U-shaped elbow flaring mechanism
By designing a U-shaped elbow flaring mechanism, automated non-stop processing of U-shaped copper tubes was achieved, solving the problems of low production efficiency and heavy operator workload in existing technologies, and improving the automation level of copper tube processing.
Patent Information
- Application Number
- CN202322885179.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-26
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2033-10-26
AI Technical Summary
Existing U-shaped copper tube flaring processing equipment requires operators to manually clamp and unclamp the U-shaped copper tubes, resulting in low production efficiency and a heavy workload for operators.
A U-shaped elbow flaring mechanism was designed. By setting multiple sets of positioning fixtures and automated flaring components on the slide table, the automatic loading and unloading of U-shaped copper tubes can be realized. The movement of the positioning fixtures and the processing of the flaring drill bit are driven by servo motors and cylinders, realizing non-stop processing.
It improves the production efficiency of U-shaped copper tubes, reduces the workload of operators, and realizes automated batch processing of U-shaped copper tubes.
Smart Images

Figure CN221966614U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of copper tube production equipment, in particular to a U-shaped elbow expansion mechanism. Background Art
[0002] U-shaped copper tubes are common pipe connectors in existing refrigeration systems. U-shaped copper tubes are generally formed by bending straight copper tubes. In order to facilitate welding other refrigeration tubes to the U-shaped copper tubes, the U-shaped copper tubes also need to be expanded.
[0003] When the existing expansion processing equipment is expanding the U-shaped copper tube, the operator needs to manually place the U-shaped copper tube on a fixed tooling, expand the U-shaped copper tube through a reaming drill, and manually remove the U-shaped copper tube from the tooling after the expansion is completed and replace it with another U-shaped copper tube to be processed for processing. Since the operator needs to manually unload the parts after each processing is completed, the operator's workload is too heavy, and the expansion processing cannot be performed when the U-shaped copper tube is disassembled and assembled, resulting in a long downtime in the production process, affecting production efficiency. Utility Model Content
[0004] In order to overcome the above-mentioned defects existing in the prior art, the utility model provides a U-shaped elbow expansion mechanism.
[0005] The technical solution adopted by the utility model to solve its technical problems is: a U-shaped elbow expanding mechanism, including a workbench, a slide table movably installed on the workbench, a plurality of groups of first blanking troughs are opened on the slide table, and positioning tooling is respectively provided above the plurality of first blanking troughs, the positioning tooling is movably installed on the slide table through a guide assembly, a expanding assembly is provided above the workbench, the expanding assembly is movably installed on a vertical plate, and the vertical plate is fixedly installed on the ground.
[0006] Furthermore, a first guide rail is fixedly installed on the top of the workbench, and the slide is slidably installed on the first guide rail through a slider, and a first lead screw nut is fixedly installed on the side of the workbench, and the first lead screw nut is cooperated and installed on the first lead screw, and both ends of the first lead screw are rotatably installed on the bearing seat, and the bearing seat is fixedly installed on the workbench, one end of the first lead screw passes through the bearing seat, and is connected to the power output shaft of the first servo motor through a first coupling, and the first servo motor is rigidly fixed to the workbench through a motor bracket.
[0007] Furthermore, the guide assembly includes several groups of guide slide rods, several groups of the guide slide rods are located on both sides of the first blanking trough, several groups of the guide slide rods are respectively fixedly installed with slide rod seats at both ends, the slide rod seats are fixedly installed on the slide table, and several groups of the guide slide rods are respectively slidably installed with positioning tooling.
[0008] Furthermore, the positioning tooling includes a first positioning seat and a second positioning seat, guide slides are fixedly installed on both side walls of the first positioning seat, the guide slides are slidably installed on the guide slide rods, a first placement groove is opened on the first positioning seat, a first cylinder is provided on the side of the first positioning seat away from the first placement groove, the first cylinder is fixedly installed on the slide through a cylinder frame, and a push rod of the first cylinder is fixedly installed on the first positioning seat.
[0009] Furthermore, a second placement groove corresponding to the first placement groove is opened on the second positioning seat, and the second positioning seat is slidably installed on the guide slide rod through a guide slide. A second cylinder is provided on the side of the second positioning seat away from the second placement groove, and the second cylinder is fixedly installed on the slide through a cylinder frame.
[0010] Further, the flaring assembly includes a dual-axis transmission box, and flaring drill bits are respectively installed on the power output shafts of the dual-axis transmission box. The dual-axis transmission box is fixedly installed on the bottom of the mounting plate, and a spindle motor is fixedly installed on the top of the mounting plate. The power output end of the spindle motor is connected to the power output shaft of the dual-axis transmission box. The mounting plate is slidably installed on the second guide rail through a slider, and the second guide rail is fixedly installed on the vertical plate. The vertical plate is provided with a groove, and a second lead screw is rotatably installed in the groove. A second lead screw nut is installed on the second lead screw, and the second lead screw nut is fixedly installed on the mounting plate. A second servo motor is fixedly installed on the top of the vertical plate, and the power output shaft of the second servo motor is connected to the second lead screw through a second coupling.
[0011] Furthermore, a base is fixedly installed at the bottom of the workbench, and a plurality of groups of material collection boxes are installed on the base. A plurality of groups of second material dropping chutes are opened on the workbench, and the positions of the second material dropping chutes correspond to the material collection boxes.
[0012] The beneficial effect of the utility model is that the design scheme of the utility model is designed with two groups of first blanking troughs on the slide, and positioning tooling is respectively provided above the two groups of first blanking troughs. During processing, the U-shaped copper tube is clamped and fixed by the positioning tooling. When processing the U-shaped copper tube on one group of positioning tooling, the operator clamps the U-shaped copper tube to the other group of positioning tooling. After the processing is completed, the positioning tooling is opened to allow the U-shaped copper tube to fall into the first blanking trough below. Therefore, the U-shaped copper tube can be loaded and unloaded without stopping during the processing, thereby improving production efficiency, and the unloading process is automatic unloading, which reduces the workload of the operator. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] The utility model is further described below in conjunction with the accompanying drawings and embodiments.
[0014] Figure 1It is a three-dimensional structural schematic diagram of the utility model;
[0015] Figure 2 It is the front view of the utility model;
[0016] Figure 3 for Figure 2 Schematic diagram of the cross-sectional structure in the AA direction;
[0017] Figure 4 It is a top view of the utility model;
[0018] Figure 5 It is a structural schematic diagram of the positioning tooling of the utility model.
[0019] In the figure: 1. workbench, 2. slide, 3. first blanking chute, 4. vertical plate, 5. first guide slide, 6. first lead screw nut, 7. bearing seat, 8. first coupling, 9. first servo motor, 10. motor bracket, 11. guide slide, 12. slide seat, 13. first positioning seat, 131. first placement slot, 14. guide slide, 15. second positioning seat, 151. second placement slot, 16. first cylinder, 17. second cylinder, 18. double-axis transmission box, 19. flaring drill, 20. mounting plate, 21. spindle motor, 22. second guide slide, 23. second lead screw, 24. second lead screw nut, 25. second servo motor, 26. second coupling, 27. base, 28. collection box, 29. second blanking chute, 30. first lead screw, 31. U-shaped copper tube. DETAILED DESCRIPTION
[0020] In order to more clearly illustrate the technical solution of the utility model, the utility model is further described below in conjunction with the accompanying drawings. Obviously, the accompanying drawings described below are only one embodiment of the utility model. For ordinary technicians in this field, without paying any creative work, other embodiments can be obtained based on this drawing and embodiment, which all belong to the protection scope of the utility model.
[0021] according to Figure 1-5 As shown, a U-shaped elbow flaring mechanism comprises a workbench 1, on which a slide 2 is movably mounted, on which two groups of first blanking troughs 3 are provided, and above the two groups of first blanking troughs 3 there are respectively provided positioning fixtures, which are movably mounted on the slide 2 through a guide assembly, and above the workbench 1 there is a flaring assembly, which is movably mounted on a vertical plate 4, and the vertical plate 4 is fixedly mounted on the ground.
[0022] In the above specific embodiment, when the expansion process is performed, the U-shaped copper tube 31 is clamped and fixed by the positioning tool, the slide 2 moves on the workbench 1, and stops moving when one set of positioning tool moves to the bottom of the expansion component, and the expansion component descends to expand the U-shaped copper tube 31. After the processing is completed, the slide 2 continues to move forward, and stops moving when another set of positioning tool moves to the bottom of the expansion component, and the expansion component descends to expand another set of U-shaped copper tubes 31. At the same time, the positioning tool for clamping the previously processed U-shaped copper tube 31 is opened, so that the clamped U-shaped The copper tube 31 falls into the first blanking trough 3 below, thereby realizing automatic unloading of the U-shaped copper tube 31. The operator can re-clamp the U-shaped copper tube 31 to be processed onto the positioning tooling. At this time, the expansion processing of another group of U-shaped copper tubes 31 is completed, and the slide 2 moves in the opposite direction on the workbench 1 to expand the newly clamped U-shaped copper tube 31. The above steps are repeated to perform batch processing of the U-shaped copper tube 31. Since the U-shaped copper tube 31 can be loaded and unloaded without stopping the machine during the processing, the production efficiency is improved, and the unloading process is automatic unloading, which reduces the workload of the operator.
[0023] A first guide rail 5 is fixedly installed on the top of the workbench 1 by bolts, and the slide 2 is slidably installed on the first guide rail 5 through a slider, and a first lead screw nut 6 is fixedly installed on the side of the workbench 1, and the first lead screw nut 6 is cooperated and installed on the first lead screw 30, and both ends of the first lead screw 30 are rotatably installed on the bearing seat 7, and the bearing seat 7 is fixedly installed on the workbench 1 by bolts, and one end of the first lead screw 30 passes through the bearing seat 7 and is connected to the power output shaft of the first servo motor 9 through the first coupling 8. The first servo motor 9 is rigidly fixed on the workbench 1 through the motor bracket 10, and the slide 2 is driven to move on the workbench 1 by the first servo motor 9.
[0024] The guide assembly includes two groups of guide slide bars 11, which are located on both sides of the first blanking trough 3. Slide bars seats 12 are fixedly installed at both ends of the two groups of guide slide bars 11. The slide bars seats 12 are fixedly installed on the slide table 2 by bolts, and positioning tooling is slidably installed on the two groups of guide slide bars 11.
[0025] The positioning tooling includes a first positioning seat 13 and a second positioning seat 15. Guide slides 14 are respectively fixedly installed on the two side walls of the first positioning seat 13 by bolts. The guide slides 14 are slidably installed on the guide slide rod 11. A first placement groove 131 is opened on the first positioning seat 13. A first cylinder 16 is provided on the side of the first positioning seat 13 away from the first placement groove 131. The first cylinder 16 is fixedly installed on the slide 2 through a cylinder frame, and a push rod of the first cylinder 16 is fixedly installed on the first positioning seat 13 by bolts.
[0026] The second positioning seat 15 is provided with a second placement groove 151 corresponding to the first placement groove 131. The second positioning seat 15 is slidably installed on the guide slide 11 through the guide slide 14. The second positioning seat 15 is provided with a second cylinder 17 on the side away from the second placement groove 151. The second cylinder 17 is fixedly installed on the slide 2 through a cylinder frame. The first positioning seat 12 and the second positioning seat 15 are opened and closed under the drive of the first cylinder 16 and the second cylinder 17.
[0027] The flaring assembly includes a dual-axis transmission box 18, and a flaring drill bit 19 is respectively installed on the power output shaft of the dual-axis transmission box 18. The dual-axis transmission box 18 is fixedly installed on the bottom of the mounting plate 20 by bolts, and a spindle motor 21 is fixedly installed on the top of the mounting plate 20 by bolts. The power output end of the spindle motor 21 is connected to the power output shaft of the dual-axis transmission box 18. The mounting plate 20 is slidably installed on the second guide rail 22 through a slider, and the second guide rail 22 is fixedly installed on the vertical plate 4 by bolts. A groove is provided on the vertical plate 4, in which a second lead screw 23 is rotatably installed, a second lead screw nut 24 is installed on the second lead screw 23, and the second lead screw nut 24 is fixedly installed on the mounting plate 20. A second servo motor 25 is fixedly installed on the top of the vertical plate 4, and the power output shaft of the second servo motor 25 is connected to the second lead screw 23 through a second coupling 26. The spindle motor 21 drives the flaring drill bit 19 on the power output shaft of the dual-axis transmission box 18 to rotate, and the flaring processing of the U-shaped copper tube 31 is completed by the flaring drill bit 19.
[0028] A base 27 is fixedly installed at the bottom of the workbench 1, and two groups of collection boxes 28 are installed on the base 27. Two groups of second material chutes 29 are opened on the workbench 1. The positions of the two groups of second material chutes 29 correspond to the collection boxes 28. The processed U-shaped tubes 31 fall into the collection boxes 28 through the second material chutes 29, thereby facilitating the collection of the U-shaped tubes 31.
[0029] The specific working process of the utility model is as follows: when clamping the U-shaped copper tube 31, the push rods of the first cylinder 16 and the second cylinder 17 are retracted to drive the first positioning seat 13 and the second positioning seat 15 to separate from each other, and the operator places the U-shaped copper tube 31 into the first placement groove 131, and the push rods of the first cylinder 16 and the second cylinder 17 are extended to close the first positioning seat 13 and the second positioning seat 15, and the U-shaped copper tube 31 is fixed on the positioning tool through the first placement groove 131 and the second placement groove 151, and the above steps are repeated. The U-shaped copper tube 31 is clamped on another set of positioning fixtures. After the clamping is completed, the first servo motor 9 is started. The slide 2 moves on the workbench 1 under the drive of the first servo motor 9. When one set of positioning fixtures moves to the bottom of the flaring component, it stops moving. At this time, the spindle motor 21 drives the flaring drill 19 on the power output shaft of the double-axis transmission box 18 to rotate, and the mounting plate 20 moves toward the direction of the workbench 1 under the drive of the second servo motor 25. The double-axis transmission box 18 moves synchronously with the mounting plate 20. The head 19 performs expansion processing on the U-shaped copper tube 31. After the expansion processing is completed, the mounting plate 20 moves up, and the first servo motor 9 continues to drive the slide 2 to move on the workbench 1. When another set of positioning tooling moves to the bottom of the double-axis transmission box 18, it stops. The double-axis transmission box 18 moves down to expand the opening. At the same time, the previously processed U-shaped copper tube 31 moves to the end of the workbench 1, and the first blanking trough 3 is located above the second blanking trough 29. The first positioning seat 13 and the second positioning seat 15 are separated from each other, so that the U-shaped copper tube 31 The U-shaped copper tube 31 passes through the first blanking chute 3 and the second blanking chute 29 and falls into the collecting box 28. The operator re-clamps the U-shaped copper tube 31 to be processed onto the positioning tooling. The first servo motor 9 drives the slide 2 to move in the opposite direction on the workbench 1 to expand the newly clamped U-shaped copper tube 31. The above steps are repeated to perform batch processing of the U-shaped copper tube 31. Since the U-shaped copper tube 31 can be loaded and unloaded without stopping the machine during the processing, the production efficiency is improved, and the unloading process is automatic, which reduces the workload of the operator.
[0030] The above embodiments are only exemplary embodiments of the present invention and are not intended to limit the present invention. The protection scope of the present invention is defined by the claims. Those skilled in the art may make various modifications or equivalent substitutions to the present invention within the essence and protection scope of the present invention, and such modifications or equivalent substitutions shall also be deemed to fall within the protection scope of the present invention.
Claims
1. A U-bend expansion mechanism, comprising a workbench (1), characterized in that: A slide (2) is movably mounted on the workbench (1), and a plurality of groups of first blanking troughs (3) are provided on the slide (2). Positioning fixtures are respectively provided above the plurality of groups of first blanking troughs (3). The positioning fixtures are movably mounted on the slide (2) through guide components. A flaring component is provided above the workbench (1), and the flaring component is movably mounted on a vertical plate (4). The vertical plate (4) is fixedly mounted on the ground.
2. A U-shaped elbow expansion mechanism according to claim 1, characterized in that: A first guide rail (5) is fixedly installed on the top of the workbench (1), and the slide (2) is slidably installed on the first guide rail (5) through a slider. A first lead screw nut (6) is fixedly installed on the side of the workbench (1), and the first lead screw nut (6) is mounted on the first lead screw (30) in a matching manner. Both ends of the first lead screw (30) are rotatably mounted on a bearing seat (7), and the bearing seat (7) is fixedly installed on the workbench (1). One end of the first lead screw (30) passes through the bearing seat (7) and is connected to the power output shaft of the first servo motor (9) through a first coupling (8). The first servo motor (9) is rigidly fixed to the workbench (1) through a motor bracket (10).
3. A U-shaped elbow expansion mechanism according to claim 1, characterized in that: The guide assembly comprises a plurality of groups of guide slide bars (11), wherein the plurality of groups of guide slide bars (11) are located on both sides of the first blanking trough (3), and slide bar seats (12) are fixedly installed at both ends of the plurality of groups of guide slide bars (11), and the slide bar seats (12) are fixedly installed on the slide table (2), and positioning tooling is slidably installed on the plurality of groups of guide slide bars (11).
4. A U-shaped elbow expansion mechanism according to claim 3, characterized in that: The positioning tool comprises a first positioning seat (13) and a second positioning seat (15), and guide slides (14) are fixedly installed on both side walls of the first positioning seat (13), and the guide slides (14) are slidably installed on the guide slide bar (11). The first positioning seat (13) is provided with a first placement groove (131), and a first cylinder (16) is provided on the side of the first positioning seat (13) away from the first placement groove (131). The first cylinder (16) is fixedly installed on the slide table (2) through a cylinder frame, and a push rod of the first cylinder (16) is fixedly installed on the first positioning seat (13).
5. A U-shaped elbow expansion mechanism according to claim 4, characterized in that: The second positioning seat (15) is provided with a second placement groove (151) corresponding to the first placement groove (131); the second positioning seat (15) is slidably mounted on the guide slide bar (11) via a guide slide seat (14); a second cylinder (17) is provided on a side of the second positioning seat (15) away from the second placement groove (151); and the second cylinder (17) is fixedly mounted on the slide table (2) via a cylinder frame.
6. A U-shaped elbow expansion mechanism according to claim 1, characterized in that: The flaring assembly comprises a double-axis transmission box (18), and the power output shafts of the double-axis transmission box (18) are respectively equipped with flaring drill bits (19), the double-axis transmission box (18) is fixedly installed on the bottom of a mounting plate (20), and a spindle motor (21) is fixedly installed on the top of the mounting plate (20), and the power output end of the spindle motor (21) is connected to the power output shaft of the double-axis transmission box (18), and the mounting plate (20) is slidably installed on a second guide rail (22) through a slider, and the The second guide rail (22) is fixedly mounted on the vertical plate (4); a groove is provided on the vertical plate (4); a second lead screw (23) is rotatably mounted in the groove; a second lead screw nut (24) is mounted on the second lead screw (23); the second lead screw nut (24) is fixedly mounted on the mounting plate (20); a second servo motor (25) is fixedly mounted on the top of the vertical plate (4); a power output shaft of the second servo motor (25) is connected to the second lead screw (23) via a second coupling (26).
7. A U-shaped elbow expansion mechanism according to any one of claims 1 to 6, characterized in that: A base (27) is fixedly installed at the bottom of the workbench (1), and a plurality of groups of material collection boxes (28) are installed on the base (27). A plurality of groups of second material drop chutes (29) are opened on the workbench (1), and the positions of the plurality of groups of second material drop chutes (29) correspond to the material collection boxes (28).