Pile conveying device for precast slab pile construction
By designing a pile feeding device with screw-driven connection bolts, the problem of difficulty in separation of pile feeding devices and prefabricated sheet piles in the prior art is solved, and the simple connection and separation of pile feeding devices and prefabricated sheet piles is realized, which improves the Construction efficiency and safety.
Patent Information
- Application Number
- CN202420353696.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-26
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2034-02-26
AI Technical Summary
In the construction of existing prefabricated sheet piles, it is difficult to separate the pile feeding device and the prefabricated sheet piles, especially after the construction is completed, the separation operation between the clamp and the prefabricated pile is not easy to implement.
A pile feeding device for prefabricated sheet pile construction is designed, using a connecting assembly in the box, including a plurality of through holes and protruding connection bolts. The connecting bolts are driven to rotate to connect or separate the embedded nuts by screwing and driving to achieve Simple connection and separation between pile feeding device and prefabricated sheet piles.
Simple connection and separation operation between pile feeding device and prefabricated sheet piles is realized, construction efficiency and safety are improved, and separation operation is avoided after construction is completed.
Smart Images

Figure CN221956725U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of piling, in particular to a pile delivery device for prefabricated sheet pile construction. Background Art
[0002] At present, there are three main methods for the construction of precast piles: hammering, static pressure and embedding. Hammering and static pressure are the traditional construction methods for precast piles, while the embedding method is novel in that it uses a construction method that uses the pile body's own weight to bury the precast pile into the pile hole after drilling, combining the advantages of both the embedding method and the factory-produced precast piles.
[0003] When the embedded precast pile is used, the connection between the precast pile and the pile delivery device is usually fixed by a clamp on the outer wall of the precast pile and the pile delivery device. After the construction of this method is completed, since the construction has been below the ground, it is difficult to separate the clamp from the precast pile, which makes it difficult to separate the pile delivery device from the precast pile. Utility Model Content
[0004] In order to solve the technical problem that the existing pile delivery device and the prefabricated pile are difficult to separate, the utility model provides a pile delivery device for prefabricated sheet pile construction.
[0005] In order to achieve the purpose of the utility model, the utility model adopts the following technical solutions:
[0006] A pile delivery device for prefabricated sheet pile construction comprises: a box body, a connecting assembly arranged in the box body; the bottom plate of the box body has a plurality of through holes arranged at predetermined intervals, the connecting assembly comprises: a plurality of connecting bolts that can extend out of the corresponding through holes to connect with pre-embedded nuts on the end faces of the prefabricated sheet piles, a plurality of screwing drives that connect and drive the corresponding connecting bolts to rotate to screw the embedded nuts, and the screwing drives are installed in the box body through an installation assembly.
[0007] Compared with the prior art, the utility model has the following beneficial effects: when it is necessary to deliver piles, the box body is first placed on the upper end of the prefabricated sheet pile, and the connecting bolts are driven by screwing to rotate and screw into the embedded nuts on the end faces of the prefabricated sheet piles, so that the pile delivery device is fixed to the upper end of the prefabricated sheet piles; after the pile delivery is completed, the connecting bolts are driven by screwing to unscrew the embedded nuts, so that the pile delivery device is disconnected from the prefabricated sheet piles, and the connection and separation operations of the pile delivery device and the prefabricated sheet piles are simple.
[0008] Furthermore, the screwing drive includes: a power source installed on the mounting assembly, a screwing shaft with two ends respectively connected to the power source and the connecting bolt, and an elastic member with two ends respectively abutting against the power source and the screwing shaft.
[0009] Furthermore, the mounting assembly includes a telescopic member with one end mounted on the top plate of the box body or on a connecting plate inside the box body, and a mounting plate connected to the other end of the telescopic member. The power source is mounted on the mounting plate, and the mounting plate has a plurality of through holes arranged at predetermined intervals for the screw shaft to pass through.
[0010] Furthermore, a limiting sleeve is provided at the lower end of the mounting plate, which is connected to the through hole and limits the radial position of the screwing shaft; the connecting bolt includes a threaded end for threading the embedded nut and a screwing end for cooperating with the screwing shaft, and the screwing end is at least partially located in the limiting sleeve.
[0011] Furthermore, the top plate or the connecting plate is provided with a limit assembly for limiting the longitudinal displacement of the telescopic member, and the limit assembly includes: a limit block installed on the telescopic member, and a limit seat installed on the top plate or the connecting plate, the limit seat having a limit groove for the telescopic member to pass through to connect to the mounting plate, and the maximum width of the limit groove is smaller than the maximum width of the limit block.
[0012] Furthermore, the telescopic member is connected to a lifting drive for longitudinal extension and retraction, and the lifting drive is installed on the top plate or on the connecting plate.
[0013] Furthermore, a guide rod is provided on the upper end of the base plate, and the mounting plate can move vertically along the guide rod.
[0014] Furthermore, a sealing sleeve is sleeved on the connecting bolt, and one end of the sealing sleeve abuts against the upper end of the bottom plate, and the other end is detachably mounted on the connecting bolt.
[0015] Furthermore, in the width direction, the box body has a joint end surface that is the same as the prefabricated sheet pile, and the joint end surface has a groove and / or a protrusion.
[0016] Furthermore, a cleaning channel is provided on at least one side plate of the box in the thickness direction, and the side plate is detachably connected to a sealing plate for sealing the cleaning channel. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0018] Figure 1 This is a schematic diagram of the connection state between the pile delivery device and the prefabricated sheet pile in the embodiment of the utility model;
[0019] Figure 2 This is a schematic diagram of the three-dimensional structure of the pile delivery device in the embodiment of the utility model;
[0020] Figure 3 This is a schematic diagram of the internal structure of the pile delivery device in the embodiment of the utility model;
[0021] Figure 4 yes Figure 3 The enlarged schematic diagram of part A in the middle;
[0022] Figure 5 yes Figure 3 The enlarged schematic diagram of part B in the middle;
[0023] Figure 6 This is a schematic diagram of the three-dimensional structure of the screw drive in the embodiment of the utility model;
[0024] Figure numerals: 1. box body; 11. bottom plate; 111. through hole; 112. guide rod; 12. sealing plate; 13. top plate; 14. connecting plate; 2. connecting assembly; 21. connecting bolt; 211. screw end; 212. screwing end; 22. screwing drive; 221. power source; 222. screwing shaft; 223. elastic member; 3. mounting assembly; 31. telescopic member; 32. mounting plate; 33. limiting sleeve; 34. lifting drive; 4. prefabricated sheet pile; 5. sealing sleeve; 6. limiting assembly; 61. limiting block; 62. limiting seat. DETAILED DESCRIPTION
[0025] In order to make the purpose, technical solution and advantages of the embodiments of the utility model clearer, the technical solution in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, rather than all the embodiments.
[0026] In this article, the terms "upper, lower, inside, outside" and the like are established based on the positional relationships shown in the drawings. The corresponding positional relationships may also change depending on the drawings, and therefore cannot be understood as absolute limitations on the scope of protection; moreover, relational terms such as "first" and "second" and the like are merely used to distinguish one component from another with the same name, and do not necessarily require or imply any actual relationship or order between these components.
[0027] Embodiment 1
[0028] See also Figure 1-6The present embodiment provides a pile delivery device for prefabricated sheet pile construction, comprising: a box body 1, a connecting assembly 2 arranged in the box body 1; the bottom plate 11 of the box body 1 has a plurality of through holes 111 arranged at intervals at predetermined positions, the connecting assembly 2 comprises: a plurality of connecting bolts 21 that can extend out of the corresponding through holes 111 to connect with the pre-embedded nuts on the end faces of the prefabricated sheet piles 4, a plurality of screwing drives 22 that connect and drive the corresponding connecting bolts 21 to rotate to screw the embedded nuts, and the screwing drive 22 is installed in the box body 1 through the installation assembly 3.
[0029] Specifically, when it is necessary to deliver the piles, the box body 1 is first placed on the upper end of the prefabricated sheet pile 4, and the connecting bolt 21 is driven to rotate by the screwing drive 22 to be screwed into the embedded nut on the end face of the prefabricated sheet pile 4, so that the pile delivery device is fixed to the upper end of the prefabricated sheet pile 4. After the pile delivery is completed, the connecting bolt 21 is driven to unscrew the embedded nut by the screwing drive 22, so that the pile delivery device is disconnected from the prefabricated sheet pile 4. The connection and separation operations of the pile delivery device and the prefabricated sheet pile 4 are simple.
[0030] In detail, the through hole 111 on the base plate 11 is set according to the position of the embedded nut on the end face of the precast sheet pile 4. The threaded end 211 of the connecting bolt 21 can pass through the through hole 111 and extend out of the base plate 11, but the screwing end 212 of the connecting bolt 21 is clamped on the bottom to avoid the connection with the screwing drive 22 due to excessive screwing when the connecting bolt 21 is screwed into the embedded nut. The specific position where the screwing drive 22 is installed in the box body 1 is not limited. It can be fixed to the box body 1 and the connecting bolt 21 can be screwed. The specific structure of the installation component 3 is also not limited. It can be fixed in the box body 1. The screwing drive 22 is set one by one with the connecting bolt 21. Of course, the screwing drive 22 can also drive each connecting bolt 21 to rotate through a gear transmission. Since the gear transmission is an existing structure, it will not be repeated here.
[0031] Furthermore, the screwing drive 22 includes: a power source 221 mounted on the mounting assembly 3, a screwing shaft 222 whose two ends are respectively connected to the power source 221 and the connecting bolt 21, and an elastic member 223 whose two ends are respectively abutted against the power source 221 and the screwing shaft 222. The screwing shaft 222 is driven to rotate by the power source 221, thereby driving the connecting bolt 21 connected to the screwing shaft 222 to rotate. The elastic member 223 is arranged between the power source 221 and the screwing shaft 222 so that the screwing shaft 222 can adaptively cooperate with the connecting bolt 21 to screw in or out of the embedded nut.
[0032] Furthermore, the mounting assembly 3 includes a telescopic member 31 with one end mounted on the top plate 13 of the box body 1 or on the connecting plate 14 in the box body 1, and a mounting plate 32 connected to the other end of the telescopic member 31. The telescopic member 31 can be directly mounted on the top plate 13 of the box body 1, or a connecting plate 14 can be provided in the box body 1, and the telescopic member 31 is mounted on the connecting plate 14; the other end of the telescopic member 31 is connected to the mounting plate 32, the power source 221 is mounted on the mounting plate 32, and the mounting plate 32 has a plurality of through holes arranged at predetermined intervals for the screwing shaft 222 to pass through, that is, the screwing drive 22 is softly connected to the box body 1 through the mounting assembly 3, so as to avoid the screwing drive 22 being damaged by excessive force during the connection operation of the pile delivery device and the prefabricated sheet pile 4. The telescopic member 31 is preferably a telescopic sleeve, or it can be a chain.
[0033] Furthermore, a limiting sleeve 33 is provided at the lower end of the mounting plate 32, which is connected to the through hole and limits the radial position of the screwing shaft 222. The limiting sleeve 33 can prevent the screwing shaft 222 from deviating from the position and being disconnected from the connecting bolt 21. The connecting bolt 21 includes a threaded end 211 threaded with an embedded nut and a screwing end 212 cooperating with the screwing shaft 222. Preferably, the screwing end 212 is at least partially located in the limiting sleeve 33, which further limits the position of the connecting bolt 21 and improves the connection accuracy between the pile delivery device and the prefabricated sheet pile 4.
[0034] Further, the top plate 13 or the connecting plate 14 is provided with a limit assembly for limiting the longitudinal displacement of the telescopic member 31, and the limit assembly 6 comprises: a limit block 61 mounted on the telescopic member 31, and a limit seat 62 mounted on the top plate 13 or the connecting plate 14, wherein the limit seat 62 has a limit groove for the telescopic member 31 to pass through to connect to the mounting plate 32, and the maximum width of the limit groove is smaller than the maximum width of the limit block 61. The limit cooperation between the limit block 61 and the limit seat 62 can limit the longitudinal displacement of the telescopic member 31, and prevent the screw shaft 222 from being disconnected from the connecting bolt 21 due to excessive displacement.
[0035] Furthermore, a guide rod 112 is provided at the upper end of the bottom plate 11 , and the mounting plate 32 can move vertically along the guide rod 112 to prevent the mounting plate 32 from shifting.
[0036] Furthermore, a sealing sleeve 5 is mounted on the connecting bolt 21, and one end of the sealing sleeve 5 abuts against the upper end of the bottom plate 11, and the other end is detachably mounted on the connecting bolt 21, so as to seal between the bottom plate 11 and the connecting bolt 21 to prevent mud from entering the box body 1 during the pile delivery process.
[0037] Furthermore, in the width direction, the box body 1 has a splicing end face that is the same as the prefabricated sheet pile 4, and the splicing end face has a groove and / or a protrusion to accommodate another prefabricated sheet pile 4 on the lateral side of the prefabricated sheet pile 4, thereby avoiding interference between the pile delivery device and the other prefabricated sheet pile 4 that affects the pile delivery.
[0038] Furthermore, a cleaning channel is provided on at least one side of the box body 1 in the thickness direction, and a sealing plate 12 for sealing the cleaning channel is detachably connected to the side plate, so as to facilitate cleaning of the inside of the box body 1 after the pile delivery is completed.
[0039] Embodiment 2
[0040] In this embodiment, the same parts as those in the first embodiment are given the same figure marks, and the same text descriptions are omitted.
[0041] See also Figure 1-6 Compared with the first embodiment, the pile delivery device for the construction of the prefabricated sheet pile 4 provided in this embodiment has the following different structural designs:
[0042] The telescopic member 31 is connected to a lifting drive 34 for longitudinal extension, and the lifting drive 34 is installed on the top plate 13 or the connecting plate 14. The telescopic member 31 is automatically controlled by the lifting drive 34 to extend and retract, and then can be accurately controlled according to actual conditions.
[0043] The above are only preferred embodiments of the present invention. The protection scope of the present invention shall be based on the scope defined by the claims. Several improvements and modifications made by those skilled in the art without departing from the spirit and scope of the present invention shall also be regarded as the protection scope of the present invention.
Claims
1. A pile delivery device for prefabricated sheet pile construction, characterized in that: include: A box body, and a connecting component arranged in the box body; The bottom plate of the box body has a plurality of through holes arranged at predetermined intervals, and the connecting assembly includes: a plurality of connecting bolts that can extend out of the corresponding through holes to connect with the embedded nuts on the end faces of the prefabricated sheet piles, and a plurality of screwing drives that connect and drive the corresponding connecting bolts to rotate to screw the embedded nuts, and the screwing drives are installed in the box body through the installation assembly.
2. The pile delivery device for prefabricated sheet pile construction according to claim 1, characterized in that: The screwing drive comprises: a power source installed on the mounting assembly, a screwing shaft with two ends respectively connected to the power source and the connecting bolt, and an elastic member with two ends respectively abutting against the power source and the screwing shaft.
3. The pile delivery device for prefabricated sheet pile construction according to claim 2, characterized in that: The mounting assembly includes a telescopic member with one end mounted on the top plate of the box or the connecting plate mounted on the box, and a mounting plate connected to the other end of the telescopic member. The power source is mounted on the mounting plate, and the mounting plate has a plurality of through holes arranged at predetermined intervals for the screw shaft to pass through.
4. The pile delivery device for prefabricated sheet pile construction according to claim 3, characterized in that: The lower end of the mounting plate is provided with a limiting sleeve which is connected to the through hole and limits the radial position of the screwing shaft; the connecting bolt includes a threaded end which is threaded with an embedded nut and a screwing end which cooperates with the screwing shaft, and the screwing end is at least partially located in the limiting sleeve.
5. The pile delivery device for prefabricated sheet pile construction according to claim 3, characterized in that: The top plate or the connecting plate is provided with a limit assembly for limiting the longitudinal displacement of the telescopic member, and the limit assembly includes: a limit block installed on the telescopic member, and a limit seat installed on the top plate or the connecting plate, the limit seat having a limit groove for the telescopic member to pass through to connect to the mounting plate, and the maximum width of the limit groove is smaller than the maximum width of the limit block.
6. The pile delivery device for prefabricated sheet pile construction according to claim 5, characterized in that: The telescopic member is connected to a lifting drive for longitudinal extension and retraction, and the lifting drive is installed on the top plate or on the connecting plate.
7. The pile delivery device for prefabricated sheet pile construction according to claim 3 or 6, characterized in that: A guide rod is arranged on the upper end of the bottom plate, and the mounting plate can move vertically along the guide rod.
8. The pile delivery device for prefabricated sheet pile construction according to any one of claims 1 to 6, characterized in that: A sealing sleeve is sleeved on the connecting bolt, and one end of the sealing sleeve abuts against the upper end of the bottom plate, and the other end is detachably mounted on the connecting bolt.
9. The pile delivery device for prefabricated sheet pile construction according to any one of claims 1 to 6, characterized in that: In the width direction, the box body has a joint end surface that is the same as that of the prefabricated sheet pile, and the joint end surface has a groove and / or a protrusion.
10. The pile delivery device for prefabricated sheet pile construction according to any one of claims 1 to 6, characterized in that: A cleaning channel is arranged on at least one side of the box in the thickness direction, and a sealing plate for sealing the cleaning channel is detachably connected to the side plate.