Automatic detection device for contact switching time of automatic transfer switching equipment
By designing a self-converting switch electrical contact conversion time detection device using soft connection, the problem of large and high cost of detection devices in the prior art is solved, convenient detection in the laboratory and production site is realized, and detection accuracy is improved. and efficiency.
Patent Information
- Application Number
- CN202323523867.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-24
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2033-12-24
AI Technical Summary
The existing automatic conversion switch electrical contact conversion time detection device requires a large test bench and a high-cost configuration, and is inconvenient to maintain, making it difficult to conduct rapid inspections at the production site.
An automatic detection device for automatic conversion switch electrical contact conversion time is designed, adopting soft connection method, including three-phase and four-wire power supply, control system and data acquisition host, through three-phase and four-wire voltage regulator, single-phase voltage regulator and Single-pole switch simulates different fault modes, combining electromagnetic relay and button control to achieve flexible power switching and fault simulation.
It realizes convenient installation and testing in the laboratory and production site, improves the accuracy and efficiency of testing, can efficiently calculate the conversion time, and is suitable for on-site inspection with large sampling volumes.
Smart Images

Figure CN221977057U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of automatic transfer switch detection, in particular to an automatic transfer switch electrical appliance contact transfer time automatic detection device. Background Art
[0002] An automatic transfer switch is a switching device that automatically switches one or more loads on one power supply to another power supply when one power supply fails. It is mainly used in scenarios with high electricity requirements such as banks, petrochemical enterprises, hospitals, and power plants. When an automatic transfer switch is successfully developed or mass-produced in certain quantities, it needs to be type tested. Among them, it is necessary to test the conversion time of the automatic transfer switch electrical contacts under the set fault mode. Most of the existing test devices use large test bench equipment. If a dual power supply workbench is required, the production cycle is long, the cost is high, and it is inconvenient to use and maintain. Summary of the invention
[0003] The utility model aims to provide an automatic detection device for the contact switching time of an automatic switching electrical appliance, which adopts a soft connection method and can be conveniently installed in a laboratory, thus solving the problems in the prior art.
[0004] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: an automatic detection device for contact switching time of an automatic transfer switch electrical appliance, comprising a three-phase four-wire power supply, a control system, a data acquisition host, a main switch for controlling the on and off of the three-phase four-wire power supply, a first test circuit connected in parallel to the main switch, a second test circuit, and a third test circuit;
[0005] The first test circuit is equipped with a three-phase four-wire voltage regulator, and the output end is used to be electrically connected to the backup power supply side of the automatic transfer switch to simulate the backup power supply;
[0006] The output ends of the second test circuit and the third test circuit are both electrically connected to the common power supply side of the automatic transfer switch to simulate common power supplies with different fault modes;
[0007] The signal collector of the data acquisition host is electrically connected to the load side of the automatic transfer switch, and is used to collect the electrical signal converted by the electrical contact when the automatic transfer switch switches between the normal power supply and the backup power supply, and the current waveform before and after the conversion is displayed on the display of the data acquisition host and the conversion time is calculated by the industrial computer;
[0008] The control system is used to interlock the second test circuit and the third test circuit when supplying power to the automatic transfer switch and / or to lack one phase or multiple phases when switching the output of the second test circuit.
[0009] Furthermore, the second test circuit is equipped with a three-phase four-wire voltage regulator 2 and each electrical connection line between the output end and the common end power supply side of the automatic transfer switch is equipped with a single-pole switch to simulate any phase failure mode of the common power supply;
[0010] A single-phase voltage regulator is installed on each single-phase circuit in the third test circuit, and the output ends of the single-phase voltage regulator are electrically connected to the corresponding single-phase ports on the common power supply side of the automatic transfer switch to simulate the unstable voltage failure mode of any phase of the common power supply.
[0011] Furthermore, the output ends of the first test circuit, the second test circuit and the third test circuit are all equipped with three-phase voltmeters for displaying the output voltage.
[0012] Furthermore, a second switch is provided at the output end of the first test circuit to control the on and off of the output of the first test circuit.
[0013] Furthermore, the electrical connection between the second test circuit and the third test circuit and the three-phase four-wire power supply is a normally open setting.
[0014] Furthermore, the control system includes:
[0015] The first button is used to control the on and off of the first electromagnetic relay. The normally open contact of the working circuit of the first electromagnetic relay is connected to the input side of the second test circuit to control the on and off of the second test circuit and the three-phase four-wire power supply.
[0016] The second button is used to control the on and off of the second electromagnetic relay. The normally open contact of the working circuit of the second electromagnetic relay is connected to the input side of the third test circuit to control the on and off of the third test circuit and the three-phase four-wire power supply. The normally closed interlocking contact of the second electromagnetic relay is connected to the control circuit of the first electromagnetic relay where the first button is located; the normally closed interlocking contact of the first electromagnetic relay is connected to the control circuit of the second electromagnetic relay where the second button is located;
[0017] The third button is used to control the on and off of the third electromagnetic relay, and the normally open contact of the working circuit of the third electromagnetic relay is bypassed at the single-pole switch of the adjacent two-wire circuit on the second test circuit;
[0018] The fourth button is used to control the on and off of the fourth electromagnetic relay. The normally open contact of the working circuit of the fourth electromagnetic relay is bypassed at the single-pole switch of the other adjacent two-wire circuit on the second test circuit; the normally closed interlocking contact of the third electromagnetic relay is connected to the control circuit of the fourth electromagnetic relay where the fourth button is located; the normally closed interlocking contact of the fourth electromagnetic relay is connected to the control circuit of the third electromagnetic relay where the third button is located.
[0019] Beneficial effects of the utility model: the automatic detection device for the contact conversion time of the automatic transfer switch provided by the utility model combines various hardware in a soft connection manner, can be conveniently installed in the laboratory, and can also be conveniently transported to the production enterprise of the automatic transfer switch for on-site detection of a large number of samples. The three-phase four-wire voltage regulator is provided to provide a voltage that meets the rated use conditions of the automatic transfer switch, the single-phase voltage regulator is used to conveniently simulate the failure mode of unstable power supply voltage, the single-pole switch and the third and fourth relays are used to flexibly simulate the phase failure state, and at the same time, the collected conversion signal is analyzed and calculated by the data acquisition host, the current waveform before and after the conversion is automatically displayed on the display, and the conversion time is automatically calculated by the industrial box meter, which has the advantages of high measurement accuracy and high measurement efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is the circuit principle diagram of the utility model;
[0021] Figure 2 for Figure 1 A partial enlarged view of point D in the middle;
[0022] Figure 3 for Figure 1 A partial enlarged view of point E in the middle. DETAILED DESCRIPTION
[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0024] See also Figure 1~Figure 3 , an automatic detection device for contact switching time of an automatic transfer switch electrical appliance, comprising a three-phase four-wire power supply, a control system, a data acquisition host 005, a main switch QS1 for controlling the on and off of the three-phase four-wire power supply, a first test circuit, a second test circuit, and a third test circuit connected in parallel to the main switch;
[0025] The first test circuit is equipped with a three-phase four-wire voltage regulator 001, and the output end is used to be electrically connected to the backup power supply side of the automatic transfer switch 006 to simulate the backup power supply;
[0026] The output ends of the second test circuit and the third test circuit are electrically connected to the common power supply side of the automatic transfer switch 006 to simulate the common power supply with different fault modes; as a specific embodiment, the second test circuit is equipped with a three-phase four-wire voltage regulator 2 002, and each electrical connection line between the output end and the common power supply side of the automatic transfer switch 006 is equipped with a single-pole switch QS3, a single-pole switch QS4, a single-pole switch QS5, and a single-pole switch QS6, and any single-pole switch is disconnected to simulate any phase failure mode of the common power supply;
[0027] Each single-phase circuit in the third test circuit is equipped with a single-phase voltage regulator 003, and the output ends of the single-phase voltage regulator 003 are electrically connected to the corresponding single-phase ports on the common power supply side of the automatic transfer switch 006 to simulate the voltage instability fault mode of any phase of the common power supply;
[0028] The data acquisition host 005 includes a signal collector, an industrial computer and a display. The signal collector of the data acquisition host 005 is electrically connected to the load side of the automatic transfer switch, and is used to collect the electrical signal of the electrical contact conversion when the automatic transfer switch switches between the normal power supply and the backup power supply. The display of the data acquisition host 005 displays the current waveform before and after the conversion, and the industrial computer calculates the conversion time. It has high response accuracy and accurate detection, and can automatically record the current / voltage waveform and conversion time data at each conversion.
[0029] The control system is used to interlock the second test circuit and the third test circuit when supplying power to the automatic transfer switch and / or to switch the output of the second test circuit when one phase or more phases are missing.
[0030] Preferably, the output ends of the first test circuit, the second test circuit and the third test circuit are equipped with three-phase voltmeters for displaying the output voltage 004, which can intuitively display the normal voltage, i.e., the voltage on the first test circuit, and the voltage in the fault mode, i.e., the voltage output by the second test circuit and the third test circuit.
[0031] Preferably, the output end of the first test circuit is also provided with a second switch QS2 for controlling the on / off of the output of the first test circuit, and the electrical connection between the second test circuit and the third test circuit and the three-phase four-wire power supply is a normally open setting. Specifically, the on / off of the second test circuit and the third test circuit and the three-phase four-wire power supply is controlled by the normally open contacts of the working circuits of the corresponding first electromagnetic relay KM1 or the second electromagnetic relay KM2. In this way, the outputs of the first test circuit, the second test circuit and the third test circuit can be turned off without cutting off the main power supply, thereby facilitating the disassembly and assembly of the automatic weighing switch 006 used for the test and ensuring safety.
[0032] Preferably, the control system includes: a first button SB1, a second button SB2, a third button SB3, and a fourth button SB4 arranged in parallel; the first button SB1 is used to control the on-off of the first electromagnetic relay KM1, and the normally open contact of the working circuit of the first electromagnetic relay KM1 is connected to the input side of the second test circuit to control the on-off of the second test circuit and the three-phase four-wire power supply;
[0033] The second button SB2 is used to control the on and off of the second electromagnetic relay KM2. The normally open contact of the working circuit of the second electromagnetic relay KM2 is connected to the input side of the third test circuit to control the on and off of the second test circuit and the three-phase four-wire power supply. The normally closed interlocking contact of the second electromagnetic relay KM2 is connected to the control circuit of the first electromagnetic relay KM1 where the first button SB1 is located; the normally closed interlocking contact of the first electromagnetic relay KM1 is connected to the control circuit of the second electromagnetic relay KM2 where the second button SB2 is located;
[0034] Through the above settings, when it is necessary to use the phase loss fault mode for testing, press the first button SB1, the first electromagnetic relay KM1 is actuated to connect the second test circuit to the three-phase four-wire power supply; at the same time, the control circuit of the second electromagnetic relay KM2 where the second button SB2 is located is disconnected to ensure that the third test circuit is in an open circuit state. At this time, the single-pole switch QS3, the single-pole switch QS4, the single-pole switch QS5 or the single-pole switch QS6 can be disconnected to simulate the fault mode of any phase open circuit, so that the automatic transfer switch 006 is actuated to detect the contact conversion time when automatically switching to the power supply state of the first test circuit;
[0035] When it is necessary to use the voltage instability fault mode for testing, press the second button SB2 to connect the third test circuit to the three-phase four-wire power supply. At the same time, the control circuit of the first electromagnetic relay KM1 where the first button SB1 is located is disconnected to ensure that the second test circuit is in an open circuit state. Then, the power supply voltage supplied to the automatic transfer switch 006 can be adjusted by adjusting each single-phase voltage regulator 003 on the third test circuit, and then the contact conversion time of the automatic transfer switch 006 when the voltage changes automatically is detected. In this way, accurate detection of the contact conversion time under different fault modes is achieved;
[0036] The third button SB3 is used to control the on and off of the third electromagnetic relay KM3. The normally open contact of the working circuit of the third electromagnetic relay KM3 is bypassed at the single-pole switch of the adjacent two-line circuit on the second test circuit. In this embodiment, the bypass is connected in parallel at the single-pole switch QS3 and the single-pole switch QS4.
[0037] The fourth button SB4 is used to control the on and off of the fourth electromagnetic relay KM4. The normally open contact of the working circuit of the fourth electromagnetic relay KM4 is bypassed at the single-pole switch of the other adjacent two-line circuit in the second test circuit. In this embodiment, the bypass is connected in parallel at the single-pole switch QS5 and the single-pole switch QS6; the normally closed interlocking contact of the third electromagnetic relay KM3 is connected to the control circuit of the fourth electromagnetic relay KM4 where the fourth button SB4 is located; the normally closed interlocking contact of the fourth electromagnetic relay KM4 is connected to the control circuit of the third electromagnetic relay KM3 where the third button SB3 is located to achieve interlocking at the two locations and ensure the singleness of the phase-missing state. That is, through the above setting, this embodiment can also simulate the two-phase circuit breaker fault mode by operating the third button SB3 or the fourth button SB4 (at this time, the single-pole switch QS3, the single-pole switch QS4, the single-pole switch QS5 and the single-pole switch QS6 are all in the disconnected state).
[0038] Here, the first button SB1, the second button SB2, the third button SB3, the fourth button SB4, the first electromagnetic relay KM1, the second electromagnetic relay KM2, the third electromagnetic relay KM3, the fourth electromagnetic relay KM4, the main switch QS1, the single-pole switch QS3, the single-pole switch QS4, the single-pole switch QS5, the single-pole switch QS6, and the second switch QS2 can be installed in an electric control box to form a module; the three-phase four-wire voltage regulator 001, the three-phase four-wire voltage regulator 002, the three single-phase voltage regulators 003 and the data acquisition host 005 are each used as a separate module, so that they are soft-connected through cables when used, which is convenient for transportation, installation and debugging, and is conducive to improving the portability of the automatic detection device for contact conversion time of automatic transfer switch electrical appliances.
[0039] here, Figure 1~Figure 3In the figure, single letters A, B, C, and N respectively represent phase A, phase B, phase C, and neutral line N corresponding to a three-phase four-wire power supply, and are used to indicate the corresponding wiring connections of each phase sequence.
[0040] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0041] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. An automatic detection device for contact switching time of an automatic transfer switch. Features: It includes a three-phase four-wire power supply, a control system, a data acquisition host, a main switch for controlling the on and off of the three-phase four-wire power supply, a first test circuit, a second test circuit, and a third test circuit connected in parallel to the main switch; The first test circuit is equipped with a three-phase four-wire voltage regulator, and the output end is used to be electrically connected to the backup power supply side of the automatic transfer switch to simulate the backup power supply; The output ends of the second test circuit and the third test circuit are both electrically connected to the common power supply side of the automatic transfer switch to simulate common power supplies with different fault modes; The signal collector of the data acquisition host is electrically connected to the load side of the automatic transfer switch, and is used to collect the electrical signal converted by the electrical contact when the automatic transfer switch switches between the normal power supply and the backup power supply, and the current waveform before and after the conversion is displayed on the display of the data acquisition host and the conversion time is calculated by the industrial computer; The control system is used to interlock the second test circuit and the third test circuit when supplying power to the automatic transfer switch and / or to lack one phase or multiple phases when switching the output of the second test circuit.
2. The automatic detection device for contact transfer time of an automatic transfer switch according to claim 1, Features: The second test circuit is equipped with a three-phase four-wire voltage regulator 2, and each electrical connection line between the output end and the common end power supply side of the automatic transfer switch is equipped with a single-pole switch to simulate any phase failure mode of the common power supply; A single-phase voltage regulator is installed on each single-phase circuit in the third test circuit, and the output ends of the single-phase voltage regulator are electrically connected to the corresponding single-phase ports on the common power supply side of the automatic transfer switch to simulate the unstable voltage failure mode of any phase of the common power supply.
3. The automatic detection device for contact transfer time of an automatic transfer switch according to claim 1, Features: The output ends of the first test circuit, the second test circuit and the third test circuit are all equipped with three-phase voltmeters for displaying the output voltage.
4. The automatic detection device for contact transfer time of an automatic transfer switch electrical appliance according to claim 1, Features: The output end of the first test circuit is also provided with a second switch for controlling the on and off of the output of the first test circuit.
5. The automatic detection device for contact transfer time of automatic transfer switch electrical equipment according to claim 2, Features: The electrical connection between the second test circuit and the third test circuit and the three-phase four-wire power supply is a normally open setting.
6. The automatic detection device for contact transfer time of automatic transfer switch electrical equipment according to claim 5, It is characterized in that The control system comprises: A first button is used to control the on and off of a first electromagnetic relay, wherein a normally open contact of a working circuit of the first electromagnetic relay is connected to an input side of the second test circuit to control the on and off of the second test circuit and the three-phase four-wire power supply; The second button is used to control the on and off of the second electromagnetic relay. The normally open contact of the working circuit of the second electromagnetic relay is connected to the input side of the third test circuit to control the on and off of the third test circuit and the three-phase four-wire power supply. The normally closed interlocking contact of the second electromagnetic relay is connected to the control circuit of the first electromagnetic relay where the first button is located; the normally closed interlocking contact of the first electromagnetic relay is connected to the control circuit of the second electromagnetic relay where the second button is located; A third button is used to control the on and off of a third electromagnetic relay, wherein a normally open contact of a working circuit of the third electromagnetic relay is bypassed at the single-pole switch of the adjacent two-wire circuit on the second test circuit; The fourth button is used to control the on and off of the fourth electromagnetic relay. The normally open contact of the working circuit of the fourth electromagnetic relay is bypassed at the single-pole switch of the other adjacent two-wire circuit on the second test circuit; the normally closed interlock contact of the third electromagnetic relay is connected to the control circuit of the fourth electromagnetic relay where the fourth button is located; the normally closed interlock contact of the fourth electromagnetic relay is connected to the control circuit of the third electromagnetic relay where the third button is located.