PCP automatic pre-stacking line
By introducing stacking load transfer mechanism and PP/core board supply mechanism in the PCP automatic pre-stacking system, combined with linear screw module and CCD camera detection, the problems of core board erasing and misalignment in the traditional technology are solved, and the product is improved Quality and capacity.
Patent Information
- Application Number
- CN202420126991.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-18
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-01-18
AI Technical Summary
In traditional PCP automatic pre-stacking wires, the core plate is prone to rubbing and misalignment during handling, resulting in low production capacity and low product quality.
An automatic pre-stacking system including stacking load transfer mechanism, no-load disk supply mechanism, PP supply mechanism, core plate supply mechanism and stacking recycling mechanism is designed, and is realized through components such as linear lead screw module and pneumatic jaws. Accurate stacking and recycling of PP and core plates, avoiding wiping, and using a CCD camera to detect the diagonal opposite edge position of PP to ensure the accuracy of stacking.
It effectively avoids the problems of brushing and misalignment of the core plate during the pre-stacking process, improves the quality and production capacity of the product, and ensures the position accuracy and cleanliness of the PP.
Smart Images

Figure CN222016894U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of PCP preparation technology, in particular to a PCP automatic pre-stacking line. Background Art
[0002] As electronic technology continues to develop in the direction of high speed, multi-function, large capacity, portability and low power consumption, the quality requirements for printed circuit boards (PCP) are becoming increasingly higher. Traditional PCP automatic pre-stacking lines have at least the following problems: (1) The PP stacked on the pallet will be uneven, resulting in misalignment of the PP-core board-PP after pre-stacking; (2) The core board incoming pattern is a whole stack, and each core board will contact each other, which will cause scratches on the core board surface and make it difficult to separate during the production and transportation process, thus failing to improve production capacity and product yield. In order to meet the needs of the client market, the utility model provides a PCP automatic pre-stacking line. Utility Model Content
[0003] In order to overcome the deficiencies of the prior art, the utility model discloses a PCP automatic pre-stacking line.
[0004] To achieve the above object, the utility model is implemented by the following technical solutions: PCP automatic pre-stacking line, characterized by comprising a stacking material transfer mechanism and an empty tray supply mechanism, at least one first PP supply mechanism, a core board supply mechanism, at least one second PP supply mechanism, and a stacking material recovery mechanism, which are arranged from left to right on one side of the stacking material transfer mechanism;
[0005] The stacking material transfer mechanism comprises a machine platform, three straight grooves are formed on the table top of the machine platform, seven stacking material carrier blocks are respectively disposed on the side walls of the three straight grooves, a first linear drive assembly is disposed at the bottom of the machine platform, six first lifting drive assemblies are respectively connected to the first linear drive assembly, and two stacking material carrier clamping assemblies are respectively connected to the six first lifting drive assemblies passing through the straight grooves on both sides;
[0006] The empty tray supply mechanism comprises two first chassis which are separated from each other, first conveyors are respectively arranged on opposite sides of the two first chassis, an empty tray lifting assembly is arranged between the two first conveyors, empty tray transfer manipulators are arranged above the first conveyors in the two first chassis, dust collecting covers are arranged above the empty tray lifting assemblies in the two first chassis, and empty tray temporary storage platforms are arranged on the rear sides of the empty tray lifting assemblies in the two first chassis, a second linear drive assembly is arranged inside one of the first chassis, a first avoidance groove is opened on the side opposite to the other first chassis, a second lifting drive assembly is connected to the second linear drive assembly, and an empty tray suction assembly is connected to the second lifting drive assembly to pass through the first avoidance groove;
[0007] The at least one first PP supply mechanism and the at least one second PP supply mechanism have the same structure, and respectively include two second chassis that are separated from each other, and second conveyors are respectively arranged on opposite sides of the two second chassis, a third lifting drive component is arranged inside one of the second chassis, and a second avoidance groove is opened on the side opposite to the other second chassis, a pallet grabbing manipulator is connected to the third lifting drive component and passes through the second avoidance groove, a pallet lifting component is arranged between the two second conveyors corresponding to the rear side of the pallet grabbing manipulator, a PP alignment platform is arranged between the two second conveyors corresponding to the rear side of the pallet lifting component, and a single PP separation component is arranged on the two second chassis corresponding to the pallet lifting component above the pallet lifting component, a third linear drive component is arranged inside one of the second chassis, and a third avoidance groove is opened on the side opposite to the other second chassis, a fourth lifting drive component and a fifth lifting drive component are connected to the third linear drive component, and the first PP suction component and the second PP suction component are respectively connected to the fourth lifting drive component and the fifth lifting drive component through the third avoidance groove;
[0008] The core board supply mechanism includes two third chassis that are separated from each other, and third conveyors are respectively arranged on opposite sides of the two third chassis, and a sixth lifting drive assembly and a seventh lifting drive assembly are sequentially arranged inside the two third chassis, and a fourth avoidance groove and a fifth avoidance groove are respectively opened on opposite sides of the two third chassis, and the two sixth lifting drive assemblies are respectively connected to the first mounting bracket passing through the fourth avoidance groove, and the two seventh lifting drive assemblies are respectively connected to the second mounting bracket passing through the fifth avoidance groove; a fourth linear drive assembly is also arranged inside one of the third chassis, and a sixth avoidance groove is opened on the side opposite to the two third chassis, and an eighth lifting drive assembly and a ninth lifting drive assembly are connected to the fourth linear drive assembly, and the eighth lifting drive assembly is connected to a core board carrier tray suction assembly passing through the sixth avoidance groove, and the ninth lifting drive assembly is connected to a core board suction assembly passing through the sixth avoidance groove;
[0009] The stacking material recovery mechanism includes two fourth chassis that are separated from each other, fourth conveyors are respectively provided on opposite sides of the two fourth chassis, tenth lifting drive components are provided inside the two fourth chassis, seventh avoidance grooves are respectively opened on opposite sides of the two third chassis, and third mounting brackets are respectively connected to the two tenth lifting drive components to pass through the seventh avoidance grooves. A fifth linear drive component is also provided inside one of the fourth chassis, and an eighth avoidance groove is opened on the side opposite to the other fourth chassis. The fifth linear drive component is connected to an eleventh lifting drive component, and the eleventh lifting drive component is connected to a stacking material carrier suction component.
[0010] It is further preferred that the first lifting drive assembly includes a lower plate, an upper plate and four first lifting drive cylinders, the lower plate is connected to the first linear drive assembly, the four first lifting drive cylinders are arranged above the lower plate, and the upper plate is connected to the first lifting drive cylinders on the lower plate.
[0011] Further preferably, the stacking tray clamping assembly is a pneumatic clamp fixed on the upper plate.
[0012] It is further preferred that an air blowing block and a dust suction block are arranged at the bottom of the dust collecting hood, a plurality of air blowing nozzles are arranged at the bottom of the air blowing block, and a plurality of dust suction nozzles are arranged at the bottom of the dust suction block.
[0013] It is further preferred that the empty plate lifting assembly and the pallet lifting assembly are both scissor fork lifting platforms.
[0014] It is further preferred that the empty tray transfer robot includes two sixth linear drive assemblies, which are respectively arranged on opposite sides of the two first chassis, and the two sixth linear drive assemblies are connected to a first arm, and a plurality of first suction cups are arranged at the bottom of the first arm.
[0015] It is further preferred that the empty carrier plate suction assembly, the first PP suction assembly, the second PP suction assembly, the core plate carrier plate suction assembly, the core plate suction assembly and the stacked material carrier plate suction assembly have the same structure, respectively comprising a translation block and two second arms, the two second arms are respectively vertically connected to the translation block, and a plurality of second suction cups are arranged at the bottom of the two second arms.
[0016] Further preferably, the PP alignment platform includes a seventh linear drive assembly, an eighth linear drive assembly and a platform body, the eighth linear drive assembly is connected to the seventh linear drive assembly, and the platform body is connected to the eighth linear drive assembly.
[0017] It is further preferred that the first linear drive assembly, the second linear drive assembly, the third linear drive assembly, the fourth linear drive assembly, the fifth linear drive assembly, the sixth linear drive assembly, the seventh linear drive assembly, the eighth linear drive assembly, the second lifting drive assembly, the third lifting drive assembly, the fourth lifting drive assembly, the fifth lifting drive assembly, the sixth lifting drive assembly, the seventh lifting drive assembly, the eighth lifting drive assembly, the ninth lifting drive assembly, the tenth lifting drive assembly and the eleventh lifting drive assembly are all linear screw modules, wherein the first linear drive assembly adopts a linear screw module with six sliders, and the third linear drive assembly and the fourth linear drive assembly adopt a linear screw module with two sliders.
[0018] It is further preferred that the first conveyor, the second conveyor, the third conveyor and the fourth conveyor are all roller conveyors.
[0019] Further preferably, the PP alignment platform includes a platform body having a U-shaped groove on one side, a pneumatic slide is provided below the platform body relative to the U-shaped groove, and a thickness gauge that can be extended into the U-shaped groove is installed on the slide of the pneumatic slide.
[0020] It is further preferred that it also includes an aluminum profile frame mounted on the outside of the stacking material transfer mechanism, the carrier plate supply mechanism, at least one first PP supply mechanism, the core plate supply mechanism, at least one second PP supply mechanism and the stacking material recovery mechanism, and at least one first PP diagonal edge detection component and at least one second PP diagonal edge detection component are arranged below the top of the aluminum profile frame; the at least one first PP diagonal edge detection component and the at least one second PP diagonal edge detection component have the same structure, respectively including a first CCD camera fixed to the aluminum profile frame through a first bracket, and a second CCD camera fixed to the aluminum profile frame through a second bracket, and the first CCD camera and the second CCD camera are arranged diagonally opposite each other front and back.
[0021] It is further preferred that the single PP separation assembly includes four telescopic drive cylinders arranged in pairs on opposite sides of the two second chassis, the piston rods of the telescopic drive cylinders are connected to telescopic blocks, the telescopic blocks are provided with second lifting drive cylinders, the piston rods of the second lifting drive cylinders are connected to the first lifting plate, and a plurality of third suction cups are provided at the bottom of the first lifting plate.
[0022] Further preferably, the pallet grabbing robot comprises a second lifting plate connected to the third lifting drive assembly, and a plurality of fourth suction cups are arranged at the bottom of the second lifting plate.
[0023] It is further preferred that the first stacking bracket, the second stacking bracket and the third stacking bracket have the same structure, and respectively include a carrier plate and two L-shaped plates arranged on the carrier plate.
[0024] The utility model achieves the following beneficial effects:
[0025] 1. The present invention can sequentially move the empty tray supplied by the empty tray supply mechanism through at least one first PP supply mechanism, a core board supply mechanism, at least one second PP supply mechanism and a stacking material recovery mechanism through a stacking material transfer mechanism. During this process, at least one first PP supply mechanism can put at least one layer of PP film into the pre-stacked tray, the core board supply mechanism can put a core board on top of the PP film in the pre-stacked tray, the second PP supply mechanism can put at least one layer of PP film on top of the core board in the pre-stacked tray, and the stacking material recovery mechanism can recover the pre-stacked PCP material and the pre-stacked tray together. In summary, the present invention pre-stacks each layer of PP film and the core board in the tray, which can avoid scratches on the core board during the pre-stacking process, and by placing each core board in a carrier for supply, scratches on multiple core boards during the stacking process and difficulty in separation can be avoided.
[0026] 2. The utility model can ensure that the position of PP will not deviate and ensure the quality of the pre-stacked PCP material by cooperating at least one first PP diagonal edge detection component with at least one first PP alignment platform and at least one second PP diagonal edge detection component with at least one second PP alignment platform.
[0027] 3. The pneumatic slide table of the utility model drives the thickness gauge into the U-shaped groove, which can facilitate the thickness gauge to detect the thickness of PP and ensure that the PP placed in the pre-stacked tray is one sheet each time, which plays a role in error prevention and has strong practicality.
[0028] 4. The utility model can blow air to the empty tray and then suck air to remove dust through the dust collecting hood, thereby ensuring the cleanliness of the empty tray, ensuring that the pre-stacked PCP material will not be contaminated with dust, and improving the pre-stack quality.
[0029] Other features and advantages of the utility model will be described in the following description, and partly become apparent from the description, or understood by implementing the utility model. The purpose and other advantages of the utility model can be realized and obtained through the structures indicated in the description and the drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] The accompanying drawings herein are incorporated in and constitute a part of the specification, illustrate embodiments consistent with the disclosure of the utility model, and together with the description, are used to explain the principles of the disclosure.
[0031] Figure 1 It is a schematic diagram of the overall structure disclosed by the utility model;
[0032] Figure 2 This is a schematic diagram of the structure of the utility model after removing the aluminum profile frame;
[0033] Figure 3It is a partial top view structural diagram of the stacking and transferring mechanism disclosed in the utility model;
[0034] Figure 4 This is a schematic diagram of the structure of the first lifting drive assembly disclosed in the utility model;
[0035] Figure 5 This is a schematic diagram of the structure of the tray supply mechanism disclosed in the utility model;
[0036] Figure 6 It is a second PP supply mechanism or a schematic diagram of the structure of the second PP supply mechanism disclosed in the utility model;
[0037] Figure 7 It is a partial side structural schematic diagram of a single PP separation component disclosed in the utility model;
[0038] Figure 8 This is a schematic diagram of the core board supply mechanism disclosed in the utility model;
[0039] Fig. 9 This is a schematic diagram of the structure of the stacked material recovery mechanism disclosed in the utility model;
[0040] Fig.10 It is a schematic diagram of the structure of the first PP diagonal edge detection component or the second PP diagonal edge detection component disclosed in the utility model;
[0041] Fig.11 It is a schematic diagram of the position structure of the first PP diagonal edge detection component or the second PP diagonal edge detection component and the PP alignment platform disclosed in the utility model. DETAILED DESCRIPTION
[0042] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.
[0043] In the description of the present invention, it should be understood that terms such as "opening", "upper", "lower", "thickness", "top", "middle", "length", "inside", "all around" and the like indicating orientation or positional relationship are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the components or elements referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0044] In order to solve the problem that the core board is difficult to separate and easy to scratch during the pre-stacking process in the prior art, and the problem that the PP and core board are misaligned after pre-stacking, such as Figure 1-Figure 11As shown, the present application discloses a PCP automatic pre-stacking line, including a stacking material transfer mechanism 10 and an empty tray supply mechanism 20, at least one first PP supply mechanism 30, a core board supply mechanism 40, at least one second PP supply mechanism 50, and a stacking material recovery mechanism 60, which are arranged from left to right on one side of the stacking material transfer mechanism;
[0045] The stacking material transfer mechanism comprises a machine table 11, on which three straight grooves 111 are provided on the table top, and seven stacking material carrier support blocks 1111 are provided on the side walls of the three straight grooves, respectively. A first linear drive assembly 12 is provided at the bottom of the machine table, and six first lifting drive assemblies 13 are respectively connected to the first linear drive assembly, and two stacking material carrier clamping assemblies 14 are respectively connected to the six first lifting drive assemblies and pass through the straight grooves on both sides;
[0046] The empty tray supply mechanism includes two first chassis 21 which are separated from each other, first conveyors 22 are respectively arranged on opposite sides of the two first chassis, an empty tray lifting assembly 23 is arranged between the two first conveyors, empty tray transfer manipulators 24 are arranged above the first conveyors of the two first chassis, dust collecting covers 25 are arranged above the empty tray lifting assemblies of the two first chassis, and empty tray temporary placement platforms 26 are arranged on the rear sides of the empty tray lifting assemblies of the two first chassis, a second linear drive assembly 27 is arranged inside one of the first chassis, a first avoidance groove (not marked) is opened on the side opposite to the other first chassis, a second lifting drive assembly 28 is connected to the second linear drive assembly, and an empty tray suction assembly 29 is connected to the second lifting drive assembly and passes through the first avoidance groove (not marked);
[0047] The at least one first PP supply mechanism and the at least one second PP supply mechanism have the same structure, and respectively include two second chassis 31 that are separated from each other, and second conveyors 32 are respectively arranged on opposite sides of the two second chassis, a third lifting drive assembly 33 is arranged inside one of the second chassis, and a second avoidance groove (not shown) is opened on the side opposite to the other second chassis, and a pallet grabbing manipulator 34 is connected to the third lifting drive assembly and passes through the second avoidance groove, and a pallet lifting assembly 35 is arranged between the two second conveyors corresponding to the rear side of the pallet grabbing manipulator, and the rear side of the pallet lifting assembly corresponds to A PP alignment platform 36 is provided between the two second conveyors, and a single PP separation component 37 is provided on the two second chassis corresponding to the pallet lifting component, a third linear drive component 38 is provided inside one of the second chassis, and a third avoidance groove (not shown) is provided on the side opposite to the other second chassis, and a fourth lifting drive component 39 and a fifth lifting drive component 311 are connected to the third linear drive component, and the first PP suction component 312 and the second PP suction component 313 are respectively connected to the fourth lifting drive component and the fifth lifting drive component through the third avoidance groove;
[0048] The core board supply mechanism includes two third chassis 41 that are separated from each other, and third conveyors 42 are respectively arranged on opposite sides of the two third chassis, and sixth lifting drive components 43 and seventh lifting drive components 44 are sequentially arranged inside the two third chassis, and fourth avoidance grooves (not shown) and fifth avoidance grooves (not shown) are respectively opened on opposite sides of the two third chassis, and first mounting brackets 45 are respectively connected to the two sixth lifting drive components, passing through the fourth avoidance grooves, and second mounting brackets 46 are respectively connected to the two seventh lifting drive components, passing through the fifth avoidance grooves; a fourth linear driving component 47 is also arranged inside one of the third chassis, and a sixth avoidance groove (not shown) is opened on the side opposite to the two third chassis, and an eighth lifting drive component 48 and a ninth lifting drive component 49 are connected to the fourth linear driving component, a core board carrier plate suction component 411 is connected to the eighth lifting drive component, passing through the sixth avoidance groove, and a core board suction component 412 is connected to the ninth lifting drive component, passing through the sixth avoidance groove;
[0049] The stacking material recovery mechanism includes two fourth chassis 51 that are separated from each other, and fourth conveyors 62 are respectively provided on opposite sides of the two fourth chassis, and tenth lifting drive assemblies 63 are provided inside the two fourth chassis, and seventh avoidance grooves (not shown) are respectively opened on opposite sides of the two third chassis, and third mounting brackets 64 are respectively connected to the two tenth lifting drive assemblies to pass through the seventh avoidance grooves. A fifth linear drive assembly 65 is also provided inside one of the fourth chassis, and an eighth avoidance groove (not shown) is opened on the side opposite to the other fourth chassis, and an eleventh lifting drive assembly 66 is connected to the fifth linear drive assembly, and the eleventh lifting drive assembly is connected to the stacking material carrier suction assembly 67.
[0050] In one specific implementation scheme, the first lifting drive assembly includes a lower plate 131, an upper plate 133 and four first lifting drive cylinders 132. The lower plate is connected to the first linear drive assembly. The four first lifting drive cylinders are arranged above the lower plate. The upper plate is connected to the first lifting drive cylinders on the lower plate. Driven by the first linear drive assembly, the lower plate, the upper plate and the four first lifting drive cylinders will move horizontally. During this process, the four first lifting drive cylinders can drive the upper plate and the two stacking tray assemblies on the upper plate to lift and lower, so that the stacking tray moves on the machine table and can reach the corresponding three stacking tray support blocks.
[0051] In one of the specific embodiments, the stacking tray clamping assembly is a pneumatic clamp fixed on the upper plate, and the pre-stacked tray can be clamped by opening and closing the pneumatic clamp.
[0052] In combination with the above two specific implementation schemes, the principle of the stacking and transplanting mechanism in this application is as follows:
[0053] Assume that there are four stacking trays located on four stacking tray support blocks from left to right on the machine table;
[0054] Firstly, the first lifting drive cylinders included in all the first lifting drive components drive the upper plate to rise, so that the pneumatic clamps pass through the straight grooves. Then, the first linear drive component drives all the first lifting drive components to move a short distance to the right, and the pneumatic clamps first clamp the stacking tray. Then, the first linear drive component drives all the first lifting drive components to move a long distance to the left, and then the four stacking trays will enter the next process position at the same time.
[0055] In one of the specific embodiments, a blowing block 251 and a dust suction block 252 are provided at the bottom of the dust hood. In actual use, the blowing block and the dust suction block of the present application are connected to a unified blowing and suction motor (not shown), and a plurality of blowing nozzles 2511 are arranged at the bottom of the blowing block, and a plurality of dust suction nozzles 2512 are arranged at the bottom of the dust suction block. When the empty tray transfer robot drives the empty tray to pass through the dust hood, the plurality of blowing nozzles will blow up the dust in the empty tray, and then the raised dust will be absorbed by the plurality of dust suction nozzles, so that the empty tray can be cleaned, thereby ensuring the cleanliness of the empty tray, ensuring that the pre-stacked PCP material will not be contaminated by dust, and improving the pre-stacked quality of the PCP material.
[0056] Preferably, both the empty plate lifting assembly and the pallet lifting assembly are scissor fork lifting platforms. When actually selected, the scissor fork lifting platform can be an electric scissor fork lifting platform or a hydraulic scissor fork lifting platform.
[0057] In one specific implementation scheme, the empty tray transferring robot includes two sixth linear drive components 241, and the two sixth linear drive components are respectively arranged on the opposite sides of the two first chassis. The two sixth linear drive components are connected to the first arm 242, and a plurality of first suction cups 243 are arranged at the bottom of the first arm. The empty tray located on the empty tray lifting component will rise under the drive of the empty tray lifting component. At this time, a plurality of first suction cups will adsorb the empty tray. Under the drive of the two sixth linear drive components, the first arm will carry the empty tray adsorbed by the first suction cup to the empty tray temporary storage platform.
[0058] In one specific embodiment, the empty carrier plate suction assembly, the first PP suction assembly, the second PP suction assembly, the core plate carrier plate suction assembly, the core plate suction assembly and the stacked material carrier plate suction assembly have the same structure, and respectively include a translation block 101 and two second arms 102, the two second arms are respectively vertically connected to the translation block, and a plurality of second suction cups 103 are arranged at the bottom of the two second arms.
[0059] It is worth noting that the translation block included in the empty carrier plate suction assembly is connected to the second lifting drive assembly, the translation block included in the first PP suction assembly is connected to the fourth lifting drive assembly, the translation block included in the second PP suction assembly is connected to the fifth lifting drive assembly, the translation block included in the core plate carrier plate suction assembly is connected to the eighth lifting drive assembly, the translation block included in the core plate suction assembly is connected to the ninth lifting drive assembly, and the eleventh lifting drive assembly included in the stacked material carrier plate suction assembly is connected;
[0060] During the specific implementation process, driven by the second linear drive assembly, the second lifting drive assembly will first reach one side of the empty tray temporary placement platform, then the second lifting drive assembly will drive the translation block included in the empty tray suction assembly to descend, and an empty tray will be sucked by all the second suction cups included in the empty tray suction assembly, after which the second lifting drive assembly drives the translation block of the empty tray suction assembly to rise, and driven by the second linear drive assembly, the second lifting drive assembly moves to the corresponding position, and when all the second suction cups stop sucking the grabbed empty tray, the grabbed empty tray will be located on the three stacking support blocks at the initial position;
[0061] Driven by the third linear drive assembly, the fourth lifting drive assembly and the fifth lifting drive assembly are first located on one side of the pallet and the PP alignment platform in sequence, and then the fourth lifting drive assembly and the fifth lifting drive assembly will respectively drive the translation block included in the first PP suction assembly and the translation block included in the second PP suction assembly to descend, at this time, all the second suction cups included in the first PP suction assembly will absorb a PP film on the pallet, and all the second suction cups included in the second PP suction assembly will absorb the PP film on the PP alignment platform, after which the third linear drive assembly drives the fourth lifting drive assembly and the fifth lifting drive assembly to move to the corresponding positions, at this time, the PP film on the pallet will be moved above the PP alignment platform, and the PP film on the PP alignment platform will be moved above the stacking carrier, after the fourth lifting drive assembly and the fifth lifting drive assembly respectively drive the translation blocks connected thereto to descend into place, all the second suction cups included in the first PP suction assembly and the second PP suction assembly will stop adsorbing the corresponding PP film, and a PP film will be re-placed on the PP film positioning platform and the stacking carrier;
[0062] Driven by the fourth linear drive assembly, the eighth lifting drive assembly and the ninth lifting drive assembly are located at the two first mounting brackets and the two second mounting brackets in sequence, and then the ninth lifting drive assembly will drive the translation block included in the core plate suction assembly to descend, at this time, all the second suction cups included in the core plate suction assembly will absorb the core plates in the uppermost core plate carriers of the two second mounting brackets, after which the ninth lifting drive assembly will drive the translation block included in the core plate suction assembly to reset, and then the fourth linear drive assembly drives the eighth lifting drive assembly and the ninth lifting drive assembly to move to the corresponding positions, and after they are in place, the eighth lifting drive assembly drives the translation block included in the core plate carrier suction assembly to descend, and the ninth lifting drive assembly drives the translation block included in the core plate suction assembly to descend, and the core plate carrier suction assembly All the second suction cups included in the assembly will absorb the empty core board carriers on the top layer of the two second mounting brackets, and all the second suction cups included in the core board absorption assembly will stop absorbing the core board. At this time, the core board will be lowered into the stacking carrier. After that, the fourth linear drive assembly drives the eighth lifting drive assembly and the ninth lifting drive assembly to reset. The eighth lifting drive assembly will drive the translation block included in the core board carrier absorption assembly to descend, and the ninth lifting drive assembly will drive the translation block included in the core board absorption assembly to descend. At this time, all the second suction cups included in the core board carrier absorption assembly will stop adsorbing the empty core board carriers, and the empty core board carriers will be placed on the two first mounting brackets, and all the second suction cups included in the core board absorption assembly will absorb the core boards in the top layer of the core board carriers of the two second mounting brackets.
[0063] Driven by the fifth linear drive assembly, the eleventh lifting drive assembly reaches the corresponding position, the eleventh lifting drive assembly drives the telescopic block included in the stacking tray suction assembly to descend, and all the second suction cups included in the stacking tray suction assembly adsorb the stacking tray pre-stacked with PCP materials on the stacking recovery mechanism. After this action is completed, the eleventh lifting drive assembly drives the translation block included in the stacking tray suction assembly to reset, and then the fifth linear drive assembly drives the eleventh lifting drive assembly to the top of the two third stacking brackets. At this time, the eleventh lifting drive assembly drives the translation block included in the stacking tray suction assembly to descend, and finally, all the second suction cups included in the stacking tray suction assembly stop adsorbing the stacking tray pre-stacked with PCP materials, and the stacking tray pre-stacked with PCP materials will be stacked on the two third stacking brackets.
[0064] In one specific implementation scheme, the PP alignment platform includes a seventh linear drive component 362, an eighth linear drive component 363 and a platform body 361. The eighth linear drive component is connected to the seventh linear drive component, and the platform body is connected to the eighth linear drive component. If the PP film is detected to have a position deviation, the seventh linear drive component and the eighth linear drive component will drive the platform body to move horizontally or vertically. As for how to detect the position deviation of the PP film, it will be given in the following implementation scheme.
[0065] In actual use, the first linear drive assembly, the second linear drive assembly, the third linear drive assembly, the fourth linear drive assembly, the fifth linear drive assembly, the sixth linear drive assembly, the seventh linear drive assembly, the eighth linear drive assembly, the second lifting drive assembly, the third lifting drive assembly, the fourth lifting drive assembly, the fifth lifting drive assembly, the sixth lifting drive assembly, the seventh lifting drive assembly, the eighth lifting drive assembly, the ninth lifting drive assembly, the tenth lifting drive assembly and the eleventh lifting drive assembly are all linear screw modules, among which the first linear drive assembly adopts a linear screw module with six sliders, and the third linear drive assembly and the fourth linear drive assembly adopt a linear screw module with two sliders.
[0066] The first conveyor, the second conveyor, the third conveyor and the fourth conveyor are all roller conveyors.
[0067] In this embodiment, in order to prevent at least one first PP suction component or at least one second PP component from sucking more than one PP film from the pallet, a U-shaped groove 3611 is provided on one side of the platform body included in the PP alignment platform in the present application, and a pneumatic slide (not shown) is provided below the platform body relative to the U-shaped groove, and the setting position of the pneumatic slide cannot affect the alignment adjustment of the relevant components of the PP alignment platform. A thickness gauge 314 that can be extended into the U-shaped groove is installed on the slide of the pneumatic slide. When the PP film is placed on the platform body included in the PP alignment platform, the pneumatic slide will drive the thickness gauge to extend into the U-shaped groove, and the thickness gauge must be located above the PP film after reaching the specified position, so as to detect its thickness. If the measured value is greater than the set value, it means that there is more than one layer of PP film on the platform body included in the PP alignment platform, otherwise, it is one layer of PP film.
[0068] In order to realize the position detection of the PP film on the PP alignment platform, the present application also includes an aluminum profile frame 70 mounted outside the stacking material transfer mechanism, the carrier plate supply mechanism, at least one first PP supply mechanism, the core plate supply mechanism, at least one second PP supply mechanism and the stacking material recovery mechanism, and at least one first PP diagonal edge detection component 90 and at least one second PP diagonal edge detection component 90 are arranged below the top of the aluminum profile frame;
[0069] The structures of at least one first PP diagonal edge detection component and at least one second PP diagonal edge detection component are the same, and respectively include a first CCD camera 92 fixed to the aluminum profile frame through a first bracket 91, and a second CCD camera 94 fixed to the aluminum profile frame through a second bracket 93, and the first CCD camera and the second CCD camera are arranged diagonally front to back.
[0070] During the specific detection process, the first CCD camera and the second CCD camera will detect the two diagonally opposite corners of the PP film, so as to determine whether there is a position deviation. As for the use principle of the first CCD camera and the second CCD camera, it is the existing technology and this application will not go into details here.
[0071] In addition, in order to ensure that the pre-stacked PCP material is processed in a dust-free environment, the aluminum profile frame in the present application is also equipped with a transparent dust cover 71 and corresponding dust removal equipment, such as an FFU high-efficiency filtering air supply fan 80.
[0072] In one specific implementation scheme, a single PP separation component includes four telescopic drive cylinders 371 arranged in pairs on opposite sides of two second chassis, a telescopic block 372 is connected to the piston rod of the telescopic drive cylinder, a second lifting drive cylinder 373 is arranged on the telescopic block, a first lifting plate 374 is connected to the piston rod of the second lifting drive cylinder, and a plurality of third suction cups 375 are arranged at the bottom of the first lifting plate. Since the PP films are stacked on a pallet and have adsorption forces on each other, the present application designs a single PP separation component. When separating the top PP film on the pallet, the four telescopic drive cylinders simultaneously drive the telescopic blocks to extend. After they are in place, the four second lifting drives the first lifting plate to descend. After they are descended into place, the four third suction cups will suck the top PP film. When the second lifting drives the first lifting plate to lift and lower back and forth, the top single PP film will be sucked out from the pallet, thereby achieving separation.
[0073] In one specific implementation scheme, the pallet grabbing robot includes a second lifting plate 341 connected to a third lifting drive assembly, and a plurality of fourth suction cups 342 are arranged at the bottom of the second lifting plate. After the PP film on the pallet is used up, the two second conveyors convey the empty pallet to the second lifting plate for descending. Then, the third lifting drive assembly drives the second lifting plate to descend. After it is in place, all the fourth suction cups on the second lifting plate will suck the pallet. When the AGV trolley conveys other pallets stacked with PP film to the two second conveyors, the two second conveyors convey the pallets stacked with PP film to a position convenient for the PP suction assembly to suck. Finally, the third lifting drive assembly drives the second lifting plate to descend, and all the fourth suction cups stop sucking the empty pallet. At this time, the pallet will fall on the AGV trolley and be taken away by the AGV trolley.
[0074] In one of the specific embodiments, the first mounting bracket, the second mounting bracket and the third mounting bracket have the same structure, and respectively include a carrier plate (451, 461, 641) and two L-shaped plates (452, 462, 642) arranged on the carrier plate; it can be understood that the carrier plates included in the first mounting bracket, the second mounting bracket and the third mounting bracket are connected to the sixth lifting drive assembly, the seventh lifting drive assembly and the tenth lifting drive assembly in sequence, and under the drive of the sixth lifting drive assembly, the seventh lifting drive assembly and the tenth lifting drive assembly respectively, the carrier plates and L-shaped plates on the first mounting bracket, the second mounting bracket and the third mounting bracket will be lifted and lowered;
[0075] The two first stacking brackets are used to place empty core plate carriers, and when the sixth lifting drive assembly drives the carrier connected thereto to rise and fall, the stacked empty core plate carriers will also rise and fall accordingly;
[0076] The two second mounting brackets are used to place core plate carriers with core plates, and when the seventh lifting drive assembly drives the carriers connected thereto to rise and fall, the stacked core plate carriers with core plates will also rise and fall accordingly;
[0077] The two third mounting brackets are used to place pre-stacked trays containing PCP materials. When the tenth lifting drive assembly drives the carrier plate connected thereto to rise and fall, the stacked trays containing PCP stacked materials will also rise and fall accordingly.
[0078] In summary, the implementation process of this application is briefly described below based on the PCP structure of PP film-PP film-core board-PP film-PP film:
[0079] The first process: The AGV trolley transports the stacked empty trays to the space between the two first conveyors, and the two first conveyors transport them to the top of the empty tray lifting assembly. The empty tray transfer robot grabs the top empty tray and passes through the dust collection hood for dust removal (after the empty tray transfer robot grabs an empty tray, the empty tray lifting assembly will lift all the stacked empty trays to a certain height). The dust-removed empty tray will be placed on the empty tray temporary platform. Then, the second linear drive assembly drives the second lifting drive assembly to the side of the empty tray temporary platform, and the second lifting drive assembly drives the suction assembly to descend and place the empty tray on the temporary platform. The empty tray is sucked (after sucking the empty tray, the second lifting drive assembly drives the empty tray sucking assembly to reset), when the second linear drive assembly drives the second lifting drive assembly to move backward for a distance, the second lifting drive assembly drives the empty tray sucking assembly to descend, and the empty tray sucking assembly places the empty tray on the initial three stacking tray supporting blocks (after placing the empty tray, the second lifting drive assembly drives the empty tray sucking assembly to reset), and when the empty tray is placed on the initial three stacking tray supporting blocks (after this, the empty tray is called the stacking tray), the stacking transfer mechanism will drive the stacking tray to the next process to wait for the placement of the first PP film.
[0080] The second process: the AGV trolley transports the stacked empty trays to between the two second conveyors included in the first PP supply mechanism, and the two second conveyors transport them to the top of the pallet lifting assembly. The fourth lifting drive assembly and the fifth lifting drive assembly will be located on one side of the pallet and the PP alignment platform (the PP film on the PP alignment platform has been detected by the first PP diagonal edge detection assembly, and the PP alignment platform has adjusted the position of the PP). The first PP suction assembly of the fourth lifting drive assembly descends, and the first PP suction assembly sucks the PP film on the top of the pallet and separates it by the single PP separation assembly (after sucking the PP film on the pallet, the fourth lifting drive assembly drives the first PP suction assembly to reset), the fifth lifting drive assembly drives the second PP suction assembly to descend, and the second PP suction assembly sucks the PP film that has been adjusted on the PP alignment platform (sucking After the PP film on the PP alignment platform is properly positioned, the fifth lifting drive assembly drives the second PP suction assembly to reset), driven by the third linear drive assembly, the fourth lifting drive assembly and the fifth lifting drive assembly move backward for a distance, at this time, the fourth lifting drive assembly will drive the first PP suction assembly to descend, and the first PP suction assembly will place the absorbed PP film on the PP alignment platform (after placing the PP film on the alignment platform, the fourth lifting drive assembly drives the first PP suction assembly to reset), the fifth lifting drive assembly will drive the second PP suction assembly to descend, and the second PP suction assembly will place the absorbed PP film on the stacking carrier on the stacking transfer mechanism (after placing the PP film on the stacking carrier, the fifth lifting drive assembly drives the second PP suction assembly to reset), and the stacking transfer mechanism will drive the stacking carrier to the next process to wait for the placement of the next first PP film.
[0081] The third process: This process repeats the placement of the first PP film. After completion, the stacking material transfer mechanism will drive the stacking material carrier to the next process to wait for the placement of the core board;
[0082] The fourth process: the AGV trolley transports the stacked core plate carrier with core plates to between the two third conveyors and the two third conveyors transport it to the top of the two second mounting brackets. The eighth lifting drive assembly and the ninth lifting drive assembly are located at the two first mounting brackets and the two second mounting brackets respectively. The ninth lifting drive assembly drives the core plate suction assembly to descend, and the core plate suction assembly first sucks the core plate in the uppermost core plate carrier (after the core plate suction assembly sucks the core plate, the ninth lifting drive assembly drives the core plate suction assembly to reset). The fourth linear drive assembly drives the eighth lifting drive assembly and the ninth lifting drive assembly to move a distance. At this time, The core plate carrier tray suction component is located above the second mounting bracket and after the eighth lifting drive component drives the core plate carrier tray suction component to descend, the core plate carrier tray suction component sucks the empty core plate carrier tray (after the core plate carrier tray sucks the empty core plate carrier tray, the eighth lifting drive component drives the core plate carrier tray suction component to reset), after the ninth lifting drive component drives the core plate suction component to descend, the core plate suction component places the sucked core plate into the stacking plate on the stacking transfer mechanism (after the core plate is placed in the stacking plate, the ninth lifting drive component drives the core plate suction component to reset), and the stacking transfer mechanism drives the stacking plate to the next process to wait for the placement of the second PP film;
[0083] After the fourth linear drive assembly drives the eighth lifting drive assembly and the ninth lifting drive assembly to reset, the eighth lifting drive assembly drives the core plate carrier tray suction assembly to descend, and the core plate carrier tray suction assembly places the empty core plate carrier tray on the two first mounting brackets (after the core plate carrier tray suction assembly places the empty core plate carrier tray on the two first mounting brackets, the eighth lifting drive assembly drives the core plate carrier tray suction assembly to reset), and the core plate suction assembly then sucks the core plate in the uppermost core plate carrier tray (after the core plate suction assembly sucks the core plate, the ninth lifting drive assembly drives the core plate suction assembly to reset);
[0084] It should be added here that after the two first stacking brackets receive an empty core board tray, the two sixth lifting drive assemblies will drive the two first stacking brackets to descend a certain height, and after an empty core board tray is taken away from the two second stacking brackets, the two seventh lifting drive assemblies will drive the two second stacking brackets to rise a certain height.
[0085] The fifth process: the AGV trolley transports the stacked empty trays to between the two second conveyors included in the second PP supply mechanism, and the two second conveyors transport them to the top of the pallet lifting assembly. The fourth lifting drive assembly and the fifth lifting drive assembly will be located on one side of the pallet and the PP alignment platform (the PP film on the PP alignment platform has been detected by the first PP diagonal edge detection assembly, and the PP alignment platform has adjusted the position of the PP). The first PP suction assembly of the fourth lifting drive assembly descends, and the first PP suction assembly sucks the PP film on the top layer of the pallet and separates it by the single PP separation assembly (after sucking the PP film on the pallet, the fourth lifting drive assembly drives the first PP suction assembly to reset), the fifth lifting drive assembly drives the second PP suction assembly to descend, and the second PP suction assembly sucks the PP film that has been adjusted on the PP alignment platform (sucking After taking the PP film on the PP alignment platform, the fifth lifting drive assembly drives the second PP suction assembly to reset), driven by the third linear drive assembly, the fourth lifting drive assembly and the fifth lifting drive assembly move backward for a distance, at this time, the fourth lifting drive assembly will drive the first PP suction assembly to descend, and the first PP suction assembly will place the sucked PP film on the PP alignment platform (after placing the PP film on the alignment platform, the fourth lifting drive assembly drives the first PP suction assembly to reset), the fifth lifting drive assembly will drive the second PP suction assembly to descend, and the second PP suction assembly will place the adsorbed PP film on the stacking carrier on the stacking transfer mechanism (after placing the PP film on the stacking carrier, the fifth lifting drive assembly drives the second PP suction assembly to reset), and the stacking transfer mechanism will drive the stacking carrier to the next process to wait for the placement of the next second PP film.
[0086] The sixth step is to repeat the process of placing the second PP film; after completion, the stacking material transfer mechanism will drive the stacking material tray to the next step to wait for the stacking material tray to be recovered.
[0087] The seventh process: After the fifth linear drive assembly drives the eleventh lifting drive assembly to move a certain distance, the eleventh lifting drive assembly drives the stacking tray suction assembly to descend, and the stacking tray suction assembly absorbs the stacking tray pre-stacked with PCP material on the stacking transfer mechanism (after absorbing the stacking tray, the eleventh lifting drive assembly drives the stacking tray suction assembly to reset), and under the drive of the fifth linear drive module, the eleventh lifting drive assembly resets, and the eleventh lifting drive assembly drives the stacking tray to descend, and the stacking tray suction assembly absorbs the stacking tray with PCP material. The material tray is placed on the two third stacking brackets (after the stacked material tray is placed on the two third stacking brackets, the eleventh lifting drive assembly drives the stacked material tray suction assembly to reset). Every time the two stacking brackets receive a stacked material tray, the two tenth lifting drive assemblies will drive the two third stacking brackets to descend a certain height. After a fixed number of stacked material trays are received, the two tenth lifting drive assemblies will drive the two stacking brackets to descend to the lowest position, and then the two fourth conveyors will transport them to the AGV trolley docking position and transport them away by the AGV trolley.
[0088] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0089] The above embodiments are only for illustrating the technical concept and features of the utility model, and their purpose is to enable technicians familiar with the technical field to understand the content of the utility model and implement it accordingly, and they cannot be used to limit the protection scope of the utility model. Any equivalent changes or modifications made according to the spirit of the utility model should be included in the protection scope of the utility model.
Claims
1. PCP automatic pre-stacking line, characterized by: It includes a stacking material transfer mechanism and an empty tray supply mechanism, at least one first PP supply mechanism, a core board supply mechanism, at least one second PP supply mechanism, and a stacking material recovery mechanism, which are arranged from left to right on one side of the stacking material transfer mechanism; The stacking material transfer mechanism comprises a machine platform, three straight grooves are formed on the table top of the machine platform, seven stacking material carrier blocks are respectively disposed on the side walls of the three straight grooves, a first linear drive assembly is disposed at the bottom of the machine platform, six first lifting drive assemblies are respectively connected to the first linear drive assembly, and two stacking material carrier clamping assemblies are respectively connected to the six first lifting drive assemblies passing through the straight grooves on both sides; The empty tray supply mechanism comprises two first chassis which are separated from each other, first conveyors are respectively arranged on opposite sides of the two first chassis, an empty tray lifting assembly is arranged between the two first conveyors, empty tray transfer manipulators are arranged above the first conveyors in the two first chassis, dust collecting covers are arranged above the empty tray lifting assemblies in the two first chassis, and empty tray temporary storage platforms are arranged on the rear sides of the empty tray lifting assemblies in the two first chassis, a second linear drive assembly is arranged inside one of the first chassis, a first avoidance groove is opened on the side opposite to the other first chassis, a second lifting drive assembly is connected to the second linear drive assembly, and an empty tray suction assembly is connected to the second lifting drive assembly to pass through the first avoidance groove; The at least one first PP supply mechanism and the at least one second PP supply mechanism have the same structure, and respectively include two second chassis that are separated from each other, and second conveyors are respectively arranged on opposite sides of the two second chassis, a third lifting drive component is arranged inside one of the second chassis, and a second avoidance groove is opened on the side opposite to the other second chassis, a pallet grabbing manipulator is connected to the third lifting drive component and passes through the second avoidance groove, a pallet lifting component is arranged between the two second conveyors corresponding to the rear side of the pallet grabbing manipulator, a PP alignment platform is arranged between the two second conveyors corresponding to the rear side of the pallet lifting component, and a single PP separation component is arranged on the two second chassis corresponding to the pallet lifting component above the pallet lifting component, a third linear drive component is arranged inside one of the second chassis, and a third avoidance groove is opened on the side opposite to the other second chassis, a fourth lifting drive component and a fifth lifting drive component are connected to the third linear drive component, and the first PP suction component and the second PP suction component are respectively connected to the fourth lifting drive component and the fifth lifting drive component through the third avoidance groove; The core board supply mechanism includes two third chassis that are separated from each other, and third conveyors are respectively arranged on opposite sides of the two third chassis, and a sixth lifting drive assembly and a seventh lifting drive assembly are sequentially arranged inside the two third chassis, and a fourth avoidance groove and a fifth avoidance groove are respectively opened on opposite sides of the two third chassis, and the two sixth lifting drive assemblies are respectively connected to the first mounting bracket passing through the fourth avoidance groove, and the two seventh lifting drive assemblies are respectively connected to the second mounting bracket passing through the fifth avoidance groove; a fourth linear drive assembly is also arranged inside one of the third chassis, and a sixth avoidance groove is opened on the side opposite to the two third chassis, and an eighth lifting drive assembly and a ninth lifting drive assembly are connected to the fourth linear drive assembly, and the eighth lifting drive assembly is connected to a core board carrier tray suction assembly passing through the sixth avoidance groove, and the ninth lifting drive assembly is connected to a core board suction assembly passing through the sixth avoidance groove; The stacking material recovery mechanism includes two fourth chassis that are separated from each other, fourth conveyors are respectively provided on opposite sides of the two fourth chassis, tenth lifting drive components are provided inside the two fourth chassis, seventh avoidance grooves are respectively opened on opposite sides of the two third chassis, and third mounting brackets are respectively connected to the two tenth lifting drive components to pass through the seventh avoidance grooves. A fifth linear drive component is also provided inside one of the fourth chassis, and an eighth avoidance groove is opened on the side opposite to the other fourth chassis. The fifth linear drive component is connected to an eleventh lifting drive component, and the eleventh lifting drive component is connected to a stacking material carrier suction component.
2. The PCP automatic pre-stacking line according to claim 1, characterized in that: The first lifting drive assembly includes a lower plate, an upper plate and four first lifting drive cylinders, the lower plate is connected to the first linear drive assembly, the four first lifting drive cylinders are arranged above the lower plate, and the upper plate is connected to the first lifting drive cylinders on the lower plate.
3. The PCP automatic pre-stacking line according to claim 2, characterized in that: The stacking tray clamping assembly is a pneumatic clamping claw fixed on the upper plate.
4. The PCP automatic pre-stacking line according to claim 1, characterized in that: An air blowing block and a dust suction block are arranged at the bottom of the dust collecting hood, a plurality of air blowing nozzles are arranged at the bottom of the air blowing block, and a plurality of dust suction nozzles are arranged at the bottom of the dust suction block.
5. The PCP automatic pre-stacking line according to claim 1, characterized in that: The empty plate lifting assembly and the pallet lifting assembly are both scissor-fork lifting platforms.
6. The PCP automatic pre-stacking line according to claim 1, characterized in that: The empty tray transfer robot includes two sixth linear drive components, which are respectively arranged on opposite sides of the two first chassis. The two sixth linear drive components are connected to the first arms, and a plurality of first suction cups are arranged at the bottom of the first arms.
7. The PCP automatic pre-stacking line according to claim 1, characterized in that: The empty tray suction assembly, the first PP suction assembly, the second PP suction assembly, the core plate tray suction assembly, the core plate suction assembly and the stacked material tray suction assembly have the same structure, and respectively include a translation block and two second arms, the two second arms are respectively vertically connected to the translation block, and a plurality of second suction cups are arranged at the bottom of the two second arms.
8. The PCP automatic pre-stacking line according to claim 7, characterized in that: The PP alignment platform includes a seventh linear drive component, an eighth linear drive component and a platform body. The eighth linear drive component is connected to the seventh linear drive component, and the platform body is connected to the eighth linear drive component.
9. The PCP automatic pre-stacking line according to claim 8, characterized in that: The first linear drive assembly, the second linear drive assembly, the third linear drive assembly, the fourth linear drive assembly, the fifth linear drive assembly, the sixth linear drive assembly, the seventh linear drive assembly, the eighth linear drive assembly, the second lifting drive assembly, the third lifting drive assembly, the fourth lifting drive assembly, the fifth lifting drive assembly, the sixth lifting drive assembly, the seventh lifting drive assembly, the eighth lifting drive assembly, the ninth lifting drive assembly, the tenth lifting drive assembly and the eleventh lifting drive assembly are all linear screw modules, wherein the first linear drive assembly adopts a linear screw module with six sliders, and the third linear drive assembly and the fourth linear drive assembly adopt a linear screw module with two sliders.
10. The PCP automatic pre-stacking line according to claim 1, characterized in that: The first conveyor, the second conveyor, the third conveyor and the fourth conveyor are all roller conveyors.
11. The PCP automatic pre-stacking line according to claim 1, characterized in that: The PP alignment platform includes a platform body with a U-shaped groove on one side, a pneumatic slide is arranged below the platform body relative to the U-shaped groove, and a thickness gauge that can be extended into the U-shaped groove is installed on the slide of the pneumatic slide.
12. The PCP automatic pre-stacking line according to claim 1, characterized in that: It also includes an aluminum profile frame mounted on the outside of the stacking material transfer mechanism, the tray supply mechanism, at least one first PP supply mechanism, the core board supply mechanism, at least one second PP supply mechanism and the stacking material recovery mechanism, and at least one first PP diagonal edge detection component and at least one second PP diagonal edge detection component are arranged below the top of the aluminum profile frame; The at least one first PP diagonal edge detection component and the at least one second PP diagonal edge detection component have the same structure, and respectively include a first CCD camera fixed to the aluminum profile frame through a first bracket, and a second CCD camera fixed to the aluminum profile frame through a second bracket, and the first CCD camera and the second CCD camera are arranged diagonally front to back.
13. The PCP automatic pre-stacking line according to claim 1, characterized in that: The single PP separation component includes four telescopic drive cylinders arranged in pairs on opposite sides of two second chassis, the piston rods of the telescopic drive cylinders are connected to telescopic blocks, the telescopic blocks are provided with second lifting drive cylinders, the piston rods of the second lifting drive cylinders are connected to the first lifting plate, and a plurality of third suction cups are provided at the bottom of the first lifting plate.
14. The PCP automatic pre-stacking line according to claim 1, characterized in that: The pallet grabbing robot comprises a second lifting plate connected to a third lifting drive assembly, and a plurality of fourth suction cups are arranged at the bottom of the second lifting plate.
15. The PCP automatic pre-stacking line according to claim 1, characterized in that: The first mounting bracket, the second mounting bracket and the third mounting bracket have the same structure, and respectively include a carrier plate and two L-shaped plates arranged on the carrier plate.