Pavement structure for repairing old airport runway
By designing the pavement structure of triangular diversion layer and polyethylene waterproof membrane on the old airport runway, the problem of permeable asphalt lamination is solved, rainwater guidance and road stability are improved, and service life is extended.
Patent Information
- Application Number
- CN202420471078.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-12
- Publication Date
- 2024-11-05
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The permeable asphalt layer of the old airport runway is prone to accumulation of water in rainy weather, resulting in water on the road area and affecting normal use.
A repair pavement structure was designed, including permeable asphalt layer, diversion layer and waterproof layer. The cross-section of the diversion layer is triangular, and a second geotextile is laid on the diversion layer. The waterproof layer is made of polyethylene waterproof film and diversion layer. The inclined surface guides rainwater to the gravel base layer to reduce water accumulation, and adds calcium lignin sulfonate as a crack strength water reducing agent to the concrete.
It effectively avoids water on the road area, reduces rainwater solidification and expansion and cracking and deformation of permeable asphalt layer, and improves the stability and life of the road surface in extreme weather.
Smart Images

Figure CN221956455U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pavement structures, and in particular to a pavement structure for repairing an old airport runway. Background Art
[0002] Most of the first batch of airport pavements built in the early days of the founding of the People's Republic of my country were designed with hexagonal (also called hexagonal) plates. Inspired by the honeycomb structure, technicians found that hexagonal plates are a block form with the best force performance under the premise of meeting the requirements of splicing plates to form a large-area pavement. Therefore, they are widely used in early airport construction. The advantages of the "hexagonal plate" design are prominent, and the disadvantages are also obvious. On the one hand, it is not convenient for mechanized operation and the construction efficiency is low; on the other hand, the plates are small and have many seams. After use, the plates settle unevenly, the edges and corners fall off seriously, and the flatness is poor, which affects the airport's support capabilities and levels. In order to improve the construction efficiency of the airport runway, concrete will be used to cover the runway foundation. After the concrete solidifies, asphalt will be laid on the concrete. Because the area has a lot of rainy seasons, in order to reduce the accumulation of water on the runway, the asphalt will use permeable asphalt, which can be put into use after the permeable asphalt solidifies.
[0003] When this pavement structure is in use, if it rains, rainwater will penetrate into the permeable asphalt layer, and then stay on the concrete layer below the permeable asphalt layer and stop penetrating. When there is too much rain, the rainwater will flow to the gravel base on both sides of the runway. After the rain stops, a small amount of rainwater will still accumulate inside the permeable asphalt layer, which may cause waterlogging on the road surface and affect the normal use of the road surface. Utility Model Content
[0004] The utility model provides a pavement structure for repairing an old airport runway, solving the problem in the related art that rainwater remains inside the asphalt layer, causing water accumulation on the road surface and affecting normal use of the road surface.
[0005] The technical solution of the utility model is as follows: a pavement structure for repairing an old airport runway, comprising a runway foundation and a permeable asphalt layer, shoulder layers are arranged on both sides of the runway foundation, a crushed stone base layer is arranged on the shoulder layer, a first geotextile is arranged on the runway foundation, a repair layer is arranged on the first geotextile, a guide layer is arranged on the repair layer, the cross-section of the guide layer is a triangular structure, a second geotextile is laid on the guide layer, a waterproof layer is arranged on the second geotextile, and the permeable asphalt layer is located on the waterproof layer.
[0006] Furthermore, the runway foundation includes a flagstone cushion layer, a lime soil base layer, and a runway layer. The lime soil base layer is laid on top of the flagstone cushion layer, and the runway layer is laid above the lime soil base layer.
[0007] Furthermore, the shoulder layer includes a shoulder base layer and a runway shoulder. The shoulder base layer is located on one side of the ash soil base layer, and the runway shoulder is laid above the shoulder base layer.
[0008] Furthermore, the guide layer is provided with reinforcing ribs inside for enhancing the strength of the repair layer.
[0009] Furthermore, a water reducing agent is provided inside the repair layer for improving the early crack resistance of concrete.
[0010] Furthermore, the waterproof layer adopts a polyethylene waterproof membrane.
[0011] The working principle and beneficial effects of the utility model are as follows: if it rains, rainwater will penetrate into the permeable asphalt layer, and then penetrate downward. When rainwater penetrates into the waterproof layer below the permeable asphalt layer, the second geotextile below the waterproof layer is fixed to the guide layer, and the waterproof layer is fixed to the second geotextile. The inclined surface of the guide layer guides the rainwater on the surface of the waterproof layer and guides the rainwater into the gravel base layer, thus avoiding water accumulation on the road surface as much as possible, reducing the possibility of rainwater remaining in the permeable asphalt layer, reducing the extent of cracking and deformation of the permeable asphalt layer caused by solidification and expansion of rainwater in extreme weather, ensuring the normal use of the road surface, and improving the service life of the road surface. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] The utility model is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0013] Figure 1 It is a schematic diagram of the structure of the utility model;
[0014] Figure 2 for Figure 1 Enlarged view of point A in the figure.
[0015] In the figure: 1. Repair layer; 2. Gravel base layer; 3. Runway shoulder; 4. Shoulder layer; 5. Shoulder base layer; 6. Stone cushion layer; 7. Lime soil base layer; 8. Runway foundation; 9. Runway layer; 10. First geotextile; 11. Diversion layer; 12. Permeable asphalt layer; 13. Second geotextile; 14. Waterproof layer; 15. Reinforcement ribs. DETAILED DESCRIPTION
[0016] The following will be combined with the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0017] like Figure 1-2As shown, this embodiment proposes a pavement structure for repairing an old airport runway, including a runway foundation 8 and a permeable asphalt layer 12. The runway foundation 8 specifically includes a flagstone cushion layer 6, a lime soil base layer 7, and a runway layer 9. The lime soil base layer 7 is laid on top of the flagstone cushion layer 6, and the runway layer 9 is laid above the lime soil base layer 7.
[0018] Shoulder layers 4 are provided on both sides of the runway foundation 8, a crushed stone base layer 2 is provided on the shoulder layer 4, a first geotextile 10 is provided on the runway foundation 8, a repair layer 1 is provided on the first geotextile 10, a guide layer 11 is provided on the repair layer 1, and the guide layer 11 is composed of cement concrete, which has high strength and compressive strength, can withstand the heavy load on the airport runway and the impact of the round-trip aircraft, and ensure the stability and durability of the road surface. The cross-section of the guide layer 11 is a triangular structure, and the guide layer 11 with a triangular cross-section can effectively guide rainwater or sewage to flow along the slope direction, reduce the possibility of water accumulation and water infiltration, and improve the drainage performance of the road surface. A second geotextile 13 is laid on the guide layer 11, a waterproof layer 14 is provided on the second geotextile 13, a permeable asphalt layer 12 is located on the waterproof layer 14, and the waterproof layer 14 adopts a polyethylene waterproof membrane, which can effectively isolate the penetration of water and prevent water from entering the pavement structure, thereby reducing the damage to the pavement and reducing the maintenance cost. The polyethylene waterproof membrane can be supplied in the form of a roll, and the roll can be fixed to the pavement structure by hot melting or cold gluing during construction. The construction is simple and quick. The guide layer 11 is provided with reinforcing ribs 15 for strengthening the strength of the repair layer 1. The reinforcing ribs 15 can effectively increase the tensile strength of the guide layer 11, so that the guide layer 11 can withstand greater tension, thereby improving the stability and bearing capacity of the overall structure.
[0019] A shoulder layer 4 is provided on both sides of the runway foundation 8. The shoulder layer 4 includes a shoulder base layer 5 and a runway shoulder 3. The shoulder base layer 5 is located on one side of the ash soil base layer 7. The runway shoulder 3 is laid on the shoulder base layer 5. A crushed stone base layer 2 is set on the runway shoulder 3. A first geotextile 10 is laid on the runway foundation 8. A repair layer 1 is provided on the first geotextile 10. A water reducer for improving the early crack resistance of concrete is provided inside the repair layer 1. The water reducer is preferably calcium lignin sulfonate. The water reducer can promote the dispersion of cement particles in concrete, thereby reducing the friction between cement particles and making the concrete easier to flow and fill. The calcium lignin sulfonate molecules in the water reducer have the characteristics of a surfactant, which can reduce the cohesion between concrete particles and improve the fluidity and pumpability of concrete. In this way, the gaps in the template can be better filled, the pores and cavities in the concrete can be reduced, thereby improving the compactness and early crack resistance of the concrete.
[0020] Specifically, the implementation process of this embodiment is as follows: if it rains, the rainwater will penetrate into the permeable asphalt layer 12, and the rainwater will penetrate downward. When the rainwater penetrates into the waterproof layer 14 below the permeable asphalt layer 12, the waterproof layer 14 is fixed to the second geotextile 13, and the second geotextile 13 is fixed to the guide layer 11. The inclined surface of the guide layer 11 guides the rainwater on the surface of the waterproof layer 14, and guides the rainwater to the gravel base layer 2. The rainwater that penetrates into the gravel base layer 2 flows into the drainage ditch.
[0021] Method for covering the runway foundation 8 with the patching layer 1:
[0022] Adding calcium lignin sulfonate to concrete can reduce the amount of water used in concrete mixing, reduce the heat of hydration, and slow down the rate of hydration reaction.
[0023] Before construction, the hexagonal plates on the runway foundation 8 must be treated for damage before the pavement cover can be constructed. Different pretreatment plans are adopted for different degrees of damage to the hexagonal plates. For the hexagonal plates on the runway with broken edges and corners and holes and pits on the surface, concrete is poured into the holes and pits. The severely damaged hexagonal plates are completely excavated. After the damaged plates are excavated, the pits are cleaned.
[0024] After completing the above work, all the hexagonal plates on the runway foundation 8 can be collectively processed by pouring concrete into the damaged and excavated pits. The height of the concrete is flush with the height of the runway layer 9, and then it is dried and cooled.
[0025] Baffles are set on both sides of the runway foundation 8, and concrete is injected on the surface of the runway foundation 8. The concrete is spread and vibrated. Before the mixed material is spread, its flatness is checked. If it is qualified, it is properly sprinkled with water to moisten it. A sunshade is set at the gravel yard, and water mist is sprayed regularly. During construction, if the temperature difference between day and night is large, construction should be avoided during the high temperature period at noon, and construction should be selected at night when the temperature is lower. Lowering the construction temperature of concrete can significantly reduce the phenomenon of micro cracks on the concrete surface.
[0026] Cement concrete should be spread and vibrated twice using a high-frequency insert vibrator unit. The timing of the two vibrations should be grasped to eliminate shrinkage cracks; the surface should be pressed and smoothed after the initial setting and before the final setting to eliminate surface cracks. Eliminate the hidden danger of stress concentration during the cooling stage. The shoulder cement concrete slab can be spread once, and the insert vibrator is vibrated with a flat vibrator. Then the three-roller vibrator is used for leveling. The unit is leveled in sections according to the operation time. The length of the operation unit is 20-30m. The time interval between the vibrating rod and the three-roller leveling process does not exceed 15min. The height difference of the three-roller rolling and vibrating material is 5-20mm higher than the top surface of the formwork. After completion, the surface is made and roughened. The surface is first leveled by a flattening beam, and then it is made by wooden trowel, plastic trowel, manual trowel and other tools in three times. After the surface work, the cement concrete surface is roughened in time. From one side of the cement concrete slab to the other side, one slab at a time.
[0027] At the end of the construction, the formwork is removed and the curing work is carried out. After the cement concrete slab has finally set, it is covered with geotextile for curing. After cutting, the geotextile is sprinkled with water for curing. The time is not less than 14 days. During the curing period, people are strictly prohibited from passing within 24 hours, and motor vehicles are not allowed to pass within 28 days.
[0028] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A pavement structure for repairing an old airport runway, comprising a runway foundation (8) and a permeable asphalt layer (12), wherein shoulder layers (4) are provided on both sides of the runway foundation (8), a crushed stone base layer (2) is provided on the shoulder layer (4), a first geotextile (10) is provided on the runway foundation (8), and a repair layer (1) is provided on the first geotextile (10), wherein the characteristics are: A guide layer (11) is provided on the repair layer (1), the cross section of the guide layer (11) is a triangular structure, a second geotextile (13) is laid on the guide layer (11), a waterproof layer (14) is laid on the second geotextile (13), and a permeable asphalt layer (12) is located on the waterproof layer (14).
2. The pavement structure for repairing an old airport runway according to claim 1 is characterized in that: The runway foundation (8) comprises a stone cushion layer (6), a lime soil base layer (7), and a runway layer (9); the lime soil base layer (7) is laid on top of the stone cushion layer (6), and the runway layer (9) is laid on top of the lime soil base layer (7).
3. The pavement structure for repairing an old airport runway according to claim 1 or 2, characterized in that: The shoulder layer (4) comprises a shoulder base layer (5) and a runway shoulder (3); the shoulder base layer (5) is located on one side of the ash soil base layer (7), and the runway shoulder (3) is laid on the shoulder base layer (5).
4. The pavement structure for repairing an old airport runway according to claim 1, characterized in that: The guide layer (11) is provided with reinforcing ribs (15) inside for reinforcing the strength of the repair layer (1).
5. The pavement structure for repairing an old airport runway according to claim 1 is characterized in that: A water reducing agent for improving the early crack resistance of concrete is provided inside the repair layer (1).
6. The pavement structure for repairing an old airport runway according to claim 1, characterized in that: The waterproof layer (14) is made of a polyethylene waterproof membrane.