Valve control type multi-mode pressure vessel test board convenient to switch

By designing a valve-controlled multi-mode test bench in the pressure vessel test equipment, the solenoid valve and safety valve are used to achieve disassembly and switch blasting and fatigue testing modes, solving the cumbersome problem of traditional equipment switching modes, improving the testing efficiency and reducing the cost.

CN221993208UActive Publication Date: 2024-11-12CHANGSHA KAIZHUO ELECTROMECHANICAL EQUIP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420341987.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-23
Publication Date
2024-11-12
Estimated Expiration
2034-02-23

AI Technical Summary

Technical Problem

Traditional pressure vessel testing equipment requires disassembly and reconnection of workpieces when switching test modes, resulting in high costs, cumbersome steps and low testing efficiency.

Method used

A valve-controlled multi-mode convenient switching pressure vessel test bench was designed. Through the reasonable connection of hydraulic oil tank, return water tank, oil cooler, water cooler, blasting cylinder and fatigue cylinder, the solenoid valve and various safety valves are used to achieve two types of This test mode has no disassembly switching, combining blasting and fatigue testing functions.

Benefits of technology

On the premise of ensuring safety, convenient switching of test mode is achieved, testing efficiency is improved, and cost savings are saved without adding functions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221993208U_ABST
    Figure CN221993208U_ABST
Patent Text Reader

Abstract

The utility model discloses a valve control type multi-mode convenient switching pressure vessel test bench, which is characterized in that the input ends of a blasting cylinder and a fatigue cylinder are communicated and connected with a hydraulic oil tank, the output ends of the blasting cylinder and the fatigue cylinder are communicated and connected with the test bench, and a water outlet end pipeline of a first water return tank is communicated and connected with a pipeline for connecting the fatigue cylinder and the test bench; a first one-way valve is installed on a pipeline connecting the explosion cylinder and the test bench, and a first pressure gauge and a normally-open solenoid valve are installed on a pipeline connecting the fatigue cylinder and the test bench. Through reasonable use of the solenoid valve and various safety valves, functions of two types of test equipment are combined together on the premise that safety is guaranteed; the testing mode can be switched under the condition that a testing workpiece is not disassembled, one machine has two purposes, the testing efficiency is improved, and the cost can be effectively saved on the premise that the same function is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of testing equipment, and more specifically, particularly to a valve-controlled multi-mode convenient switching pressure vessel testing bench. Background Art

[0002] Pressure vessels need to undergo pressure tests before leaving the factory, and the test items include high-pressure water burst test and fatigue test. When traditional testing equipment is testing pressure vessels, it is necessary to switch the test mode and remove the workpiece from the test equipment, and then reconnect it to other types of test equipment before testing. This is costly, cumbersome, and has low test efficiency. Utility Model Content

[0003] The utility model aims to provide a valve-controlled multi-mode conveniently switchable pressure vessel test bench.

[0004] In order to achieve the above-mentioned purpose, the technical solution adopted by the utility model is as follows: a valve-controlled multi-mode convenient switching pressure vessel test bench, including a test bench for placing workpieces, and also including a hydraulic oil tank, a first return water tank, a second return water tank, an oil cooler, a water cooler, a blasting cylinder and a fatigue cylinder;

[0005] The input ends of the blasting cylinder and the fatigue cylinder are both connected to the hydraulic oil tank, and the output ends of the blasting cylinder and the fatigue cylinder are both connected to the test bench. The water outlet pipe of the first return water tank is connected to the pipe connecting the fatigue cylinder and the test bench. A third one-way valve is installed on the return water end pipe of the first return water tank. A first one-way valve is installed on the pipe connecting the blasting cylinder and the test bench. A first pressure gauge and a normally open solenoid valve are installed on the pipe connecting the fatigue cylinder and the test bench. The return water end pipe of the second return water tank is connected to the return water end pipe of the first return water tank and the pipe connecting the blasting cylinder and the test bench.

[0006] Preferably, the oil cooler and the water cooler are respectively connected to the hydraulic oil tank and the fatigue cylinder.

[0007] Preferably, a two-position three-way solenoid valve reversing valve, a two-position three-way solenoid reversing valve, a second pressure sensor and a third pressure gauge are installed on the pipeline connecting the hydraulic oil tank with the blasting cylinder and the fatigue cylinder.

[0008] Preferably, a first pressure sensor is installed on the pipe connecting the second return water tank and the return water end of the first return water tank.

[0009] Preferably, a first pressure gauge is installed on the pipe connecting the fatigue cylinder and the test bench and the return water end pipe of the first return water tank.

[0010] Preferably, the output end of the blasting cylinder is connected to a return water end pipeline of the first return water tank, and a second one-way valve and a second pressure gauge are installed on the pipeline.

[0011] Preferably, two pipes are provided for connecting the return end of the second return water tank to the test bench, a normally closed solenoid valve and an overflow valve are installed on the two pipes respectively, and a third pressure sensor is installed at the connection between the two pipes and the test bench.

[0012] Compared with the prior art, the advantages of the utility model are:

[0013] The utility model combines the functions of two types of test equipment under the premise of ensuring safety by reasonably using solenoid valves and various safety valves, so that the test modes can be switched without disassembling the test workpiece, and one machine has two uses, which improves the test efficiency and can effectively save costs under the premise of achieving the same functions. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0015] Figure 1 The utility model discloses a pipeline connection diagram of a valve-controlled multi-mode convenient switching pressure vessel test bench.

[0016] In the figure: 1 test bench, 2 hydraulic oil tank, 3 first return water tank, 4 oil cooler, 5 water cooler, 6 blasting cylinder, 7 fatigue cylinder, 8 cooling water tank, 9 first one-way valve, 10 second one-way valve, 11 third one-way valve, 12 first pressure gauge, 13 first pressure sensor, 14 second pressure gauge, 15 normally open solenoid valve, 16 second pressure sensor, 17 third pressure gauge, 18 two-position three-way solenoid reversing valve, 19 two-position two-way solenoid reversing valve, 20 third pressure sensor, 21 second return water tank, 22 normally closed solenoid valve, 23 overflow valve. DETAILED DESCRIPTION

[0017] The preferred embodiments of the present invention are described in detail below in conjunction with the accompanying drawings so that the advantages and features of the present invention can be more easily understood by those skilled in the art, thereby making a clearer and more definite definition of the protection scope of the present invention.

[0018] See also Figure 1 As shown, the utility model provides 1. a valve-controlled multi-mode convenient switching pressure vessel test bench, comprising a test bench 1 for placing a workpiece, and also comprising a hydraulic oil tank 2, a first return water tank 3, a second return water tank 21, an oil cooler 5, a water cooler 5, a blasting cylinder 6 and a fatigue cylinder 7;

[0019] The blasting cylinder 6 and the fatigue cylinder 7 are both hydraulic cylinders in the prior art;

[0020] The input ends of the blasting cylinder 6 and the fatigue cylinder 7 are both connected to the hydraulic oil tank 2, and the output ends of the blasting cylinder 6 and the fatigue cylinder 7 are both connected to the test bench 1. The water outlet pipe of the first return water tank 3 is connected to the pipe connecting the fatigue cylinder 7 and the test bench 1. A third one-way valve 11 is installed on the return water end pipe of the first return water tank 3. A first one-way valve 9 is installed on the pipe connecting the blasting cylinder 6 and the test bench 1. A first pressure gauge 12 and a normally open solenoid valve 15 are installed on the pipe connecting the fatigue cylinder 7 and the test bench 1. The return water end pipe of the second return water tank 21 is connected to the return water end pipe of the first return water tank 3 and the pipe connecting the blasting cylinder 6 and the test bench 1.

[0021] In this embodiment, the oil cooler 5 and the water cooler 5 are connected to the hydraulic oil tank 2 and the fatigue cylinder 7 respectively.

[0022] In this embodiment, a two-position three-way solenoid valve 19, a two-position three-way solenoid directional valve 18, a second pressure sensor 16 and a third pressure gauge 17 are installed on the pipeline connecting the hydraulic oil tank 2 with the blasting cylinder 6 and the fatigue cylinder 7. The mode switching is achieved by the two-position three-way solenoid directional valve 18 working in different positions.

[0023] In this embodiment, a first pressure sensor 13 is installed on the pipe connecting the second return water tank 21 and the return water end of the first return water tank 3 .

[0024] In this embodiment, a first pressure gauge 12 is installed on the pipe connecting the fatigue cylinder 7 and the test bench 1 and the return water end pipe of the first return water tank 3 .

[0025] In this embodiment, the output end of the blasting cylinder 6 is connected to the return water end pipeline of the first return water tank 3, and the second one-way valve 10 and the second pressure gauge 14 are installed on the pipeline.

[0026] In this embodiment, two pipes are provided to connect the return end of the second return water tank 21 with the test bench 1 , and a normally closed solenoid valve 22 and an overflow valve 23 are installed on the two pipes respectively, and a third pressure sensor 20 is installed at the connection between the two pipes and the test bench 1 .

[0027] In the blasting mode, the blasting cylinder 6 works during the test, and the normally open solenoid valve 15 is powered on and closed, and the water pressure is established and continuously increased until the test workpiece is blasted. If the water pressure reaches 300Mpa during the continuous pressurization process and the test workpiece has not been blasted, the relief valve 23 will open to prevent the system from overpressure. After the test is completed, the parallel normally closed solenoid valve 22 is powered on and opened to achieve active pressure relief of the test workpiece.

[0028] In fatigue mode, the fatigue cylinder 7 works during the test, and the fatigue cylinder 7 provides pressure pulses for the test workpiece when working. The test cycle is much longer than that of the blasting cylinder 6, so the normally open solenoid valve 15 is selected here. In fatigue mode, the solenoid valve must not be energized and is in an open state. Taking into account the long cycle of the fatigue test and the water leakage during the test, the pre-filled water system connected in parallel can provide sufficient test water supply for the fatigue cylinder 7 to ensure that the water pressure continues to fluctuate back and forth within a certain range during the fatigue test. During the fatigue test, the overflow valve 23 provides overflow protection to ensure that the system will not be over-pressurized. After the test is completed, the hydraulic pressure can be partially relieved by controlling the hydraulic pressure, or active pressure relief can be achieved by controlling the normally closed solenoid valve 22 in parallel.

[0029] Although the embodiments of the present invention are described in conjunction with the accompanying drawings, the patent owner may make various variations or modifications within the scope of the appended claims. As long as they do not exceed the protection scope described in the claims of the present invention, they should be within the protection scope of the present invention.

Claims

1. A valve-controlled multi-mode convenient switching pressure vessel test bench, comprising a test bench for placing workpieces, characterized in that: It also includes a hydraulic oil tank, a first return water tank, a second return water tank, an oil cooler, a water cooler, a blasting cylinder and a fatigue cylinder; the input ends of the blasting cylinder and the fatigue cylinder are both connected to the hydraulic oil tank, the output ends of the blasting cylinder and the fatigue cylinder are both connected to the test bench, the water outlet pipe of the first return water tank is connected to the pipe connecting the fatigue cylinder and the test bench, a third one-way valve is installed on the return water end pipe of the first return water tank, a first one-way valve is installed on the pipe connecting the blasting cylinder and the test bench, a first pressure gauge and a normally open solenoid valve are installed on the pipe connecting the fatigue cylinder and the test bench, and the return water end pipe of the second return water tank is connected to the return water end pipe of the first return water tank and the pipe connecting the blasting cylinder and the test bench.

2. The valve-controlled multi-mode convenient switching pressure vessel test bench according to claim 1 is characterized in that: The oil cooler and the water cooler are respectively connected to the hydraulic oil tank and the fatigue cylinder.

3. The valve-controlled multi-mode convenient switching pressure vessel test bench according to claim 1 is characterized in that: A two-position three-way solenoid valve reversing valve, a two-position three-way solenoid reversing valve, a second pressure sensor and a third pressure gauge are installed on the pipeline connecting the hydraulic oil tank with the blasting cylinder and the fatigue cylinder.

4. The valve-controlled multi-mode convenient switching pressure vessel test bench according to claim 1 is characterized in that: A first pressure sensor is installed on the pipeline connecting the second return water tank and the return water end of the first return water tank.

5. The valve-controlled multi-mode convenient switching pressure vessel test bench according to claim 1 is characterized in that: The first pressure gauge is installed on the pipeline connecting the fatigue cylinder and the test bench and the return water end pipeline of the first return water tank.

6. The valve-controlled multi-mode convenient switching pressure vessel test bench according to claim 1 is characterized in that: The output end of the blasting cylinder is connected to the return water end pipeline of the first return water tank, and a second one-way valve and a second pressure gauge are installed on the pipeline.

7. The valve-controlled multi-mode convenient switching pressure vessel test bench according to claim 1 is characterized in that: There are two pipes connecting the return end of the second return water tank with the test bench, and a normally closed solenoid valve and an overflow valve are installed on the two pipes respectively, and a third pressure sensor is installed at the connection between the two pipes and the test bench.