Large hot water boiler combusting biomass briquette
By designing a reasonable structure and system in a hot water boiler, including flue gas recirculation and hierarchical air supply technology, the problems of slow combustion and incomplete combustion of biomass molded fuels are solved, and efficient combustion and low pollution emissions are achieved, improving the Boiler thermal efficiency.
Patent Information
- Application Number
- CN202323442878.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-15
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2033-12-15
AI Technical Summary
The existing hot water boilers have the problem of slow combustion speed and difficulty in burning out the biomass forming fuel. They often burn the hopper, and the volatile analysis shows that the chemical incomplete combustion is easily caused by untimely combustion.
A type of grate, boiler drum, descending pipe, furnace, burnout chamber, smoke pipe economizer convection heating surface, connecting flue, air preheater, primary air system, secondary air system, and flue gas again The large hot water boiler with the circulation system, front and rear arches, uses flue gas recirculation and hierarchy air supply technology to control the flue gas temperature and oxygen content and improve combustion efficiency by reasonably setting the furnace heating surface and the heating surface of the combustion chamber.
It has achieved high combustion efficiency, high boiler thermal efficiency and low pollution emissions. It has a modular design of angle tube boiler, short installation cycle, light furnace wall and full membrane wall structure. The boiler thermal efficiency can reach more than 88%, reducing the environmentally friendly dust collector pressure.
Smart Images

Figure CN222012306U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of biomass briquette fuel combustion boilers, in particular to a large hot water boiler burning biomass briquette fuel. Background Art
[0002] As a renewable energy, biomass has a unique renewable nature. At the same time, the smoke and sulfur dioxide emissions of combustion products are much lower than those of coal combustion. Therefore, in recent years, it has been concerned and favored by domestic and foreign boilers and related industries. The so-called biomass briquette fuel is made of woody plants, herbaceous plants and their waste materials, and is processed into briquette fuels with a certain shape (mostly regular shape) and size, high stacking density, and convenient transportation and combustion by mechanical processing (such as cutting, crushing, etc.), compact molding and other technologies. However, the high volatility and low ash content of biomass lead to slow combustion speed and difficulty in burning out. Moreover, biomass fuel is easy to ignite and often burns the hopper. In addition, volatile matter accounts for more than 70% of the biomass components, and volatile matter is composed of combustible gases such as methane, hydrogen, carbon monoxide, hydrogen sulfide and some complex organic gas compounds. After the volatiles are analyzed, if they are not burned in time, chemical incomplete combustion losses will occur (q3).
[0003] In summary, when burning biomass pellet fuel, existing hot water boilers have the problems of slow combustion speed, difficulty in burning out, frequent burning of the hopper, and easy chemical incomplete combustion loss due to untimely combustion after volatile analysis. Utility Model Content
[0004] The utility model aims to solve the problems of slow combustion speed, difficulty in complete combustion, frequent burning of the hopper, and easy chemical incomplete combustion loss due to untimely combustion after volatile analysis when burning biomass molded fuel in existing hot water boilers, and thus provide a large hot water boiler that burns biomass molded fuel.
[0005] The technical solution of the utility model is:
[0006] A large hot water boiler burning biomass briquette fuel comprises a grate 1, a boiler drum 2, a downcomer and a connecting pipe 3, a furnace 4, a burnout chamber 5, a convection heating surface 6 of a smoke tube economizer, a connecting flue 7, an air preheater 8, a primary air system 9, a secondary air system 10, a flue gas recirculation system 11, a front arch 12, a rear arch 13 and a hopper 14. The upper front end of the grate 1 is provided with a hopper 14 connected to the grate 1, a first air chamber is provided inside the grate 1, the front end of the first air chamber of the grate 1 is connected to the flue gas recirculation system 11, the bottom end of the first air chamber of the grate 1 is connected to the primary air system 9, a furnace 4 is correspondingly provided above the grate 1, a boiler drum 2 is provided above the furnace 4, and a The tube 2 is connected with the upper and lower ends of the water-cooled wall of the furnace 4 through the downcomer and the connecting pipe 3 respectively. The lower part of the furnace 4 is provided with a front arch 12 and a rear arch 13. The middle and lower part of the furnace 4 is provided with a secondary air system 10, and the secondary air system 10 is installed on the front arch 12 and the rear arch 13. The rear side of the furnace 4 is provided with a burnout chamber 5, a smoke duct economizer convection heating surface 6, a connecting flue 7 and an air preheater 8 arranged vertically in parallel from front to back. The top of the burnout chamber 5 is connected with the top of the furnace 4, the bottom of the burnout chamber 5 is connected with the bottom of the smoke duct economizer convection heating surface 6, the top of the connecting flue 7 is connected with the top of the smoke duct economizer convection heating surface 6, and the bottom of the connecting flue 7 is connected with the bottom of the air preheater 8.
[0007] Furthermore, the furnace 4 is surrounded by a front membrane water-cooled wall, a rear membrane water-cooled wall and two side membrane water-cooled walls arranged vertically.
[0008] Furthermore, the front arch 12 and the rear arch 13 are both made of concrete and attached to the inner wall of the front arch tube of the front membrane water-cooled wall and the rear arch tube of the rear membrane water-cooled wall.
[0009] Furthermore, the flue gas recirculation system 11 includes a recirculation fan and a recirculation flue gas pipeline. A recirculation flue gas inlet is opened at the front end of the first wind chamber of the grate 1, the recirculation fan outlet is connected to the recirculation flue gas inlet, the recirculation fan inlet is connected to one end of the recirculation flue gas pipeline, and the other end of the recirculation flue gas pipeline is connected to the flue gas after the induced draft fan.
[0010] Furthermore, the parameters of the recirculation fan are as follows: the pressure is 2000Pa, and the flue gas volume is 10% of the total flue gas volume.
[0011] Furthermore, the primary air system 9 includes a primary air main pipeline and multiple primary air branch pipelines. A plurality of primary air inlets are evenly arranged in sequence from front to back along the length direction of the grate at the bottom end of the first air chamber of the grate 1. The side wall at one end of the primary air main pipeline is connected to multiple primary air branch pipelines. The multiple primary air branch pipelines are respectively connected to the multiple primary air inlets at the bottom end of the first air chamber of the grate 1. The other end of the primary air main pipeline is connected to the primary air area of the air preheater 8.
[0012] Furthermore, primary air accounts for 70% of the total air volume.
[0013] Furthermore, the secondary air system 10 includes a secondary air main line, a high-pressure fan installed on the secondary air main line, and an ignition air duct group 10-1, a front secondary air duct group 10-2, a front burnout air duct group 10-3, a rear secondary air duct group 10-4 and a rear burnout air duct group 10-5 connected to one end of the secondary air main line, and the other end of the secondary air main line is connected to the secondary air area of the air preheater 8; the ignition air duct group 10-1 is arranged at the front position of the front arch 12, and the ignition air duct group 10-1 is composed of four rows, each row is provided with a plurality of ignition air nozzles; the front secondary air duct group 10-2 It is arranged at the lower part of the front arch 12, and the front secondary air duct group 10-2 consists of two rows, and each row is provided with a plurality of front secondary air nozzles; the rear secondary air duct group 10-4 is arranged at the lower part of the rear arch 13, and the rear secondary air duct group 10-4 consists of two rows, and each row is provided with a plurality of rear secondary air nozzles; the front burnout air duct group 10-3 is arranged at the uppermost part of the front arch 12, and the front burnout air duct group 10-3 consists of one row, and each row is provided with a plurality of front burnout air nozzles; the rear burnout air duct group 10-5 is arranged at the uppermost part of the rear arch 13, and the rear burnout air duct group 10-5 consists of one row, and each row is provided with a plurality of front burnout air nozzles.
[0014] Furthermore, the secondary air accounts for 30% of the total air volume, the wind pressure is 5000Pa, and the wind speed is 50-60m / s.
[0015] Furthermore, the convection heating surface 6 of the smoke tube economizer is formed by a plurality of vertical drums connected in sequence from top to bottom with coaxial ends, and a plurality of smoke tubes are arranged inside each drum. The smoke tubes are threaded, with a thread pitch of 35 mm and a thread depth of 1.5 mm. The specifications of the smoke tubes are 76×4 mm, and the smoke passing speed of the smoke tubes is 20 m / s.
[0016] Compared with the prior art, the utility model has the following effects:
[0017] 1. The utility model provides a large hot water boiler burning renewable energy - biomass briquette fuel, which has high combustion efficiency, high boiler thermal efficiency, low pollution emission and other performances, and also has the characteristics of corner tube boiler modular design concept, short installation period, light furnace wall + steel frame-free structure, full membrane wall structure, small air leakage coefficient, etc. It can be made into 14MW, 21MW, 29MW, 35MW and other large hot water series boiler products.
[0018] 2. The utility model controls the temperature of flue gas entering the flue economizer below 650°C by reasonably setting the heating surface of the furnace and the heating surface of the burnout chamber. At the same time, after the flue gas passes through the heating surface of the burnout chamber, it enters the flue economizer at 180°. The flue gas has a centrifugal process, which serves as the first-stage dust removal device of the boiler to reduce the pressure of the environmental dust collector.
[0019] 3. The utility model connects the flue gas in the flue and turns 180 degrees to enter the air preheater. The flue gas has a centrifugal process again, which serves as the second-stage dust removal device of the boiler to reduce the pressure of the environmental dust collector.
[0020] 4. The tail heating surface is a two-stage air preheater, with cold air entering from the upper stage and hot air exiting from the lower stage. The air preheater is arranged in a bedroom and uses enamel pipes for corrosion resistance. The air preheater is divided into two areas: primary air and secondary air, with a ratio of 3:7. The air preheater can heat the cold air to above 100°C. After the high-temperature hot air enters the furnace, it is more conducive to the combustion of fuel.
[0021] 5. The thermal efficiency of a large hot water boiler burning biomass pellet fuel of the utility model can reach over 88%. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 The utility model is a structural schematic diagram of a large hot water boiler burning biomass briquette fuel.
[0023] In the figure: 1 is the grate; 2 is the boiler drum; 3 is the downcomer and connecting pipe; 4 is the furnace; 5 is the burnout chamber; 6 is the convection heating surface of the smoke duct economizer; 7 is the connecting flue; 8 is the air preheater; 9 is the primary air system; 10 is the secondary air system; 10-1 is the ignition air duct group; 10-2 is the front secondary air duct group; 10-3 is the front burnout air duct group; 10-4 is the rear secondary air duct group; 10-5 is the rear burnout air duct group; 11 is the flue gas recirculation system; 12 is the front arch; 13 is the rear arch; 14 is the hopper. DETAILED DESCRIPTION
[0024] Specific implementation method 1: Combination Figure 1The present embodiment is described. A large hot water boiler for burning biomass molded fuel in the present embodiment comprises a grate 1, a boiler drum 2, a downcomer and a connecting pipe 3, a furnace 4, a burnout chamber 5, a smoke duct economizer convection heating surface 6, a connecting flue 7, an air preheater 8, a primary air system 9, a secondary air system 10, a flue gas recirculation system 11, a front arch 12, a rear arch 13 and a hopper 14. A hopper 14 connected to the grate 1 is provided at the upper front end of the grate 1, a first air chamber is provided inside the grate 1, a front end of the first air chamber of the grate 1 is connected to the flue gas recirculation system 11, a bottom end of the first air chamber of the grate 1 is connected to the primary air system 9, a furnace 4 is provided above the grate 1, and a furnace 4 is provided above the furnace 4. A boiler drum 2 is provided, which is connected with the upper and lower ends of the water-cooled walls of the furnace 4 through a downcomer and a connecting pipe 3 respectively; a front arch 12 and a rear arch 13 are provided at the lower part of the furnace 4; a secondary air system 10 is provided at the middle and lower part of the furnace 4, and the secondary air system 10 is installed on the front arch 12 and the rear arch 13; a burnout chamber 5, a flue gas economizer convection heating surface 6, a connecting flue 7 and an air preheater 8 are arranged vertically in parallel on the rear side of the furnace 4 from front to back; the top of the burnout chamber 5 is connected with the top of the furnace 4, the bottom of the burnout chamber 5 is connected with the bottom of the flue gas economizer convection heating surface 6, the top of the connecting flue 7 is connected with the top of the flue gas economizer convection heating surface 6, and the bottom of the connecting flue 7 is connected with the bottom of the air preheater 8. The dusty flue gas enters the flue economizer convection heating surface 6 from the combustion chamber 5, and has a centrifugal process, which serves as the first-stage dust removal device of the boiler; the dusty flue gas enters the air preheater 8 from the connecting flue 7, and has a centrifugal process, which serves as the second-stage dust removal device of the boiler.
[0025] Specific implementation method 2: Combination Figure 1 This embodiment is described. The furnace 4 of this embodiment is surrounded by a vertically arranged front membrane water-cooled wall, a rear membrane water-cooled wall and two side membrane water-cooled walls. This arrangement adopts a full membrane wall structure, which can effectively reduce air leakage. Other components and connection relationships are the same as those of the first embodiment.
[0026] Specific implementation method three: Combination Figure 1 To explain this embodiment, the front arch 12 and the rear arch 13 of this embodiment are both made of concrete and attached to the front arch tube of the front membrane water-cooled wall and the inner wall of the rear arch tube of the rear membrane water-cooled wall. Other components and connection relationships are the same as those of the first or second embodiment.
[0027] Specific implementation method four: Combination Figure 1To explain this embodiment, the flue gas recirculation system 11 of this embodiment includes a recirculation fan and a recirculation flue gas pipeline. A recirculation flue gas inlet is provided at the front end of the first air chamber of the grate 1, and the recirculation fan outlet is connected to the recirculation flue gas inlet. The recirculation fan inlet is connected to one end of the recirculation flue gas pipeline, and the other end of the recirculation flue gas pipeline is connected to the flue gas after the induced draft fan. With such an arrangement, the flue gas recirculation system 11 is provided to address the problem that biomass fuel has high volatility, is easy to ignite, and often burns the hopper. The flue gas recirculation system 11 extracts a portion of the high-temperature flue gas after the induced draft fan, passes through the recirculation fan, and sends it to the first air chamber of the grate 1, where it is mixed with the hot air from the primary air system 9 that enters the first air chamber. Other components and connection relationships are the same as those of the first, second, or third specific embodiments.
[0028] Specific implementation method five: Combination Figure 1 To explain this embodiment, the parameters of the recirculation fan of this embodiment are as follows: the pressure is 2000Pa, and the smoke volume is 10% of the total smoke volume. In this way, the parameters of the recirculation fan are selected according to the pressure of 2000Pa and the smoke volume is 10% of the total smoke volume. The working principle is: the oxygen content in the smoke is low, generally <9%, which is much less than the oxygen content in the air (21%), that is, in the state of lack of oxygen, the tendency of the fire to move forward is suppressed, and the phenomenon of burning the hopper is solved. Practice has proved that the system is effective. Other components and connection relationships are the same as those of the specific embodiments one, two, three or four.
[0029] Specific implementation method six: Combination Figure 1 To explain this embodiment, the primary air system 9 of this embodiment includes a primary air main line and multiple primary air branch lines. A plurality of primary air inlets are evenly arranged in sequence from front to back along the length direction of the grate at the bottom of the first air chamber of the grate 1. The side wall at one end of the primary air main line is connected to multiple primary air branch lines. The multiple primary air branch lines are respectively connected to the multiple primary air inlets at the bottom of the first air chamber of the grate 1. The other end of the primary air main line is connected to the primary air area of the air preheater 8. With such an arrangement, a reasonable front and rear arch combination is designed according to the properties of biomass such as high volatile matter and low ash content, and with the assistance of primary air, it can be burned quickly and burned out. Other components and connection relationships are the same as those of specific embodiments one, two, three, four or five.
[0030] Specific implementation method seven: Combination Figure 1 To illustrate this embodiment, the primary air in this embodiment accounts for 70% of the total air volume. Other components and connection relationships are the same as those of the specific embodiments one, two, three, four, five or six.
[0031] Specific implementation method eight: Combination Figure 1The present embodiment is described. The secondary air system 10 of the present embodiment includes a secondary air main line, a high-pressure blower installed on the secondary air main line, and an ignition air duct group 10-1, a front secondary air duct group 10-2, a front burnout air duct group 10-3, a rear secondary air duct group 10-4 and a rear burnout air duct group 10-5 connected to one end of the secondary air main line. The other end of the secondary air main line is connected to the secondary air area of the air preheater 8; the ignition air duct group 10-1 is arranged at the front position of the front arch 12, and the ignition air duct group 10-1 is composed of four rows, each row is provided with a plurality of ignition air nozzles; the front secondary air duct Group 10-2 is arranged at the lower part of the front arch 12, and the front secondary air duct group 10-2 consists of two rows, and each row is provided with a plurality of front secondary air nozzles; the rear secondary air duct group 10-4 is arranged at the lower part of the rear arch 13, and the rear secondary air duct group 10-4 consists of two rows, and each row is provided with a plurality of rear secondary air nozzles; the front burnout air duct group 10-3 is arranged at the uppermost part of the front arch 12, and the front burnout air duct group 10-3 consists of one row, and each row is provided with a plurality of front burnout air nozzles; the rear burnout air duct group 10-5 is arranged at the uppermost part of the rear arch 13, and the rear burnout air duct group 10-5 consists of one row, and each row is provided with a plurality of front burnout air nozzles. In this way, the purpose of setting the ignition air duct group 10-1 is to allow the fuel to ignite in advance, increase the ignition time, and facilitate burnout; the purpose of setting the front secondary air duct group 10-2 and the rear secondary air duct group 10-4 is to disturb the airflow, increase the oxygen content, improve the combustion state, improve the combustion efficiency, and reduce the chemical incomplete combustion loss (q3); the purpose of setting the front burnout air duct group 10-3 and the rear burnout air duct group 10-5 is to increase the oxygen content of the unburned volatile matter, improve the combustion efficiency, and further reduce the chemical incomplete combustion loss (q3). Other components and connection relationships are the same as those of the specific embodiments one, two, three, four, five, six or seven.
[0032] In this embodiment, a graded air supply technology is adopted, that is, primary air is set under the grate, and secondary air is set at multiple positions in the lower part of the furnace, and the primary and secondary air are both supplied by separate fans, among which the secondary fan uses a high-pressure fan.
[0033] Specific implementation method nine: Combination Figure 1 To illustrate this embodiment, the secondary air in this embodiment accounts for 30% of the total air volume, the wind pressure is above 5000Pa, and the wind speed is controlled at 50-60m / s. Other components and connection relationships are the same as those of the specific embodiments one, two, three, four, five, six, seven or eight.
[0034] Specific implementation method ten: Combination Figure 1To explain this embodiment, the convection heating surface 6 of the smoke tube economizer of this embodiment is formed by connecting a plurality of vertical drums coaxially from top to bottom in sequence, and a plurality of smoke tubes are arranged inside each drum. The smoke tubes are threaded, the thread pitch of the threaded smoke tubes is 35mm, the thread depth is 1.5mm, the smoke tube specification is 76×4mm, and the smoke tube smoke speed is about 20m / s. With such a configuration, the high smoke speed heat transfer coefficient is high, the heat transfer effect is good, and the dust accumulation is resisted. The other components and connection relationships are the same as those of the first, second, third, fourth, fifth, sixth, seventh, eighth or ninth embodiments.
[0035] In this embodiment, the smoke tube economizer is a plurality of vertical drums, generally four in number.
[0036] How it works
[0037] Combination Figure 1 The working principle of a large-scale hot water boiler burning biomass briquette fuel of the utility model is described as follows: the biomass briquette fuel is sent to the hopper 14 through the feeder, and the fuel falls on the grate sheet of the grate 1, and is transported forward by the grate sheet to enter the furnace 4, and the primary air system 9 is sent upward through the grate 1, and is quickly burned on the grate sheet under the reasonable matching of the front arch 12 and the rear arch 13; the slag produced after combustion continues to be transported forward by the grate sheet, and finally falls into the slag trough; and the unburned light floating fuel A secondary air system 10 is provided in the lower middle part of the furnace 4, through which air is supplied to increase the amount of oxygen so that the fuel can continue to burn; finally, the high-temperature flue gas produced by the combustion passes through the furnace 4 and flows upward; then, it turns downward and passes through the burnout chamber 5 to reach the convection heating surface 6 of the smoke tube economizer and is discharged from the main body; then, it passes through the relevant connecting flue 7, enters the air preheater 8, and is finally discharged into the atmosphere; the temperature of the flue gas discharged into the atmosphere is controlled between 140-150°C.
[0038] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A large hot water boiler burning biomass pellet fuel, characterized by: It comprises a grate (1), a boiler drum (2), a downcomer and a connecting pipe (3), a furnace (4), a burnout chamber (5), a convection heating surface of a smoke tube economizer (6), a connecting flue (7), an air preheater (8), a primary air system (9), a secondary air system (10), a flue gas recirculation system (11), a front arch (12), a rear arch (13) and a hopper (14). A hopper (14) connected to the grate (1) is provided at the upper front end of the grate (1). A first air chamber is provided inside the grate (1). The front end of the first air chamber of the grate (1) is connected to the flue gas recirculation system (11). The bottom end of the first air chamber of the grate (1) is connected to the primary air system (9). A furnace (4) is provided above the grate (1). A boiler drum (2) is provided above the furnace (4). The boiler drum (2) is connected to the primary air system (9) through the lower The downcomer and the connecting pipe (3) are respectively connected to the upper and lower ends of the water-cooled wall of the furnace (4); the lower part of the furnace (4) is provided with a front arch (12) and a rear arch (13); the middle and lower part of the furnace (4) is provided with a secondary air system (10); the secondary air system (10) is installed on the front arch (12) and the rear arch (13); the rear side of the furnace (4) is provided with a burnout chamber (5), a flue gas economizer convection heating surface (6), a connecting flue (7) and an air preheater (8) arranged vertically in parallel from front to back; the top of the burnout chamber (5) is connected to the top of the furnace (4); the bottom of the burnout chamber (5) is connected to the bottom of the flue gas economizer convection heating surface (6); the top of the connecting flue (7) is connected to the top of the flue gas economizer convection heating surface (6); the bottom of the connecting flue (7) is connected to the bottom of the air preheater (8).
2. A large hot water boiler burning biomass pellet fuel according to claim 1, characterized in that: The furnace (4) is surrounded by a front membrane water-cooled wall, a rear membrane water-cooled wall and two side membrane water-cooled walls which are arranged vertically.
3. A large hot water boiler burning biomass pellet fuel according to claim 2, characterized in that: The front arch (12) and the rear arch (13) are both made of concrete and attached to the inner wall of the front arch tube of the front membrane type water cooling wall and the rear arch tube of the rear membrane type water cooling wall.
4. A large hot water boiler burning biomass pellet fuel according to claim 3, characterized in that: The flue gas recirculation system (11) comprises a recirculation fan and a recirculation flue gas pipeline. A recirculation flue gas inlet is provided at the front end of the first wind chamber of the grate (1). The recirculation fan outlet is connected to the recirculation flue gas inlet. The recirculation fan inlet is connected to one end of the recirculation flue gas pipeline. The other end of the recirculation flue gas pipeline is connected to the flue gas after the induced draft fan.
5. A large hot water boiler burning biomass pellet fuel according to claim 4, characterized in that: The parameters of the recirculation fan are as follows: the pressure is 2000Pa, and the flue gas volume is 10% of the total flue gas volume.
6. A large hot water boiler burning biomass pellet fuel according to claim 5, characterized in that: The primary air system (9) comprises a primary air main line and a plurality of primary air branch lines. A plurality of primary air inlets are uniformly arranged in sequence from front to back along the length direction of the grate at the bottom end of the first air chamber of the grate (1). The side wall at one end of the primary air main line is connected to the plurality of primary air branch lines. The plurality of primary air branch lines are respectively connected to the plurality of primary air inlets at the bottom end of the first air chamber of the grate (1). The other end of the primary air main line is connected to the primary air area of the air preheater (8).
7. A large hot water boiler burning biomass pellet fuel according to claim 6, characterized in that: Primary air accounts for 70% of the total air volume.
8. A large hot water boiler burning biomass pellet fuel according to claim 7, characterized in that: The secondary air system (10) comprises a secondary air main line, a high-pressure fan installed on the secondary air main line, and an ignition air duct group (10-1), a front secondary air duct group (10-2), a front burnout air duct group (10-3), a rear secondary air duct group (10-4) and a rear burnout air duct group (10-5) connected to one end of the secondary air main line, and the other end of the secondary air main line is connected to the secondary air area of the air preheater (8); the ignition air duct group (10-1) is arranged at the front position of the front arch (12), and the ignition air duct group (10-1) is composed of four rows, each row is provided with a plurality of ignition air nozzles; the front secondary air duct group (10-2) is provided with At the lower part of the front arch (12), the front secondary air duct group (10-2) is composed of two rows, each row is provided with a plurality of front secondary air nozzles; the rear secondary air duct group (10-4) is arranged at the lower part of the rear arch (13), the rear secondary air duct group (10-4) is composed of two rows, each row is provided with a plurality of rear secondary air nozzles; the front burnout air duct group (10-3) is arranged at the uppermost part of the front arch (12), the front burnout air duct group (10-3) is composed of one row, each row is provided with a plurality of front burnout air nozzles; the rear burnout air duct group (10-5) is arranged at the uppermost part of the rear arch (13), the rear burnout air duct group (10-5) is composed of one row, each row is provided with a plurality of front burnout air nozzles.
9. A large hot water boiler burning biomass pellet fuel according to claim 8, characterized in that: Secondary air accounts for 30% of the total air volume, with a wind pressure of 5000Pa and a wind speed of 50-60m / s.
10. A large hot water boiler burning biomass pellet fuel according to claim 9, characterized in that: The convection heating surface (6) of the smoke tube economizer is formed by connecting a plurality of vertical drums coaxially from top to bottom in sequence, and a plurality of smoke tubes are arranged inside each drum. The smoke tubes are threaded, with a thread pitch of 35 mm and a thread depth of 1.5 mm. The specifications of the smoke tubes are 76×4 mm, and the smoke passing speed of the smoke tubes is 20 m / s.