Tool for controlling carrying precision of large-span broadside block of PCTC ship
By designing a new gate-type distance-keeping beam, the half-width accuracy of the PCTC ship's side section is controlled, and the problems of accuracy fluctuations and lifting barriers during the welding process of the side section are solved, the lifting process is optimized, the production efficiency is improved and the production efficiency is reduced. Rework volume.
Patent Information
- Application Number
- CN202420659255.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-01
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2034-04-01
AI Technical Summary
During the installation and welding of PCTC ship's side section, due to the high height of the side section, half-width data fluctuations are easily caused by assembly and alignment adjustment during operation, resulting in the accuracy not meeting the standard requirements, and the installation barrier middle of the distance-keeping beam When the deck is lifted, the side section of the side is easily tilted when it needs to be removed, which affects the accuracy control.
Design a new type of door-type distance-keeping beam including main beam and base. The base is symmetrically fixed to the inner wall of the side. Both ends of the main beam are mounted on the base. The base height is 1 meter and is rigidly fixed, and is used to control the overall section of the side. Half-width accuracy allows moving back and forth during the lifting of the XU total section, avoiding the distance-keeping beam, achieving lifting without removal, and removing the distance-keeping beam after assembly is completed.
The lifting process is optimized to meet the lifting accuracy requirements, improve production efficiency, avoid misalignment and rework caused by accuracy problems, and reduce the workload of operation and board replacement.
Smart Images

Figure CN222022853U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of shipbuilding, and in particular relates to a tooling for precision control of large-span side sections of a PCTC ship. Background Art
[0002] Pure Car Truck Carrier, referred to as PCTC ship, is used to transport cars, vans, trailers loaded with freight containers, trucks and other transportation equipment.
[0003] During the construction of the PCTC car carrier, in order to make full use of the garage space and maximize the loading of cargo vehicles, the garage area adopts a full-span hollow, wall-free design, and two support columns are set horizontally (see Figure 1 and Figure 2 ). At present, the PCTC type ship is divided into sections with S2xx and S3xx sections on both sides and U0xx, U2xx and U3xx sections in the middle. Multiple side S sections will be assembled into XS sections for hoisting, and multiple deck U0xx, U2xx and U3xx sections will be assembled into XU sections.
[0004] At present, the general section of the garage area dock loading and lifting operation process (see Figure 3 ) is: hoist the two ends of the side XS total section ① / ② - before the total section structure is lowered and loosened, weld the positioning weld - use the distance beam tooling ③ to connect and fix the side XS total section ① / ② (see Figure 4 )— Installation and welding of side XS sections ① / ②— Removal of distance beam fixture ③— Installation and patching of deck XU section ④.
[0005] Between deck 5 and deck 9 of the PCTC ship, XS29x+XS39x side sections are set. The main dimensions of this type of side section are 12m*13m*09m. After the positioning of the single-side side section is completed, the inclined steel wire rope is used to restrain and fix it before the crane is released. After the positioning of the double-sided side section is completed, the fixed distance beam tooling is used to restrain and fix the left and right connections.
[0006] At present, during the welding operation of the double-sided side section lower feet and the front and rear hull, due to the high side section and small welding volume of the lower foot structure, the XS section is prone to fluctuations in half-width data due to assembly alignment adjustments during the welding operation. Therefore, a distance-keeping beam tooling is set up to effectively control the precision data.
[0007] This precision control method can control the half-width data to a certain extent, but it has the following defects and problems: the installation position of the distance beam blocks the lifting of the XU section of the middle deck. Before the lifting of the XU section of the deck, the distance beam must be removed. During this process, the XS section on the side is very likely to tilt toward the middle of the ship, making the accuracy unable to meet the standard requirements. Utility Model Content
[0008] In order to solve the technical problems in the prior art, the utility model provides a tooling and method for carrying precision control of a large-span side section of a PCTC ship, comprising a distance-keeping beam, wherein the distance-keeping beam comprises a main beam and a base, wherein the base is two in number and symmetrically fixedly connected to the inner wall of the side of the PCTC ship, and the two ends of the main beam are mounted on the two bases.
[0009] Furthermore, the base is located at the front and rear ports of the side deck.
[0010] Furthermore, the base and the inner wall of the side of the PCTC ship, and the main beam and the base are all rigidly fixed.
[0011] Furthermore, the height of the base is 1 meter.
[0012] Compared with the prior art, the beneficial effects of the utility model are:
[0013] The utility model optimizes the hoisting process, optimizes the hoisting operation process under the premise of meeting the hoisting accuracy requirements, improves production efficiency, and avoids large-scale dislocation and gap after segmented closure due to accuracy problems, resulting in a large number of cuts and plate changes, and increases the workload of rework. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is the schematic diagram of the PCTC boat garage structure I;
[0015] Figure 2 It is the PCTC boat garage structural form diagram II;
[0016] Figure 3 This is a schematic diagram of the PCTC boat garage hoisting process;
[0017] Figure 4 This is a schematic diagram of the use of the XS total section distance beam tooling on the side of the PCTC ship;
[0018] Figure 5 It is a schematic diagram of the process of the utility model;
[0019] Figure 6 This is the structural front view of the utility model distance-keeping beam;
[0020] Figure 7 This is a structural side view of the utility model distance-keeping beam;
[0021] Figure 8 This is the effect diagram of the utility model for hoisting the XU total section. DETAILED DESCRIPTION
[0022] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention is further described below in conjunction with the accompanying drawings and specific implementation methods.
[0023] Reference Figure 6 and Figure 7 This application proposes a tooling for the precision control of the large-span side section of a PCTC ship, including an improved new type of portal distance-keeping beam, which is composed of a main beam and a base, and the base height is 1 meter. After the positioning of the side XS section is completed, the front and rear port positions of the side deck are selected, and the distance-keeping beam is installed to connect and fix rigidly. The use of the distance-keeping beam keeps the half-width precision data of the section under control during the welding operation.
[0024] In the subsequent process of hoisting the XU section, the 1-meter height space of the base in the Z-direction height direction enables the deck XU section to be hoisted into position by first moving forward and backward in the height direction, avoiding the distance beam and then falling, so as to achieve the hoisting state. The entire hoisting of the XU section can be directly in place without removing the distance beam. After the XU section is hoisted, after the assembly operation with the side XS section is started to form a rigid fixation, the distance beam is removed, thereby achieving the effect of half-width precision control.
[0025] Reference Figure 5 The method for using the tooling proposed in this application comprises the following steps:
[0026] Lift the XS section on the side and determine the half-width and horizontal data of the section;
[0027] Hoist the optimized distance-keeping beam 2 meters behind the front end of the main deck;
[0028] The XS section on the side is being welded;
[0029] Lifting deck XU section;
[0030] Remove the spacing beam.
[0031] In the original construction plan, during the welding and assembly process, when the distance-keeping beam was removed to hoist the XU deck section, the side XS section was prone to tipping over, causing fluctuations in the half-width data and making the precision data uncontrollable. The current method uses a new type of portal distance-keeping beam created by the utility model. When the XU section is hoisted, the height space is used to move the section forward and backward. There is no need to remove the distance-keeping beam that controls the side precision data. After the XU deck section and the side XS section are assembled and rigidly fixed, the distance-keeping beam is removed, thereby achieving the effect of half-width precision control.
[0032] In summary, the above are only preferred embodiments of the present utility model, and the protection scope of the present utility model is not limited thereto. All equivalent changes and modifications made according to the patent scope of the present utility model and the contents of the specification are within the scope covered by the patent of the present utility model.
Claims
1. A tool for precision control of the large-span side section of a PCTC ship, characterized by: It comprises a distance-keeping beam, which comprises a main beam and a base. There are two bases, which are symmetrically fixedly connected to the inner wall of the side of the PCTC ship, and the two ends of the main beam are mounted on the two bases.
2. The tooling according to claim 1, characterized in that: The base is located at the front and rear ports of the side deck.
3. The tooling according to claim 1, characterized in that: The base is rigidly fixed to the inner wall of the side of the PCTC ship, and the main beam and the base are rigidly fixed to each other.
4. The tooling according to claim 1, characterized in that: The height of the base is 1 meter.