Water conservancy project construction cofferdam

By designing a support structure in the cofferdam construction in the water conservancy project, the cofferdam deformation and collapse caused by excessive water pressure are solved, and the stability and safety of the cofferdam are improved.

CN222008963UActive Publication Date: 2024-11-15SICHUAN ZHONGYANG JIANXING CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420201795.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-29
Publication Date
2024-11-15
Estimated Expiration
2034-01-29

AI Technical Summary

Technical Problem

If the water pressure is too high, the cofferdam of traditional water conservancy engineering construction is not supported, and it is likely to cause deformation and collapse, causing casualties.

Method used

A construction cofferdam including the first baffle, the second baffle and the third baffle are designed. By providing a structure such as supporting block, crossbar, positioning groove, positioning plate and sleeve, the limit block and limiting block are used. The grooves are installed and adjusted to ensure stability and support between the baffles and adapt to the size changes of the cofferdam.

Benefits of technology

It effectively avoids misalignment and collapse of the cofferdam, improves construction safety, and ensures that the cofferdam remains stable under water pressure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222008963U_ABST
    Figure CN222008963U_ABST
Patent Text Reader

Abstract

The utility model discloses a hydraulic engineering construction cofferdam, which comprises a first baffle plate, a second baffle plate and a third baffle plate, the side walls of the first baffle plate, the second baffle plate and the third baffle plate are respectively provided with a support block, a cross rod is arranged in the support block, and the upper surface of the cross rod is provided with a positioning groove. Through the structure, the first baffle is matched with the second baffle, the second baffle is matched with the third baffle, the first limiting block is matched with the first limiting groove, and the second limiting block is matched with the second limiting groove, so that the baffles are mounted; cross rods are arranged on the side walls of the first baffle, the second baffle and the third baffle, positioning rods are arranged between the cross rods, the positioning rods are used for supporting the baffles so that the baffles can be kept stable, sleeves are matched with the positioning rods, the length of the positioning rods can be adjusted, adjustment can be conveniently conducted according to the size of the cofferdam, and the practicability is high. Therefore, the safety of the cofferdam is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of water conservancy projects, in particular to a water conservancy project construction cofferdam. Background Art

[0002] A cofferdam refers to a temporary retaining structure built for the construction of permanent water conservancy facilities during water conservancy project construction. Its function is to prevent water and soil from entering the construction site of the building so that drainage can be carried out within the cofferdam, foundation pits can be excavated, and buildings can be constructed. It is generally used in hydraulic structures. Except as part of a formal building, the cofferdam is generally dismantled after use. The height of the cofferdam is higher than the highest water level that may occur during the construction period.

[0003] When using traditional water conservancy project construction cofferdams, if the water pressure is too high and the cofferdams are not supported, it is easy for the cofferdams to deform and collapse, resulting in casualties. Utility Model Content

[0004] The utility model aims to provide a water conservancy project construction cofferdam to solve the technical problem in the prior art that if the water pressure is too high and the cofferdam is not supported, the cofferdam may be easily deformed and collapsed, causing casualties.

[0005] To achieve the above-mentioned purpose, a water conservancy project construction cofferdam is provided, including: a first baffle, a second baffle and a third baffle, the side walls of the first baffle, the second baffle and the third baffle are all provided with support blocks, a cross bar is provided inside the support block, a positioning groove is provided on the upper surface of the cross bar, a positioning plate is provided inside the positioning groove, a first positioning rod is fixedly connected to the side wall of the positioning plate, a sleeve is sleeved on the outside of the first positioning rod, mounting holes are provided at both ends of the sleeve, a second positioning rod is fixedly connected to the side wall of the sleeve, and a positioning plate is fixedly connected to one end of the second positioning rod, The first baffle plate is matched with the second baffle plate, the second baffle plate is matched with the third baffle plate, and the first limit block is matched with the first limit groove, and the second limit block is matched with the second limit groove to install the baffle plate. In addition, cross bars are arranged on the side walls of the first baffle plate, the second baffle plate and the third baffle plate, and positioning rods are arranged between the cross bars. The positioning rods are used to support the baffle plate to keep the baffle plate stable. The sleeve is matched with the positioning rod, and the length of the positioning rod can be adjusted, which is convenient for adjustment according to the size of the cofferdam, thereby ensuring the safety of the cofferdam.

[0006] According to the water conservancy project construction cofferdam, a second limiting groove is opened on one side of the first baffle plate, and a second limiting block is arranged on the other side of the first baffle plate.

[0007] According to the water conservancy project construction cofferdam, the second baffle plate and the third baffle plate side walls are both provided with first limiting grooves, and the third baffle plate side walls are provided with first limiting blocks.

[0008] Additional aspects and advantages of the present invention will be given in part in the following description, and in part will become apparent from the following description, or will be learned through the practice of the present invention.

[0009] The purpose of the utility model is to provide a water conservancy project construction cofferdam, the main innovation points are:

[0010] The utility model utilizes the first baffle to cooperate with the second baffle, the second baffle to cooperate with the third baffle, and utilizes the first limiting block to cooperate with the first limiting groove, and the second limiting block to cooperate with the second limiting groove, so that the baffles can be installed to keep the connected baffles stable and avoid misalignment, and cross bars are arranged on the side walls of the first baffle, the second baffle and the third baffle, and positioning rods are arranged between the cross bars, the positioning rods are used to support the baffles to keep the baffles stable, and the sleeve is used to cooperate with the positioning rod, the length of the positioning rod can be adjusted, and it is convenient to adjust according to the size of the cofferdam, thereby ensuring the safety of the cofferdam. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] The utility model is further described below in conjunction with the accompanying drawings and embodiments;

[0012] Figure 1 This is a right view of the first baffle of a water conservancy project construction cofferdam of the utility model;

[0013] Figure 2 This is a left view of the first baffle of a water conservancy project construction cofferdam of the utility model;

[0014] Figure 3 This is a top view of a water conservancy project construction cofferdam of the utility model;

[0015] Figure 4 The utility model is a cross-sectional view of a sleeve of a cofferdam for water conservancy project construction.

[0016] Legend:

[0017] 1. First baffle; 2. Second baffle; 3. Third baffle; 4. First limiting groove; 5. First limiting block; 6. Second limiting block; 7. Second limiting groove; 8. Cross bar; 9. First positioning rod; 10. Sleeve; 11. Second positioning rod; 12. Positioning groove; 13. Support block; 14. Positioning plate; 15. Mounting hole. DETAILED DESCRIPTION

[0018] This section will describe in detail the specific embodiments of the utility model. The preferred embodiments of the utility model are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the utility model, but it cannot be understood as a limitation on the protection scope of the utility model.

[0019] Reference Figure 1-4 The utility model embodiment of a water conservancy project construction cofferdam comprises: a first baffle 1, a second baffle 2 and a third baffle 3. The side walls of the first baffle 1, the second baffle 2 and the third baffle 3 are all provided with support blocks 13. The support block 13 is arranged in an L shape, which is convenient for installing the cross bar 8. The cross bar 8 is arranged inside the support block 13. The upper surface of the cross bar 8 is provided with a positioning groove 12. The positioning groove 12 cooperates with the positioning plate 14 to position the first positioning rod 9 and the second positioning rod 11, so that the first positioning rod 9 and the second positioning rod 11 can support the cofferdam. The positioning groove 12 is provided with a positioning plate 14. The side wall of the positioning plate 14 is fixedly connected with the first positioning rod 9. The outside of the first positioning rod 9 is sleeved with a sleeve 10, which can increase the length of the first positioning rod 9. Both ends of the sleeve 10 are provided with mounting holes 15. The side wall of the sleeve 10 is fixedly connected with the second positioning rod 11, and one end of the second positioning rod 11 is fixedly connected with the positioning plate 14.

[0020] A second limiting groove 7 is provided on one side of the first baffle plate 1, and the second limiting groove 7 cooperates with the second limiting block 6. A second limiting block 6 is provided on the other side of the first baffle plate 1. First limiting grooves 4 are provided on the side walls of the second baffle plate 2 and the third baffle plate 3, and the first limiting grooves 4 cooperate with the first limiting block 5. A first limiting block 5 is provided on the side wall of the third baffle plate 3.

[0021] Working principle: When in use, the second limiting groove 7 of the side wall of the first baffle plate 1 is matched with the second limiting block 6, and the side wall of the first baffle plate 1 and the second limiting block 6 are matched with the first limiting groove 4 of the side wall of the second baffle plate 2, so as to install the first baffle plate 1 and the second baffle plate 2, and the first limiting block 5 of the side wall of the third baffle plate 3 is matched with the first limiting groove 4 of the side wall of the second baffle plate 2 to facilitate the installation of the second baffle plate 2 and the third baffle plate 3, and then the cross bar 8 is conveniently installed inside the baffle side wall support block 13, and the sleeve 10 is installed at both ends of the first positioning rod 9 according to the size of the cofferdam, and then the positioning plate 14 is installed inside the positioning groove 12, so as to support the first baffle plate 1, the second baffle plate 2 and the third baffle plate 3, so that the cofferdam remains stable after installation to avoid damage to the cofferdam caused by excessive water pressure.

[0022] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments. Various changes can be made within the knowledge scope of ordinary technicians in the technical field without departing from the purpose of the present invention.

Claims

1. A water conservancy project construction cofferdam, characterized in that: include: A first baffle (1), a second baffle (2) and a third baffle (3), the side walls of the first baffle (1), the second baffle (2) and the third baffle (3) are all provided with a support block (13), a cross bar (8) is provided inside the support block (13), a positioning groove (12) is provided on the upper surface of the cross bar (8), a positioning plate (14) is provided inside the positioning groove (12), a first positioning rod (9) is fixedly connected to the side wall of the positioning plate (14), a sleeve (10) is sleeved on the outside of the first positioning rod (9), both ends of the sleeve (10) are provided with mounting holes (15), a second positioning rod (11) is fixedly connected to the side wall of the sleeve (10), and one end of the second positioning rod (11) is fixedly connected to the positioning plate (14).

2. A water conservancy project construction cofferdam according to claim 1, characterized in that: A second limiting groove (7) is provided on one side of the first baffle plate (1), and a second limiting block (6) is provided on the other side of the first baffle plate (1).

3. A water conservancy project construction cofferdam according to claim 1, characterized in that: The side walls of the second baffle plate (2) and the third baffle plate (3) are both provided with a first limiting groove (4), and the side wall of the third baffle plate (3) is provided with a first limiting block (5).