Large steel pipe support device with unloading device

Through the large steel pipe bracket device with its own unloading device, the height adjustment and rapid installation is achieved using flange and bolt connections, which solves the problems of quality control difficulties, long construction periods and environmental pollution in traditional construction methods, and improves construction efficiency and safety , reduces costs.

CN221972101UActive Publication Date: 2024-11-08ZHEJIANG XINWAN MUNICIPAL ENG CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323638732.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-29
Publication Date
2024-11-08
Estimated Expiration
2033-12-29

AI Technical Summary

Technical Problem

In the construction of temporary bridges, traditional methods have problems such as difficulty in construction quality control, long construction period, large safety hazards, high steel waste, high costs and serious environmental pollution.

Method used

The large steel pipe bracket device with its own unloading device is used to connect the flange and bolts of the steel pipe components and the sandbox unloading device to achieve adjustable height, rapid erection and reuse, reducing on-site welding and cutting, and improving the level of construction standardization.

Benefits of technology

The construction process is simplified, construction efficiency and safety is improved, costs are reduced, steel waste is reduced, and construction quality and environmental protection are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221972101U_ABST
    Figure CN221972101U_ABST
Patent Text Reader

Abstract

The utility model relates to a large steel pipe support device with a discharging device, which comprises a steel pipe assembly and a sand box discharging device, round flange plates are arranged on the upper end face and the lower end face of the steel pipe assembly, and the lower end of the steel pipe assembly is fixedly installed with a support foundation arranged on a foundation through the round flange plates. The sandbox unloading device is installed at the upper end of the steel pipe assembly and abuts against a bottom formwork used for pouring a bent cap. All the components are connected and fixed through flanges and bolts, the height of the sand box unloading device can be adjusted to be 20 cm, a large steel pipe support which can be rapidly erected to adapt to supports of various heights, can be repeatedly used, saves steel and is adjustable in height is formed, the construction standardization degree is high, the working procedure is simple and convenient, on-site welding and cutting are not needed, stress is definite, and the sand box unloading device is suitable for large-scale production. The construction quality of the support is easier to guarantee, the construction safety is good, the environmental protection property is improved, the construction cost is low, and the construction efficiency is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of temporary support construction of bridges in construction projects, and particularly relates to a large steel pipe support device with a self-unloading device. Background Art

[0002] In the construction of cast-in-place cap beam formwork, the traditional construction method mainly consists of full-span steel pipe supports with adjustable modulus of standard size and large steel pipe supports welded or cut on-site to the designed height according to the elevation. Full-span support erection process: foundation treatment → support foundation pouring → pad positioning and placement → first step of vertical pole erection → first step of horizontal pole erection → diagonal pole erection → subsequent steps repeat the first step of vertical pole, horizontal pole, diagonal pole erection method... → erect to the designed elevation → adjust the top support height to the designed elevation → erect the bottom formwork system → cap beam pouring and maintenance. The full-span support erection can use a combination of various types of standard length supports to achieve the designed erection height, but there are many processes, a large number of rods, and many connection points. Therefore, construction quality control is difficult, the construction period is long, and non-compliant erection poses great safety hazards. The erection process of ordinary large steel pipe brackets: foundation treatment → pouring the bracket foundation and pre-embedded iron plates → cutting or extending the standard length of large steel pipes on site according to the designed height of the bracket → welding with the pre-embedded iron plates → installing the unloading device → setting up the bottom formwork system → pouring and curing the cap beam. Ordinary large steel pipe brackets need to purchase large steel pipes of standard length on the market for cutting or extension processing on site, and the unloading device needs to be additionally fixed, which wastes a lot of steel, resulting in increased construction costs, increased construction period, and difficult quality control. A large amount of fire work is required on site, which causes heavy environmental pollution. Utility Model Content

[0003] The purpose of the utility model is to overcome the deficiencies of the prior art and to provide a large steel pipe bracket device with a built-in unloading device, which can be quickly erected to adapt to various height brackets and can be reused, saving steel, and has the advantages of a height-adjustable large steel pipe bracket and a high degree of construction standardization.

[0004] The purpose of the utility model is achieved through the following technical scheme. The large steel pipe support device with its own unloading device includes a steel pipe assembly and a sand box unloading device. The upper and lower end surfaces of the steel pipe assembly are provided with circular flanges. The lower end of the steel pipe assembly is installed and fixed to a support base arranged on the foundation through the circular flange. The upper end of the steel pipe assembly is provided with the sand box unloading device, and the sand box unloading device is against the bottom formwork used for casting the cap beam.

[0005] The beneficial effects of the utility model are as follows: compared with the prior art, the above-mentioned components are fixed by flanges and bolts, and the sand box unloading device can be adjusted to a height of 20 cm, forming a bracket that can be quickly erected to adapt to various heights and can be reused, saving steel, a large steel pipe bracket with adjustable height, a high degree of construction standardization, simple procedures, no on-site welding and cutting, clear force, making it easier to ensure the construction quality of the bracket, good construction safety, improved environmental protection, low construction cost, and high construction efficiency.

[0006] Preferably, the steel pipe assembly includes a plurality of steel pipes, each of which is provided with circular flanges on both upper and lower end surfaces, and adjacent steel pipes are connected via circular flanges and fixed with bolts; a plurality of reinforcing plates are welded between the circular flanges and the outer peripheral walls of the steel pipes; the steel pipes are combined by circular flanges, and the lengths of the steel pipes are different. Various height brackets can be quickly built by simply using bolts to connect them. The installation is convenient, no on-site welding and cutting are required, and the construction efficiency is high.

[0007] Preferably, the support foundation includes an iron plate and a foundation steel pipe pre-buried in the foundation, and circular flanges are provided on both upper and lower end surfaces of the foundation steel pipe. The foundation steel pipe is fixed in the iron plate by passing anchor bolts through bolt holes in the circular flanges, and the upper end of the foundation steel pipe is connected to the lower end of the steel pipe; a number of reinforcing plates are welded between the circular flange and the outer peripheral wall of the foundation steel pipe; through the arrangement of the above-mentioned structure, the support foundation is more convenient and firm to set up, so that it can be connected to the steel pipe assembly by flange and bolts, which greatly improves the installation efficiency and has low construction costs.

[0008] Preferably, the sand box unloading device comprises an upper box body and a lower box body, sand is placed in the lower box body, the upper box body is sleeved in the lower box body, and the upper box body is placed on the upper plane of the sand pile formed by stacking the sand; the upper top surface of the upper box body is provided with a square supporting steel plate, and the lower bottom surface of the lower box body is provided with a square flange, and the four end corners of the square supporting steel plate and the square flange are provided with limiting holes, and the limiting holes of the square supporting steel plate and the limiting holes of the square flange are inserted and fixed by bolt assemblies, so that the upper box body and the lower box body are limited and fixed; the sand box unloading device can be quickly positioned by sleeved upper and lower box bodies, and the sand box unloading device is limited by connecting the four corners of the square flange with the four corners of the square supporting steel plate by bolt assemblies. The construction has a high degree of standardization, the process is simple and easy to operate, the quality of bracket installation is easier to ensure, and the construction efficiency and construction safety are improved.

[0009] Preferably, the upper box body and the lower box body are both cylindrical, and the outer diameter of the upper box body is smaller than the inner diameter of the lower box body, and the box body of the upper box body is sleeved in the box body of the lower box body; through the arrangement of the above structure, the sleeve connection between the upper and lower boxes is more convenient, and it is also convenient to align the limiting holes between the four corners of the square flange and the four corners of the square supporting steel plate.

[0010] Preferably, a sand inlet and a sand outlet are provided on the box wall of the lower box body, the sand inlet is located at the upper end of the box wall of the lower box body, and the sand outlet is located at the lower end of the box wall of the lower box body, and the sand inlet and the sand outlet are relatively distributed, and the sand inlet and the sand outlet are both connected with sealing bolts; through the arrangement of the above structure, it is convenient to inlet and outlet of sand into the lower box body, and it is also convenient to fine-tune the height size of the sand box unloading device after it is installed on the top of the steel pipe assembly.

[0011] Preferably, a circular limit block is provided under the square flange, and when the sand box unloading device is installed on the top of the steel pipe assembly, the circular limit block is embedded in the top of the steel pipe assembly; in this way, the sand box unloading device can be stably limited and fixed in the top of the steel pipe assembly, and has higher safety when connected and installed with the top of the steel pipe assembly.

[0012] Preferably, the square flange is provided with a plurality of bolt connection holes, and the bolt connection holes are evenly spaced around the outer wall of the annular limit block; in this way, the sand box unloading device can be connected and fixed to the top of the steel pipe assembly through the bolt connection holes.

[0013] Preferably, a plurality of reinforcing plates are provided between the top of the square flange and the outer peripheral wall of the lower box body, and the plurality of reinforcing plates are distributed at equal intervals around the outer peripheral wall of the lower box body; this improves the strength between the square flange and the lower box body, and makes the supporting force more stable during construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a structural schematic diagram of a large steel pipe support device of the utility model.

[0015] Figure 2 It is a schematic diagram of the steel pipe structure of the utility model.

[0016] Figure 3 It is a schematic diagram of the main structure of the sandbox unloading device of the utility model.

[0017] Figure 4 It is a schematic diagram of the main cross-sectional structure of the sandbox unloading device of the utility model.

[0018] Figure 5 It is a schematic diagram of the installation structure of the sand box unloading device of the utility model and the top end of the large steel pipe support.

[0019] The numbers in the accompanying drawings are: 1. Sand box unloading device; 2. Steel pipe assembly; 3. Circular flange; 4. Bracket foundation; 5. Foundation; 6. Bottom template; 7. Steel pipe; 11. Upper box body; 12. Lower box body; 13. Square supporting steel plate; 14. Square flange; 15. Limiting hole; 16. Bolt assembly; 17. Sand inlet; 18. Sand outlet; 19. Sealing bolt; 20. Circular limiting block; 21. Bolt connection hole; 22. Reinforcement plate; 41. Iron plate; 42. Foundation steel pipe. DETAILED DESCRIPTION

[0020] The following is a detailed introduction to the utility model in conjunction with the accompanying drawings: Figures 1 to 5 As shown, the utility model includes a steel pipe assembly 2 and a sand box unloading device 1. Circular flanges 3 are provided on both upper and lower end surfaces of the steel pipe assembly 2. The lower end of the steel pipe assembly 2 is installed and fixed to a bracket base 4 arranged on a foundation 5 through the circular flange 3. The upper end of the steel pipe assembly 2 is installed with a sand box unloading device 1. The sand box unloading device 1 is against a bottom formwork 6 used for casting a cap beam.

[0021] The steel pipe assembly 2 includes a plurality of steel pipes 7, each of which is provided with a circular flange 3 on both upper and lower ends, and adjacent steel pipes 7 are fixed by the circular flange 3 and bolts; a plurality of reinforcing plates 22 are welded between the circular flange 3 and the outer peripheral wall of the steel pipe 7. The steel pipe 7 can be made into standard models such as 1 meter, 2 meters, 3 meters, and 6 meters, and the height of the combination is more flexible and changeable, and the construction is more standardized.

[0022] The bracket foundation 4 includes an iron plate 41 and a foundation steel pipe 42 pre-buried in the foundation 5. Circular flanges 3 are provided on both upper and lower end surfaces of the foundation steel pipe 42. The foundation steel pipe 42 is fixed in the iron plate 41 by means of anchor bolts passing through bolt holes in the circular flange 3. The upper end of the foundation steel pipe 42 is connected to the lower end of the steel pipe 7. A number of reinforcing plates 22 are welded between the circular flange 3 and the outer peripheral wall of the foundation steel pipe 42.

[0023] The sand box unloading device 1 includes an upper box body 11 and a lower box body 12, and is characterized in that: sand is placed in the lower box body 12, the upper box body 11 is sleeved in the lower box body 12, and the upper box body 11 is placed on the upper plane of the sand pile formed by stacking sand; the upper top surface of the upper box body 1 is provided with a square supporting steel plate 13, and the lower bottom surface of the lower box body 12 is provided with a square flange 14, and the four end corners of the square supporting steel plate 13 and the square flange 14 are provided with limiting holes 15, and the limiting holes 15 of the square supporting steel plate 13 and the limiting holes 15 of the square flange 14 are interlaced and fixed by bolt assemblies 16, so that the upper box body 11 and the lower box body 12 are limited and fixed.

[0024] The upper box body 11 and the lower box body 12 are both cylindrical, and the outer diameter of the upper box body 11 is smaller than the inner diameter of the lower box body 12 . The upper box body 11 is sleeved in the lower box body 12 .

[0025] A sand inlet 17 and a sand outlet 18 are provided on the box wall of the lower box body 12. The sand inlet 17 is located at the upper end of the box wall of the lower box body 12, and the sand outlet 18 is located at the lower end of the box wall of the lower box body 12. The sand inlet 17 and the sand outlet 18 are relatively distributed, and sealing bolts 19 are connected to the sand inlet 17 and the sand outlet 18.

[0026] A circular ring-shaped limit block 20 is provided below the square flange 14. When the sandbox unloading device is installed on the top of the steel pipe assembly, the circular ring-shaped limit block 20 is embedded in the top of the steel pipe assembly.

[0027] The square flange 14 is provided with a plurality of bolt connection holes 21 , and the bolt connection holes 21 are distributed at equal intervals around the outer wall of the annular limiting block 20 .

[0028] A plurality of reinforcing plates 22 are disposed between the upper portion of the square flange 14 and the outer peripheral wall of the lower box body 12 . The plurality of reinforcing plates 22 are distributed around the outer peripheral wall of the lower box body 12 at equal intervals.

[0029] The utility model connects standard steel pipes 7 of various modulus heights and a sandbox unloading device 1 through bolt flanges. It is easy to install and has adjustable height. The use process is: process various types of standard length steel pipes 7 → construct the support foundation 4 → match various types of steel pipes 7 and sandbox unloading devices 1 according to the designed height of the support → install the support → erect the bottom formwork 6 of the cap beam → cast and maintain the cap beam → unload the support to complete the construction. This large steel pipe support device with a built-in unloading device has a simple and easy operation process, can quickly assemble supports of different design heights, greatly improves construction efficiency, improves construction safety and construction quality, does not require on-site cutting and welding of large steel pipes, is environmentally friendly, and saves costs.

[0030] The present invention is not limited to the above-mentioned embodiments. Regardless of any changes in shape or material composition, any structural design provided by the present invention is a variation of the present invention and should be considered within the protection scope of the present invention.

Claims

1. A large steel pipe support device with a built-in unloading device, comprising a steel pipe assembly (2) and a sandbox unloading device (1), characterized in that: The upper and lower end surfaces of the steel pipe assembly (2) are both provided with circular flanges (3), the lower end of the steel pipe assembly (2) is mounted and fixed to a support base (4) provided on a foundation (5) via the circular flange (3), the upper end of the steel pipe assembly (2) is provided with the sand box unloading device (1), and the sand box unloading device (1) is against a bottom formwork (6) used for casting a cap beam.

2. The large steel pipe support device with a self-contained unloading device according to claim 1 is characterized in that: The steel pipe assembly (2) comprises a plurality of steel pipes (7), each of the upper and lower end surfaces of the steel pipe (7) being provided with circular flanges (3), and adjacent steel pipes (7) being connected via the circular flanges (3) and fixed with bolts; and a plurality of reinforcing plates (22) being welded between the circular flanges (3) and the outer peripheral walls of the steel pipes (7).

3. The large steel pipe support device with a self-contained unloading device according to claim 2 is characterized in that: The support foundation (4) comprises an iron plate (41) and a foundation steel pipe (42) pre-buried in the foundation (5); circular flanges (3) are provided on both upper and lower end surfaces of the foundation steel pipe (42); the foundation steel pipe (42) is fixed in the iron plate (41) by anchor bolts passing through bolt holes in the circular flange (3); the upper end of the foundation steel pipe (42) is connected to the lower end of the steel pipe (7); and a plurality of reinforcing plates (22) are welded between the circular flange (3) and the outer peripheral wall of the foundation steel pipe (42).

4. The large steel pipe support device with a self-contained unloading device according to claim 1 is characterized in that: The sand box unloading device (1) comprises an upper box body (11) and a lower box body (12), wherein sand is placed in the lower box body (12), the upper box body (11) is sleeved in the lower box body (12), and the upper box body (11) is placed on the upper plane of a pile of sand formed by stacking sand; the upper top surface of the upper box body (11) is provided with a square supporting steel plate (13), and the lower bottom surface of the lower box body (12) is provided with a square flange (14), and the four end corners of the square supporting steel plate (13) and the square flange (14) are provided with limiting holes (15), and the limiting holes (15) of the square supporting steel plate (13) and the limiting holes (15) of the square flange (14) are inserted and fixed by bolt assemblies (16), so that the upper box body (11) and the lower box body (12) are limited and fixed.

5. The large steel pipe support device with a self-contained unloading device according to claim 4 is characterized in that: The upper box body (11) and the lower box body (12) are both cylindrical, and the outer diameter of the upper box body (11) is smaller than the inner diameter of the lower box body (12). The upper box body (11) is sleeved in the box body of the lower box body (12).

6. The large steel pipe support device with a self-unloading device according to claim 4 or 5, characterized in that: The box wall of the lower box body (12) is provided with a sand inlet (17) and a sand outlet (18), the sand inlet (17) is located at the upper end of the box wall of the lower box body (12), the sand outlet (18) is located at the lower end of the box wall of the lower box body (12), and the sand inlet (17) and the sand outlet (18) are relatively distributed, and the sand inlet (17) and the sand outlet (18) are both connected with sealing bolts (19).

7. The large steel pipe support device with a self-contained unloading device according to claim 4 is characterized in that: A circular ring-shaped limit block (20) is provided below the square flange (14). When the sandbox unloading device is installed on the top of the steel pipe assembly, the circular ring-shaped limit block (20) is embedded in the top of the steel pipe assembly.

8. The large steel pipe support device with a self-contained unloading device according to claim 7 is characterized in that: The square flange (14) is provided with a plurality of bolt connection holes (21), and the bolt connection holes (21) are distributed at equal intervals around the outer wall of the annular limiting block (20).

9. The large steel pipe support device with a self-contained unloading device according to claim 4, characterized in that: A plurality of reinforcing plates (22) are arranged between the upper portion of the square flange (14) and the outer peripheral wall of the lower box body (12), and the plurality of reinforcing plates (22) are distributed at equal intervals around the outer peripheral wall of the lower box body (12).