Steel spring damping ballast bed section steel ring reinforcing structure

By matching and anchoring the steel ring with the lining ring, combining the cow leg and steel strip to form the overall structure, the problems of long construction time and low efficiency of existing shield tunnel reinforcement are solved, and efficient reinforcement of the shield tunnel lining ring is achieved. and stability improvement.

CN222025794UActive Publication Date: 2024-11-19CHINA RAILWAY SHANGHAI DESIGN INST GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420168574.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-24
Publication Date
2024-11-19
Estimated Expiration
2034-01-24

AI Technical Summary

Technical Problem

The existing shield tunnel reinforcement methods have problems such as long construction time, low efficiency and inability to effectively ensure the reinforcement effect, especially in the presence of existing lines.

Method used

Reinforced by steel ring structure, matched and anchored by steel ring blocks, and formed an overall structure with cow legs and steel pull strips to form a whole ring reinforcement to ensure the stability of the lining ring, and improve the support effect through epoxy resin filling .

Benefits of technology

It improves the reinforcement effect of the shield tunnel lining ring, ensures the stability of the tunnel section, is simple and efficient in construction, and is suitable for promotion and application.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222025794U_ABST
    Figure CN222025794U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of rail transit shield tunnels, in particular to a steel spring vibration reduction ballast bed section steel ring reinforcing structure which comprises a steel ring matched with a lining ring, the steel ring is composed of a plurality of steel ring blocks, the plurality of steel ring blocks are matched with the deformation condition of the lining ring at the corresponding positions respectively, and the steel spring vibration reduction ballast bed section steel ring reinforcing structure is arranged on the lining ring. The steel ring blocks are anchored on the lining ring, brackets are arranged at the bottoms of the two steel ring blocks adjacent to the two sides of the floating slab track bed respectively, the brackets are anchored on the lining ring, and the brackets located on the two sides of the floating slab track bed are connected and fixed into a whole through steel braces in an opposite-pulling mode. The steel brace penetrates through the position of the floating slab track bed. The shield tunnel lining ring reinforcing device has the advantages that the reinforcing effect on the shield tunnel lining ring is improved, and then the stability of a ballast bed section is guaranteed; the structure is simple and reasonable, construction is convenient, and efficiency is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of rail transit shield tunnels, in particular to a steel spring vibration-damping roadbed section steel ring reinforcement structure. Background Art

[0002] With the vigorous development of urban rail transit projects, more and more types of roadbeds are used in shield tunnels for rail transit lines. However, as the shield tunnel ages, its structure will inevitably shift. For example, due to the influence of settlement, the segment rings of the shield tunnel may be misaligned or misaligned, or the structural strength of the shield tunnel itself may be deformed due to the existence of upper loads.

[0003] Based on this, it is a technical problem that needs to be faced to reinforce the existing shield tunnels. In response to the above problems, the main common reinforcement methods currently include:

[0004] 1) Shotcrete reinforcement: by adding a steel mesh to the inner side of the existing shield tunnel segment structure, the steel mesh is connected to the existing segment structure to form an integral structure, and then a reinforcement layer is formed on the inner side of the existing segment structure by spraying concrete. By implementing the reinforcement layer, the structural strength of the existing segment is improved. In some cases, it is also possible to directly reinforce by spraying concrete. This method has a better reinforcement effect, but because it is necessary to wait for the concrete to solidify, the overall construction time is longer and the construction is more troublesome. In addition, when there is already a line in the shield tunnel, it is also necessary to prevent the concrete from falling and solidifying on the existing line, especially on the rails.

[0005] 2) "Patch-type" reinforcement: A reinforcement structure, such as a steel ring, is attached to the inner side of the existing shield tunnel segment structure through adhesive materials. The steel ring is fixed to the inner side of the segment structure to achieve reinforcement. This method has higher construction efficiency than shotcrete. However, similar to the shotcrete reinforcement method, the common steel ring reinforcement structure is mainly arranged in the local position of the shield segment and is restricted by the location of the existing line, so the reinforcement effect cannot be effectively guaranteed. Summary of the invention

[0006] The purpose of the utility model is to provide a steel ring reinforcement structure for a steel spring vibration-damping ballast section based on the above-mentioned deficiencies in the prior art, and to reinforce the lining ring of an existing shield tunnel through the steel ring structure. The steel ring structure is composed of a whole ring reinforcement structure matching the lining ring through corbels and steel tie rods, thereby improving the reinforcement effect of the lining ring without affecting the existing steel spring floating plate ballast section structure.

[0007] The purpose of this utility model is achieved by the following technical solutions:

[0008] A steel ring reinforcement structure for a steel spring vibration-damping ballast section is used for reinforcing the lining ring of an existing shield tunnel, wherein a floating plate ballast is arranged at the bottom of the lining ring, and is characterized in that: the reinforcement structure comprises a steel ring matching the lining ring, wherein the steel ring is composed of a plurality of steel ring blocks, and the plurality of steel ring blocks respectively match the deformation conditions of the lining ring at their corresponding positions, and the steel ring blocks are anchored on the lining ring, and the bottoms of the two steel ring blocks adjacent to both sides of the floating plate ballast are respectively provided with corbels, and the corbels are anchored on the lining ring, and the corbels located on both sides of the floating plate ballast are connected and fixed to form a whole by steel tie rods, and the steel tie rods pass through the floating plate ballast.

[0009] Along the longitudinal direction of the shield tunnel, the reinforcement includes a plurality of the steel rings, and the same-side corbels on adjacent steel rings are fixedly connected by longitudinal connecting plates to form an integral structure.

[0010] Between the tensioned corbels, a plurality of the steel tie bars are arranged at intervals along the longitudinal direction of the shield tunnel.

[0011] The steel tie rod comprises two steel tie rod segments, the outer sides of the two steel tie rod segments are respectively anchored to the steel boxes of the corresponding outer sides of the corbels, and the inner sides of the two steel tie rod segments are connected via a connector.

[0012] The steel rod segment is a prestressed threaded steel bar, and the connector is a prestressed threaded steel bar connector.

[0013] The middle part of the floating slab track bed is provided with a concrete boss, and the steel tie rod passes through the concrete boss at the position without a vibration isolator between adjacent fasteners.

[0014] A protective sleeve is arranged between the steel tie rod and the concrete boss.

[0015] The utility model has the advantages of improving the reinforcement effect of the lining ring of the shield tunnel, thereby ensuring the stability of the roadbed section; having a simple and reasonable structure, convenient construction, high efficiency, and being suitable for promotion. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the structure of the utility model;

[0017] Figure 2 for Figure 1 Middle AA section view;

[0018] Figure 3 for Figure 1 Middle BB section view;

[0019] Figure 4 It is a schematic diagram of the arrangement structure of the steel tie rods in the utility model;

[0020] Figure 5 It is a schematic diagram of the connection structure between the steel ring and the lining ring in the utility model;

[0021] Figure 6 This is a detailed diagram of the connection between the steel tie rod and the corbel in the utility model. DETAILED DESCRIPTION

[0022] The following is a further detailed description of the features of the present invention and other related features through embodiments in conjunction with the accompanying drawings to facilitate understanding by technicians in the same industry:

[0023] like Figure 1-6 As shown, the marks 1-13 in the figure respectively represent: lining ring 1, steel ring 2, chemical anchor 3, steel corbel 4, floating slab ballast 5, steel tie rod 6, concrete boss 7, prestressed threaded steel bar 8, connector 9, longitudinal connecting plate 10, vibration isolator 11, inspection port 12, threaded steel anchor 13.

[0024] Example: Figures 1 to 6 As shown, the steel ring reinforcement structure of the steel spring vibration-damping ballast section in this embodiment is used to reinforce the lining ring 1 of the existing shield tunnel. A floating plate ballast 5 with a vibration-damping effect is arranged at the bottom of the lining ring. The rails of the rail transit line are erected on the floating plate ballast 5 through a fastener system. The vibration isolator 11 located in the floating plate ballast 5 plays a vibration-damping role, that is, to prevent the vibration generated by the rails during operation from being further transmitted.

[0025] Specifically, the reinforcement structure in this embodiment includes a steel ring 2, which is a steel ring-shaped reinforcement structure that matches the inner contour shape and size of the lining ring 1. In order to ensure the pertinence and effectiveness of the reinforcement, the steel ring 2 adopts a block structure, that is, it is composed of a number of steel ring blocks. Since the lining ring 1 is also composed of a number of lining ring blocks, the design of each steel ring block is consistent with the deformation of the local lining ring block of the lining ring 1 it is targeting, so as to ensure that the steel ring block fits the inner wall of the lining ring block, and then the entire steel ring 2 fits the inner wall of the lining ring 1, thereby ensuring the reinforcement effect. When in use, the gap between the steel ring 2 and the lining ring 1 is filled densely with epoxy resin to ensure that the additional support and reinforcement provided by the steel ring 2 can be effectively transmitted to the entire lining ring 1, avoiding unevenness between the two due to the gap.

[0026] In this embodiment, the injection of epoxy resin is achieved by opening grouting holes on the steel ring 2 , and the positions of the grouting holes may preferably correspond to the positions of the grouting holes on the lining ring 1 .

[0027] like Figure 1 or Figure 5As shown, each steel ring block of the steel ring 2 is anchored on the inner wall of the lining ring 1 by a plurality of chemical anchor bolts 3. Figure 2 As shown, the chemical anchor bolts 3 are arranged in a uniform array along the longitudinal direction and the circumferential direction of the steel ring 2 to ensure the connection performance between the steel ring 2 and the lining ring 1. When in use, the chemical anchor bolts 3 are appropriately adjusted when encountering the hand holes, segment bolts and other positions on the lining ring 1.

[0028] like Figure 2 As shown, a plurality of steel rings 2 are arranged along the longitudinal direction of the lining ring 1 within its reinforcement range, and each steel ring segment of each steel ring 2 is anchored to the inner wall of the lining ring 1 by chemical anchor bolts 3 .

[0029] Combination Figure 1 and Figure 3 As shown, steel corbels 4 are respectively arranged at the bottom of the two steel ring blocks corresponding to the two sides of the floating plate ballast 5, and the steel corbels 4 are connected and fixed with the steel ring blocks to form an integral structure. The steel corbels 4 adopt a steel box structure, and each box chamber bottom plate formed is also anchored on the inner wall of the lining ring 1 by chemical anchor bolts. A horizontal steel box is arranged at the end of the steel corbels 4 adjacent to the floating plate ballast 5. A steel tie rod 6 is arranged between the steel corbels 4 on both sides, and the steel tie rod 6 can connect and fix the steel corbels 4 on both sides to form an integral structure when passing through the floating plate ballast 5, so that the steel ring 1 can form a closed "whole ring" in the cross section of the lining ring 1, thereby improving the reinforcement effect of the lining ring 1, especially the stress between the steel ring blocks can be coordinated with each other to resist further deformation of the lining ring 1.

[0030] Combination Figure 3 and Figure 6 As shown, in this embodiment, the steel tie rod 6 is composed of two sections of prestressed threaded steel bars 8, the outer ends of the two sections of prestressed threaded steel bars 8 are anchored on the horizontal steel box of the steel corbel 4 through threaded steel anchors 13, and the inner ends of the two sections of prestressed threaded steel bars 8 are connected and fixed through connectors 9, thereby forming an integral steel tie rod 6. At this time, the steel ring blocks located on both sides of the floating slab ballast 5 can transmit force through the steel tie rod 6.

[0031] In this embodiment, if Figure 3 As shown, two steel tie bars 6 are arranged between a group of corresponding steel corbels 4, and the two steel tie bars 6 are evenly spaced along the longitudinal direction of the lining ring 1; if there is a need to strengthen the connection, further steel tie bars 6 can be provided. At the same time, the steel corbels 4 of adjacent steel rings 2 are connected and fixed by longitudinal connecting plates 10 to form an integral structure, so that the adjacent steel rings 2 are also connected to form an integral structure, achieving the purpose of overall reinforcement of the lining ring 1.

[0032] Combination Figure 1 and Figure 4As shown, the steel tie rod 6 passes through the floating slab ballast 5 and under the rail, specifically, it passes through the concrete boss 7 of the floating slab ballast 5. Specifically, by adopting a cutting scheme at the concrete boss 7 where there is no isolator position between adjacent fastener systems, a groove with a certain width in the longitudinal direction and passing through the boss in the transverse direction is formed for the steel tie rod 6 to pass through; herein, the longitudinal width is the installation space reserved for the connector 9, and the transverse penetration is the passing space for the steel tie rod 6 to pass through the steel corbels 4 on both sides. After the installation of the steel tie rod 6 is completed, the concrete boss 7 is re-poured for restoration. When designing the steel tie rod 6, its position should also avoid the inspection port 12 of the isolator 11.

[0033] In this embodiment, in order to ensure the use effect of the steel tie rod 6 during the later operation period, a protective sleeve can be further provided at its penetration position, that is, a protective sleeve is provided on the part of the steel tie rod 6 on the concrete boss 7, and the protective sleeve plays a protective role, such as vibration isolation.

[0034] In the specific implementation of this embodiment: the floating plate ballast bed 5 adopts a pillowless structure, and the clearance between the rail and the ballast bed is small. In order to meet the crossing needs of the steel tie rod 6, a fastener-thickened iron pad solution is adopted to lift it, and a transition from the middle to the two ends is adopted to achieve the rail surface transition.

[0035] In the steel ring 2 with a block structure, the length of the steel ring block located at the capping block should ensure that there are at least two rows of chemical anchor bolts anchored at the positions overlapping its two adjacent blocks to ensure the integrity of the steel ring 2.

[0036] In addition to being able to significantly reinforce the lining ring 1, this embodiment also has the following implementation effects: 1) After reinforcement, the normal operation of the floating slab track bed system is not affected, and sufficient space can be reserved above and below the steel tie rod 6 to ensure that the compression and recovery of the vibration isolator 11 of the floating slab track bed 5 are not affected; 2) The existing floating slab track bed 5 cannot be installed with a gauge rod due to the presence of the concrete boss 7. After the steel tie rod 6 is installed, it can be used as a gauge rod to enhance the stability of the track.

[0037] Although the above embodiments have described the concepts and embodiments of the purpose of the utility model in detail with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and modifications can still be made to the utility model without departing from the scope of the claims, so they are not described one by one here.

Claims

1. A steel spring vibration damping ballast section steel ring reinforcement structure, used for reinforcing the lining ring of an existing shield tunnel, wherein a floating plate ballast is arranged at the bottom of the lining ring, and characterized in that: The reinforcement structure comprises a steel ring matching the lining ring, the steel ring is composed of a plurality of steel ring blocks, the plurality of steel ring blocks respectively match the deformation conditions of the lining ring at their respective corresponding positions, the steel ring blocks are anchored on the lining ring, the bottoms of the two steel ring blocks adjacent to the two sides of the floating plate ballast are respectively provided with corbels, the corbels are anchored on the lining ring, the corbels located on the two sides of the floating plate ballast are connected and fixed to form a whole by steel tie rods, and the steel tie rods pass through the floating plate ballast; Between the tensioned corbels, a plurality of the steel tie bars are arranged at intervals along the longitudinal direction of the shield tunnel; The steel tie rod comprises two steel tie rod segments, the outer sides of the two steel tie rod segments are respectively anchored and connected to the steel boxes of the corresponding outer sides of the corbels, and the inner sides of the two steel tie rod segments are connected by a connector; The steel rod segment is a prestressed threaded steel bar, and the connector is a prestressed threaded steel bar connector.

2. The steel ring reinforcement structure of the steel spring vibration damping track section according to claim 1 is characterized by: Along the longitudinal direction of the shield tunnel, the reinforcement includes a plurality of the steel rings, and the same-side corbels on adjacent steel rings are fixedly connected by longitudinal connecting plates to form an integral structure.

3. The steel ring reinforcement structure of the steel spring vibration damping track section according to claim 1 is characterized by: The middle part of the floating slab track bed is provided with a concrete boss, and the steel tie rod passes through the concrete boss at the position without a vibration isolator between adjacent fasteners.

4. The steel ring reinforcement structure of the steel spring vibration damping track bed section according to claim 3 is characterized by: A protective sleeve is arranged between the steel tie rod and the concrete boss.