Cast-in-situ bored pile construction device

By designing a drill bit and groundwater extraction system for bored piles, the problem of difficult pile positioning was solved, construction accuracy and efficiency were improved, and the system was adapted to complex geological conditions.

CN221942354UActive Publication Date: 2024-11-01SHANDONG CHANGSHENG IRON TOWER CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420340227.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-23
Publication Date
2024-11-01
Estimated Expiration
2034-02-23

AI Technical Summary

Technical Problem

The existing cast-in-place pile device cannot be moved after the location is selected, which makes it difficult to adjust the position and affects the construction accuracy and precision.

Method used

A drilling and grouting pile construction device was designed, which includes a platform, a construction mechanism and a hydraulic telescopic rod. The position of the drill bit is adjusted by means of threaded rod and motor drive, and groundwater is extracted by means of piston and motor system, which can adapt to different geological conditions.

Benefits of technology

It enables flexible adjustment of the drill bit position, improves the accuracy and adaptability of construction, adapts to complex geological conditions, and improves construction efficiency and site dryness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221942354U_ABST
    Figure CN221942354U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of cast-in-place pile construction, and discloses a cast-in-place bored pile construction device which comprises a platform, a construction mechanism is installed on the top of the platform and comprises an installation groove, the installation groove is formed in the side portion of the platform, a threaded rod is rotatably installed in the installation groove, and a first motor is fixedly installed at the end of the threaded rod. A connecting block is installed on the surface of the threaded rod in a threaded mode, a sliding barrel is fixedly installed in the connecting block, a sliding rod is slidably installed in the sliding barrel, an installation barrel is fixedly installed on the surface of the sliding rod, a plurality of cutting tool bits are fixedly installed on the surface of the installation barrel, and a drill bit is fixedly installed at the bottom of the sliding rod. Through the arrangement of the construction mechanism, the position of the drill bit can be moved left and right, and the left-right adjusting function of the cast-in-place pile can be adjusted according to specific engineering requirements, so that the cast-in-place pile can better adapt to different geological conditions and engineering requirements.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of cast-in-place pile construction, in particular to a bored cast-in-place pile construction device. Background Art

[0002] When constructing a bridge, cast-in-place piles are used. Cast-in-place piles are made by directly drilling holes at the designed pile positions. The cross section of the cast-in-place piles is circular. After the holes are formed, a steel cage is placed in the holes and concrete is poured. Cast-in-place piles are widely used in construction because of their advantages of no vibration, no soil squeezing, low noise, and suitability for use in densely populated urban areas. According to different hole-forming processes, cast-in-place piles can be divided into cast-in-place piles with dry holes, cast-in-place piles with mud wall protection holes, and cast-in-place piles with manual holes.

[0003] The existing bored pile device is basically unable to move after the location is selected, which makes it impossible to adjust the left and right. In this way, other measures need to be taken to adjust the position during the construction of the bored pile, such as rearranging the steel cage or modifying the construction plan, which increases the difficulty and complexity of the construction. The position of the bored pile deviates from the design requirements, thereby affecting the precision and accuracy of the construction. Utility Model Content

[0004] The technical problem to be solved by the utility model is to provide a bored pile construction device which can move the position of the drill bit and adapt to different geological conditions and engineering requirements.

[0005] In order to solve the above technical problems, the utility model provides the following technical solutions:

[0006] A bored pile construction device comprises a platform, a construction mechanism is installed on the top of the platform, the construction mechanism comprises a mounting groove, the mounting groove is opened on the side of the platform, a threaded rod is rotatably installed in the mounting groove, a first motor is fixedly installed at the end of the threaded rod, a connecting block is threadedly installed on the surface of the threaded rod, a slide cylinder is fixedly installed inside the connecting block, a slide rod is slidably installed inside the slide cylinder, a mounting cylinder is fixedly installed on the surface of the slide rod, a plurality of cutting bits are fixedly installed on the surface of the mounting cylinder, and a drill bit is fixedly installed on the bottom of the slide rod.

[0007] The following is a further optimization of the above technical solution by the utility model:

[0008] A sliding groove is provided on the top of the platform, a mounting block is slidably mounted inside the sliding groove, and a hydraulic telescopic rod is fixedly mounted on the top of the mounting block.

[0009] Further optimization: a mounting plate is fixedly installed on the output end of the hydraulic telescopic rod, a driving wheel is rotatably installed on the top of the mounting plate, and a supporting plate is rotatably installed on the top of the driving wheel.

[0010] Further optimization: the support plate is slidably connected to the sliding rod, a second motor is fixedly installed on the top of the support plate, and an output end of the second motor passes through the bottom of the support plate and is fixedly connected to the driving wheel.

[0011] Further optimization: a driven wheel is fixedly installed on the top of the sliding rod, and a belt is installed between the driven wheel and the driving wheel.

[0012] Further optimization: the interior of the slide rod is hollow, a piston is slidably installed inside the slide rod, and a connecting column is fixedly installed on the top of the piston.

[0013] Further optimization: a rotating rod is rotatably mounted on the end of the connecting column, a rotating wheel is rotatably mounted on the side of the rotating rod, and a first pulley is fixedly mounted on the side of the rotating wheel.

[0014] Further optimization: a third motor is fixedly installed on the top of the support plate, a second pulley is fixedly installed on the output end of the third motor, and the first pulley and the second pulley are connected by a belt.

[0015] The utility model adopts the above technical solution, and through the setting of the construction mechanism, the position of the drill bit can be moved left and right, and the left and right adjustment function of the cast-in-place pile can be adjusted according to the needs of the specific project, so that it can better adapt to different geological conditions and engineering requirements. For example, in areas with complex geological conditions, the left and right offset of the cast-in-place pile can be adjusted to cope with different geological layers to provide better bearing capacity and stability;

[0016] Through the setting of the piston and the third motor, the bored piles can extract underground sewage through the hollow drill rod, which is very useful for areas with high groundwater levels or where groundwater needs to be treated during construction. By extracting sewage, the construction site can be kept dry and construction efficiency can be improved.

[0017] The utility model is further described below in conjunction with the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the overall structure in the implementation of the utility model;

[0019] Figure 2 It is a schematic diagram of the overall front view structure in the implementation of the utility model;

[0020] Figure 3 It is a schematic diagram of the overall rear view structure in the implementation of the utility model;

[0021] Figure 4 It is a schematic diagram of the construction mechanism structure in the implementation of the utility model.

[0022] In the figure: 1-platform; 2-construction mechanism; 201-installation groove; 202-threaded rod; 203-first motor; 204-connecting block; 205-slide cylinder; 206-slide rod; 207-installation cylinder; 208-cutting head; 209-drill bit; 210-slide groove; 211-installation block; 212-hydraulic telescopic rod; 213-installation plate; 214-driving wheel; 215-support plate; 3-second motor; 4-driven wheel; 5-belt; 6-piston; 7-connecting column; 8-rotating rod; 9-rotating wheel; 10-first pulley; 11-third motor; 12-second pulley. DETAILED DESCRIPTION

[0023] like Figure 1-4 As shown, a bored pile construction device comprises a platform 1, a construction mechanism 2 is installed on the top of the platform 1, the construction mechanism 2 comprises a mounting groove 201, the mounting groove 201 is opened on the side of the platform 1, a threaded rod 202 is rotatably installed in the mounting groove 201, a first motor 203 is fixedly installed at the end of the threaded rod 202, a connecting block 204 is threadedly installed on the surface of the threaded rod 202, a slide cylinder 205 is fixedly installed inside the connecting block 204, a slide rod 206 is slidably installed inside the slide cylinder 205, a mounting cylinder 207 is fixedly installed on the surface of the slide rod 206, a plurality of cutting bits 208 are fixedly installed on the surface of the mounting cylinder 207, and a drill bit 209 is fixedly installed at the bottom of the slide rod 206.

[0024] With this design, the cutting head 208 can cut the inner wall of the borehole, thereby preventing the inner wall from collapsing during the drilling process; the movement of the connecting block 204 can drive the cutting head 208 and the drill bit 209 to move, thereby the position of the drill bit 209 can be moved according to the needs of the project.

[0025] A sliding groove 210 is provided on the top of the platform 1 , a mounting block 211 is slidably mounted inside the sliding groove 210 , and a hydraulic telescopic rod 212 is fixedly mounted on the top of the mounting block 211 .

[0026] A mounting plate 213 is fixedly mounted on the output end of the hydraulic telescopic rod 212 , a driving wheel 214 is rotatably mounted on the top of the mounting plate 213 , and a supporting plate 215 is rotatably mounted on the top of the driving wheel 214 .

[0027] With such a design, the height of the entire drill bit 209 can be adjusted by setting the hydraulic telescopic rod 212, thereby realizing the drilling operation.

[0028] The support plate 215 is slidably connected to the slide bar 206 , and a second motor 3 is fixedly mounted on the top of the support plate 215 . The output end of the second motor 3 passes through the bottom of the support plate 215 and is fixedly connected to the driving wheel 214 .

[0029] A driven wheel 4 is fixedly mounted on the top of the slide bar 206 , and a belt 5 is installed between the driven wheel 4 and the driving wheel 214 .

[0030] The interior of the slide rod 206 is hollow, a piston 6 is slidably mounted inside the slide rod 206 , and a connecting column 7 is fixedly mounted on the top of the piston 6 .

[0031] A rotating rod 8 is rotatably mounted on the end of the connecting column 7 , a rotating wheel 9 is rotatably mounted on the side of the rotating rod 8 , and a first pulley 10 is fixedly mounted on the side of the rotating wheel 9 .

[0032] A third motor 11 is fixedly mounted on the top of the support plate 215 , a second belt pulley 12 is fixedly mounted on the output end of the third motor 11 , and the first belt pulley 10 and the second belt pulley 12 are connected via a belt 5 .

[0033] With this design, the second motor 3 can drive the driving wheel 214 to rotate, and the rotation of the driving wheel 214 can drive the driven wheel 4 to rotate, thereby driving the slide bar 206 to rotate, thereby driving the cutting head 208 and the drill bit 209 to rotate, thereby realizing the drilling operation.

[0034] The third motor 11 can drive the second pulley 12 to rotate, the rotating second pulley 12 can drive the first pulley 10 to rotate, the rotating first pulley 10 can drive the rotating wheel 9 to rotate, the rotation of the rotating wheel 9 can drive the rotating rod 8 to rotate eccentrically, the eccentric rotation of the rotating rod 8 can drive the connecting column 7 to reciprocate, the reciprocating motion of the connecting column 7 can drive the piston 6 to perform piston motion inside the sliding rod 206, and then the sewage generated by the drilling can be extracted to keep the construction site dry.

[0035] When in use, the staff moves the entire device to the place where drilling is required, and then starts the hydraulic telescopic rod 212, which can drive the height of the mounting plate 213 and the support plate 215 to be adjusted. When the drill bit 209 contacts the ground, the second motor 3 is started. The second motor 3 can drive the driving wheel 214 to rotate, and the rotating driving wheel 214 can drive the driven wheel 4 to rotate. The rotation of the driven wheel 4 can drive the slide bar 206 to rotate, and the rotation of the slide bar 206 can drive the cutting head 208 and the drill bit 209 to rotate, so that the ground can be drilled. Then the third motor 11 is started, and the third motor 11 can drive the second pulley 12 to rotate, and the rotating second pulley The wheel 12 can drive the first pulley 10 to rotate, the rotating first pulley 10 can drive the rotating wheel 9 to rotate, the rotation of the rotating wheel 9 can drive the rotating rod 8 to rotate eccentrically, the eccentric rotation of the rotating rod 8 can drive the connecting column 7 to reciprocate, and the reciprocating motion of the connecting column 7 can drive the piston 6 to perform piston motion inside the sliding rod 206, thereby extracting the sewage generated inside the sliding rod 206. When the position of the drill bit 209 needs to be adjusted, the second motor 3 is started, and the second motor 3 can drive the threaded rod 202 to rotate. The rotation of the threaded rod 202 can drive the connecting block 204 to move on the surface of the threaded rod 202, thereby adjusting the position of the drill bit 209.

[0036] For ordinary technicians in this field, according to the teachings of the present invention, without departing from the principles and spirit of the present invention, changes, modifications, substitutions and variations made to the implementation methods are still within the protection scope of the present invention.

Claims

1. A bored pile construction device, characterized in that: The invention comprises a platform (1), wherein a construction mechanism (2) is installed on the top of the platform (1), wherein the construction mechanism (2) comprises a mounting groove (201), wherein the mounting groove (201) is provided on the side of the platform (1), wherein a threaded rod (202) is rotatably mounted in the mounting groove (201), wherein a first motor (203) is fixedly mounted at the end of the threaded rod (202), wherein a connecting block (204) is threadedly mounted on the surface of the threaded rod (202), wherein a slide cylinder (205) is fixedly mounted inside the connecting block (204), wherein a slide rod (206) is slidably mounted inside the slide cylinder (205), wherein a mounting cylinder (207) is fixedly mounted on the surface of the slide rod (206), wherein a plurality of cutting blades (208) are fixedly mounted on the surface of the mounting cylinder (207), and wherein a drill bit (209) is fixedly mounted on the bottom of the slide rod (206).

2. A bored pile construction device according to claim 1, characterized in that: A sliding groove (210) is provided on the top of the platform (1), a mounting block (211) is slidably mounted inside the sliding groove (210), and a hydraulic telescopic rod (212) is fixedly mounted on the top of the mounting block (211).

3. A bored pile construction device according to claim 2, characterized in that: A mounting plate (213) is fixedly mounted on the output end of the hydraulic telescopic rod (212), a driving wheel (214) is rotatably mounted on the top of the mounting plate (213), and a supporting plate (215) is rotatably mounted on the top of the driving wheel (214).

4. A bored pile construction device according to claim 3, characterized in that: The support plate (215) is slidably connected to the slide bar (206); a second motor (3) is fixedly mounted on the top of the support plate (215); an output end of the second motor (3) passes through the bottom of the support plate (215) and is fixedly connected to the driving wheel (214).

5. A bored pile construction device according to claim 4, characterized in that: A driven wheel (4) is fixedly mounted on the top of the sliding rod (206), and a belt (5) is mounted between the driven wheel (4) and the driving wheel (214).

6. A bored pile construction device according to claim 5, characterized in that: The interior of the sliding rod (206) is hollow, a piston (6) is slidably mounted inside the sliding rod (206), and a connecting column (7) is fixedly mounted on the top of the piston (6).

7. A bored pile construction device according to claim 6, characterized in that: A rotating rod (8) is rotatably mounted on the end of the connecting column (7), a rotating wheel (9) is rotatably mounted on the side of the rotating rod (8), and a first pulley (10) is fixedly mounted on the side of the rotating wheel (9).

8. A bored pile construction device according to claim 7, characterized in that: A third motor (11) is fixedly mounted on the top of the support plate (215), a second belt pulley (12) is fixedly mounted on the output end of the third motor (11), and the first belt pulley (10) and the second belt pulley (12) are connected via a belt (5).