Clamp structure for mounting super high-rise large-size curtain wall unit body
By using lifting crossbars, three-point inlay fixtures and fixed pulleys in super-high-rise buildings, the problems of poor stability and low installation efficiency in high-rise large-sized curtain wall hoisting are solved, and a safer and more efficient curtain wall is achieved Unit installation.
Patent Information
- Application Number
- CN202421293416.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-07
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-06-07
AI Technical Summary
Traditional curtain wall fixtures are difficult to steadily hoist large-sized curtain wall units in super high-rise buildings, which can easily lead to the fall and damage of glass curtain walls, and the cumbersome dismantling process affects installation efficiency.
A clamp structure including a lifting cross rod, a three-point inlay fixture and a fixed pulley is designed. The three-point inlay fixture is connected and fixed in the unit body clamping component through a wire rope, and an anti-collision rope and a fixed pulley are provided to ensure stable transportation.
It improves the stability and reliability and installation efficiency of large-sized curtain wall units, providing additional safety guarantees to prevent collision and damage during lifting.
Smart Images

Figure CN222007004U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of building construction, in particular to a clamp structure used for installing a super-high-rise large-size curtain wall unit body. Background Art
[0002] In recent years, the number of projects using curtain walls as facades in super high-rise buildings has increased. In the process of curtain wall construction of super high-rise buildings, there are very high requirements for curtain wall unit installation technology, and the corresponding construction difficulty coefficient is also increasing. Although the traditional curtain wall fixture structure is suitable for the hoisting of ordinary-sized unit panels, when dealing with hoisting at a height of more than 100 meters and large-sized unit panels, as the wind load increases, it does not have safety protection and stable clamping fixation, and the glass curtain wall is prone to falling and damage, and the disassembly process is relatively cumbersome, which affects the installation efficiency. Utility Model Content
[0003] In order to solve the above technical problems, the utility model proposes a clamp structure for the installation of super-high-rise large-size curtain wall units, aiming to solve the problems of poor clamping stability, easy falling, easy collision and slow installation efficiency of traditional curtain wall clamps when dealing with high floor heights and large unit sizes.
[0004] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0005] A fixture structure for installing a super-high-rise large-size curtain wall unit body, characterized in that it includes a lifting cross bar, a three-point embedding fixture, a unit body clamping component and a fixed pulley, the lifting cross bar and the three-point embedding fixture are connected and fixed by a steel wire rope, the three-point embedding fixture is embedded in the unit body clamping component, the three-point embedding fixture includes a first steel part, a second steel part and a steel clamping plate, a fixing groove is provided in the unit body clamping component, the steel clamping plate is fixed at the notch of the fixing groove, the first steel part and the second steel part are fixed in the fixing groove through the steel clamping plate, the first steel part includes a first vertical plate, a first horizontal plate, a connecting plate, a first clamping part and a third clamping part, the first horizontal plate is welded to the first vertical plate, and the third clamping part is welded and connected to the first horizontal plate through the connecting plate; the first clamping part is welded to the first horizontal plate, the second steel part includes a second vertical plate, a second horizontal plate and a second clamping part, the second horizontal plate is welded to the second vertical plate, and the second clamping part is welded to the second horizontal plate,
[0006] It also includes an anti-collision rope and an anti-collision cross bar, wherein the anti-collision cross bar is transversely fixed on the unit body clamping component, the middle part of the anti-collision rope is fixed on the lifting cross bar, and the two ends are respectively fixed on the two ends of the anti-collision cross bar, and the anti-collision rope and the anti-collision cross bar are fixed in a triangular shape.
[0007] It also includes a fixed pulley and a wind rope, wherein the pulleys are respectively fixed at both ends of the anti-collision cross bar. When the crane lifts the lifting cross bar, during the lifting process, the fixed pulley is lifted together with the unit body clamping component with the wind rope as a track.
[0008] In the above structure: the utility model proposes a clamp structure for installing super-high-rise large-size curtain wall units, including a lifting crossbar, a three-point embedding clamp, a unit clamping component and a fixed pulley, wherein the lifting crossbar and the three-point embedding clamp are connected and fixed by a wire rope, the three-point embedding clamp is embedded in the unit clamping component, the unit clamping component is used to fix the curtain wall, the lifting crossbar can facilitate the lifting of the upper crane, and the curtain wall fixed in the unit clamping component is driven by the lifting crossbar to move together, thereby realizing the transportation and installation of the curtain wall.
[0009] The fixing method of the three-point mounting fixture and the unit body clamping component is as follows:
[0010] The three-point inlay fixture includes a first steel part, a second steel part and a steel clamping plate. A fixing groove for installing and fixing the three-point inlay fixture is provided in the unit body clamping component, wherein the steel clamping plate is fixed at the notch of the fixing groove. The first steel part includes a first vertical plate, a first horizontal plate, a connecting plate, a first clamping member and a third clamping member. The first horizontal plate is welded to the first vertical plate. The third clamping member is welded to the first horizontal plate through the connecting plate. The first clamping member is welded to the first horizontal plate. The second steel part includes a second vertical plate, a second horizontal plate and a second clamping member. The second horizontal plate is welded to the second vertical plate. The second clamping member is welded to the second horizontal plate. An embedding groove is provided in the unit body clamping component. The first clamping member, the second clamping member and the third clamping member are respectively embedded in the embedding groove, thereby realizing the fixation of the three-point inlay fixture and the unit body clamping component.
[0011] The present application also arranges an anti-collision rope and an anti-collision cross bar to prevent the unit body clamping component from colliding with the wall during transportation, wherein the anti-collision cross bar is laterally fixed on the unit body clamping component, the middle part of the anti-collision rope is fixed on the lifting cross bar, and the two ends are respectively fixed on the two ends of the anti-collision cross bar, and the anti-collision rope and the anti-collision cross bar are fixed in a triangular shape, so that the anti-collision rope and the anti-collision cross bar have high stability.
[0012] The present application also sets a fixed pulley and a guy rope to ensure that the unit body clamping component can be transported along a specific route, wherein the pulleys are respectively fixed at both ends of the anti-collision cross bar. When the crane lifts the lifting cross bar, during the lifting process, the fixed pulley uses the guy rope as a track to be lifted together with the unit body clamping component to ensure its stable transportation.
[0013] The usage of this application is as follows:
[0014] Step 1: embed the three-point embedding fixture in the unit body clamping component and adjust it to a suitable position. In this step, there are three embedding points between the three-point embedding fixture and the unit body clamping component. Compared with traditional fixtures, it is more stable and reliable when hoisting super-high-rise large-size panels;
[0015] Step 2: Install the steel clamp, connect it to the three-point inlay fixture with bolts, and fasten it to the unit clamping component. In this step, the three-point inlay fixture and the steel clamp are easy to install and disassemble, which can effectively improve the installation efficiency of the unit clamping component.
[0016] Step 3: Connect the lifting crossbar and the three-point inlay fixture, and install the anti-fall rope, which provides further safety protection for the lifting process of the unit clamping components;
[0017] Step 4: After the unit body clamping components are cleaned, lift the unit body clamping components. During the lifting process of the unit body clamping components, the anti-collision rope and the anti-collision cross bar are always located on the back side of the unit body, and the fixed pulley and the cable wind rope form a fixed track, so that the unit body clamping components are lifted according to the predetermined fixed track during the lifting process, effectively preventing the unit body clamping components from colliding and damaging the surrounding finished objects during the lifting process.
[0018] Further: a large hanging ear and a small hanging ear are installed on the lifting cross bar, the large hanging ear is respectively installed on the upper end surface and the lower end surface of the lifting cross bar, and the small hanging ear is installed on the lower end surface of the lifting cross bar.
[0019] In the above structure: the lifting cross bar, large hanging ears and small hanging ears are all made of 120mm×80mm×8mm steel pipe and 16mm thick steel plate. Three large hanging ears are arranged on the upper end face of the lifting cross bar, and two large hanging ears and two small hanging ears are arranged on the lower end face. The three large hanging ears on the upper end face are upper lifting points. Single-point lifting or double-point lifting can be selected according to the weight of the unit clamping component. The two small hanging ears on the lower end face are connected to the three-point embedding clamp embedded in the unit clamping component through steel wire ropes. The two large hanging ears on the lower end face are anti-fall rope hanging points, which are connected to the anti-fall ring on the unit body through an anti-fall rope.
[0020] Furthermore: anti-fall rings are fixedly installed on both sides of the unit body clamping component, one end of the anti-fall rope is fixed to the large hanging ear on the lower end surface of the lifting cross bar, and the other end is fixed to the anti-fall ring.
[0021] In the above structure: the unit body clamping component and the lifting cross bar are connected and fixed by an anti-fall rope, which further improves the safety of the application when used. The anti-fall rope provides further safety protection for the unit body clamping component during the lifting process.
[0022] Further: both ends of the anti-collision cross bar are respectively provided with fixing buckles, the middle part of the anti-collision rope is fixed in the large hanging ear on the upper end surface of the lifting cross bar, and the two ends are respectively fixed in the fixing buckles.
[0023] In the above structure: the fixing buckle is used to realize the installation and fixation of the anti-collision rope, and the anti-collision rope can prevent the unit body clamping component from colliding with the wall during transportation.
[0024] Further: one end of the steel wire rope is fixed in a small hanging ear on the lower end surface of the lifting crossbar, and the other end is fixed on a three-point inlay fixture.
[0025] In the above structure: the small hanging ear on the lower end surface of the lifting crossbar is used to fix the steel wire rope, and the lifting crossbar and the three-point inlay fixture are fixed by the steel wire rope and the small hanging ear.
[0026] Furthermore: the unit body clamping component is provided with a first embedding groove, a second embedding groove and a third embedding groove, and the first clamping member, the second clamping member and the third clamping member are respectively embedded in the first embedding groove, the second embedding groove and the third embedding groove to achieve fixation.
[0027] In the above structure: the embedding grooves in the unit body clamping component include a first embedding groove, a second embedding groove and a third embedding groove, and the first clamp, the second clamp and the third clamp are respectively embedded in the first embedding groove, the second embedding groove and the third embedding groove to fix the unit body clamping component and the three-point embedding fixture.
[0028] Compared with the prior art, the beneficial effects of the utility model are:
[0029] In practical applications, the present application effectively solves the difficult problems of traditional curtain wall clamps having poor clamping stability, being easy to fall, being easy to collide and having slow installation efficiency when dealing with high floor heights and large unit sizes.
[0030] This application sets up a three-point embedding clamp, and there are three embedding points between the three-point embedding clamp and the unit clamping component. When dealing with the lifting of ultra-high-rise large-size panels, it is more stable and reliable than traditional clamps.
[0031] The steel clamp in the present application is connected to the three-point mounting fixture by bolts and fastened to the unit clamping components, so that the three-point mounting fixture and the steel clamp are easy to install and disassemble, which can effectively improve the installation efficiency of the unit clamping components.
[0032] The present application provides an anti-fall rope to provide further safety protection for the unit body clamping components during the lifting process.
[0033] The fixed pulley and the guy rope in the present application form a fixed track, so that the unit body clamping components are lifted along a predetermined fixed track during the lifting process, effectively preventing the unit body clamping components from colliding with and damaging surrounding finished objects during the lifting process. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] Figure 1 It is a schematic diagram of the overall structure of this application;
[0035] Figure 2 It is a schematic diagram of the structure of the unit clamping component in this application;
[0036] Figure 3 It is a schematic diagram of the three-point mounting fixture structure in this application.
[0037] List of reference numerals:
[0038] 1. Lifting crossbar; 11. Large hanging ear; 12. Small hanging ear; 2. Three-point inlay fixture; 21. First vertical plate; 22. Second vertical plate; 23. First horizontal plate; 22. Second horizontal plate; 25. Connecting plate; 26. First clamp; 27. Second clamp; 28. Third clamp; 29. Steel clamp; 210. First embedded groove; 211. Second embedded groove; 212. Third embedded groove; 3. Anti-collision rope; 4. Unit clamping component; 5. Anti-collision crossbar; 6. Fixed pulley; 7. Anti-fall ring; 8. Cable wind rope; 9. Wire rope; 10. Anti-fall rope. DETAILED DESCRIPTION
[0039] The present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods:
[0040] like Figure 1-3 As shown, the utility model proposes a fixture structure for installing a super-high-rise large-size curtain wall unit body, including a lifting crossbar 1, a three-point embedding fixture 2, a unit body clamping component 4 and a fixed pulley 6. The lifting crossbar 1 and the three-point embedding fixture 2 are connected and fixed by a steel wire rope 9. The three-point embedding fixture 2 is embedded in the unit body clamping component 4. The three-point embedding fixture 2 includes a first steel part, a second steel part and a steel clamping plate 29. The unit body clamping component 4 is provided with a fixing groove. The steel clamping plate 29 is fixed at the notch of the fixing groove. The first steel part, the second steel part The first steel member is fixed in the fixing groove by a steel clamping plate 29. The first steel member includes a first vertical plate 21, a first horizontal plate 23, a connecting plate 25, a first clamping member 26 and a third clamping member 28. The first horizontal plate 23 is welded to the first vertical plate 21. The third clamping member 28 is welded to the first horizontal plate 23 through the connecting plate 25. The first clamping member 26 is welded to the first horizontal plate 23. The second steel member includes a second vertical plate 22, a second horizontal plate 22 and a second clamping member 27. The second horizontal plate 22 is welded to the second vertical plate 22. The second clamping member 27 is welded to the second horizontal plate 22.
[0041] It also includes an anti-collision rope 3 and an anti-collision cross bar 5. The anti-collision cross bar 5 is transversely fixed on the unit body clamping component 4. The middle part of the anti-collision rope 3 is fixed on the lifting cross bar 1, and the two ends are respectively fixed on the two ends of the anti-collision cross bar 5. The anti-collision rope 3 and the anti-collision cross bar 5 are fixed in a triangular shape.
[0042] It also includes a fixed pulley 6 and a wind rope 8, and the pulleys are respectively fixed at both ends of the anti-collision cross bar 5. When the crane lifts the lifting cross bar 1, during the lifting process, the fixed pulley 6 is lifted together with the unit body clamping component 4 with the wind rope 8 as a track.
[0043] The utility model proposes a fixture structure for installing a super-high-rise large-size curtain wall unit body, comprising a lifting crossbar 1, a three-point embedding fixture 2, a unit body clamping component 4 and a fixed pulley 6, wherein the lifting crossbar 1 and the three-point embedding fixture 2 are connected and fixed by a steel wire rope 9, the three-point embedding fixture 2 is embedded in the unit body clamping component 4, the unit body clamping component 4 is used to fix the curtain wall, the lifting crossbar 1 can facilitate the upper crane to lift, and the curtain wall fixed in the unit body clamping component 4 is driven by the lifting crossbar 1 to move together, thereby realizing the transportation and installation of the curtain wall.
[0044] The fixing method of the three-point mounting fixture 2 and the unit body clamping component 4 is as follows:
[0045] The three-point inlay fixture 2 includes a first steel piece, a second steel piece and a steel clamping plate 29. A fixing groove for installing and fixing the three-point inlay fixture 2 is provided in the unit body clamping component 4, wherein the steel clamping plate 29 is fixed at the notch of the fixing groove. The first steel piece includes a first vertical plate 21, a first horizontal plate 23, a connecting plate 25, a first clamping piece 26 and a third clamping piece 28. The first horizontal plate 23 is welded to the first vertical plate 21. The third clamping piece 28 is connected to the first horizontal plate 23 through the connecting plate 25. The plates 23 are welded and connected, the first clamp 26 is welded to the first horizontal plate 23, the second steel member includes a second vertical plate 22, a second horizontal plate 22 and a second clamp 27, the second horizontal plate 22 is welded to the second vertical plate 22, the second clamp 27 is welded to the second horizontal plate 22, and an embedding groove is provided in the unit body clamping component 4, the first clamp 26, the second clamp 27, and the third clamp 28 are respectively embedded in the embedding groove, thereby realizing the fixation of the three-point inlay fixture 2 and the unit body clamping component 4.
[0046] The present application also arranges an anti-collision rope 3 and an anti-collision cross bar 5 to prevent the unit body clamping component 4 from colliding with the wall during transportation, wherein the anti-collision cross bar 5 is laterally fixed on the unit body clamping component 4, the middle part of the anti-collision rope 3 is fixed on the lifting cross bar 1, and the two ends are respectively fixed on the two ends of the anti-collision cross bar 5, and the anti-collision rope 3 and the anti-collision cross bar 5 are fixed in a triangular shape, so that the anti-collision rope 3 and the anti-collision cross bar 5 have high stability.
[0047] The present application also sets a fixed pulley 6 and a guy rope 8 to ensure that the unit body clamping component 4 can be transported along a specific route, wherein the pulleys are respectively fixed at both ends of the anti-collision cross bar 5. When the crane lifts the lifting cross bar 1, during the lifting process, the fixed pulley 6 is lifted together with the unit body clamping component 4 with the guy rope 8 as a track to ensure its stable transportation.
[0048] The usage of this application is as follows:
[0049] Step 1: embed the three-point embedding fixture 2 in the unit body clamping component 4 and adjust it to a suitable position. In this step, there are three embedding points between the three-point embedding fixture 2 and the unit body clamping component 4. Compared with traditional fixtures, it is more stable and reliable when dealing with the hoisting of super-high-rise large-size panels;
[0050] Step 2: Install the steel clamping plate 29, connect it to the three-point mounting fixture 2 with bolts, and fasten it to the unit body clamping component 4. In this step, the three-point mounting fixture 2 and the steel clamping plate 29 are easy to install and disassemble, which can effectively improve the installation efficiency of the unit body clamping component 4;
[0051] Step 3: Connect the lifting crossbar 1 and the three-point mounting fixture 2, and install the anti-falling rope 10, which provides further safety protection for the lifting process of the unit clamping component 4;
[0052] Step 4: After the unit body clamping component 4 is cleaned, lift the unit body clamping component 4. During the lifting process of the unit body clamping component 4, the anti-collision rope 3 and the anti-collision cross bar 5 are always located on the back side of the unit body, and the fixed pulley 6 and the cable wind rope 8 form a fixed track, so that the unit body clamping component 4 is lifted according to a predetermined fixed track during the lifting process, effectively preventing the unit body clamping component 4 from colliding and damaging the surrounding finished products during the lifting process.
[0053] In this embodiment: a large hanging ear 11 and a small hanging ear 12 are installed on the lifting crossbar 1, the large hanging ear 11 is installed on the upper end surface and the lower end surface of the lifting crossbar 1 respectively, and the small hanging ear 12 is installed on the lower end surface of the lifting crossbar 1. The lifting cross bar 1, large hanging ears 11, and small hanging ears 12 are all made of 120mm×80mm×8mm steel pipe and 16mm thick steel plate. Three large hanging ears 11 are arranged on the upper end face of the lifting cross bar 1, and two large hanging ears 11 and two small hanging ears 12 are arranged on the lower end face. The three large hanging ears 11 on the upper end face are upper lifting points. Single-point lifting or double-point lifting can be selected according to the weight of the unit clamping component 4. The two small hanging ears 12 on the lower end face are connected to the three-point embedding fixture 2 embedded in the unit clamping component 4 through a steel wire rope 9. The two large hanging ears 11 on the lower end face are hanging points for the anti-fall rope 10, which are connected to the anti-fall ring 7 on the unit body through the anti-fall rope 10.
[0054] In this embodiment: the anti-falling rings 7 are fixedly installed on both sides of the unit body clamping component 4, one end of the anti-falling rope 10 is fixed to the large hanging ear 11 on the lower end surface of the lifting cross bar 1, and the other end is fixed to the anti-falling ring 7. The unit body clamping component 4 and the lifting cross bar 1 are connected and fixed by the anti-falling rope 10, which further improves the safety of the application when used, and the anti-falling rope 10 provides further safety protection for the unit body clamping component 4 during the lifting process.
[0055] In this embodiment: the two ends of the anti-collision cross bar 5 are respectively provided with fixing buckles, the middle part of the anti-collision rope 3 is fixed in the large hanging ear 11 on the upper end surface of the lifting cross bar 1, and the two ends are respectively fixed in the fixing buckles. The fixing buckle is used to install and fix the anti-collision rope 3, and the anti-collision rope 3 can prevent the unit body clamping component 4 from colliding with the wall during transportation.
[0056] In this embodiment: one end of the steel wire rope 9 is fixed in the small hanging ear 12 on the lower end surface of the lifting crossbar 1, and the other end is fixed on the three-point mounting fixture 2. The small hanging ear 12 on the lower end surface of the lifting crossbar 1 is used to fix the steel wire rope 9, and the lifting crossbar 1 and the three-point mounting fixture 2 are fixed by the steel wire rope 9 and the small hanging ear 12.
[0057] In this embodiment: the unit body clamping component 4 is provided with a first embedding groove 210, a second embedding groove 211 and a third embedding groove 212, and the first clamp 26, the second clamp 27 and the third clamp 28 are respectively embedded in the first embedding groove 210, the second embedding groove 211 and the third embedding groove 212 to achieve fixation. The embedding grooves in the unit body clamping component 4 include the first embedding groove 210, the second embedding groove 211 and the third embedding groove 212, and the first clamp 26, the second clamp 27 and the third clamp 28 are respectively embedded in the first embedding groove 210, the second embedding groove 211 and the third embedding groove 212 to achieve fixation of the unit body clamping component 4 and the three-point inlay fixture 2.
[0058] Based on the above technical solution:
[0059] In practical applications, the present application effectively solves the difficult problems of traditional curtain wall clamps having poor clamping stability, being easy to fall, being easy to collide and having slow installation efficiency when dealing with high floor heights and large unit sizes.
[0060] The present application sets up a three-point embedding fixture 2, and there are three embedding points between the three-point embedding fixture 2 and the unit body clamping component 4. Compared with traditional fixtures, it is more stable and reliable when dealing with the lifting of ultra-high-rise large-size panels.
[0061] The steel clamp plate 29 in the present application is connected to the three-point mounting fixture 2 by bolts and is fastened to the unit body clamping component 4, so that the three-point mounting fixture 2 and the steel clamp plate 29 are easy to install and disassemble, and the installation efficiency of the unit body clamping component 4 can be effectively improved.
[0062] The present application provides an anti-fall rope 10, which provides further safety protection for the unit clamping component 4 during the hoisting process.
[0063] The fixed pulley 6 and the guy rope 8 in the present application form a fixed track, so that the unit body clamping component 4 is lifted along a predetermined fixed track during the lifting process, effectively preventing the unit body clamping component 4 from colliding with and damaging surrounding finished objects during the lifting process.
[0064] The above is only a preferred embodiment of the present invention and does not constitute any other limitation on the present invention. Any modification or equivalent change made based on the technical essence of the present invention still falls within the scope of protection required by the present invention.
Claims
1. A fixture structure for installing a super high-rise large-size curtain wall unit, characterized in that: The invention comprises a lifting crossbar (1), a three-point setting fixture (2), a unit body clamping component (4) and a fixed pulley (6); the lifting crossbar (1) and the three-point setting fixture (2) are connected and fixed by a steel wire rope (9); the three-point setting fixture (2) is set in the unit body clamping component (4); the three-point setting fixture (2) comprises a first steel part, a second steel part and a steel clamping plate (29); a fixing groove is provided in the unit body clamping component (4); the steel clamping plate (29) is fixed at the notch of the fixing groove; the first steel part and the second steel part are fixed in the fixing groove by the steel clamping plate (29); the first steel part includes a first steel part, a second steel part and a steel clamping plate (29); The steel member comprises a first vertical plate (21), a first horizontal plate (23), a connecting plate (25), a first clamp (26) and a third clamp (28), wherein the first horizontal plate (23) is welded to the first vertical plate (21), the third clamp (28) is welded to the first horizontal plate (23) via the connecting plate (25), the first clamp (26) is welded to the first horizontal plate (23), the second steel member comprises a second vertical plate (22), a second horizontal plate (22) and a second clamp (27), the second horizontal plate (22) is welded to the second vertical plate (22), the second clamp (27) is welded to the second horizontal plate (22), It also comprises an anti-collision rope (3) and an anti-collision cross bar (5), wherein the anti-collision cross bar (5) is transversely fixed on the unit body clamping component (4), the middle part of the anti-collision rope (3) is fixed on the lifting cross bar (1), and the two ends are respectively fixed on the two ends of the anti-collision cross bar (5), and the anti-collision rope (3) and the anti-collision cross bar (5) are fixed in a triangular shape. It also includes a fixed pulley (6) and a wind rope (8), wherein the pulleys are respectively fixed at both ends of the anti-collision cross bar (5). When the crane lifts the lifting cross bar (1), during the lifting process, the fixed pulley (6) is lifted together with the unit body clamping component (4) using the wind rope (8) as a track.
2. A fixture structure for installing a super high-rise large-size curtain wall unit according to claim 1, characterized in that: A large hanging ear (11) and a small hanging ear (12) are installed on the lifting crossbar (1), wherein the large hanging ear (11) is installed on the upper end surface and the lower end surface of the lifting crossbar (1), respectively, and the small hanging ear (12) is installed on the lower end surface of the lifting crossbar (1).
3. A fixture structure for installing a super high-rise large-size curtain wall unit according to claim 1 or 2, characterized in that: Anti-fall rings (7) are fixedly mounted on both sides of the unit body clamping component (4), and one end of the anti-fall rope (10) is fixed to a large hanging ear (11) on the lower end surface of the lifting crossbar (1), and the other end is fixed to the anti-fall ring (7).
4. A fixture structure for installing a super high-rise large-size curtain wall unit according to claim 1 or 2, characterized in that: The two ends of the anti-collision cross bar (5) are respectively provided with fixing buckles, the middle part of the anti-collision rope (3) is fixed in the large hanging ear (11) on the upper end surface of the lifting cross bar (1), and the two ends are respectively fixed in the fixing buckles.
5. A fixture structure for installing a super high-rise large-size curtain wall unit according to claim 1 or 2, characterized in that: One end of the steel wire rope (9) is fixed in a small hanging ear (12) on the lower end surface of the lifting crossbar (1), and the other end is fixed on a three-point embedding fixture (2).
6. The fixture structure for installing a super high-rise large-size curtain wall unit according to claim 1 is characterized in that: The unit body clamping component (4) is provided with a first embedding groove (210), a second embedding groove (211) and a third embedding groove (212); the first clamping member (26), the second clamping member (27) and the third clamping member (28) are respectively embedded in the first embedding groove (210), the second embedding groove (211) and the third embedding groove (212) to achieve fixation.