Cover beam formwork support unit for double-cantilever cover beam construction
By designing the cover beam formwork bracket unit for slide rails, pulleys, movable sheet frames and elastic guide wheels, the problems of loose parts and long crane occupancy in cantilever cover beam construction are solved, and efficient and safe modular construction is achieved, reducing the need for a lowering of the Cost and duration.
Patent Information
- Application Number
- CN202420290774.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-08
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-02-08
AI Technical Summary
The existing cantilever cover beam construction methods have problems such as loose parts, long crane occupancy time, long construction cycle, high cost and major safety hazards, and cannot adapt to modular construction needs.
A cover beam formwork bracket unit for double cantilever cover beam construction is designed, using slide rail and pulley system, a detachable movable piece frame and reinforced recessed bracket, and an elastic guide wheel to realize the overall rise, fall and translation of the bracket. Reduce the time of high-altitude installation operations and crane occupancy.
It improves construction efficiency, reduces construction costs, shortens construction period, and enhances construction safety, realizing the feasibility of modular construction.
Smart Images

Figure CN221989116U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pouring construction of bridge cantilever cap beams, in particular to a cap beam template support unit for the construction of double cantilever cap beams. Background Art
[0002] A cantilever cap beam is a bridge structure mainly composed of a support, an upper structure and a lower structure. There is no support at the cantilever end and there is a gap in the middle. The cap beam is constructed by casting in sections. After one section is completed, the bracket and mold are moved to cast the next section of the cantilever.
[0003] In the prior art, the construction of cantilever cap beams usually uses through rods or fixed clamps as supports, and then the Bailey beams, distribution beams, bottom molds, and side molds are hoisted at high positions, and then poured.
[0004] The through-steel rod method is to reserve holes in the pier column to install the corbel, build a bracket upwards from the corbel as the starting point, and set up a ladder channel from the ground, and the ladder channel is attached to the pier column at intervals. The hoop method refers to using a hoop to tighten the pier column, build a bracket upwards from the hoop as the starting point, and set up a ladder channel from the ground, and the ladder channel is attached to the pier column at intervals.
[0005] The above two methods have the following disadvantages:
[0006] 1. The parts of both methods are relatively loose, and a large number of parts need to be hoisted.
[0007] 2. It takes a long time to configure an independent crane, and because the parts that need to be hoisted by the crane are too scattered, the crane takes a long time, resulting in a long construction period and high construction costs.
[0008] 3. Most components are installed at high positions, which poses a great safety hazard.
[0009] 4. After the construction of a group of piers and cap beams is completed, all equipment components need to be transported one by one to the next group of workstations, which is time-consuming and labor-intensive.
[0010] Therefore, during the construction of the cap beam, according to the needs of on-site construction, there is an urgent need for a cap beam construction system in which the bracket, bottom formwork, side formwork, etc. can be installed in a low-position modular manner and can rise, fall and translate as a whole, so as to reduce the high-altitude installation work of scattered parts, reduce the occupancy time of cranes, improve construction efficiency, shorten the construction period, and improve the safety factor of construction.
[0011] However, the existing cap beam formwork support unit cannot adapt to the cap beam modular construction system, and there is an urgent need to provide a cap beam formwork support unit that can adapt to the cap beam modular construction. Summary of the invention
[0012] In order to solve the problems in the prior art, the present invention provides a cap beam formwork support unit for double cantilever cap beam construction, which can adapt to modular construction, improve construction efficiency and reduce construction costs.
[0013] To achieve the above object, the present invention provides the following technical solution: a cap beam formwork support unit for double cantilever cap beam construction, comprising a cap beam formwork support, a slide rail is arranged on the cap beam formwork support, and a plurality of pulleys that can slide along the slide rail are arranged on the slide rail; the pulleys can be used to load objects. For example, the pulleys can be used to load standard support sections, attachment hoops, adjustment support sections and unloading blocks of a jacking system.
[0014] According to a preferred technical solution, the cap beam formwork support is also provided with a detachable movable sheet frame; the cap beam formwork support unit also includes a detachable reinforcing recessed support matched with the movable sheet frame of the cap beam formwork support, the reinforcing recessed support having at least one makeshift space for accommodating a corresponding bridge pier; by alternately installing / disassembling the corresponding reinforcing recessed support and the movable sheet frame, the cap beam formwork support can be moved out of or into the corresponding bridge pier as a whole.
[0015] The preferred technical solution is that when the cap beam formwork support needs to be moved out of the bridge pier as a whole, the reinforcing recessed support is first installed on the corresponding cap beam formwork support, and then the corresponding movable sheet frame is disassembled, and the cap beam formwork support can be moved away from the corresponding bridge pier as a whole by using the space left by the reinforcing recessed support. After moving into place, the corresponding movable sheet frame is installed, and the corresponding reinforcing recessed support is disassembled, and the cap beam formwork support can be moved out of the corresponding bridge pier as a whole.
[0016] When it is necessary to move the cap beam formwork support as a whole into the bridge pier, first make the corresponding bridge pier located in the making way space of the corresponding reinforced concave support, then install the reinforced concave support on the corresponding cap beam formwork support, and then remove the corresponding movable sheet frame, and use the making way space of the reinforced concave support to move the cap beam formwork support as a whole close to the corresponding bridge pier. After moving into place, install the corresponding movable sheet frame, remove the corresponding reinforced concave support, and then move the cap beam formwork support as a whole into the corresponding bridge pier.
[0017] According to a preferred technical solution, the cap beam formwork support unit is equipped with a plurality of elastic guide wheels; when the cap beam formwork support unit moves up and down along the bridge pier, the elastic guide wheels roll along the surface of the bridge pier to guide the cap beam formwork support unit.
[0018] Compared with the prior art, the present invention has the following beneficial effects:
[0019] The cap beam template support unit of the utility model can move the equipment carried on it to the next cap beam construction station as a whole, eliminating the process of dismantling, rotating and installing the equipment on site, saving a lot of working time, improving work efficiency and increasing economic benefits. The modular design greatly reduces the assembly time and the time for long-distance transportation and mid-transfer, and improves work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 This is a front view of the overall structure of a double cantilever cap beam construction system.
[0021] Figure 2 A three-dimensional view of the overall structure of a double-cantilever cap beam construction system.
[0022] Figure 3 It is a schematic diagram of the base structure of a double cantilever cap beam construction system.
[0023] Figure 4 This is a schematic diagram of the structure of the cap beam formwork support.
[0024] Figure 5 It is a structural schematic diagram of the movable film rack.
[0025] Figure 6 This is a schematic diagram of the structure of a standard support section.
[0026] Figure 7 Schematic diagram of the structure of the pulley.
[0027] Figure 8 It is a schematic diagram of the structure of the elastic guide wheel.
[0028] Fig. 9 Schematic diagram of the three-dimensional structure of the elastic guide wheel.
[0029] Fig.10 This is a schematic diagram of the local structure of the cap beam formwork support.
[0030] Fig.11 It is the front view of the unloading block.
[0031] Fig.12 Schematic diagram of the three-dimensional structure of the unloading block.
[0032] Fig.13 Schematic diagram of the connection structure of the modular cap beam formwork unit on the cap beam formwork support.
[0033] Fig.14 for Fig.12 Enlarged view of part A in .
[0034] Fig.15 It is a schematic diagram of the overall structure of the modular cap beam formwork unit.
[0035] Fig.16 Schematic diagram of the structure after removing the bottom formwork and tie rods of the modular cap beam formwork unit.
[0036] Fig.17 for Fig.15 Enlarged view of part B in .
[0037] Fig.18 This is a diagram showing the installation status of the cap beam formwork support unit and the modular cap beam formwork unit in the low position.
[0038] Figures 19 to 22 This is a process diagram of the cap beam formwork support and the modular cap beam formwork unit of the present invention gradually climbing upward along the bridge pier.
[0039] Fig.23 It is a front view of the state where the cap beam formwork support and the modular cap beam formwork unit are lowered onto the translation connecting support.
[0040] Fig.24 It is a top view of the state where the cap beam formwork support and the modular cap beam formwork unit are lowered onto the translation connection support.
[0041] Fig.25 This is a three-dimensional view of the status after the reinforcement support frame is installed.
[0042] Fig.26 This is a top view of the status after the reinforcement support frame is installed.
[0043] Fig. 27 This is a three-dimensional view of the state after removing the movable film rack.
[0044] Fig.28 This is a top view of the state after removing the movable film rack.
[0045] Fig.29 This is the state diagram after the double cantilever cap beam is completely translated out of the bridge pier.
[0046] Fig.30 This is a diagram of the state after the double cantilever cap beam is completely moved out of the bridge pier and the movable frame is installed. DETAILED DESCRIPTION
[0047] An embodiment of a cap beam formwork support unit for double cantilever cap beam construction is further described with reference to the accompanying drawings.
[0048] Example 1
[0049] like Figures 1 to 30 As shown, a double cantilever cap beam construction system includes a cap beam formwork support unit 1, a modular cap beam formwork unit 2, and a jacking system 3; the modular cap beam formwork unit 2 is detachably installed on the cap beam formwork support unit 1; in this embodiment, the double cantilever cap beam construction system is also configured with a planar universal translation system 4.
[0050] The jacking system 3 includes a jacking cylinder 31, multiple standard support nodes 32, and multiple attachment hoops 33; the multiple standard support nodes 32 are detachably connected from top to bottom in sequence, and the uppermost standard support node 32 is against the cap beam formwork support unit 1; the attachment hoop 33 divides the corresponding standard support node 32 into sections and detachably locks it on the completed bridge pier 04; one end of the jacking cylinder 31 is detachably installed on the cap beam formwork support unit 1, and the other end of the jacking cylinder 31 is detachably installed on the standard support node 32; by changing the number of the standard support nodes 32, and connecting the jacking cylinder 31 to the standard support nodes 32 at different heights, the jacking cylinder 31 can drive the cap beam formwork support unit 1 to move up and down along the bridge pier 04.
[0051] The jacking system 3 also includes a plurality of adjustable support sections 34 of different lengths, and the adjustable support sections 34 are detachably installed in sequence from top to bottom between the cap beam formwork support unit 1 and the uppermost standard support section 32 .
[0052] The double cantilever cap beam construction system further includes a removal block 35, which is installed between the cap beam formwork support unit 1 and the uppermost adjustment support section 34. Fig.11 and Fig.12 The unloading block 35 is in the shape of an “I” as a whole, and includes an upper adjusting block 35, a lower adjusting block 36 and an intermediate adjusting block 37; there are two intermediate adjusting blocks 37, which are respectively arranged on the left and right sides between the upper adjusting block 35 and the lower adjusting block 36; and the upper adjusting block 35, the lower adjusting block 36 and the two intermediate adjusting blocks 37 are in contact through the inclined surface facing the center of the “I” shape, and an adjusting screw 39 for adjusting the distance between the two intermediate adjusting blocks 37 is provided between the two intermediate adjusting blocks 37. By rotating the adjusting screw 39, the opening and closing distance between the two intermediate adjusting blocks 37 is adjusted, so that the vertical distance between the upper adjusting block 35 and the lower adjusting block 36 is changed. When the two intermediate adjusting blocks 37 are far away from each other, the vertical distance between the upper adjusting block 36 and the lower adjusting block 37 becomes smaller; when the two intermediate adjusting blocks 37 are close to each other, the vertical distance between the upper adjusting block 36 and the lower adjusting block 37 becomes larger. When the entire cap beam formwork support unit 1 needs to be lowered, the height of the unloading block 35 can be finely adjusted by setting the unloading block 35, and the upper surface of the unloading block 35 can be lowered by 2 cm, making it more convenient to disassemble and adjust the support section 34.
[0053] The cap beam formwork support unit 1 includes a cap beam formwork support 11, on which a slide rail 12 is arranged, and on which a plurality of pulleys 13 that can slide along the slide rail 12 are arranged; the pulley 13 can be used to load a standard support section 32, an attachment clamp 33, an adjustment support section 34 or a unloading block 35.
[0054] The cap beam formwork support 11 is also provided with a detachable movable sheet frame 14; the cap beam formwork support unit 1 also includes a detachable reinforcing recessed support 15 used in matching with the movable sheet frame 14 of the cap beam formwork support 11, and the reinforcing recessed support 15 has at least one makeshift space for accommodating the corresponding bridge pier; by alternately installing / disassembling the corresponding reinforcing recessed support 15 and the movable sheet frame 14, the cap beam formwork support 11 and the modular cap beam formwork unit 2 can be moved out or moved into the corresponding bridge pier 04 as a whole.
[0055] When it is necessary to move the cap beam formwork support 11 and the modular cap beam formwork unit 2 out of the bridge pier 04 as a whole, first install the reinforcing recessed support 15 on the corresponding cap beam formwork support 11, then remove the corresponding movable sheet frame 14, and use the space left by the reinforcing recessed support 15 to move the cap beam formwork support 11 and the modular cap beam formwork unit 1 away from the corresponding bridge pier 04 as a whole. After moving to the right position, install the corresponding movable sheet frame 14, remove the corresponding reinforcing recessed support 15, and then move the cap beam formwork support 11 and the modular cap beam formwork unit 2 out of the corresponding bridge pier 04 as a whole.
[0056] When it is necessary to move the cap beam formwork support 11 and the modular cap beam formwork unit 2 as a whole into the bridge pier 04, first make the corresponding bridge pier 04 located in the makeshift space of the corresponding reinforced recessed support 15, then install the reinforced recessed support 15 on the corresponding cap beam formwork support 11, and then remove the corresponding movable sheet frame 14. The cap beam formwork support 11 and the modular cap beam formwork unit 2 can be moved and brought as a whole close to the corresponding bridge pier 04 by utilizing the makeshift space of the reinforced recessed support 15. After moving into place, install the corresponding movable sheet frame 14, remove the corresponding reinforced recessed support 15, and then the cap beam formwork support 11 and the modular cap beam formwork unit 2 can be moved as a whole into the corresponding bridge pier 04.
[0057] The cap beam formwork support unit 1 is equipped with a plurality of elastic guide wheels 16 ; when the lifting cylinder 31 drives the cap beam formwork support unit 1 to move up and down along the bridge pier 04 , the elastic guide wheels 16 roll along the surface of the bridge pier 05 to guide the cap beam formwork support unit 1 .
[0058] The modular cap beam template unit 2, such as Figures 15 to 17As shown, it includes a distribution beam 21, a bottom template 22, and a side template 23; the distribution beam 21 is detachably mounted on the cap beam template support unit 1; the bottom template 22 is mounted on the distribution beam 21; the side templates 23 are mounted on the distribution beam 21 and are respectively located on both sides of the bottom template 22; multiple modular cap beam template units 2 are sequentially spliced with each other, and the first and last modular cap beam template units 2 are provided with baffles 5 to form a complete cap beam template 6. The modular cap beam template unit 2 may also include a tie rod 24 located at the top for tightening the two side templates 23.
[0059] The side formwork 23 is provided with a straightening device, which includes a telescopic support rod 25, a rolling module 26, and a fixing device 27; the distribution beam 21 is a double-channel steel, which is provided with a plurality of mounting holes for mounting the fixing device 27, and the fixing device 27 can be fixed on the corresponding mounting holes of the double-channel steel as needed; one end of the telescopic support rod 25 is hinged to the side formwork 23, and the other end of the telescopic support rod 25 is hinged to the rolling module 26; the rolling module 26 can roll along the distribution beam 21, and one end of the rolling module 26 is hinged to the side formwork 23, and the other end of the rolling module 26 is against the fixing device 27; when the side formwork 23 is not fixedly installed on the distribution beam 21, it can slide along the distribution beam 21; the fixing device 27 is provided with a threaded adjustment push rod 28, and rotating the threaded adjustment push rod 28 can push the rolling module 26 to move on the distribution beam 21, so as to adjust the side formwork 23.
[0060] The modular cap beam template unit 2 is fixed to the cap beam template support 11 by a fixing clamping device 8. Fig.13 and Fig.14 As shown, the fixing clamping device 8 includes a clamping plate 81, an upper clamping block 82, and a lower clamping block 83. The upper clamping block 82 and the lower clamping block 83 are both provided at both ends of the clamping plate 81, and a fastening screw is provided between the upper clamping block 82 and the lower clamping block 83. The upper clamping block 82 is pressed downwardly on the channel steel of the distribution beam 21, and the lower clamping block 83 is pressed upwardly on the steel structure profile on the upper part of the cap beam formwork support 11, thereby fixing the modular cap beam formwork unit 2 on the cap beam formwork support 11.
[0061] like Figure 3The figure shows the working state of the bridge cap beam construction system. In this embodiment, a base 08 is additionally configured, and the base 08 is placed on the ground (in other embodiments, there may be a base, or the ground may be hardened sufficiently and the standard support section may be directly installed), and the bridge pier 04 is tightened and clamped by the threaded tie rod 07. The connecting seat 09, the bottom adjustment support section 34, and the standard support section 32 are sequentially placed on the base 08, and each standard support section 32 is tightened on the bridge pier 04 by the threaded tie rod 07 with the clamp 33 attached to fix it. The cap beam formwork support unit 1 is placed on the unloading block 35, and the side formwork 23 is placed on the cap beam formwork support 11. The planar universal translation system 4 and the translation connection bracket 7 are placed on the ground to be used for translation.
[0062] The working process of a double cantilever cap beam construction system of the present invention is as follows:
[0063] Step S1, such as Fig.18 , low-position installation cap beam template support unit 1, modular cap beam template unit 2
[0064] At the lower position of the bridge pier 04, assemble the standard support section 32, the jacking cylinder 31, and the corresponding attachment hoop 33 of the jacking system according to actual needs; assemble the cap beam template support unit 1; assemble the modular cap beam template unit 2 to the cap beam template support 11; load a certain amount of standard support sections 32, attachment hoops 33, adjustment support sections 34, and unloading blocks 35 on the pulley 13 according to actual needs;
[0065] Step S2, such as Figures 19 to 22 , the climbing of cap beam formwork support unit 1
[0066] S2a, the lifting cylinder 31 lifts a stroke, driving the cap beam formwork support unit 1 to climb to the preset position along the bridge pier 04; removes the standard support section 32 and the corresponding attachment clamp 33 from the pulley 13; the standard support section 32 removed from the pulley 13 is fixedly connected to the aforementioned uppermost standard support section 32 that has been assembled, and is locked on the bridge pier 04 through the corresponding attachment clamp 33; the lifting cylinder 31 retracts to allow the cap beam formwork support unit 1 to be temporarily supported on the current uppermost standard support section 32; the other end of the lifting cylinder 31 is removed from the lower standard support section 32, and after being reinstalled on the higher standard support section 32, the lifting cylinder 31 lifts again to drive the cap beam formwork support unit 1 to climb upward along the bridge pier 04;
[0067] S2b, repeat step S2a until the cap beam template support unit 1 is lifted to the predetermined position of the pier, remove the adjustment support section 34 and / or the unloading block 35 from the pulley 13 according to actual needs, adjust the cap beam template support unit 1 to the cap beam construction height, and carry out the cap beam construction at the current workstation;
[0068] Step S3, such as Fig.23 and Fig.24 , the cap beam formwork support unit 1 is lowered
[0069] S3a, after the cap beam construction of the current station is completed, the unloading block 35 and / or the adjustment support section 34 and / or the standard support section 32 are dismantled in sequence, and the standard support sections 32 from top to bottom are dismantled one by one by changing the connection between the jacking cylinder 31 and the standard support sections 32 of different heights from top to bottom, and the cap beam formwork support unit 1 is driven to descend;
[0070] Step S4, such as Figures 25 to 30 , move the cap beam formwork support unit 1 to the next station
[0071] When the cap beam formwork support unit 1 is lowered to a predetermined position, it is seated on the universal translation system 4 on the ground; the reinforced recessed support 15 is installed on the corresponding cap beam formwork support 11, and then the corresponding movable sheet frame 14 is disassembled, and the space left by the reinforced recessed support 15 can be utilized to adopt the universal translation system 4 to move the cap beam formwork support 11 and the modular cap beam formwork unit 2 as a whole away from the bridge pier of the current work station, and after moving into position, the corresponding movable sheet frame 14 is installed, and the corresponding reinforced recessed support 15 is disassembled, and the cap beam formwork support 11 and the modular cap beam formwork unit 2 are moved as a whole out of the bridge pier 04 of the current work station;
[0072] When the cap beam formwork support 11 and the modular cap beam formwork unit 2 are moved as a whole into the bridge pier of the next station, firstly, the corresponding bridge pier 04 is located in the making way space of the corresponding reinforced recessed support 15, and then the reinforced recessed support 15 is installed on the corresponding cap beam formwork support 11, and then the corresponding movable sheet frame 14 is removed, and the cap beam formwork support 11 and the modular cap beam formwork unit 2 can be moved as a whole close to the corresponding bridge pier by using the making way space of the reinforced recessed support 15, and then the corresponding movable sheet frame 14 is installed after moving into place, and the corresponding reinforced recessed support 15 is removed, and then the cap beam formwork support 11 and the modular cap beam formwork unit 2 can be moved as a whole into the corresponding bridge pier of the next station, so as to carry out the cap beam construction;
[0073] Repeat steps S2 to S4 until the entire cap beam construction is completed.
[0074] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. It should be pointed out that any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A cap beam formwork support unit for double cantilever cap beam construction, characterized in that: It includes a cap beam formwork support, on which a slide rail is provided, and a plurality of pulleys which can slide along the slide rail are provided on the slide rail; the pulleys can be used to load items; the cap beam formwork support is also provided with a detachable movable sheet frame; the cap beam formwork support unit also includes a detachable reinforcing recessed support used in matching with the movable sheet frame of the cap beam formwork support, and the reinforcing recessed support has at least one makeshift space for accommodating a corresponding bridge pier; by alternately installing / disassembling the corresponding reinforcing recessed support and the movable sheet frame, the cap beam formwork support can be moved out of or into the corresponding bridge pier as a whole.
2. The cap beam formwork support unit for double cantilever cap beam construction according to claim 1, characterized in that: The cap beam formwork support unit is equipped with a plurality of elastic guide wheels; when the cap beam formwork support unit moves up and down along the bridge pier, the elastic guide wheels roll along the surface of the bridge pier to guide the cap beam formwork support unit.