Turnout device for improving shield construction efficiency in narrow space

By setting up a switch device in the tunnel, using switches and rail guards to achieve the wrong and synchronous operation of battery vehicles, the problem of low shield construction efficiency in small spaces is solved, and construction efficiency and safety are improved.

CN221956444UActive Publication Date: 2024-11-05CHINA HYDROPOWER ELEVENTH ENG BUREAU (ZHENGZHOU) CO LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202323503256.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-21
Publication Date
2024-11-05
Estimated Expiration
2033-12-21

Smart Images

  • Figure CN221956444U_ABST
    Figure CN221956444U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of tunnel construction, in particular to a turnout device for improving shield construction efficiency in a narrow space, which comprises a tunnel divided into a working wellhead, a variable slope section and a normal section, and is characterized in that sleepers are laid on the surface of the inner bottom wall of the tunnel at intervals along the length direction of the tunnel; a single rail is laid on a sleeper on a variable slope section and a normal section in a tunnel, a double rail is arranged at a working wellhead, and a turnout is arranged between the single rail and the double rail; the turnout is additionally arranged in the tunnel, so that the two rows of battery cars are grouped in a narrow tunnel to be staggered and synchronously run, waiting for work when the battery cars return is not needed, the shield construction efficiency is greatly improved, and the construction period is shortened; one group of side slope sleepers of the tunnel are arranged every 1m, and the height difference between the sleepers of the variable slope section is increased by 1cm every 1m, so that the gradient of the variable slope section is slow, the phenomenon that the storage battery car falls off the road due to overlarge gradient difference is avoided, and the form safety of the storage battery car is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tunnel construction, in particular to a turnout device used for improving shield construction efficiency in a narrow space. Background Art

[0002] The shield method has the advantages of high automation, little damage to the surrounding environment, high safety, and high construction quality in tunnel construction. Especially in cases where the ground conditions are relatively poor and the surrounding environment is relatively complex, the superiority of this method is more obvious. Therefore, it has established a dominant position in the construction of urban power corridors. In recent years, shield technology has been well applied and developed. However, the size of the working shaft of the power corridor is generally small. The normal earth pressure shield machine battery car marshaling configuration is 1 traction head, 4 slag buckets, and 1 8m 3 The mortar tank and two segment trolleys have a total length of about 45m. The wellhead can only accommodate one battery car group. Each excavation interval is 2 to 3 hours. The distance between the intervals is long, and the battery car takes a longer time to go back and forth and prepare, which seriously affects the efficiency of shield construction. The tunnel excavation diameter is mostly 6.0m, and the net size of the formed tunnel is 5.4m. The conventional layout can meet the operation of the battery car. Tunnel construction has high requirements for battery cars and running tracks. All the turnover materials, consumable materials, mortar, segments and slag required for tunnel construction need to be transported by battery cars. The quality of track laying in the tunnel directly affects the transportation and construction process of the battery car.

[0003] To this end, the utility model provides a turnout device for improving shield construction efficiency in a narrow space, thereby improving the shield construction efficiency. Utility Model Content

[0004] The utility model aims to solve the problems existing in the prior art and proposes a turnout device for improving shield construction efficiency in a narrow space.

[0005] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0006] A turnout device for improving shield construction efficiency in a narrow space, comprising a tunnel, the tunnel being divided into a working wellhead, a slope-changing section, and a normal section, sleepers being laid at intervals on the inner bottom wall surface of the tunnel along the length direction of the tunnel, a single track being laid on the sleepers in the slope-changing section and the normal section in the tunnel, a double track being laid at the working wellhead, and a turnout being provided between the single track and the double track;

[0007] The turnout includes a switch and a guard rail;

[0008] The switch comprises a base rail, a point rail and a switch mechanism.

[0009] Preferably, the sleeper includes a cross beam, the single track and the double track are both arranged at the upper end of the cross beam, two vertical beams are symmetrically welded at the bottom end of the cross beam, and both ends of the cross beam and the bottom ends of the two vertical beams are consistent with the curvature of the inner wall of the tunnel.

[0010] Preferably, the sleepers are arranged one per meter.

[0011] Preferably, the vertical beam is 100 channel steel and the horizontal beam is 150H steel.

[0012] Preferably, the slope of the sleepers in the slope-changing section increases by 1 cm for every 1 m of height difference.

[0013] Preferably, the length of the beam in the working shaft opening area of ​​the tunnel is greater than 3.3 meters.

[0014] Preferably, a walkway plate is laid on the sleeper at the side of the track, and a railing is provided on the side of the walkway plate.

[0015] Compared with the prior art, the utility model provides a turnout device for improving shield construction efficiency in a narrow space, which has the following beneficial effects:

[0016] 1. By adding switches in the tunnel, two trains of electric vehicles can pass each other and operate synchronously in a narrow tunnel. There is no need for the electric vehicles to wait for work when returning to their positions, which greatly improves the efficiency of shield construction and saves construction time.

[0017] 2. The tunnel's side slope sleepers are arranged in groups every 1 meter, and the height difference between the sleepers in the slope change section increases by 1 cm for every 1 meter, so that the slope of the slope change section is gentler, avoiding the phenomenon of battery vehicles falling off the track due to excessive slope difference, and improving the safety of battery vehicles.

[0018] Other advantages, objectives and features of the present invention will be described in the following description to some extent; and will be apparent to those skilled in the art based on the following examination and study to some extent; or, may be taught from the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 This is a cross-sectional layout diagram of a shield tunnel construction according to the present utility model.

[0020] Figure 2 It is an overall schematic diagram of the installation of the turnout device of the utility model.

[0021] Figure 3 It is a schematic diagram of the turnout structure and double-track access of the utility model.

[0022] Figure 4 This is the structural diagram of slope-changing section sleepers No. 1-18 of the utility model.

[0023] Figure 5This is the structural diagram of the slope-changing section sleeper No. 19-48 of the utility model.

[0024] Figure 6 This is the structural diagram of the slope-changing section sleeper No. 49-60 of the utility model.

[0025] Figure 7 This is a structural diagram of sleeper No. 61 at the turnout of the utility model.

[0026] Figure 8 This is a schematic diagram of the plan layout of the shield machine and the battery vehicle starting at the working wellhead of the utility model.

[0027] In the figure: 1. Tunnel; 2. Sleeper; 3. Monorail; 4. Double track; 5. Switch; 6. Guard rail; 7. Walkway plate; 8. Railing; 9. Ventilation duct; 10. Light stand; 11. High-voltage cable; 12. Cooling circulation pipe and sewage pipe; 201. Crossbeam; 202. Vertical beam; 501. Basic rail; 502. Point rail; 503. Switch machinery. DETAILED DESCRIPTION

[0028] The following will be combined with the attached embodiment of the utility model Figure 1-8 , the technical solutions in the embodiments of the utility model are described clearly and completely. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all the embodiments.

[0029] Embodiment 1, in order to solve the problems existing in the prior art, this embodiment provides a turnout device for improving shield construction efficiency in a narrow space, comprising a tunnel 1, the tunnel 1 is divided into a working wellhead (40 meters), a slope-changing section (50 meters), and a normal section, sleepers 2 are laid at intervals on the inner bottom wall surface of the tunnel 1 along the length direction of the tunnel 1, and tracks are laid on the sleepers 2, and single tracks 3 are laid on the sleepers 2 in the slope-changing section and the normal section in the tunnel 1, and double tracks 4 are laid at the working wellhead, and a turnout (17 meters) is provided between the single track 3 and the double track 4;

[0030] The turnout includes a switch 5 and a guard rail 6;

[0031] The switch 5 includes a stock rail 501 , a point rail 502 and a switch mechanism 503 .

[0032] The switch mechanism 503 mainly includes a reciprocating mechanism assembly and a pull rod. The reciprocating mechanism assembly is a prior art, and is a common reciprocating moving device with a self-locking function, such as an electric telescopic rod, a hydraulic rod, etc. The pull rod penetrates the side wall of the monorail 3, and the two tips of the point rail 502 are fixedly connected to the pull rod.

[0033] The two tips of the point rail 502 are gradually inserted into the two rails of the monorail 3, and the width between the two tips of the point rail 502 is smaller than the distance between the two rails of the monorail 3;

[0034] The two ends of the pointed rail 502 facing away from the two tips are respectively connected to the ends of the basic rail 501 on the corresponding sides;

[0035] The two basic rails 501 are close to each other on the side facing away from the monorail 3;

[0036] The double track 4 is composed of two parallel single tracks 3. The ends of two adjacent rails in the double track 4 are connected and pointed. The pointed end is inserted into the middle of the two ends of the two basic rails 501 that are close to each other. The two opposite rails in the double track 4 are respectively connected to the rails of the single track 3 on the corresponding side.

[0037] The guardrail 6 is located on the opposite side of the double track 4, and the tips of the two adjacent rails of the double track 4 and the two rail ends of the base track 501 are all located within the guardrail 6, which is used to protect the wheels from safely passing through the intersection of the two rails and avoiding derailment.

[0038] The specific use process of this embodiment is as follows:

[0039] In the initial state, the two battery cars are located on the A and B tracks of the double track 4 respectively. When the battery cars are to be transferred from the single track 3 to any idle track of the double track 4, the switch mechanism 503 is operated to move the point rail 502. Figure 3 As shown, when the battery car needs to transfer to the upper track line of the double track 4, the reciprocating mechanism assembly drives the pull rod to move downward, so that the lower tip of the pointed rail 502 is attached to the inner wall of the lower track of the monorail 3, and the upper tip is separated from the upper track of the monorail 3. In this way, the track line above the double track 4 of the double track 4 is opened, and the track line below the double track 4 is closed. The battery car transitions to the guardrail 6 unit along the track line, and then enters the required track line. In this way, two trains of battery cars can be marshaled to pass each other and operate synchronously in the narrow tunnel 1. There is no need for the battery cars to wait for work when returning to their positions. When one battery car is running, the other battery car can load and unload materials. The two cars are operated synchronously, which greatly improves the efficiency of shield construction and saves construction time.

[0040] At the same time, the installation position of the circulating water pipe of this section was changed, and the changed part was connected to the original pipeline with a 90° pipe clamp. After the turnout and track are fully installed, they can resume operation only after being accepted by quality inspection personnel.

[0041] Embodiment 2: In this embodiment, a specific sleeper 2 mechanism is provided:

[0042] The sleeper 2 includes a cross beam 201, and two vertical beams 202 are symmetrically welded at the bottom end of the cross beam 201. Both ends of the cross beam 201 and the bottom ends of the two vertical beams 202 are consistent with the curvature of the inner wall of the tunnel 1. The single track 3 and the double track 4 are all arranged on the upper end of the cross beam 201. The tracks are erected in the tunnel 1 through the vertical beams 202 and the cross beams 201.

[0043] Preferably, the vertical beam 202 is 100 channel steel, the horizontal beam 201 is 150H steel, and the sleepers 2 are arranged in a group every 1 meter, so that the distribution strength of the sleepers 2 can meet the full load bearing requirements of the battery vehicle.

[0044] Preferably, the length of the crossbeam 201 in the working shaft opening area of ​​the tunnel 1 is greater than 3.3 meters, and the track is raised by 60 centimeters as a whole, so that the double-row battery car formation (1.5 meters wide) can pass each other normally at the switch.

[0045] Installation Instructions for Sleeper 2:

[0046] (1) The turnout position uses a No. 61 sleeper 2 with a length of 3628 mm. The distance between the bottom of the track and the bottom of the segment is 60 cm. The 50 between the slope change section and the normal section is laid with a No. 60-1 sleeper 2. The specific dimensions of the No. 60-1 sleeper 2 refer to the attached Figure 4 , Attachment Figure 5 , Attachment Figure 6 As shown, the bearing capacity of the sleeper 2 is adapted to the size of the slope changing section of the tunnel 1;

[0047] (2) The welding between the cross beam 201 and the vertical beam 202 of the sleeper 2 requires full welding of the weld seam, and the welding quality requires no bubbles and no debris;

[0048] (3) After welding, serial numbers are added to the surface to distinguish the installation;

[0049] (4) When placing the sleeper 2, avoid the location of the circumferential bolt connection holes of the pipe segment.

[0050] Embodiment 3, in order to ensure the safety of the battery vehicle when driving up and downhill, the slope of the sleeper 2 in the slope changing section should not be too large. Therefore, the height difference between the sleepers 2 in the slope changing section increases by 1cm for every 1m of height difference, so that the slope of the slope changing section is gentler, avoiding the phenomenon of the battery vehicle falling off the road due to excessive slope difference, and improving the safety of the battery vehicle.

[0051] In Embodiment 4, a walkway plate 7 is laid on the sleeper 2 at the side of the track for maintenance inspection and walking passage, and a railing 8 is provided on the side of the walkway plate 7 to prevent falling into the track area.

[0052] Before installation and construction, determine the number of turnouts and slope-changing sleepers 2 required for the interval tunnel 1, prepare the required raw materials in advance, and select high-tech welders for welding. In order to avoid large processing errors, each component needs to be processed first according to the actual size of the tunnel 1 for installation and verification, and batch processing begins after meeting the requirements. The shield machine starts to stop after 100m of excavation, and the 67m track and sleeper 2 at the wellhead are dismantled. Turnouts are arranged in the tunnel. The width of the battery car is 1.5m. In order to ensure that the double-row marshaling can pass normally in the tunnel, the width is not less than 3.3m. The track needs to be raised by 60cm as a whole. The 67m track platform into the tunnel is made of H150 steel. The curvature of the steel on both sides is consistent with the curvature of the existing tunnel 1 with a diameter of 5.4m. The bottom of the steel is supported by 100 channel steel. At the same time, the installation position of the circulating water pipe of this section is changed, and the changed part is connected to the original pipeline with a 90° pipe clamp. After the turnouts and tracks are fully installed, they must be inspected and accepted by the quality inspection personnel before they can resume operation.

[0053] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.

[0054] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0055] Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations of the present invention. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present invention.

Claims

1. A turnout device for improving shield construction efficiency in a narrow space, comprising a tunnel (1), wherein the tunnel (1) is divided into a working wellhead, a slope-changing section, and a normal section, and is characterized in that: The inner bottom wall surface of the tunnel (1) is provided with sleepers (2) at intervals along the length direction of the tunnel (1); a single track (3) is laid on the sleepers (2) in the slope change section and the normal section of the tunnel (1); a double track (4) is provided at the working well mouth; and a switch is provided between the single track (3) and the double track (4); The turnout comprises a switch (5) and a guard rail (6); The switch (5) comprises a base rail (501), a point rail (502) and a switch mechanism (503).

2. A turnout device for improving shield construction efficiency in a narrow space according to claim 1, characterized in that: The sleeper (2) comprises a crossbeam (201), a single rail (3) and a double rail (4) are both arranged at the upper end of the crossbeam (201), two vertical beams (202) are symmetrically welded to the bottom end of the crossbeam (201), and both ends of the crossbeam (201) and the bottom ends of the two vertical beams (202) are consistent with the curvature of the inner wall of the tunnel (1).

3. A turnout device for improving shield construction efficiency in a narrow space according to claim 2, characterized in that: The sleepers (2) are arranged one per meter.

4. A turnout device for improving shield construction efficiency in a narrow space according to claim 2, characterized in that: The vertical beam (202) is a 100 channel steel, and the horizontal beam (201) is a 150H-shaped steel.

5. A turnout device for improving shield construction efficiency in a narrow space according to claim 3, characterized in that: The slope of the sleeper (2) in the slope changing section increases by 1 cm for every 1 m height difference.

6. A turnout device for improving shield construction efficiency in a narrow space according to claim 3, characterized in that: The length of the crossbeam (201) in the working wellhead area of ​​the tunnel (1) is greater than 3.3 meters.

7. A turnout device for improving shield construction efficiency in a narrow space according to claim 4, characterized in that: A walkway plate (7) is laid on the sleeper (2) at the side of the track, and a handrail (8) is provided on the side of the walkway plate (7).