Plug structure for abandoned mine gas storage

By designing a round table-shaped plug and sealing layer system in the gas storage in the abandoned mine, and using prestressed anchors and chamfered structures, the problem of insufficient plug stability and sealing is solved, and the stability of the energy storage power station is improved. Reduced construction costs.

CN221973596UActive Publication Date: 2024-11-08XUZHOU ZHONGKUANG GEOTECHNICAL TECH CO LTD
View PDF 0 Cites 4 Cited by

Patent Information

Application Number
CN202420037018.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-08
Publication Date
2024-11-08
Estimated Expiration
2034-01-08

AI Technical Summary

Technical Problem

The prior art cannot meet the design of the plug head of the waste mine under 10MPa cycle pressure, resulting in insufficient stability and sealing of the plug head, which affects the stable operation of the energy storage power station.

Method used

The structure consists of a plug system and a sealing layer system. The plug system is round-shaped, embedded in the boundary rock and equipped with prestressed anchor rods arranged in annular direction. The sealing layer system is bonded to the inner wall of the tunnel and is equipped with a chamfered structure to enhance the Sealing and stability.

Benefits of technology

The load-bearing capacity and stability of the plug are improved, the material cost is reduced, and stress concentration is prevented through the chamfered structure, which enhances the sealing effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221973596U_ABST
    Figure CN221973596U_ABST
Patent Text Reader

Abstract

The utility model relates to a plug structure for an abandoned mine gas storage, which relates to the field of underground gas storage transformation and comprises a plug system and a sealing layer system. The plug system comprises a circular-truncated-cone-shaped plug; one end of the pre-stressed anchor rod is embedded into the surrounding rock, and the other end is embedded into the plug. A plurality of hollow structures are arranged in the plug; and the plurality of pre-stressed anchor rods are annularly arranged. And the sealing layer system is connected with the plug and is provided with a chamfering structure. The circular-truncated-cone-shaped plug is used for increasing the capacity that surrounding rock elastic resistance participates in resisting the internal pressure of the gas storage, the bearing capacity of the plug is improved, meanwhile, the pre-stressed anchor rod is arranged in the surrounding rock at the front end of the plug, a certain pre-tension force is provided, relative slippage of the plug and the surrounding rock is greatly reduced, and the overall stability is improved. The hollow structure in the plug reduces the material cost of the plug under the condition that the stability of the plug is not influenced. And a chamfer structure is formed between the front end of the plug and the inner wall of the roadway, so that the stress concentration phenomenon is reduced, and the stable work of a sealing layer is protected.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of underground gas storage reconstruction, and in particular to a plugging structure for abandoned mine gas storage. Background Art

[0002] Renewable energy generation is intermittent and volatile, and will have a serious impact on the stability of the power grid system when it is connected to the grid on a large scale. Compressed air energy storage can alleviate the impact of new energy on the power grid and ensure the stable operation of the power grid. However, the key to compressed air energy storage lies in the construction technology of the gas storage reservoir. At present, the more mature ones are ground gas storage tanks and salt cavern gas storage reservoirs. With the continuous development of large-scale energy storage technology and the limitations of ground space and construction costs, experts and scholars are actively exploring new energy storage spaces. Abandoned mines have the characteristics of stable structure, regular geometry, and large scale, which can be used as underground energy storage space. However, there are also goafs with developed fissures in abandoned mines. The core of the gas storage reservoir is sealing, so the goafs must be completely isolated from the mine tunnels, and the abandoned mine tunnels must be used for gas storage.

[0003] However, the existing technology cannot meet the requirements for the design of abandoned mine plugs under a circulating gas pressure of 10MPa. The stability and sealing of the plug directly affect the stable operation of the energy storage power station. Therefore, how to ensure the stability and sealing of the plug is crucial.

[0004] In the existing technology, there are few studies on underground gas storage plugs, most of which are centered around the sealing of gas, oil and gas. The applicability of directly applying them to high-pressure gas storage needs further verification. The existing plug structures are all large-volume concrete solid structures with a relatively simple structure, a large plug length and high construction cost. In addition, the existing public technologies have ignored the stress concentration that may occur at the junction of the front section of the plug and the mine, causing excessive deformation in the local area and resulting in sealing failure. Utility Model Content

[0005] Purpose of the utility model: to provide a plug structure for an abandoned mine gas storage reservoir to solve the above-mentioned problems existing in the prior art.

[0006] Technical solution: A plugging structure for abandoned mine gas storage, including two components: a plugging system and a sealing layer system. The plugging system includes a truncated cone-shaped plug with a predetermined operating size and supporting force; a prestressed anchor rod with a predetermined operating length, one end of which is embedded in the surrounding rock, and the other end of which is embedded in the plug. A plurality of hollow structures are provided inside the plug, and the prestressed anchor rods are in plurality and arranged in a circumferential direction. The sealing layer system is connected to the plug, and is in contact with the inner wall of the mine tunnel, and is provided with a corresponding chamfering structure, so that corresponding sealing reinforcement operations can be performed.

[0007] In a further embodiment, the front end of the plug is large and the rear end is small in the working direction, and the front and rear cross-sectional shapes in the working direction are concentric with the tunnel, and the rear end cross-sectional shape in the working direction is equal to the tunnel. A circular maintenance channel with a predetermined working length and working size is provided at the center of the plug, so that corresponding gas storage maintenance operations can be performed.

[0008] In a further embodiment, the sealing system includes two components: a sealing door and a sealing ring. The sealing door is located at the end position of the operation direction of the inspection channel, has a predetermined operation size, and is adapted to the operation size of the inspection channel, and can perform corresponding sealing operations. The sealing ring is placed at the contact position between the sealing door and the inspection channel, and is adapted to the operation size of the inspection channel. The chamfered structure is placed at the angle position between the contact surface of the plug and the sealing ring, and is arc-shaped; there are multiple chamfered structures.

[0009] In a further embodiment, the prestressed anchor rods have multiple circumferential layers, and the number of prestressed anchor rods in each layer is not less than ten; the prestressed anchor rods have a predetermined inclination angle, and the inclination angle and direction are parallel to the inclined surface of the plug.

[0010] In a further embodiment, the hollow structure is spherical and is placed inside the plug, and the hollow structure is provided inside the plug on both sides of the operating direction of the maintenance channel; a predetermined operating distance is left between the prestressed anchor rod and the hollow structure.

[0011] Beneficial effects: The utility model relates to a plug structure for an abandoned mine gas storage reservoir, and relates to the field of underground gas storage reservoir transformation, including a plug system and a sealing layer system. The plug system includes a truncated cone-shaped plug with a predetermined operating size and supporting force; a prestressed anchor rod with a predetermined operating length, one end of which is embedded in the surrounding rock, and the other end of which is embedded in the plug. A plurality of hollow structures are arranged inside the plug, and the prestressed anchor rods are multiple and arranged in a circumferential direction. The sealing layer system is connected to the plug, and is attached to the inner wall of the mine tunnel, and is provided with a corresponding chamfered structure, and corresponding sealing reinforcement operations can be performed. The present application utilizes a truncated cone-shaped plug to increase the ability of the surrounding rock elastic resistance to participate in resisting the internal pressure of the gas storage reservoir, thereby improving the bearing capacity of the plug. At the same time, a prestressed anchor rod is arranged in the surrounding rock at the front end of the plug to provide a certain pre-tension, which greatly reduces the relative slip between the plug and the surrounding rock, and improves the overall stability. The hollow structure provided in the plug reduces the material cost of the plug without affecting the stability of the plug. At the front end of the plug and the inner wall of the tunnel. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a schematic structural diagram of an implementation method of the present application.

[0013] Figure 2 It is a schematic diagram of some components in this application at any angle.

[0014] The reference numerals in the figures are: surrounding rock 1, tunnel 2, plug 3, prestressed anchor rod 4, sealing door 5, concrete 6, inspection passage 7, chamfer structure 8, hollow structure 9, sealing ring 10. DETAILED DESCRIPTION

[0015] In the following description, a large number of specific details are given to provide a more thorough understanding of the utility model. However, it is obvious to those skilled in the art that the utility model can be implemented without one or more of these details. In other examples, in order to avoid confusion with the utility model, some technical features known in the art are not described.

[0016] Embodiment 1:

[0017] The plugging structure for abandoned mine gas storage proposed in the embodiment includes two components: a plugging system and a sealing layer system. The plugging system includes a truncated cone-shaped plugging 3 with a predetermined operating size and supporting force; a prestressed anchor rod 4 with a predetermined operating length, one end of which is embedded in the surrounding rock 1 and the other end of which is embedded in the plugging 3. A plurality of hollow structures 9 are arranged inside the plugging 3, and the prestressed anchor rods 4 are multiple and arranged in a circumferential direction. The sealing layer system is connected to the plugging 3 and is attached to the inner wall of the mine tunnel 2, and is provided with a corresponding chamfering structure 8, so that corresponding sealing reinforcement operations can be performed. The front end of the plugging 3 in the operating direction is large and the rear end is small, and the front and rear cross-sectional shapes in the operating direction are concentric with the tunnel 2, and the rear end cross-sectional shape in the operating direction is equal to the tunnel 2. A circular maintenance channel 7 with a predetermined operating length and operating size is provided at the center of the plugging 3, so that corresponding gas storage maintenance operations can be performed. The sealing system includes two components: a sealing door 5 and a sealing ring 10. The sealing door 5 is located at the end position of the operation direction of the inspection channel 7, has a predetermined operation size, and is adapted to the operation size of the inspection channel 7, and can perform corresponding sealing operations. The sealing ring 10 is placed at the contact position between the sealing door 5 and the inspection channel 7, and is adapted to the operation size of the inspection channel 7. The chamfered structure 8 is placed at the angle between the contact surface of the plug 3 and the sealing ring 10, and is arc-shaped; there are multiple chamfered structures 8. The number of circumferential layers of the prestressed anchor rods 4 is multiple, and the number of operation of the prestressed anchor rods 4 in each layer is not less than ten; the prestressed anchor rods 4 have a predetermined inclination angle, and the inclination angle and direction are parallel to the inclined surface of the plug 3. The hollow structure 9 is spherical and is placed inside the plug 3, and the hollow structures 9 are provided inside the plug 3 on both sides of the operation direction of the inspection channel 7; a predetermined operation distance is left between the prestressed anchor rods 4 and the hollow structure 9.

[0018] Embodiment 2:

[0019] On the basis of the first embodiment, the plug 3 is truncated cone-shaped, with a large front end and a small rear end, and the radius of the upper section and the lower section differ by at least 1.5m, and the front and rear section shapes are concentric with the tunnel 2 and the rear section is equal to the tunnel 2, which increases the contact area between the surrounding rock 1 and the plug 3, increases the friction force on the plug 3, and increases the thrust of the surrounding rock 1 on the plug 3 provided by the elastic resistance of the surrounding rock 1, thereby comprehensively increasing the bearing capacity of the plug 3. The plug 3 is filled with concrete 6 material, generally using C25 and above concrete 6, and multiple hollow structures 9 are arranged in the plug 3, which can reduce the amount of concrete 6, thereby reducing the overall cost of the plug 3, and the hollow structure 9 is generally ellipsoidal in shape, which does not affect the overall force of the plug 3. Prestressed anchor rods 4 are arranged in the surrounding rock 1, parallel to the upper and lower surfaces of the plug 3. One section of the prestressed anchor rod 4 is embedded in the surrounding rock 1, and the other end is embedded in the plug 3. The prestressed anchor rods 4 are not less than two layers and are arranged circumferentially along the tunnel 2. There are not less than ten single-layer circumferential prestressed anchor rods 4. The prestressed force of the prestressed anchor rods 4 should reach the ultimate strength of the surrounding rock 1 and give full play to its role. When the plug 3 is subjected to the thrust of the internal pressure, the prestressed force provided by the prestressed anchor rods 4 is first borne. When the thrust of the plug 3 exceeds the prestressed force, the plug 3 is subjected to the conventional tension of the prestressed anchor rods 4, which greatly increases the stability of the plug 3 and reduces the relative sliding of the contact surface between the plug 3 and the surrounding rock 1. The inspection channel 7 is located in the center of the plug 3 and is a circular structure, which is convenient for personnel to enter and exit the gas storage for inspection. The sealing layer system is composed of the inner wall of the tunnel 2, the sealing door 5, the chamfered structure 8, and the sealing layer. Among them, the sealing door 5 is located at the end of the maintenance passage 7 and is a steel door. A sealing ring 10 is provided at the contact between the sealing door 5 and the maintenance passage 7 to prevent air leakage. The chamfered structure 8 is mainly a force transmission layer, generally made of asphalt material, which does not bear internal pressure and is only used for force transmission. The arc of the chamfer is 45°-90°, which avoids the generation of stress concentration. The sealing layer is in direct contact with the inner wall of the tunnel 2, and is set to the same shape as the chamfered structure 8 area, and the sealing layer is thickened in this area. The sealing layer extends all the way to the sealing door 5 to prevent damage to the sealing layer. The sealing layer can be a polymer material, a thin iron plate or an inorganic rubber material, which fully guarantees the sealing of the plug 3. The direction of the prestressed anchor rod 4 is parallel to the inclined surface of the plug 3 and does not exceed 30°. The prestress provided by the prestressed anchor rod 4 does not exceed the ultimate strength of the surrounding rock 1. The diameter of the inspection channel 7 is not less than 1.5 m, the ellipsoidal hollow body is located on both sides of the inspection channel 7 and is symmetrical up and down, the prestressed anchor rod 4 shall not pass through the interior of the hollow body structure, and the volumes of the hollow body structures may be different from each other.

[0020] The present application provides a plugging structure for an abandoned mine gas storage reservoir, which can effectively solve the problem of plugging the end of the abandoned mine gas storage reservoir and has the following beneficial effects:

[0021] (1) Improved stability of plug 3: prestressed anchor rods 4 are arranged in the surrounding rock 1. Before gas storage (when the pressure in the gas storage reservoir is 0.05 or very small), the anchor rods provide a certain pulling force on the plug 3. After storing high-pressure gas, the force acting on the plug, in addition to offsetting the force equal to the prestress, can also provide a certain pulling force. Secondly, the structure of plug 3 is in the shape of a truncated cone and the small cross-section of the truncated cone is the same circle as the tunnel 2, which maximizes the friction between the surrounding rock 1 and the plug 3 and makes full use of the elastic resistance of the surrounding rock 1, thereby greatly increasing the overall stability of the plug 3.

[0022] (2) Improved sealing effect: A layer of force transmission material is sprayed on the right-angle contact area formed by the large cross-section of the plug 3 and the inner wall of the tunnel 2. The right-angle area is designed to be chamfered, and the sealing layer is arranged on the inner side of the chamfer. The sealing layer is thickened at the chamfer, thereby preventing the failure of the sealing layer caused by stress concentration at the right angle.

[0023] (3) The amount of the plug 3 is reduced: the interior of the plug 3 is designed as a partially ellipsoidal hollow body structure, which does not affect the overall stability of the plug 3 while reducing the amount of concrete 6 material used, thereby reducing the construction cost of the plug 3.

[0024] As described above, although the present invention has been shown and described with reference to specific preferred embodiments, it should not be interpreted as limiting the present invention itself. Various changes can be made to it in form and detail without departing from the spirit and scope of the present invention defined in the appended claims.

Claims

1. A plugging structure for an abandoned mine gas storage reservoir, characterized in that include: The plugging system includes a plugging head of predetermined working size and supporting force and is in the shape of a truncated cone; A prestressed anchor rod having a predetermined operating length, one end of which is embedded in the surrounding rock and the other end of which is embedded in the plug; The plug is provided with a plurality of hollow structures inside, and the prestressed anchor rods are multiple and arranged in a ring direction; The sealing layer system is connected to the plug and is in contact with the inner wall of the mine tunnel. It is also provided with a corresponding chamfering structure and can perform corresponding sealing reinforcement operations.

2. A plugging structure for an abandoned mine gas storage according to claim 1, characterized in that: The front end of the plug in the working direction is large and the rear end is small, and the front and rear cross-sectional shapes in the working direction are concentric with the tunnel, and the rear end cross-sectional shape in the working direction is equal to the tunnel; A circular maintenance channel with a predetermined operating length and operating size is provided at the center of the plug, so that corresponding maintenance operations of the gas storage reservoir can be carried out.

3. A plugging structure for an abandoned mine gas storage according to claim 2, characterized in that: The sealing layer system comprises: A sealing door, located at the end of the inspection channel in the operation direction, has a predetermined operation size and is adapted to the operation size of the inspection channel, and can perform corresponding sealing operations; A sealing ring, which is placed at the contact position between the sealing door and the inspection passage and is adapted to the operating size of the inspection passage; The chamfered structure is disposed at the angle between the contact surfaces of the plug and the sealing ring and is arc-shaped; there are multiple chamfered structures.

4. A plugging structure for an abandoned mine gas storage according to claim 2, characterized in that: The prestressed anchor rods have multiple circumferential layers, and the number of prestressed anchor rods in each layer is not less than ten; the prestressed anchor rods have a predetermined inclination angle, and the inclination angle and direction are parallel to the inclined surface of the plug.

5. The plugging structure for abandoned mine gas storage according to claim 2 is characterized in that: The hollow structure is spherical and is placed inside the plug. The hollow structure is provided inside the plugs on both sides of the operating direction of the inspection channel. A predetermined operating distance is left between the prestressed anchor rod and the hollow structure.

Citation Information

Cited By

  • Underground high-pressure gas storage unfavorable geological section treatment structure and design method thereof

    CN119244278A

  • Treatment structure and design method of bad geological section of underground high-pressure gas storage

    CN119244278B

  • Underground high-pressure gas storage unfavorable geological section treatment structure and design method thereof

    CN119616528A

  • Treatment method for unfavorable geological cavern section of underground storage cavern

    CN121139012A