Standard pile for erecting static load datum beam
The design of anti-sinking and support components solved the problem of benchmark pile subsidence, improved the accuracy and safety of benchmark beam erection, adapted to benchmark beams of different heights and lengths, and simplified the operation.
Patent Information
- Application Number
- CN202420613687.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-27
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-03-27
AI Technical Summary
Traditional benchmark piles are prone to sinking due to weight pressure when supporting benchmark beams, which reduces the accuracy and safety of the erection and makes the operation cumbersome when the height is not suitable.
The structure employs a barrier plate for the anti-sinking component and a support rod for the support component. The barrier plate limits the depth of the fixed rod, and the support rod can slide and rotate to adapt to the reference beams of different heights and lengths. It is then combined with the placement rod of the auxiliary placement component for clamping and fixing.
It improves the accuracy and safety of benchmark beam erection, reduces the settlement depth of fixing rods, adapts to the needs of benchmark beams of different heights and lengths, and simplifies the operation process.
Smart Images

Figure CN221989411U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of civil engineering and building construction, and in particular to a reference pile for erecting a static load reference beam. Background Art
[0002] In civil engineering and construction, the erection of static load reference beams is one of the key links. Reference piles are a concept in surveying, also known as reference points. In static load tests, they are mainly used to erect reference beams.
[0003] Traditional benchmark piles usually consist of a base and a support frame. The base is driven into the foundation, and the benchmark beam is placed on the support frame, which supports the benchmark beam. However, since the height of the support frame is fixed, it can only accommodate benchmark beams of a specific height. For benchmark beams that do not match the height, it is usually necessary to dig a hole in the ground and place the base in the hole to adapt to the required height. The operation is cumbersome and inefficient.
[0004] In view of the above-mentioned related technologies, in order to solve the problem of height mismatch, some projects have adopted adjustable height support frames. However, in actual operations, since the support frame has to support the reference beam, under the weight pressure of the reference beam, the reference piles inserted into the foundation may sink and settle, thereby affecting the installation accuracy and safety of the reference beam. Therefore, reducing the depth of the reference pile settlement is an issue that needs to be urgently addressed. Utility Model Content
[0005] In order to reduce the amplitude of the settlement of the reference pile, the present application provides a reference pile for erecting a static load reference beam.
[0006] The present application provides a reference pile for erecting a static load reference beam, which adopts the following technical solution:
[0007] A reference pile for erecting a static load reference beam, comprising a fixing rod, an anti-sinking assembly and a supporting assembly;
[0008] The anti-sinking assembly comprises a blocking plate, the blocking plate is connected to the fixing rod, the blocking plate is perpendicular to the fixing rod, and the blocking plate is slidably connected to the blocking plate along the rod length direction of the fixing rod;
[0009] The support assembly includes a support rod, the support rod is directly or indirectly connected to the fixing rod, and the support rod is located above the blocking plate.
[0010] By adopting the above technical solution, during construction, a fixing rod is driven into the foundation, and the reference beam is supported by the support rod. Since the reference beam has a certain weight, the fixing rod may sink under pressure, which will affect the accuracy and safety of the erection of the reference beam. For this reason, the depth of the fixing rod inserted into the foundation is limited by the blocking plate on the fixing rod. After the fixing rod is inserted into the foundation, the blocking plate is slid to make the blocking plate contact with the ground, and the position of the blocking plate on the fixing rod can be adjusted by the depth of the fixing rod inserted into the foundation, so that the position of the fixing rod in the foundation is positioned and fixed by the blocking plate. By setting the blocking plate, the depth of the settlement of the reference pile is reduced, and the accuracy of the erection of the reference beam is improved.
[0011] Optionally, the anti-sinking assembly also includes a sliding member and a locking nut, the sliding member is provided with a first through hole along a first direction, the fixing rod is passed through the first through hole, the sliding member is fixedly connected to the blocking plate, the sliding member is located on a side of the blocking plate close to the support rod, the sliding member is slidably connected to the fixing rod along the rod length direction of the fixing rod, the locking nut passes through the side wall of the sliding member and is tightened against the fixing rod, and the locking nut is threadedly connected to the sliding member.
[0012] By adopting the above technical solution, the sliding member is fixed to the blocking plate, so that the blocking plate is positioned on the fixed rod by the sliding member, the sliding member slides along the rod length direction of the fixed rod, and the sliding member is fixed by the locking nut.
[0013] Optionally, the support rod is slidably connected to the fixing rod along the rod length direction of the fixing rod.
[0014] By adopting the above technical solution, since the installation positions of the reference beams are different, in order to make the support rods adapt to the installation heights of reference beams of different heights, the support rods are slidably connected to the fixed rods along the rod length direction of the fixed rods.
[0015] Optionally, the support assembly also includes a mounting seat, which is sleeved on the fixing rod, one end of the fixing rod is fixedly connected to the mounting seat, the mounting seat is detachably connected to the fixing rod, the mounting seat is rotatably connected to the fixing rod, and the mounting seat is parallel to the first direction along the rotation axis of the fixing rod.
[0016] By adopting the above technical solution, in order to drive the support rod to slide, the mounting seat is detachably connected to the fixed rod, so that the supporting rod can be driven to slide along the rod length direction of the fixed rod through the sliding mounting seat. In addition, due to the different installation positions of the reference beam, if the position needs to be changed, personnel are required to pull up or rotate the fixed rod, which is a cumbersome and labor-intensive process. For this reason, the mounting seat and the fixed rod are detachably connected. Therefore, the mounting seat can be rotated along the circumference of the fixed rod to further enable the support rod to rotate along the circumference of the fixed rod, so that the support rod can be installed for reference beams with different position requirements.
[0017] Optionally, a positioning nut is threadedly connected to the support rod, and the positioning nut is slidably connected to the support rod along the rod length direction of the support rod.
[0018] By adopting the above technical solution, after the reference beam is erected on the support rod, in order to prevent the reference beam from slipping, the reference beam is threadedly connected to the support rod through a positioning nut, so that the positioning nut can tighten the reference beam.
[0019] Optionally, one end of the fixing rod close to the blocking plate is tapered, and an outer diameter of the tapered portion of the fixing rod gradually decreases toward a side away from the blocking plate.
[0020] By adopting the above technical solution, in order to smoothly insert the fixing rod into the foundation, one end of the fixing rod is tapered. The tapered fixing rod can reduce the contact area with the ground, so that the fixing rod can be inserted into the foundation more smoothly.
[0021] Optionally, an auxiliary placement component is also included, which includes a connecting rod and a placement rod, the connecting rod is parallel to the second direction, the second direction is perpendicular to the first direction, one end of the connecting rod is directly or indirectly connected to the support rod, and the other end is fixedly connected to the placement rod, so that a placement gap is formed in a third direction by the support rod and the connecting rod, and the third direction is perpendicular to both the first direction and the second direction.
[0022] By adopting the above technical solution, since the lengths of the reference beams are different, in order to improve the supporting force for the reference beams of different lengths and to improve the stability of the reference beams, a placing rod is connected to the supporting rod to further improve the supporting force for the reference beam.
[0023] Optionally, the auxiliary placement assembly also includes a mounting nut, which is threadedly connected to the support rod, and one end of the connecting rod close to the support rod is fixedly connected to the mounting nut, the connecting rod is rotatably connected to the support rod, and the connecting rod is parallel to the second direction along the rotation axis of the support rod. In the first direction, when the connecting rod rotates along the support rod to be parallel to the support rod, a placement area is formed between the connecting rod and the support rod.
[0024] By adopting the above technical solution, after the reference beam is erected on the support rod, the reference beam is clamped only by the positioning nut. If the size of the reference beam is large, there is still a risk of slipping. For this reason, the nut is installed by the station east to further drive the placement rod to rotate along the circumference of the fixed rod to a state parallel to the fixed rod in the first direction. The reference beam is located in the placement area, so that the reference beam is clamped and fixed by the fixed rod and the placement rod to reduce the reference beam from falling.
[0025] Optionally, the connecting rod is a telescopic rod structure, the fixed section of the connecting rod is fixedly connected to the mounting nut, and the fixed section of the connecting rod is slidably connected to one end of the movable section.
[0026] By adopting the above technical solution, due to the different lengths of the reference beams, in order to be able to better adapt to reference beams of different lengths, the connecting rod is a telescopic rod structure, so that the width of the placement gap and the depth of the placement area can be adjusted by adjusting the length of the connecting rod, so that the placement rod has adaptability.
[0027] Optionally, a scale is provided on the outer wall of the fixing rod.
[0028] By adopting the above technical solution, during construction, two reference piles are erected at both ends of the reference beam. In order to keep the reference beam in a horizontal state, the two support rods need to be at the same horizontal height. For this purpose, a scale is provided on the fixed rod, which facilitates personnel to observe the position of the support rod on the fixed rod when sliding the support rod along the rod length direction of the fixed rod.
[0029] In summary, the present application includes at least one of the following beneficial technical effects:
[0030] 1. The present application can reduce the depth of the fixing rod inserted into the foundation through the anti-sinking assembly, so as to improve the erection accuracy and construction safety of the static load reference beam;
[0031] 2. The present application can further support reference piles of different lengths through the placement rod of the auxiliary placement assembly to improve the stability of the reference piles;
[0032] 3. In the present application, the placing rod is rotated along the circumference of the supporting rod. When the placing rod is rotated above the supporting rod, the placing rod and the supporting rod clamp and fix the reference beam. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 It is a structural schematic diagram of an anti-sinking component and a supporting component of a reference pile for erecting a static load reference beam of the present application;
[0034] Figure 2 This is a schematic diagram of the structure of the auxiliary placement component of this application from the first perspective;
[0035] Figure 3 This is a schematic diagram of the structure of the auxiliary placement component of the present application from a second perspective;
[0036] Figure 4 It is a structural schematic diagram of the fixing rod of the present application.
[0037] Explanation of the accompanying drawings: 1. fixing rod; 11. scale groove; 2. anti-sinking assembly; 21. blocking plate; 211. second through hole; 22. sliding member; 221. first through hole; 23. locking nut; 3. supporting assembly; 31. mounting seat; 311. through groove; 312. connecting plate; 3121. mounting hole; 32. supporting rod; 321. positioning nut; 4. auxiliary placement assembly; 41. connecting rod; 42. mounting nut; 43. placement rod; 431. placement gap; 432. placement area; 44. fixing member. DETAILED DESCRIPTION
[0038] The following is combined with Figure 1-4 This application is described in further detail.
[0039] Embodiment 1:
[0040] The present application embodiment discloses a reference pile for erecting a static load reference beam. Figure 1 The reference pile for erecting a static load reference beam includes a fixed rod 1, an anti-sinking component 2 and a supporting component 3. The anti-sinking component 2 is slidably connected to the fixed rod 1 along the rod length direction of the fixed rod 1 so that the anti-sinking component 2 limits the depth of the fixed rod 1 inserted into the foundation. The supporting component 3 is connected to the fixed rod 1 so that the supporting component 3 supports the reference beam.
[0041] Reference Figure 1The anti-sinking assembly 2 includes a blocking plate 21, a sliding member 22 and a locking nut 23. The blocking plate 21 is perpendicular to the fixed rod 1. The sliding member 22 is provided with a first through hole 221 along the first direction. The blocking plate 21 is provided with a second through hole 211 along the first direction. The fixed rod 1 is sequentially penetrated through the first through hole 221 and the second through hole 211. The bottom wall of the sliding member 22 is fixedly connected to the blocking plate 21. The sliding member 22 is slidably connected to the fixed rod 1 along the length direction of the fixed rod 1 to drive the blocking plate 21 to slide along the length direction of the fixed rod 1 and lock the locking nut 23. After the nut 23 passes through the side wall of the sliding member 22, it is tightened against the fixing rod 1, and the locking nut 23 is threadedly connected to the sliding member 22; after determining the depth of the fixing rod 1 in the foundation, one end of the fixing rod 1 is inserted into the foundation, and the sliding member 22 is slid along the length direction of the fixing rod 1 so that the bottom wall of the blocking plate 21 is in contact with the ground. When there are other external forces acting on the fixing rod 1, the blocking effect of the blocking plate 21 will further reduce the phenomenon of the fixing rod 1 sinking into the foundation. In this embodiment, the cross-section of the fixing rod 1 is circular.
[0042] Reference Figure 1 In order to support the reference beam, the support assembly 3 includes a mounting seat 31 and a support rod 32. The mounting seat 31 is sleeved on the fixed rod 1. The mounting seat 31 is located above the sliding member 22. The mounting seat 31 is detachably connected to the fixed rod 1. Specifically, the mounting seat 31 is provided with a through slot 311 perpendicular to the first direction. Both ends of the notch of the through slot 311 are fixedly connected with a connecting plate 312. Each connecting plate 312 is provided with a corresponding mounting hole 3121. The mounting seat 31 is threadedly engaged with the mounting hole 3121 by screws to realize 31 is connected with the fixed rod 1, the support rod 32 is arranged horizontally, and one end of the support rod 32 is fixedly connected to the mounting seat 31. Due to the different erection heights of the reference beam, the mounting seat 31 is slidably connected to the fixed rod 1 along the rod length direction of the fixed rod 1 to further drive the support rod 32 to slide along the rod length direction of the fixed rod 1 to the construction position. In addition, since the mounting seat 31 and the fixed rod 1 are detachably connected, the mounting seat 31 can rotate along the circumference of the fixed rod 1 to further enable the support rod 32 to erect reference beams required at different positions.
[0043] Reference Figure 1 After the reference beam is placed on the support rod 32, in order to limit and clamp the position of the reference beam on the support rod 32, in this embodiment, the support rod 32 is a screw rod, and a positioning nut 321 is threadedly connected to the support rod 32. The positioning nut 321 is slidably connected to the support rod 32 along the rod length direction of the support rod 32, so that the support rod 32 is clamped by the positioning nut 321 to prevent the reference beam from slipping off the support rod 32.
[0044] Reference Figure 1In order to facilitate the insertion of the fixing rod 1 into the foundation, the end of the fixing rod 1 close to the blocking plate 21 is tapered, and the outer diameter of the tapered part of the fixing rod 1 gradually decreases toward the side away from the blocking plate 21. The tapered end of the fixing rod 1 is inserted into the foundation for fixation.
[0045] Embodiment 2:
[0046] Reference Figure 2 During construction, two reference piles are generally placed at both ends of the reference beam. When in use, the personnel first set up one end of the reference beam on one of the support rods 32, and then set up the other end on the other support rod 32. Due to the different lengths of the reference beams, in order to further improve the supporting force of the reference beams, the reference piles for erecting static load reference beams also include an auxiliary placement assembly 4, the auxiliary placement assembly 4 includes a connecting rod 41, a mounting nut 42 and a placement rod 43, the mounting nut 42 is threadedly connected to the support rod 32, the connecting rod 41 is horizontally arranged, the connecting rod 41 is parallel to the second direction, and the second direction is perpendicular to the first direction, one end of the connecting rod 41 is fixedly connected to the mounting nut 42, and the other end is fixedly connected to the placement rod 43. In this embodiment, the placement rod 43 is arranged parallel to the support rod 32, so that a placement gap 431 is formed in the third direction by the placement rod 43 and the support rod 32, so that the placement rod 43 can improve the supporting force of the reference beam.
[0047] Reference Figure 2 Due to the different lengths of the reference beams, in order to further increase the supporting force for the reference beam, the connecting rod 41 is a telescopic rod structure, the fixed section of the connecting rod 41 is fixedly connected to the side wall of the mounting nut 42, the movable section of the connecting rod 41 is fixedly connected to the placement rod 43 at one end away from the fixed section, the fixed section of the connecting rod 41 is slidably connected to the end close to the movable section, the sliding direction of the movable section of the connecting rod 41 is parallel to the third direction, the movable section of the connecting rod 41 is fixedly connected to the fixed section by a fixing member 44, in this embodiment, the fixing member 44 is a screw, specifically, one end of the fixing member 44 passes through the fixed section and then abuts against the movable section, so that the width of the placement gap 431 can be adjusted by adjusting the length of the connecting rod 41, if the length of the reference beam is longer, the length of the connecting rod 41 can be appropriately extended to further enable the placement rod 43 to support the reference beam.
[0048] Reference Figure 3When the reference beam is placed on the support rod 32, in order to prevent the reference beam from falling or moving, which would affect subsequent construction operations, the connecting rod 41 can rotate along the circumference of the support rod 32 by installing the nut 42, further driving the placement rod 43 to rotate along the circumference of the support rod 32. In the first direction, when the placement rod 43 rotates along the support rod 32 to a position parallel to the support rod 32, a placement area 432 is formed between the placement rod 43 and the support rod 32. When the placement rod 43 is located above the support rod 32, the length of the connecting rod 41 is adjusted to make the placement rod 43 abut against the top wall of the reference beam, so that the reference beam is clamped by the connecting rod 41 and the placement rod 43.
[0049] Reference Figure 2 and Figure 3 The different positions of the rod 43 have different effects on the reference beam, which can be divided into the following cases:
[0050] In the third direction, when the placement rod 43 rotates along the circumference of the support rod 32 to be parallel to the support rod 32, the placement rod 43 can support the reference beam, and the supporting force for reference beams of different lengths can be further improved by adjusting the length of the connecting rod 41;
[0051] In the first direction, when the placement rod 43 rotates along the circumference of the support rod 32 to be parallel to the support rod 32, and the placement rod 43 is above the support rod 32, the reference beam is clamped by the placement rod 43 and the support rod 32 by adjusting the length of the connecting rod 41;
[0052] In the first direction, when the placement rod 43 rotates along the circumference of the support rod 32 to be parallel to the support rod 32 and the placement rod 43 is below the support rod 32, the reference beam can be placed on the placement rod 43 to adapt to reference beams with different height requirements.
[0053] Reference Figure 4 During construction, in order to ensure that the reference beam remains horizontal, the two support rods 32 need to be flush with the fixed rod 1. To this end, the fixed rod 1 is provided with a scale groove 11 along the length of the rod itself. Personnel can adjust the positions of the two support rods 32 to a horizontal state by observing the scale on the fixed rod 1 to ensure that the reference beam is in a horizontal state.
[0054] The implementation principle of a reference pile for erecting a static load reference beam in an embodiment of the present application is as follows: insert a fixed rod 1 with a cone at one end into the foundation, adjust the locking nut 23, slide the sliding member 22 along the rod length direction of the fixed rod 1 to make the blocking plate 21 abut against the ground, determine the position of the support rod 32 on the fixed rod 1 by adjusting the mounting seat 31, and place the reference beam on the support rod 32. If the reference beam is longer, the reference beam is further supported by the placement rod 43 by adjusting the length of the connecting rod 41, and the positioning nut 321 is rotated until it abuts against the reference beam. If the reference beam is shorter, rotate the mounting nut 42 to rotate the placement plate to a position horizontal with the fixed rod 1 in the height direction, and clamp the reference beam by the placement plate and the support rod 32 by adjusting the length of the connecting rod 41.
[0055] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A reference pile for erecting a static load reference beam, characterized in that: It comprises a fixing rod (1), an anti-sinking component (2) and a supporting component (3); The anti-sinking assembly (2) comprises a baffle plate (21), the baffle plate (21) is connected to the fixing rod (1), the baffle plate (21) is perpendicular to the fixing rod (1), and the baffle plate (21) is slidably connected to the baffle plate (21) along the rod length direction of the fixing rod (1); The support assembly (3) comprises a support rod (32), the support rod (32) being directly or indirectly connected to the fixing rod (1), and the support rod (32) being located above the blocking plate (21).
2. The reference pile for erecting a static load reference beam according to claim 1, characterized in that: The anti-sinking component (2) also includes a sliding member (22) and a locking nut (23); the sliding member (22) is provided with a first through hole (221) extending through the sliding member (22) along a first direction; the fixing rod (1) is passed through the first through hole (221); the sliding member (22) is fixedly connected to the blocking plate (21); the sliding member (22) is located on a side of the blocking plate (21) close to the supporting rod (32); the sliding member (22) is slidably connected to the fixing rod (1) along the length direction of the fixing rod (1); the locking nut (23) passes through the side wall of the sliding member (22) and is pressed against the fixing rod (1); the locking nut (23) is threadedly connected to the sliding member (22).
3. The reference pile for erecting a static load reference beam according to claim 1, characterized in that: The support rod (32) is slidably connected to the fixing rod (1) along the rod length direction of the fixing rod (1).
4. The reference pile for erecting a static load reference beam according to claim 2, characterized in that: The support assembly (3) further comprises a mounting seat (31), the mounting seat (31) being sleeved on the fixing rod (1), one end of the fixing rod (1) being fixedly connected to the mounting seat (31), the mounting seat (31) being detachably connected to the fixing rod (1), the mounting seat (31) being rotatably connected to the fixing rod (1), and the mounting seat (31) being parallel to the first direction along the rotation axis of the fixing rod (1).
5. The reference pile for erecting a static load reference beam according to claim 4, characterized in that: A positioning nut (321) is threadedly connected to the support rod (32), and the positioning nut (321) is slidably connected to the support rod (32) along the rod length direction of the support rod (32).
6. The reference pile for erecting a static load reference beam according to claim 1, characterized in that: One end of the fixing rod (1) close to the blocking plate (21) is tapered, and the outer diameter of the tapered portion of the fixing rod (1) gradually decreases toward a side away from the blocking plate (21).
7. A reference pile for erecting a static load reference beam according to any one of claim 2, characterized in that: It also includes an auxiliary placement component (4), the auxiliary placement component (4) includes a connecting rod (41) and a placement rod (43), the connecting rod (41) is parallel to a second direction, the second direction is perpendicular to the first direction, one end of the connecting rod (41) is directly or indirectly connected to the support rod (32), and the other end is fixedly connected to the placement rod (43), so that a placement gap (431) is formed in a third direction by the support rod (32) and the connecting rod (41), and the third direction is perpendicular to both the first direction and the second direction.
8. The reference pile for erecting a static load reference beam according to claim 7, characterized in that: The auxiliary placement assembly (4) also includes a mounting nut (42), the mounting nut (42) being threadedly connected to the support rod (32), one end of the connecting rod (41) close to the support rod (32) being fixedly connected to the mounting nut (42), the connecting rod (41) being rotatably connected to the support rod (32), the connecting rod (41) being parallel to the second direction along the rotation axis of the support rod (32), and in the first direction, when the connecting rod (41) is rotated along the support rod (32) to be parallel to the support rod (32), a placement area (432) is formed between the connecting rod (41) and the support rod (32).
9. The reference pile for erecting a static load reference beam according to claim 8, characterized in that: The connecting rod (41) is a telescopic rod structure, the fixed section of the connecting rod (41) is fixedly connected to the mounting nut (42), and the fixed section of the connecting rod (41) is slidably connected to one end close to the movable section.
10. The reference pile for erecting a static load reference beam according to claim 8, characterized in that: The outer wall of the fixing rod (1) is provided with a scale groove (11).