High-filling embankment drainage blind ditch
By introducing cover and support mechanisms into blind ditches of high-filled embankments, the problem of blind ditch collapse is solved, extending service life and improving drainage effect.
Patent Information
- Application Number
- CN202420455813.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-11
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-03-11
AI Technical Summary
Due to the lack of support structure in the high-filled embankment, existing blind drainage ditches are prone to collapse under pressure, affecting their service life and drainage effect.
A high-filled embankment drainage blind ditch including a cover mechanism and a support mechanism is designed. The cover mechanism is used to hide the blind ditch body. The support mechanism supports and fixes the blind ditch body through components such as traction springs, support screws and fix seats to ensure that Its stability.
It effectively avoids the collapse of blind grooves, extends the service life, and ensures the stable drainage function of blind grooves.
Smart Images

Figure CN222008870U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction engineering, in particular to a high-filled embankment drainage blind ditch. Background Art
[0002] High embankment refers to a roadbed with a height of more than 6m built with fine-grained kernels in rice fields or areas with long-term waterlogging. In other areas, the total height of the fill exceeds 18.0m (soil) or 20.0m (stone). Common diseases of high embankment include overall or partial subsidence of the roadbed, longitudinal cracking of the roadbed, sliding of the roadbed or slope collapse. Blind ditch refers to a drainage and interception ditch set in the roadbed or foundation, filled with coarse-grained materials such as crushed and gravel and paved with a filter layer (some of which have permeable pipes buried in it). Blind ditch, also called culvert, is an underground drainage channel used to remove groundwater and lower the groundwater level.
[0003] The disclosure discloses a road subgrade drainage blind ditch with publication number CN207143644U, which solves the problem that the existing common blind ditch cannot be applied to the situation where the terrain is low, the subgrade is composed of fine particles and the groundwater level is high. The disclosure can timely and effectively drain the groundwater from the subgrade, prevent water accumulation on the road, and effectively prevent the loss of fine particles such as silt and fine sand. The technical scheme is as follows: a double-layer filter layer, a filter resistance layer, and a drainage pipe are sequentially arranged from the outside to the inside, the filter resistance layer is wrapped around the outer wall of the drainage pipe, a plurality of rows of through holes are arranged along the outer periphery of the drainage pipe, and the drainage pipe is filled with coarse sand; the double-layer filter layer includes a medium-fine sand layer and a medium-coarse sand layer arranged from the outside to the inside, and the medium-coarse sand layer is coated on the outside of the filter resistance layer.
[0004] Deficiencies in the existing technology: During the operation of the existing drainage blind ditch, the outer side is covered with multiple layers of filling, and the driving of vehicles on the road will squeeze the drainage blind ditch. The interior of the drainage blind ditch lacks support, which makes the blind ditch prone to collapse under pressure, affecting the service life of the drainage blind ditch and making it impossible to stably use the drainage blind ditch for drainage work. Utility Model Content
[0005] To this end, an embodiment of the utility model provides a high-fill embankment drainage blind ditch to solve the problem in the prior art that the blind ditch is easily damaged due to collapse due to the lack of a supporting structure inside the drainage blind ditch, and cannot be stably used for drainage work.
[0006] In order to achieve the above-mentioned purpose, the embodiment of the utility model provides the following technical solution: a high-filled embankment drainage blind ditch, including a blind ditch body, and also including:
[0007] The covering mechanism is arranged on the outside of the blind ditch body and is used to cover and hide the blind ditch body;
[0008] The supporting mechanism is arranged inside the blind ditch body and is used to support and fix the blind ditch body;
[0009] The support mechanism includes multiple fixed seats, and traction springs are fixedly installed around the outer walls of the fixed seats. A support plate is fixedly installed on one end of the traction spring away from the fixed seat. Support screws are arranged between the inner walls around the fixed seat and the four support plates. A fastening nut is threadedly sleeved on the outer wall of one end of the support screw located on the inner side of the fixed seat, and a connecting pipe is arranged between two adjacent fixed seats.
[0010] Preferably, the covering mechanism comprises a gravel layer, the gravel layer is arranged on the outside of the blind ditch body, and a coarse sand layer is arranged on the outside of the gravel layer.
[0011] Preferably, a filling layer is arranged outside the coarse sand layer, and the blind ditch body is arranged as a circular plastic blind ditch.
[0012] Preferably, the supporting mechanism comprises fixing pins, and the fixing pins are provided in two groups, and the two groups of fixing pins are respectively fixedly mounted on the outer walls at both ends of the fixing seat.
[0013] Preferably, both ends of the connecting tube are movably connected to adjacent fixing pins respectively, and the vertical cross-sectional area dimension of the inner wall of the connecting tube when viewed from the left is the same as the vertical cross-sectional area dimension of the inner wall of the fixing seat when viewed from the left.
[0014] Preferably, the inner wall of the fixing seat is threadedly connected to the outer walls of four support screws respectively, one end of the four support screws away from the fixing seat is abutted against the adjacent support plate, and the support screws are movably inserted into the inner side of the adjacent traction spring.
[0015] Preferably, the four traction springs are arranged in a ring shape with equal spacing, and a protective pad is fixedly installed on the outer side of the support plate.
[0016] Preferably, the outer wall of the protective pad is movably connected to the inner wall of the blind ditch body, and the left-side vertical section of the support plate and the protective pad is arranged to be a fan-shaped structure.
[0017] The utility model embodiment has the following advantages:
[0018] 1. The utility model can support the support plate through the support screw, and can conveniently adjust the position of the support plate according to the size of the blind ditch body. Then, through the connection between the fastening nut and the support screw, the support plate can stably support and fix the inner wall of the blind ditch body. Through the connection between the connecting pipe and the adjacent fixing pin, the two fixing seats can be pulled and limited, so that the support mechanism can stably support and reinforce the blind ditch body, which can avoid the blind ditch body from being damaged due to the collapse of the covering mechanism during use, and can improve the service life of the blind ditch body, thereby ensuring the stable drainage work of the blind ditch body.
[0019] 2. The utility model can pull and limit the support plate through the traction spring, which can prevent the support plate from being separated from the fixing seat. At the same time, the provision of the protective pad can protect the contact between the support plate and the inner wall of the blind ditch body, so that the support plate can stably support and fix the blind ditch body. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] In order to more clearly illustrate the implementation of the utility model or the technical solution in the prior art, the following is a brief introduction to the drawings required for the implementation or the prior art description. Obviously, the drawings in the following description are only exemplary, and for ordinary technicians in this field, other implementation drawings can be derived from the provided drawings without creative work.
[0021] The structures, proportions, sizes, etc. illustrated in this specification are only used to match the contents disclosed in the specification so as to facilitate understanding and reading by persons familiar with the technology. They are not used to limit the conditions under which the present invention can be implemented, and therefore have no substantial technical significance. Any structural modification, change in proportion or adjustment of size shall still fall within the scope of the technical contents disclosed in the present invention without affecting the effects and purposes that can be achieved by the present invention.
[0022] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0023] Figure 2 It is a front vertical sectional view of the utility model;
[0024] Figure 3 For this utility model Figure 2 A magnified view of part A;
[0025] Figure 4 This is a three-dimensional structural diagram of the covering mechanism of the utility model;
[0026] Figure 5 It is an exploded view of the three-dimensional structure of the support mechanism of the utility model.
[0027] In the figure: 1. Blind ditch body;
[0028] 2. Covering mechanism; 201. Gravel layer; 202. Coarse sand layer; 203. Filling layer;
[0029] 3. Support mechanism; 301. Fixed seat; 302. Traction spring; 303. Support plate; 304. Protective pad; 305. Support screw; 306. Fastening nut; 307. Fixing pin; 308. Connecting pipe. DETAILED DESCRIPTION
[0030] The following is a specific embodiment of the present invention. People familiar with the technology can easily understand the other advantages and functions of the present invention from the contents disclosed in this specification. Obviously, the described embodiment is a part of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0031] Refer to the instruction manual Figure 1 A high-filled embankment drainage blind ditch of this embodiment includes a blind ditch body 1, and also includes:
[0032] The covering mechanism 2 is arranged on the outer side of the blind ditch body 1 and is used to cover and hide the blind ditch body 1;
[0033] The supporting mechanism 3 is arranged inside the blind ditch body 1 and is used for supporting and fixing the blind ditch body 1 .
[0034] In order to keep the blind ditch body 1 stable during operation, Figure 2-3 and Figure 5 As shown, the support mechanism 3 includes a plurality of fixed seats 301, and traction springs 302 are fixedly installed around the outer walls of the fixed seats 301, and a support plate 303 is fixedly installed on one end of the traction spring 302 away from the fixed seat 301, and support screws 305 are arranged between the inner walls around the fixed seat 301 and the four support plates 303, and a fastening nut 306 is threadedly sleeved on the outer wall of one end of the support screw 305 located on the inner side of the fixed seat 301, and a connecting pipe 308 is arranged between two adjacent fixed seats 301, and the inner wall of the blind ditch body 1 can be supported and fixed by the support plate 303, and the connection between the fastening nut 306 and the support screw 305 enables the support screw 305 to support and reinforce the support plate 303.
[0035] In order to facilitate the installation of the blind ditch body 1 into the high embankment, Figure 2 and Figure 4As shown, the covering mechanism 2 includes a crushed stone layer 201, which is arranged on the outside of the blind ditch body 1, a coarse sand layer 202 is arranged on the outside of the crushed stone layer 201, and a fill layer 203 is arranged on the outside of the coarse sand layer 202. The blind ditch body 1 is configured as a circular plastic blind ditch. The blind ditch body 1 can be covered and installed by the crushed stone layer 201, the coarse sand layer 202 and the fill layer 203, so that the blind ditch body 1 can remain stable inside the high embankment.
[0036] In order to ensure that the two adjacent fixing seats 301 can stably support the blind ditch body 1, as shown in FIG. Figure 2-3 and Figure 5 As shown, the support mechanism 3 includes a fixing pin 307, and the fixing pin 307 is provided with two groups. The two groups of fixing pins 307 are respectively fixedly installed on the outer walls at both ends of the fixing seat 301, and the two ends of the connecting pipe 308 are respectively movably connected with the adjacent fixing pins 307. The vertical cross-sectional area size of the inner wall of the connecting pipe 308 when viewed from the left is the same as the vertical cross-sectional area size of the inner wall of the fixing seat 301 when viewed from the left. The connecting pipe 308 can connect and fix two adjacent fixing seats 301, can support the two fixing seats 301, and can prevent the fixing seats 301 from being offset and moving inside the blind ditch body 1.
[0037] In order to make the support screw 305 able to stably support and reinforce the support plate 303, as shown in FIG. Figure 2-3 and Figure 5 As shown, the inner wall of the fixing seat 301 is threadedly connected to the outer walls of four support screws 305 respectively, and the ends of the four support screws 305 away from the fixing seat 301 are abuttingly connected to the adjacent support plate 303, and the support screws 305 are movably inserted into the inner side of the adjacent traction spring 302. The fixing seat 301 can install and fix the support screws 305, and the support screws 305 can support the support plates 303, so that the four support plates 303 can stably support the inner wall of the blind ditch body 1.
[0038] In order to make the support plate 303 able to stably support the inner wall of the blind ditch body 1, as shown in FIG. Figure 2 and Figure 5 As shown, four traction springs 302 are arranged in a ring with equal intervals, and a protective pad 304 is fixedly installed on the outer side of the support plate 303. The outer wall of the protective pad 304 is movably connected to the inner wall of the blind ditch body 1. The left-view vertical section of the support plate 303 and the protective pad 304 is arranged as a fan-shaped structure. The arrangement of the protective pad 304 can reduce the wear between the support plate 303 and the inner wall of the blind ditch body 1, so that the support plate 303 can stably support the inner wall of the blind ditch body 1.
[0039] The specific implementation method is as follows: when installing the blind ditch body 1, the blind ditch body 1 is installed inside the high embankment, and then the support screw 305 is inserted into the inner wall around the fixing seat 301 so that it can support the support plate 303, and the four support plates 303 can be pushed outward, so that the four traction springs 302 are extended, so that the outer sides of the four protection pads 304 can contact the inner wall of the blind ditch body 1, and then the adjusted support screw 305 can be fixed with the fastening nut 306, so that the support screw 305 can stably support the support plate 303, and then the fixing seat 301 is placed inside the blind ditch body 1, so that the four support plates 303 can support the inner wall around the blind ditch body 1, and then the connecting pipe 308 is sleeved onto the outer side of the fixing pin 307 at one end of one of the fixing seats 301, and then the other fixing seat 301 is inserted into the connecting pipe 308 away from one of the fixing seats 301. The inner wall of one end of the blind ditch body 1 is supported, so that multiple fixing seats 301 can be placed inside the blind ditch body 1, so that the inner walls at different positions inside the blind ditch body 1 can be stably supported and fixed, and then the crushed stone layer 201 is covered on the outside of the blind ditch body 1, and then the coarse sand layer 202 is covered on the outside of the crushed stone layer 201, so that the coarse sand layer 202 can fill the gap of the crushed stone layer 201, and then the fill layer 203 is covered on the outside of the coarse sand layer 202, so that the fill layer 203 can fill the gap between the coarse sand layer 202 and the crushed stone layer 201, and at the same time, the blind ditch body 1 can be fully covered, so that the blind ditch body 1 can be stably used for drainage of high-filled embankments. By supporting the inner wall of the blind ditch body 1, the collapse of the blind ditch body 1 due to external force can be avoided, and the service life of the blind ditch body 1 can be extended. This embodiment specifically solves the problem that the blind ditch for drainage of high-filled embankments in the prior art is prone to collapse and the drainage effect is poor.
[0040] Although the utility model has been described in detail above with general descriptions and specific embodiments, it is obvious to those skilled in the art that some modifications or improvements can be made to the utility model. Therefore, these modifications or improvements made without departing from the spirit of the utility model are within the scope of protection claimed by the utility model.
Claims
1. A high embankment drainage blind ditch, comprising a blind ditch body (1), characterized in that: Also includes: A covering mechanism (2) is arranged on the outside of the blind ditch body (1) and is used to cover and hide the blind ditch body (1); A supporting mechanism (3) is arranged inside the blind ditch body (1) and is used to support and fix the blind ditch body (1); The support mechanism (3) comprises a plurality of fixed seats (301), traction springs (302) are fixedly mounted on the outer walls of the fixed seats (301), a support plate (303) is fixedly mounted on one end of the traction spring (302) away from the fixed seats (301), support screws (305) are arranged between the inner walls of the fixed seats (301) and the four support plates (303), a fastening nut (306) is threadedly sleeved on the outer wall of one end of the support screw (305) located on the inner side of the fixed seats (301), and a connecting pipe (308) is arranged between two adjacent fixed seats (301).
2. A high embankment drainage blind ditch according to claim 1, characterized in that: The covering mechanism (2) comprises a crushed stone layer (201), the crushed stone layer (201) is arranged on the outside of the blind ditch body (1), and a coarse sand layer (202) is arranged on the outside of the crushed stone layer (201).
3. A high embankment drainage blind ditch according to claim 2, characterized in that: A filling layer (203) is arranged outside the coarse sand layer (202), and the blind ditch body (1) is arranged as a circular plastic blind ditch.
4. A high embankment drainage blind ditch according to claim 1, characterized in that: The support mechanism (3) comprises fixing pins (307), and two groups of the fixing pins (307) are provided. The two groups of the fixing pins (307) are respectively fixedly mounted on the outer walls at both ends of the fixing seat (301).
5. A high embankment drainage blind ditch according to claim 4, characterized in that: Both ends of the connecting tube (308) are movably connected to adjacent fixing pins (307) respectively, and the vertical cross-sectional area size of the inner wall of the connecting tube (308) when viewed from the left is the same as the vertical cross-sectional area size of the inner wall of the fixing seat (301) when viewed from the left.
6. A high embankment drainage blind ditch according to claim 1, characterized in that: The inner wall of the fixing seat (301) is threadedly connected to the outer walls of four support screws (305) respectively. One end of the four support screws (305) away from the fixing seat (301) is abutted against the adjacent support plate (303). The support screws (305) are movably inserted into the inner side of the adjacent traction spring (302).
7. The high embankment drainage blind ditch according to claim 1, characterized in that: The four traction springs (302) are arranged in a ring shape with equal spacing, and a protective pad (304) is fixedly mounted on the outer side of the support plate (303).
8. A high embankment drainage blind ditch according to claim 7, characterized in that: The outer wall of the protective pad (304) is movably connected to the inner wall of the blind ditch body (1), and the left-view vertical section of the support plate (303) and the protective pad (304) is arranged to be a fan-shaped structure.