Anti-scaling evaporative crystallization equipment

By introducing the inner viewing component and the inner wall swelling component in the evaporation crystallization equipment, real-time monitoring and cleaning of the inner wall of the evaporation tank is achieved, which solves the problem of smaller evaporation area and waste of material caused by the scaling of the inner wall of the equipment, and improves the equipment's Operating efficiency and stability.

CN222033673UActive Publication Date: 2024-11-22HUNAN XIANGHENG SALT CHEM
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420986217.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-08
Publication Date
2024-11-22
Estimated Expiration
2034-05-08

AI Technical Summary

Technical Problem

Common evaporation and crystallization equipment lacks a rotatable spray cleaning and descaling structure, which makes it very easy to cause crystallization of the inner wall during the evaporation process, resulting in smaller evaporation area and waste of material.

Method used

A anti-scaling evaporation and crystallization device is designed, including an inner vision component and an inner wall shower assembly. The inner vision component monitors the scaling condition in real time through a monitor and an endoscopic probe to determine the cleaning time. The inner wall shower assembly is carried out through a cleaning pump and spray head. To achieve cleaning of the inner wall of the evaporation tank, avoiding scaling and waste of material discharge.

Benefits of technology

Through real-time monitoring and cleaning operations, the scale crystallization is effectively reduced, the waste of material discharge caused by the decrease in the evaporation area is avoided, and the equipment's use efficiency and operation stability are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222033673U_ABST
    Figure CN222033673U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of evaporative crystallization, in particular to anti-scaling evaporative crystallization equipment. The technical problems that common evaporative crystallization equipment lacks a rotatable spraying, cleaning and descaling structure, so that crystallization and scaling are extremely prone to occurring on the inner wall in the evaporation process, the evaporation area is reduced, and material leakage and waste exist are solved. According to the technical scheme, the anti-scaling evaporative crystallization equipment comprises an evaporation tank. According to the utility model, the scaling condition in the evaporation tank is monitored in real time through the internal view assembly, so that the cleaning opportunity is judged, the inner wall of the evaporation tank is cleaned through the inner wall showering assembly, and scaling and crystallization are reduced, so that material leakage and waste caused by reduction of the evaporation area are avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of evaporation and crystallization, in particular to an anti-scaling evaporation and crystallization device. Background Art

[0002] Evaporation crystallization equipment is a kind of equipment used to concentrate the dissolved substances in the solution to saturation by evaporation, and then crystallize out pure solids. It is widely used in chemical, pharmaceutical, food processing and other fields. By controlling the temperature and pressure of the solution, it evaporates and concentrates inside the equipment.

[0003] Common evaporation and crystallization equipment lacks a rotatable spray cleaning and descaling structure, which leads to crystallization and scaling on the inner wall during the evaporation process, resulting in a smaller evaporation area and material waste.

[0004] Therefore, the above-mentioned evaporation crystallization equipment lacks a rotatable spray cleaning and descaling structure, which easily leads to crystallization and scaling on the inner wall, resulting in a smaller evaporation area and waste of materials, which urgently needs to be solved to improve the usage scenario. Utility Model Content

[0005] In order to overcome the problem that common evaporation crystallization equipment lacks a rotatable spray cleaning and descaling structure, crystallization and scaling are very likely to occur on the inner wall.

[0006] The technical scheme of the utility model is: an anti-scaling evaporation crystallization device, comprising an evaporator, a feed pipe is installed near the upper end of the right side of the evaporator, a steam discharge pipe is arranged on the top of the evaporator, a collecting tank is connected to the bottom of the evaporator, a first connecting pipe is connected to the bottom of the collecting tank, a first solenoid valve is installed near the bottom of the collecting tank on the first connecting pipe, an axial flow pump is arranged on the left end of the first connecting pipe, a second connecting pipe is connected to the top of the left end of the axial flow pump, a heat exchanger is connected to the upper end of the second connecting pipe, the top of the heat exchanger is connected to the middle position of the left side of the evaporator through the third connecting pipe, an inner sight assembly is installed at the middle position of the right end of the evaporator, a fixed plate is arranged near the top of the left end of the evaporator, an inner wall shower assembly is connected to the upper end of the fixed plate, and a discharge assembly is connected to the right side of the collecting tank.

[0007] Preferably, the scaling condition inside the evaporator is monitored in real time by the provided inner viewing component, so as to judge the cleaning timing, and the inner wall of the evaporator is cleaned by the provided inner wall shower component to reduce scaling and crystallization, thereby avoiding the waste of materials caused by a smaller evaporation area, so as to solve the problem that common evaporation and crystallization equipment lacks a rotatable spray cleaning and descaling structure, which leads to the situation that scaling and crystallization easily occur on the inner wall during the evaporation process, resulting in a smaller evaporation area and a waste of materials.

[0008] Preferably, the internal viewing component includes a monitor and an endoscope probe; a monitor is embedded in the middle position on the right side of the evaporator, and an endoscope probe is installed on the left end of the monitor. The endoscope probe can be used to monitor the scaling condition inside the evaporator in real time, so as to determine the cleaning time.

[0009] Preferably, the interior viewing component includes a connecting block and a fill light; the upper end of the monitor is connected to the connecting block, and the top of the connecting block is equipped with a fill light, which can provide fill light for illumination.

[0010] Preferably, the inner wall shower assembly includes a cleaning pump and a water inlet pipe; the cleaning pump is installed on the upper end of the fixed plate, the left end of the cleaning pump is connected to the water inlet pipe, and the water inlet pipe is connected to the external water supply pipeline.

[0011] Preferably, the inner wall shower assembly includes a hanger, a fixed pipe, and a fourth connecting pipe; a hanger is hung on the inner wall of the upper end of the evaporator, a fixed pipe is fixedly installed in the middle position of the hanger, the top of the fixed pipe is connected to the right end of the cleaning pump through the fourth connecting pipe, and the cleaning pump is started to transport clean water to the fixed pipe through the fourth connecting pipe.

[0012] Preferably, the inner wall shower assembly includes a rotating tube, a mounting tube, a first cleaning tube, and a second cleaning tube; the lower end of the fixed tube is connected to the rotating tube through a bearing, the bottom of the rotating tube is connected to the mounting tube, the left end of the mounting tube is installed with the first cleaning tube, the right end of the mounting tube is connected with the second cleaning tube, and a plurality of nozzles are equidistantly installed on the front side of the first cleaning tube and the back side of the second cleaning tube. Clean water passes through the fixed tube, the rotating tube, and the mounting tube to reach the first cleaning tube and the second cleaning tube, and is sprayed out through the nozzles. Under the action of the impact force, the first cleaning tube and the second cleaning tube rotate, thereby cleaning the inner wall of the evaporator tank, reducing scaling and crystallization, and thus avoiding the waste of materials caused by a smaller evaporation area.

[0013] Preferably, the discharging assembly includes a fifth connecting pipe, a second solenoid valve, a discharging pump, and a discharging pipe; the fifth connecting pipe is connected to the right side of the collecting tank, the second solenoid valve is installed in the middle of the fifth connecting pipe, the right end of the fifth connecting pipe is connected to the discharging pump, and the right end of the discharging pump is provided with a discharging pipe, the first solenoid valve is closed, the second solenoid valve is opened, the discharging pump is started, and the material is discharged through the discharging pipe.

[0014] Beneficial effects of the utility model:

[0015] 1. The internal visual component is used to monitor the scaling inside the evaporator in real time, so as to determine the cleaning time. The inner wall of the evaporator is cleaned by the inner wall shower component, reducing scaling and crystallization, thereby avoiding the waste of materials caused by the reduction of the evaporation area. This solves the problem that common evaporation and crystallization equipment lacks a rotatable spray cleaning and descaling structure, which leads to the easy occurrence of crystal scaling on the inner wall during the evaporation process, resulting in a reduction of the evaporation area and the waste of materials.

[0016] 2. The fill light can be used for fill lighting. The endoscope can monitor the scaling inside the evaporator in real time to judge the cleaning time. The cleaning pump is started to transport clean water to the fixed pipe through the fourth connecting pipe. The clean water reaches the first cleaning pipe and the second cleaning pipe through the fixed pipe, the rotating pipe and the installation pipe, and is sprayed out through the nozzle. Under the action of the impact force, the first cleaning pipe and the second cleaning pipe rotate, thereby cleaning the inner wall of the evaporator, reducing scaling crystallization, and avoiding the waste of material caused by the reduction of the evaporation area. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 What is shown is a three-dimensional structural schematic diagram of an anti-scaling evaporation crystallization device of the utility model;

[0018] Figure 2 What is shown is a schematic diagram of the internal structure of an anti-scaling evaporation crystallization device of the utility model;

[0019] Figure 3 What is shown is a schematic diagram of the internal structure of components of an anti-scaling evaporation crystallization device of the utility model;

[0020] Figure 4 Shown is a schematic diagram of the structure of an inner wall shower assembly of an anti-scaling evaporation crystallization device of the utility model;

[0021] Figure 5 Shown is a schematic diagram of the structure of a discharge component of an anti-scaling evaporation crystallization device of the utility model.

[0022] In the figure: 1, evaporator; 2, feed pipe; 3, steam discharge pipe; 4, collecting tank; 5, first connecting pipe; 6, first solenoid valve; 7, axial flow pump; 8, second connecting pipe; 9, heat exchanger; 10, third connecting pipe; 11, internal viewing assembly; 12, fixing plate; 13, inner wall shower assembly; 14, discharge assembly; 1101, monitor; 1102, endoscope probe; 1103, connecting block; 1104, fill light; 1301, cleaning pump; 1302, water inlet pipe; 1303, hanger; 1304, fixed pipe; 1305, fourth connecting pipe; 1306, rotating pipe; 1307, mounting pipe; 1308, first cleaning pipe; 1309, second cleaning pipe; 1401, fifth connecting pipe; 1402, second solenoid valve; 1403, discharge pump; 1404, discharge pipe. DETAILED DESCRIPTION

[0023] The utility model is further described below in conjunction with the accompanying drawings and embodiments.

[0024] See also Figure 1-2The utility model provides an embodiment: an anti-scaling evaporation crystallization device, comprising an evaporation tank 1, a feed pipe 2 is installed near the upper end of the right side of the evaporation tank 1, a steam discharge pipe 3 is arranged on the top of the evaporation tank 1, a collecting tank 4 is connected to the bottom of the evaporation tank 1, a first connecting pipe 5 is connected to the bottom of the collecting tank 4, a first solenoid valve 6 is installed near the bottom of the first connecting pipe 5, an axial flow pump 7 is arranged on the left end of the first connecting pipe 5, a second connecting pipe 8 is connected to the top of the left end of the axial flow pump 7, a heat exchanger 9 is connected to the upper end of the second connecting pipe 8, the top of the heat exchanger 9 is connected to the middle position of the left side of the evaporation tank 1 through a third connecting pipe 10, an inner viewing component 11 is installed at the middle position of the right end of the evaporation tank 1, a fixing plate 12 is arranged near the top of the left end of the evaporation tank 1, an inner wall shower component 13 is connected to the upper end of the fixing plate 12, and a discharging component 14 is connected to the right side of the collecting tank 4.

[0025] See also Figure 3 In this embodiment, the internal viewing component 11 includes a monitor 1101 and an endoscope probe 1102; the monitor 1101 is embedded in the middle position on the right side of the evaporation tank 1, and the endoscope probe 1102 is installed on the left end of the monitor 1101. The scaling condition inside the evaporation tank 1 can be monitored in real time through the endoscope probe 1102, so as to determine the cleaning time. The internal viewing component 11 includes a connecting block 1103 and a fill light 1104; the upper end of the monitor 1101 is connected to the connecting block 1103, and the top of the connecting block 1103 is installed with the fill light 1104, which can play the role of fill light illumination.

[0026] See also Figure 4In this embodiment, the inner wall shower assembly 13 includes a cleaning pump 1301 and a water inlet pipe 1302; the cleaning pump 1301 is installed on the upper end of the fixed plate 12, the left end of the cleaning pump 1301 is connected to the water inlet pipe 1302, the water inlet pipe 1302 is connected to the external water supply pipeline, the inner wall shower assembly 13 includes a hanger 1303, a fixed pipe 1304, and a fourth connecting pipe 1305; a hanger 1303 is hung on the inner wall of the upper end of the evaporator 1, and a fixed pipe 1304 is fixedly installed in the middle position of the hanger 1303. The top of the fixed pipe 1304 is connected to the right end of the cleaning pump 1301 through the fourth connecting pipe 1305. The cleaning pump 1301 is started to transport clean water to the fixed pipe 1304 through the fourth connecting pipe 1305. The inner wall shower assembly 13 includes a rotating pipe 1306, an installation pipe 1307, a first Cleaning pipe 1308 and second cleaning pipe 1309; the lower end of the fixed pipe 1304 is connected to the rotating pipe 1306 through a bearing, the bottom of the rotating pipe 1306 is connected to the mounting pipe 1307, the left end of the mounting pipe 1307 is installed with the first cleaning pipe 1308, the right end of the mounting pipe 1307 is connected with the second cleaning pipe 1309, and a plurality of nozzles are equidistantly installed on the front side of the first cleaning pipe 1308 and the back side of the second cleaning pipe 1309. Clean water passes through the fixed pipe 1304, the rotating pipe 1306 and the mounting pipe 1307 to reach the first cleaning pipe 1308 and the second cleaning pipe 1309, and is sprayed out through the nozzles. Under the action of the impulse, the first cleaning pipe 1308 and the second cleaning pipe 1309 rotate, thereby cleaning the inner wall of the evaporator 1, reducing scaling and crystallization, and thus avoiding the waste of running materials caused by the reduction of the evaporation area.

[0027] See also Figure 5 In this embodiment, the discharging component 14 includes a fifth connecting pipe 1401, a second solenoid valve 1402, a discharging pump 1403, and a discharging pipe 1404; the fifth connecting pipe 1401 is connected to the right side of the collecting tank 4, the second solenoid valve 1402 is installed in the middle of the fifth connecting pipe 1401, the right end of the fifth connecting pipe 1401 is connected to the discharging pump 1403, and the right end of the discharging pump 1403 is provided with a discharging pipe 1404, the first solenoid valve 6 is closed, the second solenoid valve 1402 is opened, the discharging pump 1403 is started, and the material is discharged through the discharging pipe 1404.

[0028] During operation, the scaling condition inside the evaporator 1 can be monitored in real time through the endoscope 1102, so as to judge the cleaning time. The fill light 1104 can play the role of fill light illumination, and the cleaning pump 1301 is driven to transport clean water to the fixed pipe 1304 through the fourth connecting pipe 1305. The clean water reaches the first cleaning pipe 1308 and the second cleaning pipe 1309 through the fixed pipe 1304, the rotating pipe 1306, and the installation pipe 1307, and is sprayed out through the nozzle. Under the action of the impulse, the first cleaning pipe 1308 and the second cleaning pipe 1309 rotate, so as to realize the cleaning of the inner wall of the evaporator 1, reduce scaling crystallization, and avoid the waste of running materials caused by the reduction of the evaporation area. After the concentration is completed, the first solenoid valve 6 is closed, the second solenoid valve 1402 is opened, and the discharge pump 1403 is started to discharge the materials through the discharge pipe 1404.

[0029] Through the above steps, the scaling condition inside the evaporator can be monitored in real time by the provided inner viewing component 11, so as to judge the cleaning time, and the inner wall of the evaporator can be cleaned by the provided inner wall shower component 13, so as to reduce scaling and crystallization, thereby avoiding the waste of materials caused by the reduction of the evaporation area, so as to solve the problem that the common evaporation and crystallization equipment lacks a rotatable spray cleaning and descaling structure, which leads to the situation that scaling and crystallization are easily formed on the inner wall during the evaporation process, resulting in the reduction of the evaporation area and the waste of materials.

[0030] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of those skilled in the art without departing from the purpose of the present invention.

Claims

1. An anti-scaling evaporation crystallization device, comprising an evaporation tank (1), Features: A feed pipe (2) is installed near the upper end of the right side of the evaporator (1); a steam discharge pipe (3) is arranged at the top of the evaporator (1); a collecting tank (4) is connected to the bottom of the evaporator (1); a first connecting pipe (5) is connected to the bottom of the collecting tank (4); a first solenoid valve (6) is installed near the bottom of the collecting tank (4) on the first connecting pipe (5); an axial flow pump (7) is installed at the left end of the first connecting pipe (5); a second connecting pipe (8) is connected to the top of the left end of the axial flow pump (7); a heat exchanger (9) is connected to the upper end of the second connecting pipe (8); the top of the heat exchanger (9) is connected to the middle position of the left side of the evaporator (1) through a third connecting pipe (10); an inner sight assembly (11) is installed at the middle position of the right end of the evaporator (1); a fixing plate (12) is arranged near the top of the left end of the evaporator (1); an inner wall shower assembly (13) is connected to the upper end of the fixing plate (12); and a discharge assembly (14) is connected to the right side of the collecting tank (4).

2. The anti-scaling evaporation crystallization equipment according to claim 1, Features: The internal viewing component (11) comprises a monitor (1101) and an endoscope probe (1102); the monitor (1101) is embedded in the middle position on the right side of the evaporation tank (1), and the endoscope probe (1102) is installed at the left end of the monitor (1101).

3. The anti-scaling evaporation crystallization equipment according to claim 2, Features: The internal viewing component (11) comprises a connecting block (1103) and a fill light (1104); the upper end of the monitor (1101) is connected to the connecting block (1103), and the top of the connecting block (1103) is installed with the fill light (1104).

4. The anti-scaling evaporation crystallization equipment according to claim 1, Features: The inner wall shower assembly (13) comprises a cleaning pump (1301) and a water inlet pipe (1302); the cleaning pump (1301) is installed on the upper end of the fixed plate (12); the left end of the cleaning pump (1301) is connected to the water inlet pipe (1302); and the water inlet pipe (1302) is connected to an external water supply pipeline.

5. The anti-scaling evaporation crystallization equipment according to claim 4, Features: The inner wall shower assembly (13) comprises a hanger (1303), a fixed pipe (1304), and a fourth connecting pipe (1305); the hanger (1303) is hung on the inner wall of the upper end of the evaporation tank (1), the fixed pipe (1304) is fixedly installed in the middle of the hanger (1303), and the top of the fixed pipe (1304) is connected to the right end of the cleaning pump (1301) through the fourth connecting pipe (1305).

6. The anti-scaling evaporation crystallization equipment according to claim 5, Features: The inner wall shower assembly (13) comprises a rotating tube (1306), a mounting tube (1307), a first cleaning tube (1308), and a second cleaning tube (1309); the lower end of the fixed tube (1304) is connected to the rotating tube (1306) via a bearing, the bottom of the rotating tube (1306) is connected to the mounting tube (1307), the left end of the mounting tube (1307) is installed with the first cleaning tube (1308), the right end of the mounting tube (1307) is connected with the second cleaning tube (1309), and a plurality of nozzles are equidistantly installed on the front side of the first cleaning tube (1308) and the back side of the second cleaning tube (1309).

7. The anti-scaling evaporation crystallization equipment according to claim 1, Features: The discharge assembly (14) comprises a fifth connecting pipe (1401), a second solenoid valve (1402), a discharge pump (1403), and a discharge pipe (1404); the fifth connecting pipe (1401) is connected to the right side of the collecting tank (4), the second solenoid valve (1402) is installed in the middle of the fifth connecting pipe (1401), the right end of the fifth connecting pipe (1401) is connected to the discharge pump (1403), and the right end of the discharge pump (1403) is provided with a discharge pipe (1404).