Gas pipeline drainage device
By designing an integrally sealed water seal box and multi-stage water seal chamber structure, the problem of existing gas pipeline drainage devices need to be disassembled and unblocked when the water seal pipe is blocked, the production efficiency is improved, and breakdown is prevented under high air pressure. It realizes efficient discharge and cleaning of condensate in gas pipelines.
Patent Information
- Application Number
- CN202420129997.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-19
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2034-01-19
AI Technical Summary
The existing gas pipeline drainage device needs to be disassembled and unblocked when the water seal pipe is blocked, resulting in low production efficiency and time-consuming and labor-intensive drainage, and is prone to breakdown when the air pressure is too high.
A gas pipeline drainage device is designed, using an integrally sealed water seal box, divided into multiple water seal chambers through multiple parallel partitions, and connected adjacent water seal chambers by vertically arranged water seal pipes. There is a dredging pipe on the top, allowing cleaning by opening the dredging pipe valve when the water seal pipe is blocked, avoiding disassembly operations, and providing anti-breakdown function when the air pressure is too high.
It realizes that the water seal pipe is unblocked without disassembly, improves production efficiency, and effectively prevents breakdown under high air pressure, ensuring the safe operation of gas pipelines.
Smart Images

Figure CN221943965U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of gas transportation, and in particular to a gas pipeline drainage device. Background Art
[0002] Blast furnace gas produced in the blast furnace ironmaking process is an important by-product and fuel. During the pipeline transportation process, due to changes in temperature and pressure, the saturated steam in the gas will form condensed water, and the injected scale inhibitor and desulfurizer will produce mechanical water. The condensed water and mechanical water separated from the gas will accumulate in the pipeline, causing the pipeline to be overloaded due to excessive water accumulation, aggravating the corrosion of the pipeline and other adverse effects.
[0003] As an important auxiliary equipment to ensure the smooth flow of gas pipelines, the main function of the gas drainer is to collect and discharge gas condensate, mechanical water and dirt in the gas pipeline on the basis of sealing the gas in the pipeline, so as to ensure the safe operation of the gas pipeline network. In actual use, since these gases are produced in the process of steel smelting, they will inevitably carry dust, as well as tar and other substances produced in the process of coal combustion. These substances are mixed with condensate and discharged into the gas drainer, which can easily lead to blockage of the water seal pipe. In addition, the existing water seal pipes mostly use 90° elbows. For example, the water seal pipe in the gas drainer provided in the publication number CN116951325A "A kind of anti-leakage gas drainer and method without steam purge" adopts a 90° elbow structure. When the water seal pipe is blocked, this structure requires the drainer to be opened as a whole, the water seal pipe to be disassembled, and the water seal pipe to be dredged, which not only affects the production process and production efficiency, but also the dredging process is quite time-consuming and laborious. Utility Model Content
[0004] The present application provides a gas pipeline drainage device, which is used to solve the problem that when the water seal pipe of the existing gas pipeline drainage device is blocked, the water seal pipe needs to be disassembled for unblocking, which affects the production efficiency and the unblocking process is time-consuming and labor-intensive.
[0005] The present application provides a gas pipeline drainage device, including an integrally sealed water seal box;
[0006] The water seal box is divided into multiple water seal chambers by multiple parallel partitions;
[0007] The partition includes a first vertical plate and a second vertical plate, and a connecting plate, one end surface of the connecting plate is connected to the lower end surface of the first vertical plate, and the other end surface of the connecting plate is connected to the upper end surface of the second vertical plate;
[0008] Two adjacent water seal chambers are connected via a water seal pipe, which passes through the connecting plate and is vertically arranged;
[0009] A liquid inlet is provided at the top of the water seal chamber at one end of the water seal box, and the liquid inlet is connected to the gas pipeline through a valve; an overflow drain pipe is connected to the upper part of one side of the water seal box away from the liquid inlet;
[0010] A sewage outlet is provided at the lower part of the side of the water seal box where each water seal chamber is located.
[0011] The upper surface of the water seal box is connected with a plurality of dredging pipes; the plurality of dredging pipes correspond to the plurality of water seal pipes one by one;
[0012] The dredge pipe is sealed by a dredge pipe valve.
[0013] Optionally, the overflow drain pipe is connected to the drainage device.
[0014] Optionally, the drainage device includes a liquid receiving funnel connected in series and a sewage pool connected to the liquid receiving funnel through a pipeline.
[0015] Optionally, the connecting plate is inclined in a direction from a connection point with the first vertical plate to a connection point with the second vertical plate, and the inclination direction forms an elevation angle greater than or equal to 0° and less than 90° with respect to the horizontal direction.
[0016] Optionally, a heat pipe is provided in the lower part of at least one water seal chamber, and the heat pipe extends inward through the side wall of the water seal box. One end of the heat pipe extending into the water seal box is sealed, and the other end is open for installing the electric heating pipe.
[0017] Optionally, the heat pipe includes a tube shell; a heat conducting layer is coaxially arranged inside the tube shell, the heat conducting layer is arranged close to the inner wall of the tube shell, and an accommodating cavity is arranged at the axial position of the heat conducting layer for installing the electric heating pipe.
[0018] Optionally, the material of the heat conducting layer is one of graphite, silicon carbide or silicon nitride.
[0019] The present application provides a gas pipeline drainage device, which is divided into multiple water seal chambers by a water seal box using a plurality of "Z"-shaped partitions formed by connecting a first vertical plate, a second vertical plate and a connecting plate, and adjacent water seal chambers are connected by vertically arranged water seal pipes, and at the same time, a dredging pipe sealed by a dredging pipe valve is opened at the top of the water seal box corresponding to the water seal pipe, and the dredging pipe valve can be opened when the water seal pipe is blocked, and the water seal pipe can be dredged by a dredging tool without disassembling the water seal box. The device of the present application can realize the discharge of condensed water in the gas pipeline and conveniently clean the water seal pipe through the coordinated use of the above structure, overcoming the existing gas pipeline drainage device, which needs to be disassembled for dredging after the water seal pipe in the water seal box is blocked, which affects the production efficiency and the time-consuming and labor-intensive dredging process. In addition, the device of the present application, the water seal box is divided into multiple water seal chambers in series by partitions, and when the gas pressure in the gas pipeline is too high, it can also play a good role in preventing breakdown. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, a brief introduction will be given below to the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0021] Figure 1 A schematic diagram of the structure of a gas pipeline drainage device provided in one embodiment of the present application;
[0022] Figure 2 A schematic diagram of the structure of a partition provided in one embodiment of the present application;
[0023] Figure 3 A schematic diagram of the structure of a gas pipeline drainage device provided in another embodiment of the present application;
[0024] Figure 4 A schematic diagram of a drainage device provided in one embodiment of the present application;
[0025] Figure 5 A schematic diagram of the internal three-dimensional structure of a water seal box provided in one embodiment of the present application;
[0026] Figure 6 A schematic diagram of the structure of a heat pipe provided in one embodiment of the present application.
[0027] Description of reference numerals:
[0028] 1. Water seal box; 10. Gas pipeline; 11. Partition; 12. Water seal pipe; 13. Drainage device; 14. Heat transfer pipe; 15. Electric heating pipe; 100. Valve; 101. Liquid inlet; 102. Overflow drain pipe; 103. Sewage outlet; 104. Dredge pipe; 111. First vertical plate; 112. Second vertical plate; 113. Connecting plate; 131. Liquid receiving funnel; 132. Sewage tank; 141. Tube shell; 142. Heat transfer layer; 200. Dredge pipe valve. DETAILED DESCRIPTION
[0029] In order to make the purpose, technical scheme and advantages of the embodiments of the present application clearer, the technical scheme in the embodiments of the present application is clearly and completely described below. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work also fall within the scope of protection of the present application.
[0030] like Figure 1 and Figure 2 As shown, the present application provides a gas pipeline drainage device, including an integrally sealed water seal box 1;
[0031] The water seal box 1 is divided into a plurality of water seal chambers by a plurality of parallel partitions 11;
[0032] The partition 11 includes a first vertical plate 111 and a second vertical plate 112, and a connecting plate 113, one end surface of the connecting plate 113 is connected to the lower end surface of the first vertical plate 111, and the other end surface of the connecting plate 113 is connected to the upper end surface of the second vertical plate 112;
[0033] Two adjacent water seal chambers are connected via a water seal pipe 12, and the water seal pipe 12 is vertically arranged through the connecting plate 113;
[0034] A liquid inlet 101 is provided at the top of the water seal chamber at one end of the water seal box 1, and the liquid inlet 101 is connected to the gas pipeline 10 through a valve 100; an overflow drain pipe 102 is connected to the upper part of one side surface of the water seal box 1 away from the liquid inlet 101;
[0035] A sewage outlet 103 is provided at the lower side of the water seal box 1 where each water seal chamber is located.
[0036] The upper surface of the water seal box 1 is connected with a plurality of dredging pipes 104; the plurality of dredging pipes 104 correspond to the plurality of water seal pipes 12 one by one;
[0037] The clearing pipe 104 is sealed by the clearing pipe valve 200 .
[0038] In the present application, the interior of the water seal box 1 is divided into multiple water seal chambers by a partition 11 provided with a water seal tube 12, that is, the divided water seal chambers are connected in series into multi-stage water seal chambers through adjacent water seal tubes 12, which can effectively prevent the risk of gas leakage caused by the sudden increase in gas pressure in the gas pipeline 10 and the breakdown of the water seal.
[0039] In the present application, the interior of the water seal box 1 is divided by a partition 11. At this time, for the connecting plate 113, its upper surface is in the water seal chamber of the upper level (that is, the water seal chamber into which the water of the gas pipeline first flows, that is, the water seal chamber near the liquid inlet 101), and the lower surface of the connecting plate 113 is in the water seal chamber of the lower level. Therefore, when setting, after the water seal pipe 12 passes through the connecting plate 113, the upper end should be above the upper surface of the connecting plate 113, that is, in the water seal chamber of the upper level, and the lower end of the water seal pipe 12 should be in the water seal chamber of the lower level.
[0040] In actual use, the volume of the first-stage water seal chamber, that is, the water seal chamber where the liquid inlet 101 is located, should be larger than that of the subsequent multi-stage water seal chambers. Generally, the volume of the first-stage water seal chamber is 1.5 to 2.0 times the volume of the subsequent single water seal chamber to ensure that the first-stage water seal chamber has sufficient space to precipitate the silt, tar and other substances contained in the water discharged from the gas pipeline 10.
[0041] The plurality of dredging pipes 104 correspond to the plurality of water seal pipes 12 one by one, that is, the surface of the water seal box 1 directly above each water seal pipe 12 is the dredging pipe 104 that is opened. When the water seal pipe 12 is blocked, the dredging pipe valve 200 is opened, and the dredging tool is extended from the dredging pipe 104 into the water seal pipe 12 to clean the water seal pipe 12 without disassembling the water seal pipe 12. It should be noted that the dredging pipe valve 200 used in the present application is a gate valve or a ball valve, because the interior of these two valves is straight and has no bending part, so that the dredging tool can be extended into the water seal pipe 12 for cleaning after the dredging pipe valve 200 is opened. In a feasible manner, the dredging pipe valve 200 can be replaced with a sealing cover that matches the dredging pipe 104 to achieve the sealing effect of the above-mentioned dredging pipe valve 200 and the effect of allowing the dredging tool to enter after opening.
[0042] When in use, a certain height of water should be injected into each water seal chamber (the water level should be above the lower end of the water seal pipe 12 to act as a water seal and prevent gas leakage), and then the valve 100 is opened, and the condensed water in the gas pipeline 10 flows into the water seal chamber where the liquid inlet 101 is located through the valve 100. When the water level in the water seal chamber where the liquid inlet 101 is located is higher than the upper end of the water seal pipe 12, excess water will flow into the next-level water seal chamber through the water seal pipe 12 until the water level is flush with the height of the upper end of the water seal pipe 12, and so on. The working process of subsequent water seal chambers is the same until the last-level water seal chamber (i.e., the water seal chamber connected to the overflow drain pipe 102). When the water level in the last-level water seal chamber is higher than the height of the overflow drain pipe 102, excess water will be discharged through the overflow drain pipe 102 for centralized treatment.
[0043] Since coal gas is produced in the process of metal smelting, it contains a large amount of dust, tar and other substances. These substances will enter the condensed water of the gas pipeline together with the condensation of water vapor. Therefore, after the water seal box 1 has been working for a period of time, sludge will be deposited at the bottom of each water seal chamber. The sludge mainly contains tar, dust and other substances. At this time, the sewage outlet 103 at the bottom of the water seal chamber should be opened to discharge the sludge. The discharged sludge is dehydrated by means of filter pressing and other means, and then sent to the solid waste treatment section for treatment.
[0044] During use, the inner wall of the water seal pipe 12 will also adhere to and deposit these tar-like sludges, resulting in a smaller effective diameter of the water seal pipe 12, affecting the water seal effect. At this time, the dredging pipe valve 200 (the dredging pipe valve 200 in this application is a gate valve or a ball valve) can be opened, and dredging tools (such as dredging iron bars, dredging brushes, etc.) can be extended from the dredging pipe 104 into the water seal pipe 12 to clean the water seal pipe 12 without disassembling the water seal pipe 12. The dredged sludge falls into the bottom of the water seal chamber and is discharged from the sewage outlet 103.
[0045] The present application provides a gas pipeline drainage device, which is divided into multiple water seal chambers by a "Z"-shaped partition 11 formed by connecting a first vertical plate 111, a second vertical plate 112 and a connecting plate 113 through a water seal box 1, and adjacent water seal chambers are connected through a vertically arranged water seal pipe 12, and at the same time, a dredging pipe 104 sealed by a dredging pipe valve 200 is opened on the top of the water seal box 1 corresponding to the water seal pipe 12, and when the water seal pipe 12 is blocked, the dredging pipe valve 200 can be opened and the water seal pipe 12 can be dredged by a dredging tool without disassembling the water seal box 1. The device of the present application can discharge condensed water in the gas pipeline and conveniently clean the water seal pipe 12 through the coordinated use of the above-mentioned structure, thereby overcoming the disadvantages of the existing gas pipeline drainage device that the water seal pipe in the water seal box needs to be disassembled for dredging after being blocked, which affects the production efficiency and the dredging process is time-consuming and labor-intensive. In addition, in the device of the present application, the water seal box 1 is divided into a plurality of water seal chambers connected in series by the partition 11, which can also play a good role in preventing breakdown when the gas pressure in the gas pipeline is too high.
[0046] like Figure 3 As shown, optionally, the overflow drain pipe 102 is connected to the drainage device 13.
[0047] In the present application, the overflow drain pipe 102 is connected to the drainage device 13, and the drainage device 13 can drain the water discharged from the overflow drain pipe 102 to the processing section for processing.
[0048] like Figure 4 As shown, optionally, the drainage device 13 includes a liquid receiving funnel 131 connected in series and a sewage pool 132 connected to the liquid receiving funnel 131 through a pipeline.
[0049] In the present application, a liquid receiving funnel 131 is used to receive the water discharged from the overflow drain pipe 102, which can play a good role in gathering. In the present application, the sewage pool 132 can be divided into a sedimentation area and a flocculation area by a partition plate. The water entering the sewage pool 132 first enters the sedimentation area for sedimentation, and the dirt in the water is first precipitated. The supernatant after precipitation can overflow to the flocculation area. The solid matter that has not been precipitated in the supernatant is sunk to the bottom by adding flocculants, so that the cleanliness of the water discharged from the sewage pool 132 is improved. The water treated by the sewage pool 132 can be used for cleaning in the factory or other sections with low water quality requirements; or the water treated by the sewage pool can be deeply purified and supplied to sections with high water quality requirements to reduce waste.
[0050] Optionally, the connecting plate 113 is inclined in a direction from a connection with the first vertical plate 111 to a connection with the second vertical plate 112 , and the inclined direction forms an elevation angle greater than or equal to 0° and less than 90° with respect to the horizontal direction.
[0051] In the present application, the connecting plate 113 is inclined toward the water seal chamber in the direction of water input. This method can reduce the deposition of sludge carried in the water on the connecting plate 113, making it easier to keep the connecting plate 113 clean. In actual use, the inclination angle of the connecting plate 113 is preferably between 15 and 60 degrees.
[0052] like Figure 5 and Figure 6 As shown, optionally, a heat pipe 14 is provided in the lower part of at least one water seal chamber, and the heat pipe 14 extends inward through the side wall of the water seal box 1. One end of the heat pipe 14 extending into the water seal box 1 is sealed, and the other end is open for installing an electric heating pipe 15.
[0053] In the present application, the heat pipe 14 is used to conduct the heat generated by the electric heating pipe 15 and protect the electric heating pipe 15. When set, the heat pipe 14 can be integrally formed with the water seal box 1 or connected to the water seal box 1 by welding.
[0054] like Figure 6 As shown, optionally, the heat pipe 14 includes a tube shell 141; a heat conductive layer 142 is coaxially arranged in the tube shell 141, and the heat conductive layer 142 is arranged close to the inner wall of the tube shell 141. An accommodating cavity is arranged at the axial position of the heat conductive layer 142 for installing the electric heating tube 15.
[0055] In the present application, the heat conducting layer 142 is used to conduct the heat generated by the electric heating tube 15, so that the heat generated by the electric heating tube 15 can be evenly distributed on the heat conducting tube, thereby heating the water in the water seal chamber.
[0056] The heat conducting layer 142 can be made into a sleeve inside the tube shell 141 and can be detachably connected to the tube shell 141, so that when the heat conducting layer 142 is damaged or the conduction efficiency is low, the heat conducting layer 142 can be removed in time for replacement or repair. Accordingly, since the electric heating pipe 15 is used when the temperature is low and the electric heating pipe 15 can be left uninstalled when the temperature is normal, a sealing cover or a sealing plug should be provided at the open end of the heat conducting pipe 14 to prevent dust, water, etc. from entering the heat conducting pipe 14 when the heat conducting pipe 14 is idle and causing adverse effects on the heat conducting pipe 14.
[0057] Optionally, the heat conducting layer 142 is made of one of graphite, silicon carbide or silicon nitride.
[0058] In the present application, materials such as graphite, silicon carbide or silicon nitride are excellent heat-conducting materials, which can provide a better heat-conducting effect as the heat-conducting layer 142. In the present application, the thickness of the heat-conducting layer 142 can be 3 to 10 mm.
[0059] A gas pipeline drainage device, the working process of which is as follows:
[0060] When in use, a certain height of water should be injected into each water seal chamber (the water level should be above the lower end of the water seal pipe 12 to act as a water seal and prevent gas leakage), and then the valve 100 is opened, and the condensed water in the gas pipeline 10 flows into the water seal chamber where the liquid inlet 101 is located through the valve 100. When the water level in the water seal chamber where the liquid inlet 101 is located is higher than the upper end of the water seal pipe 12, the water will flow into the next-level water seal chamber through the water seal pipe 12 until the water level is flush with the height of the upper end of the water seal pipe 12, and so on. The working process of the subsequent water seal chambers is the same until the last-level water seal chamber (i.e., the water seal chamber connected to the overflow drain pipe 102). When the water level in the last-level water seal chamber is higher than the height of the overflow drain pipe 102, the excess water will enter the sewage pool 132 through the liquid receiving funnel 131. The water entering the sewage pool 132 is used for daily cleaning of the factory or enters the subsequent treatment equipment for deep purification after natural sedimentation and flocculation precipitation, and is used in the section with high water quality requirements.
[0061] Since coal gas is produced in the process of metal smelting, it contains a large amount of dust, tar and other substances. These substances will enter the condensed water of the gas pipeline together with the condensation of water vapor. Therefore, after the water seal box 1 has been working for a period of time, sludge will be deposited at the bottom of each water seal chamber. The sludge mainly contains tar, dust and other substances. At this time, the sewage outlet 103 at the bottom of the water seal chamber should be opened to discharge the sludge. The discharged sludge is dehydrated by means of filter pressing and other means, and then sent to the solid waste treatment section for treatment.
[0062] During use, the inner wall of the water seal pipe 12 will also adhere to and deposit these tar-like sludges, resulting in a smaller effective diameter of the water seal pipe 12, affecting the water seal effect. At this time, the dredging pipe valve 200 (the dredging pipe valve 200 in this application is a gate valve or a ball valve) can be opened, and dredging tools (such as dredging iron bars, dredging brushes, etc.) can be extended from the dredging pipe 104 into the water seal pipe 12 to clean the water seal pipe 12 without disassembling the water seal pipe 12. The dredged sludge falls into the bottom of the water seal chamber and is discharged from the sewage outlet 103.
[0063] In cold seasons or when the temperature is low, the heating pipe 15 can be turned on to heat the water in the water seal chamber through the heat pipe 14 to prevent the water in the water seal box 1 from freezing due to too low a temperature, thereby affecting the use effect of the water seal box 1.
[0064] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit it. Although the present application has been described in detail with reference to the aforementioned embodiments, ordinary technicians in the field should understand that they can still modify the technical solutions recorded in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present application.
Claims
1. A gas pipeline drainage device, characterized in that: It comprises an integrally sealed water seal box (1); The water seal box (1) is divided into a plurality of water seal chambers by a plurality of parallel partitions (11); The partition (11) comprises a first vertical plate (111) and a second vertical plate (112) which are vertically arranged, and a connecting plate (113), wherein one end surface of the connecting plate (113) is connected to the lower end surface of the first vertical plate (111), and the other end surface of the connecting plate (113) is connected to the upper end surface of the second vertical plate (112); Two adjacent water seal chambers are connected via a water seal pipe (12), and the water seal pipe (12) passes through the connecting plate (113) and is vertically arranged; A liquid inlet (101) is provided at the top of the water seal chamber at one end of the water seal box (1), and the liquid inlet (101) is connected to the gas pipeline (10) via a valve (100); an overflow drain pipe (102) is connected to the upper part of a side surface of the water seal box (1) away from the liquid inlet (101); A sewage outlet (103) is provided at the lower side of the water seal box (1) where each water seal chamber is located; The upper surface of the water seal box (1) is connected to a plurality of dredging pipes (104); the plurality of dredging pipes (104) correspond one to one to the plurality of water seal pipes (12); The dredging pipe (104) is sealed by a dredging pipe valve (200).
2. The gas pipeline drainage device according to claim 1, characterized in that: The overflow drain pipe (102) is connected to the drainage device (13).
3. The gas pipeline drainage device according to claim 2, characterized in that: The drainage device (13) comprises a liquid receiving funnel (131) connected in series and a sewage pool (132) connected to the liquid receiving funnel (131) via a pipeline.
4. The gas pipeline drainage device according to claim 1, characterized in that: The connecting plate (113) is inclined in a direction from a connection point with the first vertical plate (111) to a connection point with the second vertical plate (112), and the inclination direction forms an elevation angle greater than or equal to 0° and less than 90° with respect to the horizontal direction.
5. The gas pipeline drainage device according to any one of claims 1 to 4, characterized in that: A heat conducting pipe (14) is arranged in the lower part of at least one of the water seal chambers. The heat conducting pipe (14) passes through the side wall of the water seal box (1) and extends inward. One end of the heat conducting pipe (14) extending into the water seal box (1) is sealed, and the other end is open for installing an electric heating pipe (15).
6. The gas pipeline drainage device according to claim 5, characterized in that: The heat-conducting tube (14) comprises a tube shell (141); a heat-conducting layer (142) is coaxially arranged inside the tube shell (141); the heat-conducting layer (142) is arranged closely to the inner wall of the tube shell (141); and an accommodating cavity is arranged at the axial center position of the heat-conducting layer (142) for installing the electric heating tube (15).
7. The gas pipeline drainage device according to claim 6, characterized in that: The material of the heat conducting layer (142) is one of graphite, silicon carbide or silicon nitride.