), and the blocking plate (2) is rotatably connected to the screw rod (32).
3. A formwork for secondary structure casting according to claim 2, Features: The support plate (31) is rotatably connected to a side of the guide plate (12) away from the template (1), and a fixing component (4) for fixing the support plate (31) is provided on the guide plate (12).
4. A formwork for secondary structure casting according to claim 3, Features: The fixing assembly (4) comprises an insertion rod (41) that is inserted through the guide plate (12); the guide plate (12) is provided with a first insertion hole (42) for the insertion rod (41) to pass through; and the support plate (31) is provided with a second insertion hole (43) for the insertion rod (41) to pass through.
5. A formwork for secondary structure casting according to claim 4, Features: A spring (44) is sleeved on the insertion rod (41); one end of the spring (44) is connected to the insertion rod (41), and the other end of the spring (44) is connected to the guide plate (12); the spring (44) is in a stretched state, and the spring (44) causes the insertion rod (41) to have a tendency to slide towards the support plate (31).
6. A formwork for secondary structure casting according to claim 4, Features: One end of the insertion rod (41) close to the support plate (31) is spherical.
7. A formwork for secondary structure casting according to claim 1, Features: An anti-sticking layer (21) is provided on one side of the sealing plate (2) close to the pouring port (11).
8. A formwork for secondary structure casting according to claim 2, Features: The screw rod (32) is provided with a handle (33).