Honeycomb type reinforcing structure for soil conservation and water locking of side slope

By laying honeycomb grids and anchoring units on the slopes, the problems of complex processes and environmental impact of the existing protective structure are solved, simple construction and soil stability are achieved, and soil loss and ecological damage are avoided.

CN222008946UActive Publication Date: 2024-11-15THE 8TH GRP OF CHINA RAILWAY 1ST ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323660823.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-29
Publication Date
2024-11-15
Estimated Expiration
2033-12-29

AI Technical Summary

Technical Problem

The existing slope protection structure has complex processes and has an impact on the ecological environment, which cannot effectively solve the problem of soil loss during heavy rains.

Method used

A honeycomb reinforcement structure is adopted, including a drainage plate and a honeycomb grid along the slope. The honeycomb grid is composed of a diamond grid and is fixed in the slope through an anchor unit. The anchor unit includes anchor rods and limit steel bars, which avoids large-area concrete pouring. , simplifies the construction process.

Benefits of technology

The construction process is simplified, the impact on the ecological environment is avoided, soil loss is effectively restricted, and the stability and ecological protection of the slope are enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222008946U_ABST
    Figure CN222008946U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of side slope supporting, in particular to a honeycomb type reinforcing structure for soil conservation and water locking of a side slope, which comprises drainage plates vertically arranged along the side slope at equal intervals and honeycomb grids fully paved on the side slope, the honeycomb grids are positioned above the drainage plates, and the honeycomb grids are formed by combining rhombic grids which are fixedly connected with one another. An anchoring unit is connected to the honeycomb grid, the anchoring unit is anchored into the side slope, the anchoring unit comprises an anchor rod body, a plurality of limiting frame bodies are fixedly installed on the anchor rod body, each limiting frame body at least comprises two limiting steel bars, and the limiting steel bars are of a trapezoidal structure. By means of the scheme, the problems that an existing slope protection structure is complex in working procedure and influences the ecological environment are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of slope support, in particular to a honeycomb reinforcement structure for retaining soil and locking water on the slope. Background Art

[0002] Artificial slopes are formed during roadbed construction or foundation pit excavation. In order to prevent the artificial slope from being eroded by rainwater runoff and causing soil and water loss, it is usually necessary to lay soil on the slope and plant green plants. At the same time, in order to avoid the loss of green plants along with the soil due to long-term large runoff during heavy rain, it is also necessary to set up protective structures on the slope, such as arch frames, herringbone frames, prism frames and other protective structures, to restrict the soil.

[0003] However, the above protective structures are all made of concrete. Large areas of concrete not only affect the ecological environment, but also consume a lot of concrete raw materials. In addition, the construction process is complicated, and it is necessary to dig the skeleton groove according to the drawings, place the skeleton steel bars, install the formwork, grouting in the formwork, skeleton maintenance, and demolding. Therefore, it is necessary to design a structure with simple procedures and no impact on the ecological environment. Utility Model Content

[0004] The utility model aims to provide a honeycomb reinforcement structure for slope soil conservation and water locking, so as to solve the problems of the existing slope protection structure having complicated procedures and causing impact on the ecological environment.

[0005] To achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a honeycomb reinforcement structure for soil conservation and water locking on the slope, including drainage boards equidistantly arranged vertically along the slope, and a honeycomb grid fully spread on the slope, the honeycomb grid is located above the drainage boards, the honeycomb grid is composed of diamond grids connected and fixed to each other, a plurality of anchoring units are connected to the honeycomb grid, the anchoring units are anchored in the slope, the anchoring units include an anchor rod body, a plurality of limit frames are fixedly installed on the anchor rod body, each limit frame includes at least two limit steel bars, and the limit steel bars are trapezoidal in structure.

[0006] The advantages of this solution are:

[0007] 1. This scheme only requires laying honeycomb grids on the slope and fixing them with anchoring units, so the construction process is simpler than the existing protective structure. In addition, the honeycomb grids composed of several diamond grids on the slope can restrict the soil inside to prevent soil from being washed away. At the same time, this scheme does not require large-scale concrete pouring on the slope to form a skeleton, so it will not affect the slope ecology.

[0008] 2. The anchoring unit in this scheme not only fixes the honeycomb grid, but also strengthens the slope support.

[0009] 3. In this scheme, the limit frame is composed of a plurality of trapezoidal limit steel bars, which increases the resistance between the anchor rod body and the concrete in the anchor hole. When the slope soil is unstable and moves toward the free surface, the anchor rod body is subjected to tension, which is dispersed and transmitted under the friction resistance of the limit frame, thereby ensuring the stability of the slope.

[0010] Preferably, as an improvement, the anchoring unit is divided into anchoring steel bars and fixed steel bars, one end of the anchoring steel bars fixing the honeycomb grid is a bending portion with a bending angle of 180° and a circular arc transition, and the fixed steel bars are straight.

[0011] Preferably, as an improvement, the longitudinal spacing and the transverse spacing between adjacent anchoring steel bars are both 2m.

[0012] Preferably, as an improvement, the longitudinal spacing and the transverse spacing between adjacent fixed steel bars are both 1 m, and the fixed steel bars in each row are staggered.

[0013] Preferably, as an improvement, the limiting steel bar is an open isosceles trapezoidal structure, including a bottom edge and waist edges integrally formed at both ends of the bottom edge.

[0014] Preferably, as an improvement, the free ends of the two waist edges extend horizontally in the transverse direction to form a connecting piece, and the connecting piece is parallel to the bottom edge.

[0015] Preferably, as an improvement, a plurality of water holes are opened on the side wall of each of the diamond-shaped grids. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a front view of an embodiment of the utility model.

[0017] Figure 2 for Figure 1 Side view of.

[0018] Figure 3 Schematic diagram of the structure of the anchoring unit. DETAILED DESCRIPTION

[0019] The following is further described in detail through specific implementation methods:

[0020] The reference numerals in the drawings of the specification include: honeycomb grid 1, drainage board 2, anchor rod body 3, limiting frame body 4, bottom edge 5, waist edge 6, connecting piece 7, anchoring steel bar 8, and fixing steel bar 9.

[0021] The embodiment is basically as shown in the attached Figure 1-3As shown: a honeycomb reinforcement structure for slope soil conservation and water lock, including drainage boards 2 arranged vertically equidistantly along the entire length of the slope, the drainage boards 2 are plastic drainage boards 2 and are arranged at intervals of 2m. It also includes a honeycomb grid 1 fully spread on the slope, the honeycomb grid 1 is spread above the drainage board 2, the honeycomb grid 1 is composed of a plurality of integrated diamond grids, the wall thickness of the diamond grid does not exceed 2mm, the depth of the diamond grid is 200mm, and the side wall of each diamond grid is provided with several water holes, so that the water in the honeycomb grid 1 can gradually flow downward through the water holes during the rainy season, avoiding excessive water accumulation in the diamond grid which is not conducive to vegetation growth. The honeycomb grid 1 is made of soft plastic material, and polypropylene material is used in this embodiment.

[0022] The honeycomb grid 1 is supported and fixed by anchoring units, and the anchoring units are anchored into the slope. Figure 3 As shown: the anchor unit includes an anchor body 3. In this solution, the anchor body 3 is welded in parallel with two anchor steel bars. The anchor body 3 is fixedly welded with a limiting frame 4 every 1m along its axial direction. Each limiting frame 4 includes at least two limiting steel bars. In this embodiment, three are preferably used, and they are evenly distributed along the circumference of the anchor body 3. The setting of the limiting frame 4 can ensure that when the anchor body 3 is installed in the drill hole, the free end of the anchor body 3 is prevented from generating excessive deflection, and the problem of stirring the hole wall when inserted into the drill hole is avoided; at the same time, it is ensured that there is enough cement mortar around the anchor body 3 to strengthen the anchoring property of the anchor body 3.

[0023] The limiting steel bar is an open isosceles trapezoidal structure, specifically including a bottom edge 5 and waist edges 6 integrally formed at both ends of the bottom edge 5, the free ends of the waist edges 6 extend horizontally in the transverse direction to form a connecting piece 7, and the connecting piece 7 is parallel to the bottom edge 5. The length of the limiting steel bar is 200 mm, of which the length of the bottom edge 5 is 50 mm, and the angle between the bottom edge 5 and the waist edge 6 is 135°.

[0024] The anchoring unit is divided into anchoring steel bars 8 and fixing steel bars 9. The fixing steel bars 9 are straight and have a diameter of 14 mm. The fixing steel bars 9 are mainly used to hang the honeycomb grid 1. Figure 1 As shown, the distribution of the fixed steel bars 9 on the slope is as follows: the longitudinal and transverse spacings between adjacent fixed steel bars 9 are both 1 m, and the fixed steel bars 9 in each row are staggered, so that the honeycomb grid 1 laid on the slope is stretched and expanded to the optimal state, that is, each diamond grid is evenly expanded, so that the use area of ​​the honeycomb grid 1 is fully utilized, and at the same time it is beneficial to the spraying and consolidation of the planting soil.

[0025] The diameter of the anchor steel bar 8 is 16 mm, and one end of the anchor steel bar 8 that fixes the honeycomb grid 1 is a bent portion, the bending angle is 180°, the bending portion is an arc transition, the arc diameter is 50 mm, and the bending length is 200 mm. The anchor steel bar 8 is mainly used to fix the honeycomb grid 1 in its bent portion to fix the honeycomb grid 1 to prevent it from falling off, and at the same time make the honeycomb grid 1 close to the slope surface. The longitudinal spacing and transverse spacing between adjacent anchor steel bars 8 are both 2 m.

[0026] The specific implementation process is as follows: drill anchor holes according to the distribution of the above-mentioned fixed steel bars 9 and anchor steel bars 8, install drainage boards 2 every 2m along the slope, lay the honeycomb grid 1 on the slope, first construct the anchor steel bars 8 on the top of the slope to fix the honeycomb grid 1, then spread the honeycomb grid 1 flat on the slope and fit it, and install the remaining anchor steel bars 8 and fixed steel bars 9 to fix the honeycomb grid 1.

[0027] The above is only an embodiment of the utility model, and the common knowledge such as the known specific technical solutions and / or characteristics in the solution is not described in detail here. It should be pointed out that for those skilled in the art, without departing from the technical solution of the utility model, several deformations and improvements can be made, which should also be regarded as the protection scope of the utility model, and these will not affect the effect of the implementation of the utility model and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.

Claims

1. Honeycomb reinforcement structure for slope soil and water conservation, characterized by: It includes drainage boards arranged vertically at equal intervals along the slope, and a honeycomb grid fully spread on the slope. The honeycomb grid is located above the drainage boards. The honeycomb grid is composed of diamond grids connected and fixed to each other. A plurality of anchoring units are connected to the honeycomb grid. The anchoring units are anchored in the slope. The anchoring units include an anchor rod body. A plurality of limiting frames are fixedly installed on the anchor rod body. Each limiting frame includes at least two limiting steel bars. The limiting steel bars are trapezoidal in structure.

2. The honeycomb reinforcement structure for slope soil conservation and water locking according to claim 1 is characterized in that: The anchoring unit is divided into anchoring steel bars and fixed steel bars. One end of the anchoring steel bar fixing the honeycomb grid is a bending portion with a bending angle of 180°. The bending portion is an arc transition, and the fixed steel bar is in a straight line.

3. The honeycomb reinforcement structure for slope soil conservation and water locking according to claim 2 is characterized in that: The longitudinal and transverse spacings between adjacent anchor steel bars are both 2m.

4. The honeycomb reinforcement structure for slope soil conservation and water locking according to claim 3 is characterized in that: The longitudinal and transverse spacing between adjacent fixed steel bars is 1m, and the fixed steel bars in each row are staggered.

5. The honeycomb reinforcement structure for slope soil conservation and water lock according to claim 4 is characterized in that: The limiting steel bar is in an open isosceles trapezoidal structure, including a bottom edge and waist edges integrally formed at both ends of the bottom edge.

6. The honeycomb reinforcement structure for slope soil conservation and water lock according to claim 5 is characterized in that: The free ends of the two waist edges extend horizontally in the transverse direction to form a connecting piece, and the connecting piece is parallel to the bottom edge.

7. The honeycomb reinforcement structure for slope soil conservation and water lock according to claim 6 is characterized in that: A plurality of water holes are opened on the side wall of each of the rhombus-shaped cells.