Mounting structure of bridge spanning steel box girder

By designing the installation structure of the bridge spanning the steel box girder, using support frames, tracks and thrust mechanisms, the problem of high-voltage lines being too close to the construction surface is solved, construction safety and efficient utilization of resources are achieved, and the precise installation and construction of steel box girders are ensured. schedule.

CN221972107UActive Publication Date: 2024-11-08CCCC (FUZHOU) CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420271066.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-04
Publication Date
2024-11-08
Estimated Expiration
2034-02-04

AI Technical Summary

Technical Problem

During the bridge construction process, the problem of the high-voltage line being too close to the construction surface leads to a complex construction environment and high safety risks, which cannot be effectively solved by the existing technology.

Method used

A bridge spanning steel box girder is designed, including a parallel support frame, track, skid truck and thrust mechanism. The steel box girder is driven from the outside of the high-voltage line to move below to ensure that Construction safety.

Benefits of technology

On the premise of ensuring construction safety, the problem of high-voltage lines being too close to the construction surface is solved, the traffic pressure on the construction site is alleviated, resource waste is avoided, and the precise positioning and efficient installation of steel box girders are achieved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221972107U_ABST
    Figure CN221972107U_ABST
Patent Text Reader

Abstract

The utility model relates to a mounting structure for a bridge to span a steel box girder, which is characterized by comprising piers used for supporting the steel box girder in a highway bridge, and a plurality of groups of support frames longer than the piers are arranged between two adjacent piers in parallel. Two parallel rails are laid on the outer side, located in the length direction of the pier, of the supporting frame, a sliding trolley is arranged between the bottom face of the steel box girder to be moved to the pier and the rails, and a pushing mechanism for driving the steel box girder to move from the outside of the high-voltage line to the pier located below the high-voltage line is further arranged between the bottom face of the steel box girder and the rails. According to the installation structure of the bridge spanning steel box girder, on the premise that construction safety is guaranteed, the problem that a high-voltage line is too close to a construction face due to the fact that the high-voltage line is not moved and changed by a related department is solved, and traffic pressure outside a construction site is relieved; and the idling phenomenon of a construction site is avoided, and waste of resources such as equipment and manpower is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical field:

[0002] The utility model relates to an installation structure for a bridge spanning a steel box girder. Background technology:

[0004] With the rapid development of highway bridge construction, construction technology has also encountered more and more challenges. When the bridge crosses an existing level crossing, a steel box girder design is often used, that is, prefabricated steel box girders are lifted onto the bridge piers by a crane to minimize the impact of cross-road construction on existing traffic.

[0005] However, with the continuous development of urbanization, 110KVA high-voltage lines are often found at intersections, causing the steel box girder installation environment to cross the existing traffic arteries while also passing under the high-voltage lines. Not only must it meet the traffic clearance requirements, but it must also meet the safe distance between the construction and the high-voltage lines. The working environment is more complex and the safety risks are higher.

[0006] Currently, Chinese patent CN114319067A has been retrieved, which is a large-section steel box girder and a construction method thereof. The invention scheme includes the following construction steps: step one, construction preparation; step two, transportation of steel box girder segments; step three, pre-assembly of steel box girder; step four, installation of steel box girder; step five, welding of steel box girder; step six, painting of steel box girder until the construction is completed. Although the invention has the advantages of high construction efficiency, low lifting difficulty, and prevention of deformation of steel box girder; it cannot solve the problem that the relevant departments have not relocated the high-voltage lines, resulting in the high-voltage lines being too close to the construction surface. Summary of the invention:

[0008] In order to overcome the difficulties in steel box girder construction under the above-mentioned complex working environment, the purpose of the utility model is to provide an installation structure for a bridge spanning a steel box girder. The installation structure for a bridge spanning a steel box girder is reasonably designed, which solves the problem that the relevant departments have not relocated the high-voltage lines, resulting in the high-voltage lines being too close to the construction surface.

[0009] The technical solution of the utility model is as follows:

[0010] The utility model is an installation structure for a steel box girder across a bridge, and is characterized in that it includes piers for supporting the steel box girder in a highway bridge, a plurality of groups of support frames longer than the piers are arranged in parallel between two adjacent piers, two parallel tracks are laid on the support frames on the outer sides in the length direction of the piers, a sliding vehicle is arranged between the bottom surface of the steel box girder to be moved to the piers and the track, and a pushing mechanism is also arranged between the bottom surface of the steel box girder and the track for driving the steel box girder to move from outside the high-voltage line to the pier located below the high-voltage line.

[0011] Preferably, the pushing mechanism comprises a hydraulic clamp capable of clamping on the rail and a push jack having a first end connected to the hydraulic clamp, and a second end of the push jack being connected to the bottom surface of the steel box girder.

[0012] Preferably, the hydraulic clamp has two working states: clamping the rail and releasing the clamping of the rail, and the push jack has two working states: extending and shortening.

[0013] Preferably, the first end of the push jack is rotatably hinged to the hydraulic clamp, the bottom surface of the steel box girder is provided with a downward convex mounting block, and the second end of the push jack is connected to the downward convex mounting block.

[0014] Preferably, the above-mentioned sliding vehicle includes a steel pipe connected to the bottom surface of the steel box beam and a cover shell connected to the steel pipe, a support bar and a rolling chain wound around the support bar and capable of rolling on a track are fixedly installed in the cover shell, the rolling chain includes a chain frame and a plurality of rollers arranged in the chain frame, and the lower end of each roller located below the support bar abuts against the track surface.

[0015] Preferably, the support frame includes an expanded foundation, a steel pipe bracket, a crossbeam and a sliding track beam. The expanded foundation is a concrete expanded foundation cast on the ground, the steel pipe bracket is arranged above the expanded foundation, the crossbeam is supported on multiple groups of steel pipe brackets, the sliding track beam is made of double-pieced HN700×300×13×24H steel, and the track is a P50 steel rail and is arranged on the sliding track beam.

[0016] The installation structure of the bridge spanning the steel box girder of the utility model can, under the premise of ensuring construction safety, solve the problem that the high-voltage lines are too close to the construction surface due to the failure of relevant departments to relocate them, and also ease the traffic pressure outside the construction site; avoid idle work at the construction site and avoid the waste of equipment, manpower and other resources. Description of the drawings:

[0018] The utility model is further described below in conjunction with the accompanying drawings;

[0019] Figure 1 It is the front view of the utility model;

[0020] Figure 2 yes Figure 1 A top view of

[0021] Figure 3 yes Figure 1 A partial view of

[0022] Figure 4 is a cross-sectional view of the support frame (i.e. Figure 2 AA section view);

[0023] Figure 5 It is a schematic diagram of the connection structure of the push mechanism;

[0024] Figure 6It is a schematic diagram of the connection section structure of the skid steer;

[0025] Figure 7 yes Figure 6 Side view of. Specific implementation method:

[0027] The utility model is further described below in conjunction with the accompanying drawings and specific implementation methods.

[0028] The utility model bridge spans the installation structure of the steel box girder, including the pier 2 for supporting the steel box girder 1 in the highway bridge. The steel box girder 1 is pre-made by the project and pre-hoisted to the track far away from the bottom of the high-voltage line before installation. The pier 2 is designed by the company and needs to be constructed.

[0029] Several groups of support frames 3 are arranged in parallel between two adjacent piers 2. The support frames 3 are longer than the piers. Two parallel tracks 4 are laid on the outer sides of the support frames 3 in the length direction of the piers. The distance between the two tracks 4 is greater than the length of the piers (e.g. Figure 1 portrait orientation shown).

[0030] A sliding vehicle 5 is provided between the bottom surface of the steel box girder 1 to be moved to the bridge pier and the track 4, and there are multiple sliding vehicles 5 on each track. A pushing mechanism 7 for driving the steel box girder to move from outside the high-voltage line 6 to the bridge pier located below the high-voltage line is also provided between the bottom surface of the steel box girder and the track, and the pushing mechanism 7 also has multiple groups.

[0031] For construction safety, a fence 8 is provided on the outer side of the support frame 3 .

[0032] The pushing mechanism 7 can be a pulling mechanism pulled by a winch through a cable, or a thrust mechanism with thrust that can move on a track.

[0033] Specifically, the pushing mechanism 7 of the present application includes a hydraulic clamp 701 that can be clamped on the rail and a push jack 702 whose first end is connected to the hydraulic clamp, the hydraulic clamp 701 is a hydraulic caliper (which can be a hydraulic caliper or a hydraulic crimping pliers produced by Taizhou Sitong Machinery Factory), and the second end of the push jack 702 is connected to the bottom surface of the steel box girder 1; the hydraulic clamp 701 has two working states of clamping the rail and releasing the clamping of the rail, and the push jack 702 has two working states of extension and shortening; the first end of the push jack 702 is rotatably hinged with the hydraulic clamp 701, the bottom surface of the steel box girder is provided with a downward convex mounting block 703, and the second end of the push jack is connected to the downward convex mounting block.

[0034] The specific working method of the pushing mechanism 7 to drive the steel box girder to move along the track 4 is: the hydraulic clamp 701 is clamped on the track as a reaction point, the telescopic rod of the push jack 702 is extended, and the push lower convex mounting block 703 and the steel box girder 1 move forward; when the telescopic rod of the push jack 702 has completed its travel, the hydraulic clamp 701 releases its clamping of the track, the telescopic rod of the push jack 702 shrinks during its return stroke, and the hydraulic clamp 701 moves forward with the return stroke of the jack. When the push jack 702 returns to its position, the hydraulic clamp 701 clamps the track again and the push jack 702 continues to push, and so on and so forth, finally completing the pushing of the steel box girder along the track to the designed position.

[0035] The above-mentioned sliding vehicle 5 plays a role in supporting the weight of the steel box girder and is conducive to the smooth movement of the steel box girder on the track.

[0036] Specifically, the above-mentioned sliding vehicle 5 includes a steel pipe 501 connected to the bottom surface of the steel box beam and a cover shell 502 connected to the steel pipe. The height size of the steel pipe 501 is adjusted according to the different positions of the steel box beam. A support bar 503 and a rolling chain 504 wound around the support bar and capable of rolling on the track are fixedly installed in the cover shell 502 (the rolling chain can be a 08BS series single-speed chain produced by Jinhua Huiding Chain Co., Ltd.). The rolling chain includes a chain frame 505 and a plurality of rollers 506 arranged in the chain frame. The lower ends of the rollers 506 located below the support bar abut against the surface of the track 4. When in use, as the steel box beam is pushed and moved along the track 4 by the pushing mechanism 7, the rolling chain 504 rolls around the support bar 503 on the track and plays a role in supporting the steel box beam. The rolling chain 504 plays a role in reducing the travel resistance of the steel box beam.

[0037] In order to achieve a good supporting effect, the support frame 3 includes an enlarged foundation 301, a steel pipe support 302, a crossbeam 303 and a sliding track beam 304 from bottom to top. The enlarged foundation 301 adopts a concrete enlarged foundation cast on the ground, the steel pipe support 302 is arranged above the enlarged foundation, the crossbeam 303 is supported on multiple groups of side-by-side steel pipe supports 302, the sliding track beam 304 adopts double-pieced HN700×300×13×24H steel, and the track adopts P50 steel rail and is arranged on the sliding track beam.

[0038] The specific construction steps of the installation structure of the bridge spanning the steel box girder in this application are described in detail below:

[0039] S1: Measurement and setting out: Measure and set out the elevation of the beam 303. According to the design elevation of the steel box beam, weld the adjustable steel pipe on the beam as a temporary support for the steel box beam segment;

[0040] S2: Segment hoisting: Use a truck crane to hoist the steel box girder segments onto the adjustment steel pipes one by one. After all the transverse segments are hoisted, weld the segments into a whole to form a steel box girder;

[0041] S3: Weld inspection: Since the steel box girder is located under the high-voltage line after sliding into place, the weld cannot be repaired. The weld inspection must be completed before sliding to ensure the weld quality is qualified;

[0042] S4: Install the sliding vehicle: Install the sliding vehicle on the track, and install the steel pipe 501 on the sliding vehicle 5. The steel pipe 501 is welded to the bottom surface of the steel box beam 1 and the cover 502 to ensure that the steel box beam does not move relative to each other during the sliding process. Thus, the first load-bearing support system conversion is completed;

[0043] S5: Sliding construction: Cut off the adjusting steel pipe of the temporary support of the steel box beam segment, weld the convex mounting block 703 at the bottom of the steel beam, install the top push jack 702 and weld it to the convex mounting block, use the controller to control the sliding process, ensure that the push mechanism 7 on the tracks on both sides slide synchronously, and a special person should be assigned to check the push mechanism during the sliding process;

[0044] S6: Removal of the pushing mechanism: After the steel box girder is slid into place, re-measure the elevation, axis deviation and other data. After all the data indicators are qualified, set the support tube on the beam 303, weld and fix the support tube to the beam, and connect the top to the steel box girder without leaving any gap. After completing the second load support system conversion, remove the pushing mechanism.

[0045] The utility model solves the problem of successfully completing the installation of steel box girders that cross traffic trunk lines and pass under high-voltage lines under the condition that the high-voltage lines have not been relocated. This technology does not block traffic during the construction process, alleviates surrounding traffic pressure, and greatly reduces the impact of construction on society. In addition, the construction environment is safe and the quality is controllable. The steel box girder is accurately positioned after sliding, which effectively guarantees the progress of the project.

[0046] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail with reference to the preferred embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the utility model can still be modified or some technical features can be replaced by equivalents without departing from the spirit of the technical solution of the utility model, which should be included in the scope of the technical solution for protection of the utility model.

Claims

1. An installation structure for a bridge spanning a steel box girder, Features: It includes piers for supporting steel box girders in highway bridges, and several groups of support frames longer than the piers are arranged in parallel between two adjacent piers. Two parallel tracks are laid on the outer sides of the support frames in the length direction of the piers, and a sliding vehicle is arranged between the bottom surface of the steel box girder to be moved to the piers and the track. A pushing mechanism is also arranged between the bottom surface of the steel box girder and the track to drive the steel box girder to move from outside the high-voltage line to the pier located below the high-voltage line.

2. The installation structure of the bridge spanning steel box girder according to claim 1, Features: The pushing mechanism comprises a hydraulic clamp capable of clamping on the track and a push jack whose first end is connected to the hydraulic clamp, and a second end of the push jack is connected to the bottom surface of the steel box beam.

3. The installation structure of the bridge spanning steel box girder according to claim 2, Features: The hydraulic clamp has two working states of clamping the rail and releasing the clamping of the rail, and the push jack has two working states of extending and shortening.

4. The installation structure of the bridge spanning steel box girder according to claim 2, Features: The first end of the push jack is rotatably hinged with the hydraulic clamp, the bottom surface of the steel box beam is provided with a downward convex mounting block, and the second end of the push jack is connected with the downward convex mounting block.

5. The installation structure of the bridge spanning steel box girder according to claim 1, Features: The sliding vehicle includes a steel pipe connected to the bottom surface of the steel box beam and a cover shell connected to the steel pipe, a support bar and a rolling chain wound around the support bar and capable of rolling on a track are fixedly installed in the cover shell, the rolling chain includes a chain frame and a plurality of rollers arranged in the chain frame, and the lower end of each roller located below the support bar abuts against the track surface.

6. The installation structure of the bridge spanning steel box girder according to claim 1, Features: The support frame includes an expanded foundation, a steel pipe support, a crossbeam and a sliding track beam. The expanded foundation adopts a concrete expanded foundation cast on the ground. The steel pipe support is arranged above the expanded foundation. The crossbeam is supported on multiple groups of steel pipe supports. The sliding track beam adopts double-pieced HN700×300×13×24H steel. The track adopts P50 steel rail and is arranged on the sliding track beam.