Frost heaving prevention drainage structure for highway subgrade in cold region

By setting up transverse seepage channels and gravel seepage ditches inside the roadbed of highways in cold regions, combined with drainage pipes and layered filling, the problem of frost heave in highways in cold regions has been solved, achieving rapid drainage and mitigation of frost heave.

CN222024816UActive Publication Date: 2024-11-19陕西华山路桥集团有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420391410.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-29
Publication Date
2024-11-19
Estimated Expiration
2034-02-28

AI Technical Summary

Technical Problem

Existing technologies cannot effectively solve the problem of frost heave caused by the inability of moisture to drain from road surfaces in cold regions. Existing methods, such as laying hydrophobic waterproof and waterproof layers, have limited effectiveness and are costly to grout.

Method used

Transverse seepage channels and gravel seepage ditches are set up inside the roadbed, connected to drainage pipes, and combined with layered filling and horizontal waterproofing layers to form a three-dimensional drainage structure that can quickly drain water from the roadbed.

Benefits of technology

It achieves efficient drainage, reduces water accumulation in the roadbed, alleviates frost heave problems, and extends the service life of highways in cold regions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222024816U_ABST
    Figure CN222024816U_ABST
Patent Text Reader

Abstract

The utility model belongs to the field of highway subgrade structures, and discloses a frost heaving prevention drainage structure for a highway subgrade in a cold region, which comprises a drainage ditch, a horizontal waterproof layer, a drainage pipeline, a transverse water seepage channel and macadam sewers, the macadam sewers are respectively arranged on two sides of the subgrade, and water on two sides of the subgrade is collected into the macadam sewers. A drainage pipeline is arranged at the bottom of the gravel sewerage, and water gathered into the gravel sewerage is rapidly drained; the roadbed adopts layered filling, the horizontal waterproof layer is arranged on the surface of the bottom roadbed and used for blocking upward migration of water vapor in the lower roadbed and reducing the water content above the roadbed, and the transverse water seepage channel is arranged in each layer of roadbed and connected with the macadam sewers, so that water in the roadbed can be collected into the macadam sewers; the highway drainage system has the advantages of being high in drainage efficiency and good in drainage effect, and the frost heaving problem of the highway in the cold region can be effectively relieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of highway roadbed structures, and in particular relates to a cold region highway roadbed anti-freezing and swelling drainage structure. Background Art

[0002] Frost heave is a common roadbed disease in cold regions of my country and one of the main causes of water damage to my country's highway pavement. The main reason for roadbed frost heave is that the roadbed water is affected by low temperatures in winter, and the higher temperature water migrates to the lower temperature soil layer. Under the action of temperature difference, the water quickly gathers and gradually forms an ice layer. After freezing, the soil expands and increases, forming frost heave.

[0003] At present, the existing technology has proposed a structure or method for controlling moisture in cold-region roadbeds, such as: laying a hydrophobic waterproof layer within the foundation soil below the roadbed, or laying a waterproof layer and a drainage layer inside the roadbed, grouting at the bottom of the roadbed, and increasing the roadbed filling height. However, these technologies have some disadvantages, such as: although the path of underground water migration upward is blocked by laying a hydrophobic waterproof layer within the foundation soil below the roadbed, the problem of moisture in the roadbed itself and the infiltration of surface water on the road surface cannot be effectively solved; the traditional roadbed waterproof layer can only play a certain moisture isolation effect and cannot actively discharge the moisture in the roadbed; grouting at the bottom of the roadbed is costly and the construction is complicated.

[0004] In order to effectively solve the frost heave problem and extend the service life of the roadbed, it is key to quickly drain the water from the roadbed and pavement. To this end, a three-dimensional drainage structure is developed to speed up drainage efficiency and improve drainage effects to alleviate the frost heave problem of roads in cold regions. Summary of the invention

[0005] The utility model aims to provide a cold region highway subgrade anti-freezing and drainage structure to solve the problem in the prior art that the water body on the cold region highway pavement cannot be discharged in time, resulting in freezing and swelling of the highway.

[0006] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0007] The utility model provides a cold region highway roadbed anti-freezing and swelling drainage structure, comprising a transverse water seepage channel, the transverse water seepage channel is connected to gravel seepage ditches on both sides of the roadbed, and the gravel seepage ditches are connected to drainage pipes.

[0008] A further improvement of the utility model is that the roadbed is filled in layers, and the transverse water seepage channel is located inside each layer of the filled roadbed.

[0009] A further improvement of the utility model is that the transverse water seepage channel is located in the middle of the gravel seepage grooves on both sides.

[0010] A further improvement of the utility model is that drainage ditches are arranged on both sides of the roadbed.

[0011] A further improvement of the utility model is that a plurality of drainage pipes are fixedly installed at the middle and bottom of the gravel infiltration ditch, and the drainage pipes are arranged outside the gravel infiltration ditch.

[0012] A further improvement of the utility model is that transverse slopes are arranged on both sides of the roadbed, and the slope angle is set to 2°.

[0013] A further improvement of the utility model is that the water outlet of the drainage pipe is higher than the slope surface of the transverse slope of the roadbed.

[0014] A further improvement of the utility model is that a lower soil body is arranged on the bottom layer of the roadbed, and a horizontal waterproof layer is arranged on the surface of the lower soil body.

[0015] A further improvement of the utility model is that the horizontal waterproof layer adopts an impermeable geomembrane, a waterproof geotextile or a waterproof board.

[0016] Compared with the prior art, the utility model has the following beneficial effects:

[0017] The utility model arranges a transverse seepage channel inside the roadbed, and the transverse seepage channel connects the gravel seepage ditches on both sides of the roadbed, so that the water inside the roadbed can be collected into the gravel seepage ditch through the transverse seepage channel, and the gravel seepage ditch is connected to the drainage pipe, so that the water collected into the gravel seepage ditch can be quickly discharged through the drainage pipe. The utility model has the characteristics of high drainage efficiency and good drainage effect, and can effectively alleviate the frost heave problem of highways in cold regions.

[0018] Furthermore, the roadbed is filled in layers, and the transverse seepage channel is located inside each layer of the filled roadbed, so that the water inside the roadbed can be collected on both sides of the roadbed.

[0019] Furthermore, drainage ditches are set on both sides of the roadbed, which can collect water flowing out of the drainage pipes into the drainage ditches, so as to facilitate centralized treatment of water and avoid secondary pollution.

[0020] Furthermore, transverse slopes are set on both sides of the roadbed, and the slope angle is set to 2° to facilitate the water in the middle of the roadbed to gather to both sides.

[0021] Furthermore, the water outlet of the drainage pipe is higher than the slope surface of the roadbed transverse slope, thereby preventing the scouring effect of water from damaging the roadbed slope surface.

[0022] Furthermore, a lower soil body is arranged on the bottom layer of the roadbed, and a horizontal waterproof layer is arranged on the surface of the lower soil body. The horizontal waterproof layer can block the upward migration of water vapor in the lower soil body and reduce the water content above the roadbed. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a schematic diagram of the combined drainage structure inside the roadbed of the utility model.

[0024] Among them, 1. drainage ditch; 2. lower soil; 3. horizontal waterproof layer; 4. drainage pipe; 5. cross slope; 6. horizontal seepage channel; 7. gravel seepage ditch. DETAILED DESCRIPTION

[0025] The present invention is further described below in conjunction with the accompanying drawings and embodiments, but it should not be understood that the above subject matter of the present invention is limited to the following embodiments. Without departing from the above technical ideas of the present invention, various substitutions and changes are made according to common technical knowledge and conventional means in the field, which should all be included in the protection scope of the present invention.

[0026] See also Figure 1 The anti-freezing and heaving drainage structure for cold-region highway roadbed comprises a drainage ditch 1, a lower soil body 2, a horizontal waterproof layer 3, a drainage pipe 4, a transverse slope 5, a transverse seepage channel 6 and a gravel seepage ditch 7;

[0027] Drainage ditches 1 are arranged on both sides of the roadbed, and a horizontal waterproof layer 3 is arranged inside the roadbed. The horizontal waterproof layer 3 can block the upward migration of water vapor in the lower soil 2 and reduce the water content above the roadbed. The horizontal waterproof layer 3 adopts an impermeable geomembrane, a waterproof geotextile or a waterproof board. Gravel infiltration ditches 7 are laid on the left and right sides of the roadbed. The inside of the roadbed is filled in layers, and a transverse seepage channel 6 is arranged inside each layer of the roadbed. The transverse seepage channel 6 connects the gravel infiltration ditches 7 on both sides of the roadbed, so that the water inside the roadbed is collected to the gravel infiltration channel 6. In the stone seepage ditch 7, a plurality of drainage pipes 4 are fixedly installed in the middle and bottom of the gravel seepage ditch 7. The drainage pipes 4 are arranged outside the gravel seepage ditch 7. The drainage pipes 4 are convenient for quickly discharging the water flowing into the gravel seepage ditch 7. The water discharged by the drainage pipes 4 flows into the drainage ditch 1. The roadbed is built in an inclined manner. A transverse slope 5 is arranged on both sides of the roadbed with an inclination angle of 2°, so that the water in the middle of the roadbed can be gathered to both sides. The water outlets of the drainage pipes 4 are all higher than the slope surface of the transverse slope 5 of the roadbed to prevent the scouring effect of water from damaging the slope surface of the roadbed.

[0028] During the roadbed construction, the lower soil 2 is first filled, and then a horizontal waterproof layer 3 is laid on the surface of the lower soil 2. The frost heave problem of the roadbed of cold-region highways is mainly caused by water seepage on the road surface and the upward movement of water vapor under the roadbed. By laying the horizontal waterproof layer 3, the channel for water vapor under the roadbed to seep upward can be isolated. The horizontal waterproof layer 3 adopts an impermeable geomembrane, a waterproof geotextile or a waterproof board; then the roadbed is filled in layers, and a certain angle of cross slope 5 is reserved when each layer is filled. The slope angle is set to 2°, and inside each layer of filled roadbed A layer of transverse seepage channel 6 is set up, and the transverse seepage channel 6 is made of permeable material to facilitate the water inside the roadbed to be collected on both sides of the roadbed. Then, gravel seepage ditches 7 are set on both sides of the roadbed to collect the water on both sides of the roadbed into the gravel seepage ditch 7. In order to speed up the drainage efficiency and improve the drainage effect, drainage pipes 4 are set in the middle and bottom of the gravel seepage ditch 7 to quickly drain the water in the roadbed. At the same time, drainage ditches 1 are excavated on both sides of the roadbed, and the water flowing out of the drainage pipes 4 is collected in the drainage ditch 1, which can effectively alleviate the frost heave problem of cold-region roads.

[0029] The above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field can still modify or replace the specific implementation methods of the present invention. Any modifications or equivalent replacements that do not depart from the spirit and scope of the present invention are within the scope of protection of the claims of the present invention to be approved.

Claims

1. A cold region highway subgrade anti-freezing and drainage structure, characterized in that: It comprises a transverse water seepage channel (6), the transverse water seepage channel (6) is connected to the gravel seepage ditch (7) on both sides of the roadbed, and the gravel seepage ditch (7) is connected to the drainage pipe (4).

2. The cold region highway subgrade anti-freezing and drainage structure according to claim 1, characterized in that: The roadbed is filled in layers, and the transverse seepage channel (6) is located inside each layer of the filled roadbed.

3. The cold region highway subgrade anti-freezing and drainage structure according to claim 1, characterized in that: The transverse water seepage channel (6) is located between the gravel seepage ditches (7) on both sides.

4. The cold region highway subgrade anti-freezing and drainage structure according to claim 1, characterized in that: Drainage ditches (1) are arranged on both sides of the roadbed.

5. The cold region highway subgrade anti-freezing and drainage structure according to claim 1, characterized in that: A plurality of drainage pipes (4) are fixedly installed in the middle and bottom of the gravel infiltration ditch (7), and the drainage pipes (4) are arranged outside the gravel infiltration ditch (7).

6. The cold region highway subgrade anti-freezing and drainage structure according to claim 1, characterized in that: A transverse slope (5) is set on both sides of the roadbed, and the slope angle is set to 2°.

7. A cold region highway subgrade anti-freezing and drainage structure according to claim 6, characterized in that: The water outlet of the drainage pipe (4) is higher than the slope surface of the roadbed transverse slope (5).

8. The cold region highway subgrade anti-freezing and drainage structure according to claim 1, characterized in that: A lower soil body (2) is arranged on the bottom layer of the roadbed, and a horizontal waterproof layer (3) is arranged on the surface of the lower soil body (2).

9. A cold region highway subgrade anti-freezing and drainage structure according to claim 8, characterized in that: The horizontal waterproof layer (3) adopts an impermeable geomembrane, a waterproof geotextile or a waterproof board.