Pile foundation construction hole cleaning device
By using cone nets and ring nets in pile foundation hole cleaning device to block unsealed drilling slag, combined with the side port reflow design, the problem of low hole cleaning efficiency caused by incomplete precipitation of mud and drilling slag is solved, and more efficient cleaning is achieved Operate the hole and ensure the stability of the device through counterweight and rubber ring.
Patent Information
- Application Number
- CN202420175137.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-24
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2034-01-24
AI Technical Summary
In the existing pile foundation hole cleaning technology, the incomplete precipitation of mud and drilling slag leads to a reduction in hole cleaning efficiency. The unprecipitated drilling slag enters the pile hole again with the mud, affecting the hole cleaning effect.
Design a pile foundation construction hole cleaning device, including a casing, a cone mesh and a sleeve, the cone mesh is fixed around the casing, the ring mesh is connected to the outer ring of the casing, multiple connecting rods are fixed, and the cone mesh and the ring mesh are blocked For unprecipitated drilling slag, the mud enters the cartridge through the side opening and then flows back to the pile hole to improve the hole cleaning efficiency.
Through the blocking effect of the cone and ring network, unsalted drilling slag is prevented from entering the pile hole again, improving the hole cleaning efficiency, and ensuring the stability of the device through the counterweight ring and rubber ring.
Smart Images

Figure CN222025754U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pile foundation hole cleaning, in particular to a pile foundation construction hole cleaning device. Background Art
[0002] The foundation pile hole is a hole for pouring concrete piles to reinforce the underground foundation and improve the bearing capacity and earthquake resistance of the building foundation. After the foundation pile hole is drilled, a steel cage is put into the hole and then concrete is poured. After the concrete solidifies, it becomes a foundation pile in close contact with the surrounding soil layer. In order to make the foundation pile able to withstand tension, the pile hole is drilled to the bottom and then the bottom is expanded to pour into the foundation pile. Therefore, after the pile foundation hole is formed, the impurities at the bottom of the pile foundation hole must be cleaned by a hole cleaning device before pouring.
[0003] The reverse circulation hole cleaning method has lower cost. When cleaning the hole, the mud and drilling cuttings in the pile hole are pumped out by a mud pump in cooperation with a drill rod and discharged into a mud pool. After sedimentation, the mud is allowed to flow back into the pile hole through the opening on the surface of the fixed steel casing above the pile hole. During operation, it is easy for the drilling cuttings to not be completely settled and enter the pile hole again with the mud, resulting in reduced hole cleaning efficiency. Therefore, we propose a hole cleaning device for pile foundation construction. Utility Model Content
[0004] The utility model aims to provide a pile foundation construction hole cleaning device, which connects the casing to the steel casing above the pile hole by means of a sleeve, and allows the mud entering the sedimentation tank to settle and remove the drill cuttings, and then flows back into the pile hole through the side port again, while the drill cuttings that have not been completely settled will be blocked by the cone net and the ring net and cannot enter the inner side of the casing from the side port, and will not enter the interior of the pile hole again with the mud, thereby improving the hole cleaning efficiency and solving the problems raised in the background technology.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a pile foundation construction hole cleaning device, comprising a casing and a cone net, the cone net is fixed around the lower outer ring of the casing, the upper outer ring of the cone net is integrally connected and fixed with a ring net, and a plurality of connecting rods are evenly connected and fixed between the inner ring of the ring net and the outer ring of the casing; the lower part of the casing is integrally connected with a sleeve connected with the interior thereof, the sleeve is located below the cone net, and a plurality of side openings connected with the interior thereof are evenly opened on the outer ring surface of the casing, and the height of the side openings is less than the height above the ring net and greater than the height of the bottom of the cone net.
[0006] By adopting the above technical solution, the casing is placed above the steel sleeve of the pile hole, and then connected to the steel sleeve of the pile hole through the sleeve. The mud pumped by the mud pump is sent to the sedimentation tank arranged in the outer circle of the pile hole, and then after sedimentation, it passes through the cone net and the ring net to block the unsettled drilling cuttings, so that the mud enters the casing through the side port again and enters the inside of the pile hole.
[0007] Optionally, a counterweight ring is fixed around the outer ring of the sleeve, and the counterweight ring is located below the outer ring of the sleeve.
[0008] By adopting the above technical solution, the counterweight ring plays a counterweight role on the casing and the sleeve, so that the overall center of gravity of the device is biased downward to ensure its stability.
[0009] Optionally, an inner rubber ring is fixed around the inner ring of the sleeve below the counterweight ring, and the inner rubber ring is fixed to the inner surface of the sleeve by fitting.
[0010] By adopting the above technical solution, when the sleeve is connected to the pile hole by being placed on the outer ring of the steel sleeve, the inner rubber ring of the inner ring thereof abuts against the outer surface of the steel sleeve to ensure a stable connection.
[0011] Optionally, an outer rubber ring is fixed around the outer ring of the sleeve below the counterweight ring, and the inner ring of the outer rubber ring is tightly attached to the outer surface of the sleeve.
[0012] By adopting the above technical solution, when the sleeve is connected to the pile hole by being inserted into the inner ring of the steel sleeve, the outer rubber ring of the outer ring thereof abuts against the inner surface of the steel sleeve to ensure a stable connection.
[0013] Optionally, lifting rings are fixed to upper surfaces on both sides of the casing, and the lifting rings are fixed to the outer surface of the casing by welding.
[0014] By adopting the above technical solution, the sheath and the sleeve can be conveniently lifted and moved to another position by means of the lifting ring.
[0015] Compared with the prior art, the technical solution of this application has the following beneficial effects:
[0016] 1. The technical solution of the present application connects the casing to the steel casing above the pile hole by means of a sleeve. After the mud enters the sedimentation tank and settles the drill cuttings, it flows back into the pile hole through the side port again. The drill cuttings that have not been completely settled will be blocked by the cone net and the ring net and cannot enter the inner side of the casing from the side port, and will not enter the interior of the pile hole again with the mud, thereby improving the hole cleaning efficiency.
[0017] 2. The technical solution of the present application is to fix a counterweight ring around the lower outer ring of the sleeve. The counterweight ring acts as a counterweight so that the overall center of gravity of the casing and sleeve is located at the bottom to ensure stability, and the counterweight ring can be used to support the casing and sleeve. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Other features, objects and advantages of the present invention will become more apparent by reading the detailed description of non-limiting embodiments with reference to the following drawings:
[0019] Figure 1 This is a schematic diagram of the overall structure of the pile foundation construction hole cleaning device of the utility model;
[0020] Figure 2 It is a schematic diagram of the cross-sectional structure of the sleeve of the pile foundation construction hole cleaning device of the utility model.
[0021] In the figure: 1, casing; 11, side opening; 12, lifting ring; 2, cone net; 21, ring net; 211, connecting rod; 3, sleeve; 31, counterweight ring; 32, inner rubber ring; 33, outer rubber ring. DETAILED DESCRIPTION
[0022] See also Figure 1-2 The utility model provides a technical solution: a pile foundation construction hole cleaning device, including a casing 1 and a cone net 2. A sleeve 3 connected to the inside of the casing 1 is connected below the casing 1. The sleeve 3 is connected to the casing 1 as a whole. An inner rubber ring 32 is fixed around and around below the inner ring of the sleeve 3. The inner rubber ring 32 is fixed to the inner surface of the sleeve 3 by fitting, so that the sleeve 3 can be sleeved on the outer ring of the steel sleeve above the pile hole, and the inner rubber ring 32 can be in contact with the outer surface of the steel sleeve, so that the sleeve 3 can be stably sleeved on the outer ring of the steel sleeve. An outer rubber ring 33 is fixed around and around below the outer ring of the sleeve 3, and the inner ring of the outer rubber ring 33 is tightly in contact with the outer surface of the sleeve 3. The sleeve 3 can be inserted into the inner ring of the steel sleeve above the pile hole, and the outer rubber ring 33 can be in contact with the inner surface of the steel sleeve, so that the sleeve 3 can be stably sleeved on the inner ring of the steel sleeve.
[0023] A counterweight ring 31 is fixed around the outer ring of the sleeve 3, and the counterweight ring 31 is located on the outer ring of the sleeve 3 above the inner rubber ring 32 and the outer rubber ring 33. After the sleeve 3 is connected to the steel sleeve of the pile hole, the counterweight ring 31 is supported on the soil surface to limit the height of the sleeve 3 and the casing 1, and the center of gravity is biased downward to ensure its stability. Lifting rings 12 are fixed to the upper surfaces of both sides of the casing 1. The lifting rings 12 are fixed to the outer surface of the casing 1 by welding, and the casing 1 and the sleeve 3 can be conveniently lifted and transferred through the lifting rings 12.
[0024] The cone net 2 is fixed around the lower outer ring of the casing 1, and the upper inner diameter of the cone net 2 is larger than the lower inner diameter thereof. A ring net 21 is connected and fixed to the upper outer ring of the cone net 2 as a whole. In order to achieve a firm fixation of the ring net 21, a plurality of connecting rods 211 are evenly connected and fixed between the inner ring of the ring net 21 and the outer ring of the casing 1. The mud pumped into the sedimentation tank of the outer ring of the pile hole by the mud pump will cause the drilling cuttings to settle in the sedimentation tank, and then the mud passes through the cone net 2 and the ring net 21 into the inner ring, and the slag is blocked by the cone net 2 and the ring net 21 and cannot pass through.
[0025] The outer surface of the casing 1 is evenly provided with a plurality of side openings 11 connected to the interior thereof. The height of the side openings 11 is less than the height above the ring net 21 and greater than the height at the bottom of the cone net 2, so that the mud can flow back to the interior of the casing 1 through the side openings 11 and finally enter the pile hole.
[0026] When in use, the casing 1 and the sleeve 3 can be lifted and transferred by the lifting ring 12, and the casing 1 is placed above the pile hole, so that the sleeve 3 below it is sleeved on the outer ring of the steel sleeve arranged above the pile hole, or inserted into the inner ring of the steel sleeve, and the counterweight ring 31 is supported on the surface of the soil to support the casing 1 and connect it to the pile hole. The sedimentation tank is arranged on the outer ring of the casing 1. When the hole is cleaned, the mud pump will introduce the mud and drilling slag mixture drawn from the pile hole into the sedimentation tank which is less than the height of the cone net 2. After the mud containing drilling slag is precipitated in the sedimentation tank, the mud is allowed to pass through the cone net 2 or the ring net 21 and then enter the casing 1 from the side port 11, and then flow back to the pile hole. In this process, the cone net 2 and the ring net 21 have a blocking effect on the slag that has not been completely precipitated in the mud, so as to prevent the unprecipitated slag from entering the casing 1 through the side port 11 again and entering the pile hole.
Claims
1. A pile foundation construction hole cleaning device, comprising a casing (1) and a cone net (2), characterized in that: The cone net (2) is fixed around the lower outer ring of the casing (1), the upper outer ring of the cone net (2) is integrally connected and fixed with a ring net (21), and a plurality of connecting rods (211) are evenly connected and fixed between the inner ring of the ring net (21) and the outer ring of the casing (1); The casing (1) is integrally connected below with a sleeve (3) in communication with the interior thereof. The sleeve (3) is located below the cone net (2). The outer ring surface of the casing (1) is evenly provided with a plurality of side openings (11) in communication with the interior thereof. The height of the side openings (11) is less than the height above the ring net (21) and greater than the height at the bottom of the cone net (2).
2. A pile foundation construction hole cleaning device according to claim 1, characterized in that: A counterweight ring (31) is fixedly disposed around the outer ring of the sleeve (3), and the counterweight ring (31) is located slightly below the outer ring of the sleeve (3).
3. A pile foundation construction hole cleaning device according to claim 2, characterized in that: An inner rubber ring (32) is fixed around the inner ring of the sleeve (3) below the counterweight ring (31), and the inner rubber ring (32) is fixed to the inner surface of the sleeve (3) by fitting.
4. A pile foundation construction hole cleaning device according to claim 2, characterized in that: An outer rubber ring (33) is fixedly mounted around the outer ring of the sleeve (3) below the counterweight ring (31), and the inner ring of the outer rubber ring (33) is tightly attached to the outer surface of the sleeve (3).
5. A pile foundation construction hole cleaning device according to claim 1, characterized in that: Lifting rings (12) are fixed to upper surfaces on both sides of the casing (1), and the lifting rings (12) are fixed to the outer surface of the casing (1) by welding.