Fabricated modular ground overhead mounting structure
By adopting the cross-structure design of splicing blocks and connecting members and fixtures in the assembled modular floor overhead installation structure, the problem of low installation efficiency caused by the complex thread connection in the prior art is solved, and a fast and stable floor installation is achieved.
Patent Information
- Application Number
- CN202323427292.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-15
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2033-12-15
AI Technical Summary
In the existing prefabricated floor overhead installation technology, the connectors, support components and connecting blocks are connected by threads, resulting in complex installation processes and low efficiency, which affects the installation speed and efficiency of the floor.
The cross-structure design of splicing blocks and connecting members and fixtures is adopted, and the connection grooves and plugs are quickly installed. The fixtures cooperate with the reserved grooves and bumps of the connecting members to ensure connection stability and accuracy.
The floor installation process is simplified, the installation speed and efficiency are improved, the connection stability and strength between the splicing blocks and the connecting members are enhanced, and the installation accuracy and stability are ensured.
Smart Images

Figure CN222009465U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of interior decoration, in particular to an assembled modular ground overhead installation structure. Background Art
[0002] With the introduction of policies to promote the development of prefabricated technology by the state and local governments, various prefabricated technologies have achieved fruitful results through technological innovation and research and development by various enterprises and units. Among them, the prefabricated floor technology is mainly based on overhead installation. The unevenness of the ground is eliminated by supporting and adjusting the base, and the base plate is set up on the base as the installation base, and then various floor veneers are installed by wet pasting or dry laying.
[0003] A Chinese patent with application number 202220139457.0 discloses a modular adjustable leveling elevated floor system. The above-disclosed leveling elevated floor system includes a connecting member, a connecting plate, and a plurality of groups of support members arranged between the connecting plate and the ground. The support member includes a support seat and a support plate. The support seat is arranged below the support plate, and the two are threadedly connected. A positioning hole is provided in the top center of the support plate, and circular notches are symmetrically provided on both sides of the long side of the connecting plate. The number of support members matches the number of circular notches, and the connecting member is arranged between adjacent connecting plates. A Chinese patent with application number 202221644377.7 discloses a composite overhead modular floor. The above-mentioned overhead modular floor includes first connecting blocks installed on both sides of the outside of the first overhead modular floor panel and the second overhead modular floor panel, a second connecting block installed between the first overhead modular floor panel and the second overhead modular floor panel, adjusting screws installed at the lower inside of the first connecting block and the second connecting block, an integrally formed extended limit plate is provided on one side of the outside of the second connecting block, and the first overhead modular floor panel and the second overhead modular floor panel are supported by each other through the extended limit plate.
[0004] In the above-disclosed prior art, the base structure is constructed by suspending the connecting plate through connecting parts and supporting components or suspending the modular floor panel through connecting blocks. However, the supporting structures such as connecting parts, supporting components and connecting blocks are connected by threads, and the installation process is long and involves many steps, which affects the installation efficiency of the floor. Utility Model Content
[0005] The utility model aims to overcome the defects in the prior art and provides an assembled modular ground overhead installation structure which has a simple structure and can be quickly installed.
[0006] In order to achieve the above-mentioned purpose of the utility model, the utility model adopts the following technical solutions: an assembled modular ground overhead installation structure, including a plurality of splicing blocks spliced into a floor, a connecting member for installing and suspending the splicing blocks is arranged at the bottom of the splicing blocks, and a connecting groove for clamping the connecting member is formed at the bottom of the splicing blocks; fixing members for connecting adjacent splicing blocks are arranged between adjacent splicing blocks, the fixing members are arranged at the corners of the splicing blocks, and the fixing members are connected to the connecting members; the connecting members include an upper connecting member and a lower connecting member which are plugged into each other.
[0007] As a preferred solution of the utility model, the connecting groove consists of a first connecting groove and a second connecting groove which are arranged crosswise with each other, and the two ends of the first connecting groove and the second connecting groove are arranged corresponding to the corners of the splicing block, and the upper connecting piece and the lower connecting piece are respectively inserted into the first connecting groove and the second connecting groove.
[0008] As a preferred solution of the utility model, a reserved groove adapted to the fixing piece is formed at the corner of the splicing block, and the reserved groove is connected to the first connecting groove or the second connecting groove.
[0009] As a preferred solution of the present invention, the connecting member and the connecting groove are interference fit, and the height of the connecting member is greater than the depth of the connecting groove.
[0010] As a preferred solution of the utility model, an upper plugging groove for connecting with the lower connecting member is formed in the middle of the upper connecting member, and the upper plugging groove is arranged along the width direction of the upper connecting member.
[0011] As a preferred solution of the utility model, a first protrusion is provided at the top end of the upper connecting member along the length direction of the upper connecting member, and the first protrusion is inserted into the first connecting groove or the second connecting groove.
[0012] As a preferred solution of the utility model, a lower plugging groove matching with the upper plugging groove is formed in the middle of the lower connecting member, and the lower plugging groove is arranged along the width direction of the lower connecting member.
[0013] As a preferred solution of the utility model, a second protrusion is provided at the top end of the lower connecting member along the length direction of the lower connecting member, and the second protrusion is inserted into the second connecting groove or the first connecting groove.
[0014] As a preferred solution of the utility model, the top ends of the plugged upper connecting member and the lower connecting member are located in the same plane.
[0015] As a preferred solution of the utility model, a mounting groove adapted to the connecting member is formed on the fixing member.
[0016] Compared with the prior art, the beneficial effects of the utility model are:
[0017] 1. Under the action of the connecting member clamped on the splicing block and the fixing member used to install and fix the connecting member, by setting the fixing member on the ground, when the splicing block is installed overhead, it is only necessary to insert the connecting member into the connecting groove of the splicing block and install the connecting member on the fixing member to achieve the installation of the floor. The whole floor installation process is simple and convenient, which improves the installation speed and efficiency of the floor;
[0018] 2. Furthermore, by means of a connecting groove composed of a first connecting groove and a second connecting groove arranged crosswise, the connecting groove and the connecting member are interference-fitted, thereby avoiding shaking of the splicing block and improving the connection stability between the splicing block and the connecting member. At the same time, by means of a reserved groove arranged at the corner of the splicing block for matching with the fixing piece, the connection accuracy between the fixing piece and the connecting member is ensured, thereby improving the stability between the connecting member and the fixing piece. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a structural schematic diagram of the utility model;
[0020] Figure 2 It is a schematic diagram of the structure of the splicing block;
[0021] Figure 3 is a schematic diagram of the structure of the upper connecting member;
[0022] Figure 4 is a schematic diagram of the structure of the lower connecting member;
[0023] Figure 5 This is a schematic diagram of the structure of the fixing parts
[0024] Figure markings: splicing block 1, connecting groove 101, first connecting groove 1011, second connecting groove 1012, reserved groove 102, connecting member 2, upper connecting member 201, upper plug-in groove 2011, first protrusion 2012, lower connecting member 202, lower plug-in groove 2021, second protrusion 2022, fixing member 3, installation groove 301. DETAILED DESCRIPTION
[0025] The embodiments of the utility model are described in detail below with reference to the accompanying drawings.
[0026] like Figure 1-Figure 5 As shown, an assembled modular ground overhead installation structure includes a plurality of splicing blocks 1 spliced into a floor, a connecting member 2 for installing and suspending the splicing block 1 is arranged at the bottom of the splicing block 1, and a connecting groove 101 for clamping the connecting member 2 is formed at the bottom of the splicing block 1; fixing members 3 for connecting adjacent splicing blocks 1 are arranged between adjacent splicing blocks 1, the fixing members 3 are arranged at the corners of the splicing block 1, and the fixing members 3 are connected to the connecting member 2; the connecting member 2 includes an upper connecting member 201 and a lower connecting member 202 which are plugged into each other.
[0027] Furthermore, the splicing block 1 is a rectangular structure, and several splicing blocks 1 are spliced together to form a floor covering the ground. The connecting member 2 is clamped on the splicing block 1 through a connecting groove 101 set at the bottom of the splicing block 1. The fixing member 3 is arranged in an array on the ground according to the size of the splicing block 1, and then the connecting member 2 and the splicing block 1 are installed together in the fixing member 3, thereby realizing the installation and fixation of the splicing block 1. Under the action of the connecting member 2, the splicing block 1 is suspended, and at the same time, under the action of the fixing member 3, the connection and fixation between adjacent splicing blocks 1 are realized.
[0028] In addition, the upper connecting member 201 and the lower connecting member 202 are both rectangular plate structures. The upper connecting member 201 and the lower connecting member 202 are plugged into each other to form a cross-shaped connecting member 2. The cross-shaped connecting member 2 has a higher structural strength. When the connecting member 2 is clamped in the connecting groove 101, the connection strength and connection stability between the connecting member 2 and the splicing block 1 are guaranteed.
[0029] The connecting groove 101 is composed of a first connecting groove 1011 and a second connecting groove 1012 which are arranged crosswise with each other, and the two ends of the first connecting groove 1011 and the second connecting groove 1012 are arranged corresponding to the corners of the splicing block 1, and the upper connecting member 201 and the lower connecting member 202 are respectively inserted into the first connecting groove 1011 and the second connecting groove 1012. Furthermore, the first connecting groove 1011 and the second connecting groove 1012 are arranged on the diagonal line of the splicing block 1, and the first connecting groove 1011 and the second connecting groove 1012 are connected in the middle.
[0030] A reserved groove 102 adapted to the fixing member 3 is formed at the corner of the splicing block 1, and the reserved groove 102 is connected to the first connecting groove 1011 or the second connecting groove 1012. Furthermore, by setting the reserved groove 102 adapted to the fixing member 3 at the corner of the splicing block 1, the connection accuracy between the fixing member 3 and the connecting component 2 is guaranteed, and the stability between the connecting component 2 and the fixing member 3 is improved.
[0031] The connecting member 2 is interference fit with the connecting groove 101, and the height of the connecting member 2 is greater than the depth of the connecting groove 101. Furthermore, the width of the upper connecting member 201 and the lower connecting member 202 of the connecting member 2 is greater than the width of the connecting groove 101, thereby improving the connection strength and stability of the connecting member 2 and the connecting groove 101.
[0032] An upper plugging groove 2011 for connecting with the lower connecting member 202 is formed in the middle of the upper connecting member 201 . The upper plugging groove 2011 is arranged along the width direction of the upper connecting member 201 . Furthermore, the opening direction of the upper plugging groove 2011 is arranged toward the lower end of the upper connecting member 201 .
[0033] The top of the upper connecting member 201 is provided with a first protrusion 2012 arranged along the length direction of the upper connecting member 201. The first protrusion 2012 is inserted into the first connecting groove 1011 or the second connecting groove 1012. Further, the first protrusion 2012 and the upper insertion groove 2011 are respectively arranged on opposite sides of the upper connecting member 201.
[0034] A lower plugging groove 2021 matching with the upper plugging groove 2011 is formed in the middle of the lower connecting member 202 . The lower plugging groove 2021 is arranged along the width direction of the lower connecting member 202 . Furthermore, the opening direction of the lower plugging groove 2021 is arranged toward the upper end of the lower connecting member 202 .
[0035] The top of the lower connecting member 202 is provided with a second protrusion 2022 arranged along the length direction of the lower connecting member 202 , and the second protrusion 2022 is inserted into the second connecting groove 1012 or the first connecting groove 1011 . Further, the second protrusion 2022 and the lower insertion groove 2021 are arranged on the same side of the lower connecting member 202 .
[0036] The top ends of the plugged upper connecting member 201 and the lower connecting member 202 are located in the same plane. When the upper connecting member 201 and the lower connecting member 202 are snapped into the connecting groove 101, the upper connecting member 201 and the lower connecting member 202 are both abutted against the top of the connecting groove 101, thereby ensuring the connection strength and connection stability of the upper connecting member 201, the lower connecting member 202 and the connecting groove 101.
[0037] A mounting groove 301 adapted to the connecting member 2 is formed on the fixing member 3 . The mounting groove 301 is arranged on the upper surface of the fixing member 3 , and is a cross structure adapted to the connecting member 2 .
[0038] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention; therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
[0039] Although this article uses more of the following terms: splicing block 1, connecting groove 101, first connecting groove 1011, second connecting groove 1012, reserved groove 102, connecting member 2, upper connecting member 201, upper plugging groove 2011, first convex block 2012, lower connecting member 202, lower plugging groove 2021, second convex block 2022, fixing member 3, mounting groove 301, etc., it does not exclude the possibility of using other terms. These terms are used only to more conveniently describe and explain the essence of the utility model; interpreting them as any additional restrictions is contrary to the spirit of the utility model.
Claims
1. An assembled modular ground overhead installation structure, comprising a plurality of splicing blocks (1) spliced into a floor, It is characterized in that A connecting member (2) for mounting and suspending the splicing block (1) is provided at the bottom of the splicing block (1); a connecting groove (101) for clamping the connecting member (2) is formed at the bottom of the splicing block (1); fixing members (3) for connecting adjacent splicing blocks (1) are provided between adjacent splicing blocks (1); the fixing members (3) are arranged at the corners of the splicing block (1), and the fixing members (3) are connected to the connecting member (2); the connecting member (2) comprises an upper connecting member (201) and a lower connecting member (202) which are plugged into each other.
2. The assembled modular ground overhead installation structure according to claim 1, It is characterized in that The connection groove (101) is composed of a first connection groove (1011) and a second connection groove (1012) which are arranged crosswise with each other, and the two ends of the first connection groove (1011) and the second connection groove (1012) are arranged corresponding to the corners of the assembly block (1), and the upper connection piece (201) and the lower connection piece (202) are respectively inserted into the first connection groove (1011) and the second connection groove (1012).
3. The assembled modular ground overhead installation structure according to claim 2, It is characterized in that A reserved groove (102) adapted to the fixing member (3) is formed at a corner of the splicing block (1), and the reserved groove (102) is connected to the first connecting groove (1011) or the second connecting groove (1012).
4. The assembled modular ground overhead installation structure according to claim 1, It is characterized in that The connecting member (2) and the connecting groove (101) are interference fit, and the height of the connecting member (2) is greater than the depth of the connecting groove (101).
5. The assembled modular ground overhead installation structure according to claim 1, It is characterized in that An upper plugging groove (2011) for connecting with the lower connecting member (202) is formed in the middle of the upper connecting member (201), and the upper plugging groove (2011) is arranged along the width direction of the upper connecting member (201).
6. The assembled modular ground overhead installation structure according to claim 2, It is characterized in that The top end of the upper connecting member (201) is provided with a first protrusion (2012) arranged along the length direction of the upper connecting member (201), and the first protrusion (2012) is inserted into the first connecting groove (1011) or the second connecting groove (1012).
7. The assembled modular ground overhead installation structure according to claim 5, It is characterized in that A lower plugging groove (2021) matching with the upper plugging groove (2011) is formed in the middle of the lower connecting member (202), and the lower plugging groove (2021) is arranged along the width direction of the lower connecting member (202).
8. The assembled modular ground overhead installation structure according to claim 2, It is characterized in that The top end of the lower connecting member (202) is provided with a second protrusion (2022) arranged along the length direction of the lower connecting member (202), and the second protrusion (2022) is inserted into the second connecting groove (1012) or the first connecting groove (1011).
9. The assembled modular ground overhead installation structure according to claim 1, It is characterized in that The top ends of the plugged upper connecting piece (201) and the lower connecting piece (202) are located in the same plane.
10. The assembled modular ground overhead installation structure according to claim 1, It is characterized in that The fixing member (3) is formed with a mounting groove (301) adapted to the connecting member (2).