Auxiliary platform for testing high-voltage electrical equipment

By designing an auxiliary platform for high-voltage electrical equipment testing, the problem of inconvenience in carrying and transfer of facilities is solved, centralized placement and light transfer of facilities are realized, and the efficiency and safety of use are improved.

CN222028285UActive Publication Date: 2024-11-19SHANDONG ELECTRIC POWER CONSTR NO 2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323408214.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-13
Publication Date
2024-11-19
Estimated Expiration
2033-12-13

AI Technical Summary

Technical Problem

During the test of high-voltage electrical equipment, it is inconvenient to carry supporting facilities, and multiple people need to cooperate. The transfer and placement of facilities take up a large space, which affects the efficiency of use.

Method used

A high-voltage electrical equipment test auxiliary platform is designed, including a power storage box, a test equipment storage box and a removable expansion support frame, equipped with mobile ground wheels and reinforced fixtures, which facilitate centralized placement and light transfer of facilities. The intervals can be freely combined and split as needed.

Benefits of technology

One-time transfer and transportation of facilities is realized, labor demand is reduced, convenience and safety of use are improved, and the problem of separation of facilities due to bumps during transportation is avoided.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222028285U_ABST
    Figure CN222028285U_ABST
Patent Text Reader

Abstract

The utility model discloses an auxiliary platform for testing high-voltage electrical equipment, which comprises a power supply storage box, movable land wheels, a test equipment storage box and an expansion support frame, reinforcing fixing devices are arranged between the test equipment storage box and the adjacent capacity expansion supporting frames, between the adjacent capacity expansion supporting frames and between the power supply storage box and the adjacent capacity expansion supporting frames respectively, and an opening and closing box cover is hinged to the top end of the test equipment storage box. Rubber insulation pads are respectively fixed on the top surface of the test equipment storage box and the top surface of the opening and closing box cover, and an insulation handle is also fixed at the top end of the test equipment storage box; the test facility can be transferred or transported at a site at a time, use is convenient and labor-saving, due to the fact that all the components are detachably arranged, reinforcing and fixing are conducted through the reinforcing and fixing device, the test facility is prevented from being automatically separated due to bumpy roads in the pushing and walking process, and use is safer and more stable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of auxiliary tools for testing high-voltage electrical equipment, in particular to an auxiliary platform for testing high-voltage electrical equipment. Background Art

[0002] High-voltage electrical equipment needs to be electrically tested after production is completed, before installation and use, and at regular intervals during operation. The test after production is mainly used to detect whether the production of the equipment meets the requirements. The test before installation and use is mainly used to detect whether the equipment fails during transportation to ensure that it can be used normally and safely after installation. The test during operation is a routine test of the equipment to ensure safety and stability during later use. When testing high-voltage electrical equipment, many supporting facilities are required, such as test power supplies, test wires, wiring tools, maintenance tools, spare new parts to be replaced, etc., which are inconvenient to carry and require the cooperation of multiple people to complete the one-time transfer of supporting facilities. After the facilities are in place, they are generally placed on the spot, occupying a large space, so they are inconvenient to use. When changing the test location according to the installation location of the high-voltage electrical equipment, the above problems will become more prominent. Utility Model Content

[0003] The technical problem to be solved by the utility model is to provide an auxiliary platform for high-voltage electrical equipment testing, which can centrally place and transfer supporting facilities during high-voltage electrical equipment testing, and the facilities are easy to transfer and the capacity is flexible and adjustable.

[0004] To solve the above technical problems, the technical solution of the utility model is: an auxiliary platform for testing high-voltage electrical equipment, comprising a power supply storage box arranged at the bottom layer, the bottom end of the power supply storage box is evenly provided with movable ground wheels, the top end of the power supply storage box is opened, a test equipment storage box is arranged directly above the power supply storage box, a detachable expansion support frame is provided between the power supply storage box and the test equipment storage box, a storage drawer is movably installed on the expansion support frame, and a reinforcing fixing device is respectively arranged between the test equipment storage box and the adjacent expansion support frame, between the adjacent expansion support frames, and between the power supply storage box and the adjacent expansion support frame, an opening and closing box cover is hinged on the top end of the test equipment storage box, rubber insulating pads are respectively fixed on the top surface of the test equipment storage box and the top surface of the opening and closing box cover, and an insulating handle for easy operation is also fixed on the top end of the test equipment storage box.

[0005] As a preferred technical solution, the reinforced fixing device includes three reinforced fixing holes that are evenly distributed linearly in the upper and lower directions, wherein a group of two adjacent reinforced fixing holes are located on both sides of the boundary line between the test equipment storage box and the adjacent expansion support frame, the boundary line between the adjacent expansion support frame, or the boundary line between the power supply storage box and the adjacent expansion support frame, and a reinforced fixing block is detachably provided between two adjacent reinforced fixing holes in a group, and a surface of the reinforced fixing block is provided with a reinforced plug-in shaft corresponding to the two reinforced fixing holes.

[0006] As a preferred technical solution, fixed block grooves are respectively provided across the boundary line between the test equipment storage box and the adjacent expansion support frame, across the boundary line between the adjacent expansion support frame, and across the boundary line between the power supply storage box and the adjacent expansion support frame, and the reinforced fixing holes are all provided in the corresponding fixed block grooves.

[0007] As a preferred technical solution, the outer surface of the reinforced fixing block is provided with a pull ring for easy operation, and the end of the reinforced plug-in shaft is provided with a plug-in guide surface with a reduced outer diameter.

[0008] As a preferred technical solution, the top of the power storage box and the top of the expansion support frame are respectively provided with assembly plug-in slots, and the bottom of the expansion support frame and the bottom of the test equipment storage box are respectively provided with protruding assembly plug-in ring plates.

[0009] As a preferred technical solution, the side wall of the power storage box is provided with an operating box door that can be opened and closed and a ventilating hole for achieving air circulation in the box.

[0010] As an improvement to the above technical solution, a rubber insulating layer is attached to the inner wall of the power storage box, and a foam shock absorbing layer is attached to the inner walls of the test equipment storage box and the storage drawer.

[0011] Due to the adoption of the above technical scheme, the utility model has the following beneficial effects: the UPS uninterruptible power supply is placed in the power supply storage box, various test equipment is placed in the test equipment storage box, the connecting wires, connecting tools, test wires, wiring tools, maintenance tools, spare new parts to be replaced, etc. for testing can be placed in the storage drawer, and the above facilities can be transferred or transported at one time by pushing the insulating handle with the help of movable ground wheels, which is convenient and labor-saving to use, and the number of expansion support frames can be freely combined and disassembled according to the number of facilities. Since the components are detachably arranged, they are strengthened and fixed by setting a strengthening fixing device to prevent them from automatically separating due to road bumps during pushing and walking, and the use is safer and more stable. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] The following drawings are only intended to illustrate and explain the present invention, and do not limit the scope of the present invention.

[0013] Figure 1 It is a schematic diagram of the structure of a relatively large capacity embodiment of the utility model;

[0014] Figure 2 It is a schematic diagram of the structure of a relatively small capacity embodiment of the utility model;

[0015] Figure 3 yes Figure 2 A schematic diagram showing the enlarged comparison of the structure before and after the strengthening fixture is installed at A in the middle;

[0016] Figure 4 It is a side view of the reinforced fixing block and the reinforced plug-in shaft of the embodiment of the utility model;

[0017] Figure 5 It is a schematic diagram of the assembly process of an embodiment of the utility model;

[0018] In the figure: 1-power storage box; 2-mobile ground wheels; 3-test equipment storage box; 4-capacity expansion support frame; 5-storage drawer; 6-operation box door; 7-ventilation port; 8-rubber insulation layer; 9-foam shock-absorbing layer; 10-opening and closing box cover; 11-rubber insulation pad; 12-insulating handle; 13-reinforced fixing hole; 14-reinforced fixing block; 15-reinforced plug-in shaft; 16-fixing block groove; 17-pull ring; 18-plug-in guide surface; 19-assembly plug-in groove; 20-assembly plug-in ring plate. DETAILED DESCRIPTION

[0019] The present invention is further described below in conjunction with the accompanying drawings and examples. In the following detailed description, only certain exemplary embodiments of the present invention are described by way of illustration. Needless to say, those skilled in the art will recognize that the described embodiments may be modified in various ways without departing from the spirit and scope of the present invention. Therefore, the drawings and descriptions are illustrative in nature and are not intended to limit the scope of protection of the claims.

[0020] like Figure 1 and Figure 2As shown, the auxiliary platform for testing high-voltage electrical equipment is used to support the use of supporting test facilities when testing high-voltage electrical equipment, and can transfer supporting test facilities for testing high-voltage electrical equipment at one time, such as test power supply, test wire, wiring tool, maintenance tool, spare new parts to be replaced, etc., without the cooperation of multiple people for carrying, and is convenient and labor-saving to use. Specifically, it includes a power storage box 1 arranged at the bottom layer, the bottom end of the power storage box 1 is evenly distributed with movable ground wheels 2, the top of the power storage box 1 is opened, and a test equipment storage box 3 is arranged directly above the power storage box 1, and an expansion support frame 4 is detachably provided between the power storage box 1 and the test equipment storage box 3, and a storage drawer 5 is movably installed on the expansion support frame 4. Among them, the power storage box 1 is used to store UPS uninterruptible power supply, the test equipment storage box 3 is used to store test equipment, and the storage drawer 5 is used to store connection wires, connection tools, test wires, wiring tools, maintenance tools, spare new parts to be replaced, etc. for testing, and the number of the expansion support frames 4 can be freely adjusted according to the number of facilities. With the help of the mobile ground wheel 2, the above facilities can be transferred or transported at one time, achieving the effect of convenient use and labor saving. The mobile ground wheel 2 can be set as a universal wheel, a composite wheel or a mixture of the two. Among them, the universal wheel has good passability on flat roads and flexible steering; the composite wheel has good passability and shock absorption performance on complex roads, making it safer and more convenient to transport equipment.

[0021] In this embodiment, an operating box door 6 that can be opened and closed and a vent 7 for realizing air circulation in the box are provided on the side wall of the power storage box 1. The operating box door 6 is arranged corresponding to the power connection position on the UPS uninterruptible power supply, so as to connect it with an external wire to realize power supply and charging during the test of high-voltage electrical equipment. The vent 7 can realize air circulation inside and outside the power storage box 1, which is convenient for heat dissipation when the UPS uninterruptible power supply is working. In order to improve the heat dissipation effect, a fan can also be arranged at the vent 7. A rubber insulating layer 8 is attached to the inner wall of the power storage box 1 to ensure safety during the test. The rubber insulating layer 8 can also play a shock-absorbing role to protect the UPS uninterruptible power supply. Foam shock-absorbing layers 9 are attached to the inner walls of the test equipment storage box 3 and the storage drawer 5 to reduce vibration and protect the test facilities in the box.

[0022] The top of the test equipment storage box 3 is hinged with an opening and closing box cover 10, and rubber insulating pads 11 are fixed to the top surface of the test equipment storage box 3 and the top surface of the opening and closing box cover 10 respectively. When in use, the test equipment is placed in the test equipment storage box 3 and closed by the opening and closing box cover 10 to facilitate the safe transportation and storage of the equipment. The provision of the rubber insulating pad 11 helps to improve the safety during the test of high-voltage electrical equipment. The top of the test equipment storage box 3 is also fixed with an insulating handle 12 for easy operation, and the entire platform can be moved by pushing the insulating handle 12 with the help of the movable ground wheel 2.

[0023] like Figure 3 and Figure 4 As shown, reinforcing fixing devices are arranged between the test equipment storage box 3 and the adjacent expansion support frame 4, between the adjacent expansion support frames 4, and between the power supply storage box 1 and the adjacent expansion support frame 4, respectively, to enhance the firmness of the two adjacent components to prevent separation due to road bumps. Specifically, the reinforcing fixing device includes three reinforcing fixing holes 13 evenly distributed linearly up and down, wherein a group of two adjacent reinforcing fixing holes 13 are located on both sides of the boundary line between the test equipment storage box 3 and the adjacent expansion support frame 4, the boundary line between the adjacent expansion support frame 4, or the boundary line between the power supply storage box 1 and the adjacent expansion support frame 4, wherein a group of two adjacent reinforcing fixing holes 13 is detachably provided with a reinforcing fixing block 14, and one surface of the reinforcing fixing block 14 is provided with a reinforcing plug-in shaft 15 corresponding to the two reinforcing fixing holes 13. When in use, the reinforcing fixing block 14 is placed across the boundary line, and the reinforcing plug-in shaft 15 is plugged in and matched to achieve the reinforcing fixation between adjacent components, thereby preventing the components from being separated due to road bumps. After a component is disassembled, the reinforcing fixing block 14 is plugged into the two reinforcing fixing holes 13 on the same component, thereby achieving the storage of the reinforcing fixing block 14 and preventing it from being lost.

[0024] In this embodiment, a fixing block groove 16 is provided across the boundary line between the test equipment storage box 3 and the adjacent expansion support frame 4, across the boundary line between the adjacent expansion support frame 4, and across the boundary line between the power supply storage box 1 and the adjacent expansion support frame 4, and the reinforced fixing holes 13 are all arranged in the corresponding fixing block grooves 16, so that when the reinforced fixing block 14 is used or stored, the surface of the test equipment storage box 3, the expansion support frame 4 or the power supply storage box 1 is relatively flat. The outer surface of the reinforced fixing block 14 is provided with a pull ring 17 for easy operation to facilitate the position change of the reinforced fixing block 14. The end of the reinforced plug-in shaft 15 is provided with a plug-in guide surface 18 with a reduced outer diameter, so that it is more convenient to insert it into the corresponding reinforced fixing hole 13.

[0025] like Figure 5 As shown, the top of the power storage box 1 and the top of the expansion support frame 4 are respectively provided with assembly plug-in slots 19, and the bottom of the expansion support frame 4 and the bottom of the test equipment storage box 3 are respectively provided with protruding assembly plug-in ring plates 20. When used, the assembly plug-in ring plates 20 are inserted into the corresponding assembly plug-in slots 19 to realize the assembly of adjacent components, and the combination or disassembly is simple and convenient.

[0026] The description of the present invention is given for the purpose of illustration and description, and is not intended to be exhaustive or to limit the present invention to the disclosed form. Many modifications and variations will be apparent to those of ordinary skill in the art. The embodiments are selected and described to better illustrate the principles and practical applications of the present invention and to enable those of ordinary skill in the art to understand the present invention and design various embodiments with various modifications suitable for specific uses.

Claims

1. An auxiliary platform for testing high-voltage electrical equipment, comprising a power storage box arranged on the bottom layer, wherein the bottom ends of the power storage box are uniformly provided with movable ground wheels, characterized in that: The power supply storage box is provided with an opening at the top, a test equipment storage box is provided directly above the power supply storage box, a capacity expansion support frame is detachably provided between the power supply storage box and the test equipment storage box, a storage drawer is movably installed on the capacity expansion support frame, reinforcement fixing devices are respectively arranged between the test equipment storage box and the adjacent capacity expansion support frames, between the adjacent capacity expansion support frames, and between the power supply storage box and the adjacent capacity expansion support frames, an opening and closing box cover is hinged at the top of the test equipment storage box, rubber insulating pads are respectively fixed on the top surface of the test equipment storage box and the top surface of the opening and closing box cover, and an insulating handle for easy operation is also fixed on the top of the test equipment storage box.

2. The auxiliary platform for high-voltage electrical equipment testing according to claim 1, characterized in that: The reinforced fixing device includes three reinforced fixing holes which are evenly distributed linearly in the upper and lower parts, wherein a group of two adjacent reinforced fixing holes are located on both sides of the boundary line between the test equipment storage box and the adjacent expansion support frame, the boundary line between the adjacent expansion support frame or the boundary line between the power supply storage box and the adjacent expansion support frame, and a reinforced fixing block is detachably provided between two adjacent reinforced fixing holes in a group, and a surface of the reinforced fixing block is provided with a reinforced plug-in shaft corresponding to the two reinforced fixing holes.

3. The auxiliary platform for testing high-voltage electrical equipment according to claim 2, characterized in that: Fixed block grooves are respectively provided across the boundary line between the test equipment storage box and the adjacent expansion support frame, across the boundary line between the adjacent expansion support frame, and across the boundary line between the power supply storage box and the adjacent expansion support frame, and the reinforced fixing holes are all provided in the corresponding fixed block grooves.

4. The auxiliary platform for testing high-voltage electrical equipment according to claim 2, characterized in that: The outer surface of the reinforced fixing block is provided with a pull ring for easy operation, and the end of the reinforced plug-in shaft is provided with a plug-in guide surface with a reduced outer diameter.

5. The auxiliary platform for testing high-voltage electrical equipment according to claim 1, characterized in that: The top of the power storage box and the top of the expansion support frame are respectively provided with assembly plug-in slots, and the bottom of the expansion support frame and the bottom of the test equipment storage box are respectively provided with protruding assembly plug-in ring plates.

6. The auxiliary platform for testing high-voltage electrical equipment according to claim 1, characterized in that: The side wall of the power storage box is provided with an operating box door that can be opened and closed and a ventilating hole for realizing air circulation in the box.

7. The auxiliary platform for testing high-voltage electrical equipment according to claim 1, characterized in that: A rubber insulating layer is attached to the inner wall of the power storage box, and a foam shock-absorbing layer is attached to the inner walls of the test equipment storage box and the storage drawer.