Novel shield segment

By using arc-shaped tube sheets, pins, anchors and locking components in the shield tube sheet, the cumbersome construction and installation problems and water leakage problems are solved, and more stable and efficient tunnel inner wall sealing and structural stability are achieved to adapt to the tunnel. The challenge of uneven inner walls.

CN221942449UActive Publication Date: 2024-11-01SHANDONG RUNGUO CONSTRUCTION IND TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420802637.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-17
Publication Date
2024-11-01
Estimated Expiration
2034-04-17

AI Technical Summary

Technical Problem

The existing shield pipe sheets are cumbersome during construction and installation, which are prone to water leakage and uneven installation problems, resulting in uneven inner walls of the tunnel, serious misalignment of the installation of arc pipe sheets, and requires multiple people to cooperate, resulting in damage or removal of the waterproof adhesive strips. The water leakage cannot be effectively solved.

Method used

A new type of shield pipe piece was designed, using arc pipe piece, pin, anchor, connecting assembly and locking assembly, including circular and elliptical slot sleeve structures, the insertion end of the pin is conical, arc pipe piece The pins on both sides are arranged symmetrically, the anchors are combined with the clips, the PU spring provides forward force, and the clips lock the assembly for stable connection and sealing.

Benefits of technology

It improves the stability and sealing of arc-shaped pipe splicing installation, reduces construction personnel and time, prevents water leakage, enhances construction efficiency and structural stability, and adapts to errors and interference problems caused by uneven inner walls of the tunnel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221942449U_ABST
    Figure CN221942449U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of tunnel engineering, and particularly relates to a novel shield segment, which adopts the technical scheme that the novel shield segment comprises an arc-shaped segment and pins respectively arranged on two sides of the arc-shaped segment, a plurality of inserting holes are formed in one end of the arc-shaped segment, an anchoring part is arranged at the other end of the arc-shaped segment, and the inserting holes are communicated with the anchoring part. A connecting assembly is arranged in the inserting hole, the connecting assembly comprises an anchoring sleeve, the anchoring sleeve is fixedly arranged in the inserting hole, a clamping piece is arranged on the inner side of the anchoring sleeve, a pu spring is arranged at the end, away from the inserting hole, of the clamping piece, and locking assemblies are arranged at the ends, away from the pin, of the two sides of the arc-shaped pipe piece correspondingly; due to the arrangement of the connecting assembly, the anchoring part can only move forwards after entering the clamping piece and cannot move backwards, and the firmness of splicing installation of the arc-shaped duct pieces can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of tunnel engineering, and specifically refers to a new shield segment. Background Art

[0002] The shield segment is the main assembly component of the shield construction and the innermost barrier of the tunnel. It is responsible for resisting soil pressure, groundwater pressure and some special loads. The shield segment is the permanent lining structure of the shield tunnel. The quality of the shield segment is directly related to the overall quality and safety of the tunnel, and affects the waterproof performance and durability of the tunnel.

[0003] During the advancement of the shield machine, the shield segments are assembled into a ring inside the shield machine, and the jacks press the ringed shield segments and the installed segments tightly. After one ring is installed, the end of the shield machine will inject grout into the installed segments to fill the gap between the shield segments and the rock formation. However, the existing shield segments are complicated in construction and installation, and water leakage and uneven installation are unsolvable problems. The shield machine cannot move according to the designed route during advancement, which causes the arc segment installation to be seriously misaligned due to the uneven inner wall of the tunnel. In addition, the installation of the segments requires at least 3 people to cooperate. Due to manual operation, the installed segments will collide with the installed segments, knocking off the waterproof strips bonded to the surface of the segments, or shifting. The resulting water leakage is an unsolvable difficulty and pain point in the assembly of all current shield segments. Utility Model Content

[0004] In order to solve at least one shortcoming in the prior art, the utility model proposes a new shield segment.

[0005] The technical solution adopted by the utility model is as follows: the utility model provides a new type of shield segment, including an arc-shaped segment, and pins respectively arranged on both sides of the arc-shaped segment, one end of the arc-shaped segment is provided with a plurality of sockets, the other end of the arc-shaped segment is provided with an anchor, a connecting component is provided in the socket, the connecting component includes an anchor sleeve, the anchor sleeve is fixed in the socket, a clip is provided on the inner side of the anchor sleeve, a PU spring is provided at the end of the clip away from the socket, and locking components are respectively provided at the ends of both sides of the arc-shaped segment away from the pins.

[0006] Furthermore, the locking assembly comprises a circular slot 1, which is arranged at an end of the side wall of the arc-shaped pipe segment away from the pin, and a circular pipe sleeve 1 is fixedly arranged in the circular slot 1.

[0007] Furthermore, the locking assembly includes a second elliptical slot, which is arranged at an end of the side wall of the arc-shaped pipe segment away from the pin, and a second elliptical pipe sleeve is fixedly arranged in the second elliptical slot.

[0008] Furthermore, the insertion end of the pin is a conical structure.

[0009] Furthermore, the pins on both sides of the arc-shaped tube segment are centrally symmetrically arranged.

[0010] Furthermore, the insertion end of the pin is inclined outwards.

[0011] The beneficial effects achieved by the utility model using the above structure are as follows:

[0012] (1) The setting of the connection assembly, after the anchor on the arc segment enters the clamp in another arc segment, it can only move forward and cannot move backward, thereby improving the stability and firmness of the ring-to-ring structure after the arc segment is spliced ​​and installed, and applying a stable stress to the waterproof strip between the rings to achieve the purpose of water stopping and waterproofing.

[0013] (2) The function of the pu spring is to apply a force to the clip in the direction of the anchor, so that the retraction amount of the anchor clip of the clip lock anchor is controlled to the minimum.

[0014] (3) The insertion end of the pin is tilted outward, so that the gap between the arc segments can become smaller and smaller during the locking process, thereby compressing the waterproof sealing strip between the arc segments, playing the role of water stopping, waterproofing, and structural stability, thereby achieving the effect of connection locking.

[0015] (4) The pins on both sides of the arc segment are arranged symmetrically, which facilitates the splicing and installation of the arc segment and improves the construction efficiency.

[0016] (5) The setting of the second elliptical pipe sleeve can improve the flexibility of the arc segment splicing and installation. Since the shield tunnel and the shield machine rear supporting protective plate are not concentric, the setting of the elliptical pipe sleeve can adjust part of the resulting error, thereby preventing the arc segment and the shield machine rear supporting bushing from interfering with each other due to the unevenness of the tunnel inner wall, resulting in splicing and installation failure. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solution of the utility model, the drawings required for use in the description will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0018] Figure 1 A three-dimensional diagram of a first embodiment of a new shield segment of the utility model Figure 1 ;

[0019] Figure 2 A three-dimensional diagram of a first embodiment of a new shield segment of the utility model Figure 2 ;

[0020] Figure 3 This is a front view of a first embodiment of a new shield segment of the utility model;

[0021] Figure 4 This is a bottom view of a first embodiment of a new shield segment of the utility model;

[0022] Figure 5 This is a schematic diagram of the structure of a connection assembly of a first embodiment of a novel shield segment of the utility model;

[0023] Figure 6 This is a schematic diagram of the pin structure of the first embodiment of a new shield segment of the utility model;

[0024] Figure 7 This is a cross-sectional view of the left side wall of a curved segment of the first embodiment of a new shield segment of the utility model;

[0025] Figure 8 This is a structural schematic diagram of a circular pipe sleeve of a first embodiment of a new shield segment of the utility model;

[0026] Fig. 9 This is a three-dimensional diagram of the arc-shaped pipe segment splicing and installation state of the first embodiment of the utility model;

[0027] Fig.10 A second embodiment of a new shield segment of the utility model is shown in FIG. Figure 1 ;

[0028] Fig.11 This is a schematic diagram of the second locked state of the oval tube sleeve in the second embodiment of the utility model.

[0029] Among them: 1. arc-shaped pipe segment, 2. pin, 3. anchor, 4. socket, 7. clip, 8. PU spring, 9. anchor sleeve, 10. circular slot one, 11. circular pipe sleeve one, 12. oval slot two, 13. oval pipe sleeve two. DETAILED DESCRIPTION

[0030] In order to make the purpose, features and advantages of the utility model more obvious and easy to understand, the technical scheme of the utility model will be clearly and completely described below in combination with the drawings in the specific embodiment. Obviously, the embodiments described below are only part of the embodiments of the utility model, not all of them. Based on the embodiments in this patent, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this patent.

[0031] Embodiment 1

[0032] like Figure 1-Figure 9As shown, the utility model proposes a new shield segment, including an arc segment 1, and pins 2 respectively arranged on both sides of the arc segment 1, the insertion end of the pin 2 is a conical structure, the insertion end of the pin 2 is inclined outward, the pins 2 on both sides of the arc segment 1 are centrally symmetrically arranged, one end of the arc segment 1 is provided with a plurality of insertion holes 4, the other end of the arc segment 1 is provided with an anchor 3, a connecting component is arranged in the insertion hole 4, the connecting component includes an anchor sleeve 9, the anchor sleeve 9 is fixed in the insertion hole 4, a clamp 7 is provided on the inner side of the anchor sleeve 9, a pu spring 8 is provided at the end of the clamp 7 away from the insertion hole 4, locking components are respectively provided at the ends of both sides of the arc segment 1 away from the pin 2, the locking component includes a circular slot 10, the circular slot 10 is arranged at the end of the side wall of the arc segment 1 away from the pin 2, and a circular pipe sleeve 11 is fixed in the circular slot 10.

[0033] When used specifically, the first step is to use special equipment to splice and install the first arc segment 1 in the tunnel completed by the shield. The process is as follows: the anchor 3 of the arc segment 1 is inserted into the socket 4 of the previous ring of segments that have been installed, and the hydraulic push rod of the shield machine gives the arc segment 1 a thrust, so that the anchor enters the clamp 7 to achieve the effect of locking the first segment. The second step is to install the second arc segment 1, and use the pin 2 on the arc segment 1 to insert it into another circular slot 10. Since the pin 2 moves along the axis of the pin during the process of entering the circular sleeve 11, the pin and the sleeve have a certain inclination, so that the pin locking process is to compress and lock the waterproof strips between the arc segments 1 to achieve the purpose of water stopping, waterproofing, and structural stability. At the same time as the pin 2 is inserted into the segment slot 10, the anchor 3 of the arc segment 1 is inserted into the socket 4 of the previous ring of arc segments 1 that has been installed before. Since the socket 4 is provided with a clamp 7, the anchor 3 can only enter the clamp 7 after entering the clamp 7. Move forward and cannot move backward. The function of the pu spring 8 is to give the clip 7 an outward thrust, so that the clip always tightly locks the anchor 3, so that the anchor can only move in one direction. The function of the pu spring is to give the clip a force in the direction of the anchor, so that the retraction amount of the anchor clip of the clip lock anchor is controlled to the minimum, so that the waterproof strips between the rings of the locked pipe segment 1 are compressed and squeezed, achieving water-stopping and waterproofing, and playing a role in stabilizing the structure. The third step: repeat the second step to splice and install the next arc-shaped pipe segment 1 until one ring is completed. The above is the overall working process of the utility model, and this step can be repeated when splicing and installing the next ring.

[0034] It can be seen from the above embodiments that the beneficial effects of the utility model are:

[0035] The setting of the connecting component ensures that the anchor can only move forward and cannot move backward after entering the clip, which can improve the firmness of the arc segment splicing and installation; the function of the PU spring is to give the clip a force in the direction of the anchor, preventing the clip from entering the innermost end of the socket, while controlling the retraction of the anchor clip of the clip lock anchor to the minimum, so as to achieve the purpose of always locking the anchor with the clip; the insertion end of the pin is inclined outward, which can better enter the circular pipe sleeve 1, thereby achieving the effect of connecting and locking; the pins on both sides of the arc segment are centrally symmetrically arranged, which facilitates the splicing and installation of the arc segment and improves the construction efficiency; the setting of the elliptical pipe sleeve 2 can improve the flexibility of the arc segment splicing and installation, and prevent the tunnel forming deviation caused by the inner wall of the tunnel due to the operation of the shield machine, and the interference between the arc segment 1 and the matching bushing behind the shield machine, resulting in the failure of the arc segment splicing and installation.

[0036] Embodiment 2

[0037] The difference between this embodiment and embodiment 1 is: Figure 10-11 As shown, the locking assembly includes an elliptical slot 12 , which is arranged at one end of the side wall of the arc-shaped pipe segment 1 away from the pin 2 , and an elliptical pipe sleeve 13 is fixedly arranged in the elliptical slot 12 .

[0038] During specific use, the first step is to use special equipment to splice and install the first curved segment 1 in the tunnel completed by the shield machine. The process is as follows: the anchor 3 of the curved segment 1 is inserted into the installed socket 4 of the previous ring of segments, and the hydraulic jack of the shield machine gives the curved segment 1 a thrust, so that the anchor enters the clamp 7 to achieve the effect of locking the first segment.

[0039] Step 2: Install the second arc-shaped segment 1, and insert the pin 2 on the arc-shaped segment 1 into another elliptical slot 12. Since the pin 2 moves along the axial direction of the pin when entering the elliptical sleeve 13, the pin and the sleeve have a certain inclination, so that the pin locking process compresses and locks the waterproof strips between the arc-shaped segments 1 to achieve the purpose of water stopping, waterproofing, and structural stability. In addition, since the pin 2 is inserted into the elliptical slot, there is a certain gap above and below the elliptical slot after the pin is inserted, the installation position of the segments can be adjusted to ensure that the uneven gap caused by the eccentricity of the tunnel completed by the shield and the supporting guard plate behind the shield machine causes the problem of unsuccessful segment installation. When the pin 2 is inserted into the segment slot 2 12 and enters the elliptical pipe sleeve 2 13, the anchor 3 of the arc segment 1 is inserted into the socket 4 of the previous ring of arc segment 1 that has been installed before. Since a clip 7 is provided in the socket 4, the anchor 3 can only move forward after entering the clip 7 and cannot retreat. The function of the pu spring 8 is to give the clip 7 an outward thrust, so that the clip always tightly locks the anchor 3, so that the anchor can only move in one direction. The function of the pu spring is to give the clip a force in the direction of the anchor, so that the retraction amount of the anchor clip of the clip lock anchor is controlled to the minimum, so that the waterproof strips between the rings of the locked segment 1 are compressed and squeezed, achieving water-stopping and waterproofing, and playing a role in structural stability.

[0040] Step 3: Repeat the second step to splice and install the next arc-shaped pipe segment 1 until one ring is completed. The above is the overall working process of the utility model. Just repeat this step when splicing and installing the next ring.

[0041] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A new shield segment, characterized by: The invention comprises an arc-shaped tube segment (1) and pins (2) respectively arranged on both sides of the arc-shaped tube segment (1); one end of the arc-shaped tube segment (1) is provided with a plurality of insertion holes (4); the other end of the arc-shaped tube segment (1) is provided with an anchor (3); and the invention is characterized in that: a connecting component is arranged in the insertion hole (4); the connecting component comprises an anchor sleeve (9); the anchor sleeve (9) is fixed in the insertion hole (4); a clip (7) is arranged on the inner side of the anchor sleeve (9); a PU spring (8) is arranged at one end of the clip (7) away from the insertion hole (4); and locking components are respectively arranged at one end of both sides of the arc-shaped tube segment (1) away from the pins (2).

2. A new shield segment according to claim 1, characterized in that: The locking assembly comprises a circular slot one (10), wherein the circular slot one (10) is arranged at an end of the side wall of the arc-shaped pipe segment (1) away from the pin (2), and a circular pipe sleeve one (11) is fixedly arranged in the circular slot one (10).

3. A new shield segment according to claim 1, characterized in that: The locking assembly comprises an elliptical slot 2 (12), which is arranged at an end of the side wall of the arc-shaped pipe segment (1) away from the pin (2), and an elliptical pipe sleeve 2 (13) is fixedly arranged in the elliptical slot 2 (12).

4. A new shield segment according to claim 1, characterized in that: The insertion end of the pin (2) is a conical structure.

5. The novel shield segment according to claim 1 is characterized in that: The pins (2) on both sides of the arc-shaped tube segment (1) are arranged symmetrically with respect to the center.

6. A new shield segment according to claim 1, characterized in that: The insertion end of the pin (2) is inclined outwards.