Assembly structure for cold-mounted shaft sleeve in deep hole
Through the deep-hole cold-assembled shaft sleeve assembly structure with liquid nitrogen cooling and guide section matching, the problem of shaft sleeve and deep-hole assembly is solved, and the rapid and accurate assembly is achieved. It is suitable for narrow spaces and reduces the risk of accessories scrapping.
Patent Information
- Application Number
- CN202323600116.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-28
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2033-12-28
AI Technical Summary
In the prior art, it is difficult to achieve rapid and accurate assembly of the shaft sleeve and deep mounting hole, and the small operating space leads to a long and inaccurate assembly time, which easily leads to scrapping of accessories.
An assembly structure of a cold-assembled shaft sleeve in deep hole is designed, using the first tool shaft and the second tool shaft to reduce the diameter of the sleeve by cooling with liquid nitrogen, and clamp the shaft sleeve by the coordination of the guide section and the mounting section. It is sent to the long shaft to enhance stability by using arc-shaped protrusions to achieve fast and accurate assembly.
It greatly shortens assembly time and precise positioning, and is suitable for assembly of deep holes and narrow operating spaces, reduces the probability of accessories being scrapped, and significantly improves assembly speed and accuracy.
Smart Images

Figure CN222021037U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of mechanical assembly, and in particular relates to an assembly structure of a shaft sleeve cold-mounted in a deep hole. Background Art
[0002] Among the existing mechanical accessories, there is one type of accessory that consists of a long shaft and a sleeve installed in a mounting hole on the long shaft. The sleeve is required not to fall off from the mounting hole during use, so the sleeve and the mounting hole of the long shaft are designed to be interference fit. Since the long shaft is slender and the mounting hole is deep, the operating installation space is extremely small, and the assembly must be successful in one go, otherwise the accessory will be scrapped. The conventional assembly method of the sleeve and the mounting hole is to align the sleeve with the mounting hole, pad the sleeve with a wooden pad, and then evenly hit the wooden pad with a hammer. The sleeve is forced to slowly enter the mounting hole, which is time-consuming and labor-intensive, and the installation accuracy cannot be guaranteed. It is only applicable to mounting holes with shallow depths. Therefore, it is necessary to design an assembly structure suitable for deep mounting holes and sleeves. Utility Model Content
[0003] In order to solve the above problems in the prior art, the utility model provides an assembly structure for a shaft sleeve in a deep hole, which can quickly and accurately assemble the shaft sleeve into the deeper inner hole.
[0004] The specific technical solution adopted by the utility model is:
[0005] The invention discloses an assembly structure for a cold-mounted sleeve in a deep hole, which is used for assembling the sleeve and a long shaft. A first long hole, a mounting hole and a second long hole are sequentially arranged in the long shaft along its axial direction. The inner diameter of the first long hole is larger than the inner diameter of the second long hole. The key point is that the assembly structure includes a first tooling shaft and a second tooling shaft which are coaxially arranged. The first tooling shaft includes a conveying end and a connecting end which are sequentially arranged along its axial direction. A clamping block is arranged on the connecting end. The second tooling shaft includes a guide section which is sequentially arranged along its axial direction and cooperates with the guide of the second long hole, and a mounting section which cooperates with the sleeve. The mounting section and the connecting end are connected to each other. The sleeve is sleeved on the mounting section. The clamping block cooperates with the guide section to press the sleeve on the mounting section along the axial direction. The guide section and the conveying end are also respectively provided with a disassembly part located outside the long shaft.
[0006] The diameter of the conveying end and the diameter of the pressing block are both smaller than the inner diameter of the first long hole.
[0007] A nylon sleeve is coaxially arranged on the installation section.
[0008] A group of arc-shaped protrusions are arranged on the nylon sleeve.
[0009] The arc-shaped protrusions are arranged in pairs, and the opening directions of the arc-shaped protrusions arranged in pairs are arranged opposite to each other.
[0010] The beneficial effects of the utility model are:
[0011] The utility model adopts the cooperation of the first tooling shaft and the second tooling shaft to clamp the shaft sleeve and send it to the long shaft for assembly. It takes less than 30 seconds from the fixed connection of the first tooling shaft and the second tooling shaft to the assembly of the shaft sleeve into place, which greatly shortens the time required for assembly and achieves accurate assembly position. It solves the technical problem of difficulty in assembling the shaft sleeve into a deeper installation hole in the prior art and is suitable for the assembly of shaft sleeves with a deep installation position and a narrow operating space. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a schematic diagram of the structure of the utility model;
[0013] Figure 2 is a schematic structural diagram of the first tooling axis;
[0014] Figure 3 is a schematic structural diagram of the second tooling shaft;
[0015] Figure 4 It is the left view of the second tooling axis;
[0016] Figure 5 for Figure 4 A magnified schematic diagram of the local A in the middle;
[0017] Figure 6 is a schematic diagram of the structure of the long axis;
[0018] Figure 7 It is a schematic diagram of the structure of the shaft sleeve;
[0019] Figure 8 It is a schematic diagram of the working state of the utility model;
[0020] In the accompanying drawings, 1. bushing, 2. long shaft, 3. first long hole, 4. mounting hole, 5. second long hole, 6. first tooling shaft, 7. second tooling shaft, 8. guide section, 9. mounting section, 10. conveying end, 11. connecting end, 12. clamping block, 13. disassembly part, 14. nylon sleeve, 15. arc-shaped protrusion. DETAILED DESCRIPTION
[0021] The utility model is further described below in conjunction with the accompanying drawings and specific embodiments:
[0022] Specific implementation examples Figure 1-6As shown, the long shaft 2 is provided with a first long hole 3, a mounting hole 4 and a second long hole 5 in sequence along its axial direction, the inner diameter of the first long hole 3 is larger than the inner diameter of the mounting hole 4, and the inner diameter of the mounting hole 4 is larger than the inner diameter of the second long hole 5. The outer diameter of the sleeve 1 is φ42.08mm, the inner diameter of the mounting hole 4 on the long shaft 2 is φ42.02mm, the interference is 0.06mm, and the distance between the mounting hole 4 and the left end face of the long shaft 1 is 300mm. In this embodiment, an iron long shaft 2 and a copper sleeve 1 are selected.
[0023] An assembly structure for cold-fitting a sleeve in a deep hole, comprising a first tooling shaft 6 and a second tooling shaft 7 arranged coaxially, wherein the first tooling shaft 6 comprises a conveying end 10 and a connecting end 11 arranged in sequence along its axial direction, and a clamping block 12 is arranged on the connecting end 11, and the second tooling shaft 7 comprises a guide section 8 arranged in sequence along its axial direction to cooperate with the second long hole 5 and a mounting section 9 to cooperate with the sleeve 1, wherein the mounting section 9 and the connecting end 11 are connected to each other, and the diameters of the clamping block 12 and the guide section 8 are both larger than the inner diameter of the sleeve 1 and smaller than the outer diameter of the sleeve 1. An internal threaded hole is arranged at the end of the mounting section 9, and a screw is arranged at the end of the connecting end 11, and the mounting section 9 and the connecting end 11 are connected and fixed by means of the screw and the internal threaded hole. The clamping block 12 is a gasket.
[0024] When assembling the shaft sleeve 1 and the long shaft 2, first prepare a cooling tank and a stainless steel bucket dedicated to liquid nitrogen. The cooling tank has a capacity of 20L. A round hole is provided at the bottom of the stainless steel bucket so that the liquid nitrogen in the stainless steel bucket can leak out when the stainless steel bucket is lifted from the liquid nitrogen level, making it easy to take the shaft sleeve 1 out of the stainless steel bucket.
[0025] Place the long shaft 2 on the bracket and adjust it to be stable; place the cooling tank filled with liquid nitrogen in a safe area, put the shaft sleeve 1 into a stainless steel bucket, and then put the stainless steel bucket into the cooling tank for cooling. The outer diameter of the shaft sleeve 1 is reduced to 42.01 mm, meeting the assembly conditions;
[0026] The staff wears heat-insulating gloves to avoid liquid nitrogen splashing on their hands and causing frostbite. They slowly lift the stainless steel bucket out of the cooling tank. When the stainless steel bucket is about to leave the liquid nitrogen surface, they slowly lift it out to prevent the liquid nitrogen from leaking from the bottom of the stainless steel bucket and dripping onto the liquid nitrogen surface to cause splashing. Take the sleeve 1 out of the stainless steel bucket and quickly put it on the installation section 9 of the second tooling shaft 7. Put a clamping block 12 on the sleeve 1. Then, by means of the screw on the connecting end 11 and the internal threaded hole on the installation section 9, the first tooling shaft 6 and the second tooling shaft 7 are fixedly connected. The clamping block 12 cooperates with the guide section 8 to axially press the sleeve 1 on the installation section 9. The guide section 8 and the conveying end 10 are also respectively provided with a disassembly portion 13 located outside the long axis 2; in this embodiment, the disassembly portion 13 is a square shaft that cooperates with a wrench.
[0027] Insert the connected first tooling shaft 6 and second tooling shaft 7 along the first long hole 3, and guide the guide section 8 after entering the second long hole 5 to guide the second long hole 5, to ensure that the sleeve 1 is coaxial with the mounting hole 4, and continue to push the first tooling shaft 6 and the second tooling shaft 7 to assemble the sleeve 1 in place; to check whether it is assembled in place, make the distance from the left end of the conveying end 10 on the connected first tooling shaft 6 and the second tooling shaft 7 to the right end of the guide section 8 equal to the length of the long axis 2. When installed in place, the left end of the conveying end 10 is flush with the left end of the long axis 2, and the right end of the guide section 8 is flush with the right end of the long axis 2; the staff can directly use a ruler to check the installation position of the sleeve 1;
[0028] When the sleeve 1 is assembled in place, it absorbs heat with the help of the long shaft 2. Since the thermal conductivity of copper is 5 times that of iron, the sleeve 1 can quickly absorb heat in the long shaft 2 to reach a thermal equilibrium state, so that the mounting hole 4 hugs the outer diameter of the sleeve 1 to meet the technical requirements of interference fit; the inner diameter of the sleeve 1 returns to the cooling size, and a gap is generated between the mounting section 9.
[0029] Finally, the first tooling shaft 6 and the second tooling shaft 7 are separated by clamping the disassembly part 13 with the help of a wrench, and the first tooling shaft 6 and the second tooling shaft 7 are taken out from the long shaft 2 respectively, so as to complete the assembly of the sleeve 1 and the long shaft 2.
[0030] By utilizing the assembly structure of this embodiment, the first tooling shaft 6 and the second tooling shaft 7 are fixedly connected to assemble the sleeve 1 into place, which only takes 20 seconds, greatly shortening the time required for assembly, and the assembly position is accurate, solving the technical problem in the prior art that it is difficult to assemble the sleeve 1 into a deeper mounting hole 4, and is suitable for the assembly of sleeves with deep installation positions and narrow operating spaces.
[0031] The diameter of the conveying end 10 and the diameter of the clamping block 12 are both smaller than the inner diameter of the first long hole 3, which facilitates the first tooling shaft 6 to enter and exit the first long hole 3. The sleeve 1 and the mounting hole 4 can be coaxially arranged only with the help of the guide section 8 and the second long hole 5.
[0032] A nylon sleeve 14 is also coaxially arranged on the mounting section 9. The sleeve 1 is pre-mounted on the nylon sleeve 14 after cooling, which effectively isolates the heat exchange between the sleeve 1 and the mounting section 9 and prevents the sleeve 1 from absorbing too much heat when not assembled in place, causing the outer diameter to increase, thereby affecting the smooth completion of the assembly.
[0033] A group of arc-shaped protrusions 15 are provided on the nylon sleeve 14 . When the shaft sleeve 1 is sleeved on the nylon sleeve 14 , the arc-shaped protrusions 15 are squeezed to enhance the stability of the shaft sleeve 1 on the mounting section 9 .
[0034] The arc-shaped protrusions 15 are arranged in pairs, and the opening directions of the arc-shaped protrusions 15 arranged in pairs are arranged opposite to each other. When the arc-shaped protrusions 15 are squeezed by the sleeve 1, the paired arc-shaped protrusions 15 move closer to each other and resist each other, making the nylon sleeve 14 and the sleeve 1 more stable, effectively preventing the sleeve 1 from moving during assembly; when the sleeve 1 reaches thermal equilibrium, the pressure of the sleeve 1 on the arc-shaped protrusions 15 becomes smaller, and the second tooling shaft 7 with the nylon sleeve 14 can be removed.
[0035] The utility model has the advantages of simple structure, convenient operation and precise assembly, which reduces the probability of scrapping the long shaft and the shaft sleeve and significantly improves the assembly speed.
Claims
1. An assembly structure for a cold-mounted sleeve in a deep hole, used for assembling a sleeve (1) and a long shaft (2), wherein a first long hole (3), a mounting hole (4) and a second long hole (5) are sequentially arranged in the long shaft (2) along its axial direction, and the inner diameter of the first long hole (3) is larger than the inner diameter of the second long hole (5), characterized in that: The assembly structure comprises a first tooling shaft (6) and a second tooling shaft (7) which are coaxially arranged. The first tooling shaft (6) comprises a conveying end (10) and a connecting end (11) which are arranged in sequence along its axial direction. A pressing block (12) is arranged on the connecting end (11). The second tooling shaft (7) comprises a guide section (8) which is arranged in sequence along its axial direction and is matched with the second long hole (5) for guiding, and a mounting section (9) which is matched with the shaft sleeve (1). The mounting section (9) and the connecting end (11) are connected to each other. The shaft sleeve (1) is sleeved on the mounting section (9). The pressing block (12) cooperates with the guide section (8) to press the shaft sleeve (1) onto the mounting section (9) in the axial direction. The guide section (8) and the conveying end (10) are also respectively provided with a disassembly section (13) located outside the long axis (2).
2. The assembly structure of a deep hole cold-mounted sleeve according to claim 1, characterized in that: The diameter of the conveying end (10) and the diameter of the pressing block (12) are both smaller than the inner diameter of the first long hole (3).
3. The assembly structure of a deep hole cold-mounted sleeve according to claim 1, characterized in that: A nylon sleeve (14) is coaxially arranged on the installation section (9).
4. The assembly structure of a deep hole cold-mounted sleeve according to claim 3, characterized in that: A group of arc-shaped protrusions (15) are arranged on the nylon sleeve (14).
5. The assembly structure of a deep hole cold-mounted sleeve according to claim 4, characterized in that: The arc-shaped protrusions (15) are arranged in pairs, and the opening directions of the arc-shaped protrusions (15) arranged in pairs are arranged opposite to each other.