Scaffold quick connecting structure

By designing a quick connection structure including vertical steel pipe columns, load-bearing disks, transverse steel pipe columns, clamps, pins and springs, the problem of slow erecting speed of existing buckle scaffolds is solved, and the rapid connection of scaffolds is achieved. Simplify the setting process.

CN222009569UActive Publication Date: 2024-11-15SHANXI MECHANIZATION CONSTRUCTION GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420608847.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-27
Publication Date
2024-11-15
Estimated Expiration
2034-03-27

AI Technical Summary

Technical Problem

The existing buckle scaffolding requires manual positioning and tapping of the latch when erecting, resulting in slow erection speed and long construction time.

Method used

A quick connection structure including vertical steel pipe columns, load-bearing discs, transverse steel pipe columns, clamps, pin shafts and springs is designed. The pin shaft is realized by cooperating with the wedge surface through the clamps and wedge surfaces, and gravity and springs are used to realize the pin shaft. Automatic insertion and removal simplifies the connection process between the vertical and horizontal bars.

Benefits of technology

The rapid connection between transverse steel pipe columns and vertical steel pipe columns in scaffolding is realized, simplifying the erection process and improving the erection speed and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222009569U_ABST
    Figure CN222009569U_ABST
Patent Text Reader

Abstract

The utility model discloses a quick connecting structure of a scaffold, and belongs to the technical field of scaffolds. Comprising a vertical steel pipe column, a bearing disc is fixedly arranged in the middle of the vertical steel pipe column, four through grooves evenly distributed in the circumference are formed in the bearing disc, four transverse steel pipe columns matched with the through grooves in position are arranged on the bearing disc, clamping blocks are arranged on the transverse steel pipe columns, one end of each clamping block is fixed to the corresponding transverse steel pipe column, and the other end of each clamping block is fixed to the corresponding through groove. A wedge-shaped face is arranged at the other end of each clamping block, a pin hole is formed in the middle of the portion, above the wedge-shaped face, of each clamping block, four installation blocks which are evenly distributed in the circumferential direction are arranged on the edge of the lower portion of the bearing disc, one ends of the installation blocks are fixed to the bearing disc, pin shafts which are in sliding connection with the installation blocks are arranged on the installation blocks, and the pin shafts are matched with the pin holes in diameter. A spring is arranged on the side face, facing the vertical steel pipe column, of the mounting block, and the sleeve is arranged on the pin shaft. According to the technical scheme, the problem that in the prior art, the erecting speed of a ring-lock type scaffold is low is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of scaffolds, and in particular relates to a scaffold quick connection structure. Background Art

[0002] Scaffolding is a common construction tool in the construction process. It is a working platform set up to ensure the smooth progress of each construction process. At present, my country's scaffolding system includes disc-type scaffolding, bowl-type scaffolding, wheel-type scaffolding, etc. Among them, disc-type scaffolding is favored by more and more construction companies due to its advantages of fast and convenient installation, wide application range and high bearing capacity.

[0003] For example, a mortise and tenon structured scaffolding with patent number CN202321892448.X comprises vertical poles, horizontal poles and latches. A connecting tenon is provided on the vertical pole, and the connecting tenon is provided with a connecting hole and a protruding tenon; a buckle mortise is provided on the end of the horizontal pole, and the buckle mortise is provided with a horizontal socket, a vertical socket and a recessed mortise, and the vertical socket passes through the horizontal socket and the mortise. The horizontal pole forms a mortise and tenon structure with the connecting tenon through the buckle mortise and the connecting tenon. The latch passes through the vertical socket and the connecting hole to lock the buckle mortise with the connecting tenon, thereby realizing a tight connection between the vertical pole and the horizontal pole.

[0004] The existing disc-type scaffolding is the same as that in the existing patent literature. In actual use, it is necessary to manually knock the pins into the connecting tenon to achieve the connection between the vertical poles and the horizontal poles, and the pins need to be manually positioned and knocked. This process will take a certain amount of time, which will lead to a slow erection speed of the scaffolding and a long construction period. Utility Model Content

[0005] In view of this, the purpose of the utility model is to provide a scaffolding quick connection structure to solve the problem of slow erection speed of the disc-type scaffolding in the prior art.

[0006] In order to achieve the above object, the utility model provides the following technical solutions:

[0007] The utility model discloses a scaffolding quick connection structure, comprising a vertical steel pipe column, a bearing plate is fixedly provided in the middle part of the vertical steel pipe column, the bearing plate is provided with four through grooves evenly distributed around the circumference, the bearing plate is provided with four transverse steel pipe columns matching the positions of the through grooves, a clamping block is provided on the transverse steel pipe column, one end of the clamping block is fixed to the transverse steel pipe column, the other end of the clamping block is provided with a wedge-shaped surface, a pin hole is provided in the middle part of the clamping block above the wedge surface, four mounting blocks evenly distributed around the circumference are provided on the lower edge of the bearing plate, one end of the mounting block is fixed to the bearing plate, the mounting block is provided with a pin shaft slidably connected thereto, the pin shaft matches the diameter of the pin hole, a spring is provided on the side of the mounting block facing the vertical steel pipe column, the spring is sleeved on the pin shaft, one end of the spring is fixed to the mounting block, and the other end of the spring is fixed to the pin shaft.

[0008] Furthermore, a guide round head is provided at one end of the pin shaft facing the vertical steel pipe column.

[0009] Furthermore, four groups of right-angle baffles are provided on the bearing plate, and the four groups of right-angle baffles are evenly distributed on the circumference of the bearing plate, and the ends of the transverse steel pipe columns are located between adjacent right-angle baffles.

[0010] Furthermore, the through slot is a rectangular slot, the clamping block is a rectangular block, and the length and width of the through slot match the length and width of the clamping block.

[0011] Furthermore, when the end of the transverse steel pipe column is pressed against the surface of the vertical steel pipe column, the position of the block coincides with the position of the through groove.

[0012] Furthermore, the edge of the right-angle baffle is provided with a chamfer with a smooth transition.

[0013] Furthermore, the edge of the mounting block is provided with a chamfer with a smooth transition.

[0014] Furthermore, one end of the pin shaft facing the vertical steel pipe column is normally located in the middle of the through groove, and the diameter of the pin shaft is smaller than the diameter of the pin hole.

[0015] The beneficial effects of the utility model are:

[0016] In this technical solution, it is only necessary to put the block provided at the end of the transverse steel pipe column into the through groove and then press it downward to insert the pin shaft into the pin hole to achieve connection and installation. The connection method is simple and can achieve rapid connection between the transverse steel pipe column and the vertical steel pipe column in the scaffolding.

[0017] Other advantages, objectives and features of the utility model will be described in the following description and will be apparent to those skilled in the art to some extent, or those skilled in the art can be taught from the practice of the utility model. The objectives and other advantages of the utility model can be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In order to make the purpose, technical solution and beneficial effects of the utility model clearer, the utility model is described with the following drawings:

[0019] Figure 1 It is a three-dimensional schematic diagram of the scaffolding quick connection structure in the utility model;

[0020] Figure 2 It is a three-dimensional schematic diagram of another viewing angle of the scaffolding quick connection structure in the utility model;

[0021] Figure 3 It is a schematic diagram of an exploded view of the scaffolding quick connection structure in the utility model.

[0022] The following are marked in the accompanying drawings:

[0023] Vertical steel pipe column 1, horizontal steel pipe column 2, bearing plate 3, right-angle baffle 4, through slot 5, clamping block 6, pin hole 7, mounting block 8, spring 9, pin shaft 10, fixing ring 11. DETAILED DESCRIPTION

[0024] like Figure 1-Figure 3 As shown, the utility model is a scaffolding quick connection structure, including a vertical steel pipe column 1, a bearing plate 3 is fixedly arranged in the middle of the vertical steel pipe column 1, the middle of the bearing plate 3 is welded and fixed on the vertical steel pipe column 1, four circumferentially evenly distributed through grooves 5 are arranged on the upper surface of the bearing plate 3, four transverse steel pipe columns 2 matching the positions of the through grooves 5 are arranged on the bearing plate 3, a clamping block 6 is arranged on the transverse steel pipe column 2, one end of the clamping block 6 is welded and fixed on the transverse steel pipe column 2, and a wedge-shaped surface is arranged on the other end of the clamping block 6, and the middle of the clamping block 6 above the wedge surface is A pin hole 7 is provided, and four circumferentially evenly distributed mounting blocks 8 are provided on the lower edge of the carrying plate 3. One end of the mounting block 8 is fixed on the carrying plate 3. A pin shaft 10 slidably connected thereto is provided on the mounting block 8. The pin shaft 10 matches the diameter of the pin hole 7. A spring 9 is provided on the side of the mounting block 8 facing the vertical steel pipe column 1, which is sleeved on the pin shaft 10. One end of the spring 9 is fixed on the mounting block 8, and the other end of the spring 9 is fixed to the surface of a fixing ring 11 provided on the pin shaft 10. The middle part of the fixing ring 11 is welded and fixed to the pin shaft 10.

[0025] The principle of quick connection of this technical solution is:

[0026] Put the block 6 set at the end of the horizontal steel pipe column 2 into the through groove 5. Under the action of gravity, the block 6 moves downward, and the wedge surface set on it will contact the pin 10. Then, under the guidance of the inclined surface, the pin 10 will compress the spring 9 and slide outward. When the end position of the pin 10 is flush with the pin hole 7, the pin 10 loses its obstruction and is reset under the action of the spring 9. Then, the pin 10 is inserted into the pin hole 7 to realize the connection and installation. When removing, you only need to pull the pin 10 outward and then lift the horizontal steel pipe column 2.

[0027] like Figure 3 As shown, in an implementable manner, a guide round head is provided at one end of the pin shaft 10 facing the vertical steel pipe column 1. The setting of the guide round head can reduce the sliding resistance between it and the block 6, improve the sliding effect, and at the same time make it easier for the end of the pin shaft 10 to enter the pin hole 7.

[0028] In one feasible manner, four groups of right-angle baffles 4 are provided on the supporting plate 3, and the four groups of right-angle baffles 4 are evenly distributed on the circumference of the supporting plate 3. The end of the transverse steel pipe column 2 is located between adjacent right-angle baffles 4. The transverse steel pipe column 2 is located between the right-angle baffles 4, which can improve the stability of the transverse steel pipe column 2 and also play a guiding role. When the transverse steel pipe column 2 is located between adjacent right-angle baffles 4, the block 6 and the groove are in a straight line, which is also convenient for rapid positioning and assembly.

[0029] In an operative manner, the through slot 5 is a rectangular slot, the block 6 is a rectangular block, and the length and width of the through slot 5 match the length and width of the block 6. Preferably, when the end of the transverse steel pipe column 2 is pressed against the surface of the vertical steel pipe column 1, the position of the block 6 coincides with the position of the through slot 5, so that during assembly, it is only necessary to press the end of the transverse steel pipe column 2 against the vertical steel pipe column 1, and then press down to make the block 6 enter the through slot 5, further improving the assembly speed.

[0030] In an practicable manner, the edge of the right-angle baffle 4 is provided with a chamfer with a smooth transition, and the edge of the mounting block 8 is provided with a chamfer with a smooth transition. The chamfer is provided to prevent the sharp edges from causing scratches to the staff.

[0031] In one feasible method, the end of the pin shaft 10 facing the vertical steel pipe column 1 is normally located in the middle of the through slot 5, and the diameter of the pin shaft 10 is smaller than the diameter of the pin hole 7. The small diameter of the pin shaft 10 can ensure that the block 6 does not slip out of the through slot 5 while allowing the pin shaft 10 to enter the pin hole 7 more easily.

[0032] Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the utility model.

Claims

1. A scaffolding quick connection structure, characterized in that: It includes a vertical steel pipe column, a bearing plate is fixedly provided in the middle part of the vertical steel pipe column, the bearing plate is provided with 4 through grooves evenly distributed around the circumference, the bearing plate is provided with 4 transverse steel pipe columns matching the positions of the through grooves, a clamping block is provided on the transverse steel pipe column, one end of the clamping block is fixed to the transverse steel pipe column, the other end of the clamping block is provided with a wedge-shaped surface, a pin hole is provided in the middle part of the clamping block above the wedge-shaped surface, and 4 mounting blocks evenly distributed around the circumference are provided on the lower edge of the bearing plate, one end of the mounting block is fixed to the bearing plate, the mounting block is provided with a pin shaft slidably connected thereto, the pin shaft matches the diameter of the pin hole, a spring is provided on the side of the mounting block facing the vertical steel pipe column, the spring is sleeved on the pin shaft, one end of the spring is fixed to the mounting block, and the other end of the spring is fixed to the pin shaft.

2. A scaffolding quick connection structure according to claim 1, characterized in that: A guide round head is arranged at one end of the pin shaft facing the vertical steel pipe column.

3. A scaffolding quick connection structure according to claim 1, characterized in that: The bearing plate is provided with four groups of right-angle baffles, which are evenly distributed on the bearing plate on a circumference, and the ends of the transverse steel pipe columns are located between adjacent right-angle baffles.

4. A scaffolding quick connection structure according to claim 1, characterized in that: The through slot is a rectangular slot, the clamping block is a rectangular block, and the length and width of the through slot match the length and width of the clamping block.

5. A scaffolding quick connection structure according to claim 1, characterized in that: When the end of the transverse steel pipe column is pressed against the surface of the vertical steel pipe column, the position of the block coincides with the position of the through groove.

6. A scaffolding quick connection structure according to claim 3, characterized in that: The edge of the right-angle baffle is provided with a chamfer with a smooth transition.

7. A scaffolding quick connection structure according to claim 1, characterized in that: The edge of the mounting block is provided with a chamfer with a smooth transition.

8. A scaffolding quick connection structure according to claim 1, characterized in that: The end of the pin shaft facing the vertical steel pipe column is normally located in the middle of the through groove, and the diameter of the pin shaft is smaller than the diameter of the pin hole.