Civil air defense facility
By setting up pipeline mezzanine and seismic isolation structures in the civil defense facilities, the problems of building main body drop and material waste caused by soil cladding thickness in the civil defense basement are solved, and the structural safety is improved and energy-saving and material-saving effects are achieved, while facilitating pipeline equipment Overhaul and maintenance.
Patent Information
- Application Number
- CN202323595741.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-27
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2033-12-27
Smart Images

Figure CN221973167U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of civil air defense facilities, and in particular to a civil air defense facility. Background Art
[0002] Civil defense basements are a type of civil defense facility, which include outer walls, buffer walls, explosion-proof doors, enclosed walls, protective partition walls and other parts. They are mainly used as temporary shelters for civil air defense, wartime air defense command centers, communication centers, shelters, etc.
[0003] The existing urban civil air defense basements are covered with a soil layer. The civil air defense basements located under some building main bodies will pass through the soil layer and be directly connected to the building main body. Since there are design requirements for the thickness of the soil layer on the civil air defense basements, the floor slabs of the building main body will drop below the height of the outdoor floor. At this time, filling materials are required to be higher than the outdoor floor, resulting in a waste of energy and materials. Utility Model Content
[0004] In order to solve the above technical problems, the present application provides a civil air defense facility.
[0005] In the first aspect, the present application provides a civil defense facility, including a civil defense space, a covering layer and a building body, wherein the civil defense space is arranged below the covering layer, and the building body passes through the covering layer and is connected with the civil defense space. The facility also includes a pipeline interlayer, which is arranged between the building body and the civil defense space. The top of the pipeline interlayer is connected with the building body and is used to accommodate the pipeline equipment of the building body.
[0006] Optionally, the bottom of the pipeline interlayer is flush with the top of the civil air defense space.
[0007] Optionally, the top of the pipeline interlayer is higher than the top of the covering layer.
[0008] Optionally, the height of the covering layer is 600mm-3000mm, and the height of the pipeline interlayer is 1600mm-3000mm.
[0009] Optionally, the height of the covering layer is 1800 mm, and the height of the pipeline interlayer is 2100 mm.
[0010] Optionally, a first connecting port and a second connecting port are respectively provided at the top and the bottom of the pipeline interlayer, and stairs are provided at the first connecting port and the second connecting port.
[0011] Optionally, the first communication port is arranged opposite to the second communication port.
[0012] Optionally, the pipeline interlayer is provided with a plurality of first pipeline openings communicating with the covering layer and a plurality of second pipeline openings communicating with the building body.
[0013] Optionally, part of the covering soil layer is used for laying pipeline equipment.
[0014] Optionally, it further comprises a plurality of support columns for supporting the pipeline interlayer, and a seismic isolation structure is provided at the middle portion of each support column.
[0015] Optionally, a first buffer gap is left between the support column and a partition plate on the peripheral side of the pipeline interlayer for connecting to the covering layer.
[0016] Optionally, a second buffer gap is left between the building body and the top of the partition plate on the peripheral side of the pipeline interlayer for connecting to the covering layer.
[0017] Compared with the prior art, the technical solution provided by the embodiments of the present application has the following advantages:
[0018] The civil air defense facilities provided in the present application can, through the setting of pipeline mezzanines, add a buffer layer between the building main body and the civil air defense space, and can also fill the connection between the civil air defense space and the building main body, thereby reducing the filling material of the civil air defense space here, reducing the height of the civil air defense space while saving energy and materials. Such a setting can also increase the structural safety of the civil air defense project; and the staff can realize the inspection and maintenance of the pipeline equipment of the building main body in the pipeline mezzanine, which also provides convenience for the maintenance of the pipeline equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and, together with the description, serve to explain the principles of the present application.
[0020] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.
[0021] Figure 1 This is a schematic diagram of the structure of the civil air defense facilities described in an embodiment of the present application.
[0022] Among them, 1. Civil defense space; 2. Covering layer; 3. Building main body; 4. Pipeline mezzanine; 41. First connecting port; 42. Second connecting port; 43. First pipe opening; 44. Second pipe opening; 5. Support column; 61. Seismic isolation structure; 621. First buffer gap; 622. Second buffer gap. DETAILED DESCRIPTION
[0023] In order to more clearly understand the above-mentioned purposes, features and advantages of the present application, the scheme of the present application will be further described below. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.
[0024] In the following description, many specific details are set forth to facilitate a full understanding of the present application, but the present application may also be implemented in other ways different from those described herein; obviously, the embodiments in the specification are only part of the embodiments of the present application, rather than all of the embodiments.
[0025] Civil defense basements are a type of civil defense facility, which include outer walls, buffer walls, explosion-proof doors, enclosed walls, protective partition walls and other parts. They are mainly used as temporary shelters for civil air defense, wartime air defense command centers, communication centers, shelters, etc.
[0026] Existing urban civil air defense facilities often pass through some building entities. The bottom of the existing building entities is directly connected to the top of the civil air defense basement. Since there are design requirements for the thickness of the covering soil layer on the civil air defense basement, an empty groove will be formed in the civil air defense basement relative to the building entity, which will increase the height of the civil air defense and waste energy and materials.
[0027] Based on this, this embodiment provides a civil air defense facility. Through the setting of the pipeline interlayer, it can add a buffer layer between the building body and the civil air defense space, and can also fill the connection between the civil air defense space and the building body, reducing the filling material of the civil air defense space here, reducing the height of the civil air defense space, and saving energy and materials. Such a setting can also increase the structural safety of the civil air defense project; and the staff can realize the maintenance of the pipeline equipment of the building body in the pipeline interlayer, which also provides convenience for the maintenance of the pipeline equipment. The following is a detailed description of it through specific embodiments:
[0028] Reference Figure 1 As shown, a civil defense facility provided in this embodiment includes a civil defense space 1, a covering layer 2 and a building body 3. The civil defense space 1 is arranged below the covering layer 2. The building body 3 passes through the covering layer 2 and is connected with the civil defense space 1. It also includes a pipeline interlayer 4. The pipeline interlayer 4 is arranged between the building body 3 and the civil defense space 1. The top of the pipeline interlayer 4 is connected with the building body 3 and is used to accommodate the pipeline equipment of the building body 3. It should be understood that the pipeline equipment includes water supply and drainage pipes, cable pipes, heating pipes, etc.
[0029] The civil defense facilities provided in this embodiment can, through the setting of the pipeline interlayer 4, add a buffer layer between the building body 3 and the civil defense space 1, and can also fill the connection between the civil defense space 1 and the building body 3, thereby reducing the filling material of the civil defense space 1 here. The filling material specifically refers to the materials such as steel bars, concrete, steel frames or wooden frames used to fill the space where the pipeline interlayer 4 is located. While reducing the height of the civil defense space 1, energy and material saving are utilized. Such a setting can also increase the structural safety of the civil defense project; and the staff can realize the inspection and maintenance of the pipeline equipment of the building body 3 in the pipeline interlayer 4, which also provides convenience for the maintenance of the pipeline equipment.
[0030] In some embodiments, the bottom of the pipeline interlayer 4 is flush with the top of the civil defense space 1; such a setting can prevent the entire civil defense space 1 from being affected by the building main body 3, maintain its overall height consistency, and at the same time ensure the design requirements of the civil defense space 1.
[0031] Continue to refer to Figure 1 As shown, the top of the pipeline interlayer 4 is higher than the top of the covering layer 2; such an arrangement can erect the pipeline interlayer 4 while ensuring that the floor height of the building body 3 is higher than the external ground.
[0032] In some embodiments, the height of the covering layer 2 is 600mm-3000mm, and the height of the pipeline interlayer 4 is 1600mm-3000mm; in a further embodiment, the height of the covering layer 2 is 1800mm, and the height of the pipeline interlayer 4 is 2100mm; it should be understood that the bottom of the covering layer 2 can be at the same height as the bottom of the pipeline interlayer 4.
[0033] In some embodiments, a first connecting port 41 and a second connecting port 42 are respectively provided at the top and the bottom of the pipeline interlayer 4, and stairs are provided at the first connecting port 41 and the second connecting port 42. The stairs can specifically be structures such as ladders or steps, as long as they can facilitate the passage of people; through the setting of the first connecting port 41, it is convenient for staff to enter the pipeline interlayer 4 from the building main body 3 to carry out maintenance work, and through the setting of the second connecting port 42, an entrance and exit to the civil defense space 1 can be formed at the pipeline interlayer 4. It should be understood that a structurally reliable isolation door is provided at the position of the second connecting port 42 to ensure that the civil defense space 1 can be isolated from the outside world.
[0034] In a further embodiment, the first connecting port 41 is arranged opposite to the second connecting port 42. The first connecting port 41 can also be staggered with the second connecting port 42. It can be specifically designed according to the structural arrangement in the pipeline interlayer 4. When the first connecting port 41 is arranged opposite to the second connecting port 42, it will be more convenient for personnel to enter and exit from the building main body 3 to the civil defense space 1, and the reaction speed will be faster.
[0035] Continue to refer to Figure 1 As shown, the pipeline interlayer 4 is provided with a plurality of first pipeline openings 43 connected to the covering layer 2 and a plurality of second pipeline openings 44 connected to the building body 3; in some embodiments, part of the covering layer 2 is used for laying pipeline equipment; such a configuration enables the building body 3 to be connected to the surrounding pipelines by means of the pipeline interlayer 4, and the laying of the surrounding pipeline equipment does not need to bypass the building body 3, which can significantly reduce the difficulty of laying the surrounding pipelines.
[0036] Continue to refer to Figure 1 As shown, the civil air defense facility also includes a plurality of support columns 5 for supporting the pipeline interlayer 4, and a seismic isolation structure 61 is provided in the middle portion of each support column 5; it should be understood that the top and the bottom of the support column 5 are respectively connected to the top plate and the floor of the pipeline interlayer 4, and the seismic isolation structure 61 is arranged in the middle portion of the support column 5, so that each support column 5 can form a buffering effect in the direction of gravity, thereby reducing the vibration transmitted from the building main body 3 to the civil air defense space 1 or reducing the vibration transmitted from the civil air defense space 1 to the building main body 3; wherein, the seismic isolation structure 61 can be a buffer pad, a buffer bracket or other structures that can form a shock absorbing effect along the extension direction of the support column 5; at this time, the pipeline interlayer 4 can be used as a seismic isolation layer to reduce the impact of earthquakes and other conditions on the civil air defense space 1.
[0037] In some embodiments, a first buffer gap 621 is left between the support column 5 and the partition 45 on the side of the pipeline interlayer 4 for connecting the covering layer 2; this arrangement can prevent the support column 5 and the partition 45 from colliding when a large vibration occurs, and there is a movable gap between the two, thereby better protecting the structural integrity of the pipeline interlayer 4 and the civil defense space 1.
[0038] In a further embodiment, a second buffer gap 622 is left between the top of the partition 45 for connecting the covering layer 2 on the surrounding side of the building body 3 and the pipeline interlayer 4; by setting the second buffer gap 622, it is possible to avoid collision between the floor of the building body 3 and the partition 45 of the pipeline interlayer 4 when a large vibration occurs, and a movable gap is provided between the two, thereby better protecting the structural integrity of the pipeline interlayer 4 and the building body 3.
[0039] The specific implementation method and implementation principle are the same as those in the above embodiment, and can bring the same or similar technical effects, which will not be elaborated here one by one. For details, please refer to the description of the above civil defense facility embodiment.
[0040] It should be noted that, in this article, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0041] The above description is only a specific implementation of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments described herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A civil air defense facility, comprising a civil air defense space (1), a soil covering layer (2) and a building main body (3), wherein the civil air defense space (1) is arranged below the soil covering layer (2), and the building main body (3) passes through the soil covering layer (2) and is connected to the civil air defense space (1), characterized in that: It also includes a pipeline interlayer (4), which is arranged between the building body (3) and the civil air defense space (1), and the top of the pipeline interlayer (4) is connected to the building body (3) and is used to accommodate the pipeline equipment of the building body (3).
2. The civil air defense facility according to claim 1, characterized in that: The bottom of the pipeline interlayer (4) is flush with the top of the civil air defense space (1).
3. The civil air defense facility according to claim 2, characterized in that: The top of the pipeline interlayer (4) is higher than the top of the covering soil layer (2).
4. The civil air defense facility according to claim 3, characterized in that: The height of the soil covering layer (2) is 600 mm-3000 mm, and the height of the pipeline interlayer (4) is 1600 mm-3000 mm.
5. The civil air defense facility according to claim 4, characterized in that: The height of the covering soil layer (2) is 1800 mm, and the height of the pipeline interlayer (4) is 2100 mm.
6. The civil air defense facility according to claim 1, characterized in that: The top and bottom of the pipeline interlayer (4) are respectively provided with a first communication opening (41) and a second communication opening (42), and stairs are provided at the first communication opening (41) and the second communication opening (42).
7. The civil air defense facility according to any one of claims 1 to 6, characterized in that: The pipeline interlayer (4) is provided with a plurality of first pipeline openings (43) communicating with the covering layer (2) and a plurality of second pipeline openings (44) communicating with the building body (3).
8. The civil air defense facility according to any one of claims 1 to 6, characterized in that: It also comprises a plurality of support columns (5) for supporting the pipeline interlayer (4), and a seismic isolation structure (61) is provided at the middle portion of each support column (5).
9. The civil air defense facility according to claim 8, characterized in that: A first buffer gap (621) is left between the support column (5) and a partition (45) on the peripheral side of the pipeline interlayer (4) for connecting to the covering layer (2).
10. The civil air defense facility according to claim 9, characterized in that: A second buffer gap (622) is left between the building body (3) and the top of the partition (45) on the peripheral side of the pipeline interlayer (4) for connecting to the covering layer (2).