Finished beam transfer protection device
By designing the finished beam transport protection device, the combination of ply plates, curved plates, stainless steel hoisting rings, liners and anti-collision pads is solved, and the box beam is stable lifting and transporting is achieved, reducing the number of box beams The beam body damage and lifting frequency are improved, and the working efficiency is improved.
Patent Information
- Application Number
- CN202420455285.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-09
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2034-03-09
AI Technical Summary
In the prefabricating process of box beams, conventional padding is not firm and under weak stress, which can easily lead to damage to the flange plate of the beam body, affect the appearance quality, and increase the lifting and hoisting frequency.
A finished beam transport protection device is designed, including plywood, curved plate, stainless steel hoisting ring, liner and anti-collision pad. Through the cooperation of these components, the box beam is stable lifting and transported, avoiding rope binding, and improving Operational efficiency.
The box beam is stable lifting and transported, which reduces the damage to the beam body, improves work efficiency, avoids the rope binding process, and increases friction and protection effect.
Smart Images

Figure CN222042380U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of finished beam transportation, in particular to a finished beam transportation protection device. Background Art
[0002] At present, with the progress of society and the continuous development of the times, there is a certain impact on the travel pressure of people. Therefore, the traffic pressure is extremely huge. With the connection of the expressway network, the travel pressure can be well alleviated, thereby further improving the requirements for road construction. At present, for expressways, the source of fast, efficient and convenient construction generally adopts centralized prefabrication plants to prefabricate box girders, which are transported to designated locations for erection, thereby completing subsequent bridge deck construction. This greatly reduces construction risks and improves construction efficiency.
[0003] However, in the box girder prefabrication stage, according to the requirements of the design and construction drawings, prestressing and grouting are allowed after reaching 85% of the designed concrete strength and elastic modulus. After this stage, the beam needs to be transferred from the pedestal to the beam storage area. Since the box girder cannot be transported in time, this causes a secondary transfer, which invisibly increases the frequency of lifting and hoisting the beam.
[0004] In conventional box girder lifting, pads (usually rubber sheets) are placed at the arc chamfers of the bottom plate of the beam and the top flange plate for protection. However, it is inconvenient to operate and fix the pads, and the force is weak, which can easily damage the flange plate of the beam and affect the appearance quality. Therefore, a finished beam transfer protection device is proposed. Utility Model Content
[0005] The utility model aims to provide a finished beam transport protection device to solve the problems in the above background technology that the conventional pads are not reliable, weak in force, and easy to deviate when not fixed.
[0006] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0007] A finished beam transfer protection device comprises: a clamping plate, a control arm is fixedly installed on the upper surface of the clamping plate, an arc plate is fixedly installed inside the clamping plate, a top pressure plate is arranged at the end of the arc plate, and the top pressure plate is planar.
[0008] Preferably, the control arm is tilted to one side so that the two groups of clamps are rotatably connected to form a clamp through the control arm.
[0009] Preferably, a threaded hole is provided on the upper surface of the control arm, and a stainless steel lifting ring is installed in the threaded hole.
[0010] Preferably, the arc surface of the arc plate is consistent with and fits the chamfer radius of the finished box beam.
[0011] Preferably, a gasket is fixedly mounted on the arc surface of the arc plate, and the gasket is made of strip-shaped rubber material.
[0012] Preferably, an anti-collision pad is fixedly installed on one end of the top pressure plate, and the anti-collision pad is made of block-shaped rubber material. The top pressure plate can be pressed against one side of the planar filling plate through the anti-collision pad.
[0013] Compared with the prior art, the beneficial effects of the utility model are:
[0014] 1. Through the design of top pressure plate, curved plate, stainless steel lifting ring and pad, when lifting and transporting the box girder, two gantry cranes can be used to tie the lifting ropes in two sets of stainless steel lifting rings, and then the gantry cranes can be lowered to drive the lifting ropes to drive the two sets of clamps to descend to the upper sides of the box girder, and then the clamps will touch the two sides of the box girder through the inclined surface at the lower end, so that the clamps can be pushed to the two ends to unfold. With the continuous driving of the clamps to descend, the clamps can be put on both sides of the outer surface of the box girder, and the top pressure plate will not be pushed by the box girder, so that the top pressure plate can touch the box girder, and the clamps can move toward the center. In the process of moving together, the splint will drive the arc plate to touch the chamfered arc of the box beam, and the arc plate will be tightly attached to the chamfered arc. Then the gantry crane can be started to reel in the lifting rope to pull up the splint. In the process of pulling up the splint, the wire rope will be tightened into a straight line due to the pulling force, and the straight wire rope will drive the two sets of control arms to the center, so that the splint can always be kept in a closed clamping state, making it more stable during the lifting process and not easy to loosen and fall off. In addition, the lifting process of the box beam eliminates the process of using ropes to bundle the box beam, thereby increasing work efficiency.
[0015] 2. Through the design of pads and anti-collision pads, the pads and anti-collision pads are respectively arranged on the curved plate and the top pressure plate, so that when the curved plate touches the chamfer radius of the box girder, it can avoid damaging the box girder, and at the same time increase the friction and increase the stability during the lifting process. The top pressure plate that touches the filling plate side will also touch it through the anti-collision pad, so that the transportation process of the hoisted box girder can achieve the maximum protection effect, thereby achieving a good transportation effect for the box girder, convenient and fast, and can minimize the damage to the beam body, which can be widely promoted in the prefabrication process of centralized beam factories. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the structure of the overall device of the utility model clamping a box beam with a chamfered arc;
[0017] Figure 2 This is a schematic diagram of the unfolded structure of the splint of the utility model;
[0018] Figure 3 It is a schematic diagram of the structure of the arc plate and the top pressure plate of the utility model.
[0019] In the figure: 1. clamping plate; 101. anti-collision pad; 102. liner; 103. top pressure plate; 104. arc plate; 2. control arm; 201. threaded hole; 3. stainless steel lifting ring. DETAILED DESCRIPTION
[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0021] See also Figure 1-Figure 3 , this embodiment provides the following technical solutions:
[0022] like Figure 1-Figure 3 As shown, a finished beam transfer protection device includes: a protection component for protecting the finished box beam, the protection component includes a splint 1, a control arm 2 is fixedly installed on the upper surface of the splint 1, an arc plate 104 is fixedly installed inside the splint 1, a top pressure plate 103 is provided at the end of the arc plate 104, and the top pressure plate 103 is planar.
[0023] The control arm 2 is tilted to one side, so that the two groups of clamps 1 are connected to form a clamp by rotation through the control arm 2.
[0024] A threaded hole 201 is provided on the upper surface of the control arm 2 , and a stainless steel lifting ring 3 is installed in the inner thread of the threaded hole 201 .
[0025] The arc surface of the arc plate 104 is consistent with and fits the chamfer radius of the finished box beam.
[0026] A gasket 102 is fixedly mounted on the arc surface of the arc plate 104 , and the gasket 102 is made of strip-shaped rubber material.
[0027] Among them, an anti-collision pad 101 is fixedly installed at one end of the top pressure plate 103. The anti-collision pad 101 is made of block-shaped rubber material. The top pressure plate 103 can be pressed on one side of the planar filling plate through the anti-collision pad 101.
[0028] Through the design of the top pressure plate 103, the curved plate 104, the stainless steel lifting ring 3 and the liner 102, when the box beam is lifted and transported, the two gantry cranes can be used to tie the lifting ropes in the two groups of stainless steel lifting rings 3, and then the gantry cranes can be lowered and the lifting ropes can drive the two groups of clamps 1 to be lowered to the upper sides of the box beam respectively, and then the clamps 1 will touch the two sides of the box beam through the inclined surface at the lower end, so that the clamps 2 can be pushed to the two ends to unfold, and as the clamps 2 are continuously driven to descend, the clamps 1 can be sleeved on both sides of the outer surface of the box beam, and the top pressure plate 103 will not be pushed by the box beam, so that the top pressure plate 103 can touch the box beam, and the clamps When the plate 1 moves toward the center, the clamping plate 1 will drive the arc plate 104 to touch the chamfer of the box beam, and the arc plate 104 will be tightly attached to the chamfer. Then the gantry crane can be started to reel in the lifting rope to pull up the clamping plate 1. In the process of pulling up the clamping plate 1, the wire rope will be tightened into a straight line due to the pulling force, and the straight wire rope will drive the two sets of control arms 2 to be in the center, so that the clamping plate 1 can always be kept in a closed clamping state, making it more stable during the lifting process and not easy to loosen and fall off. In addition, the process of binding the box beam with ropes is eliminated, thereby increasing work efficiency.
[0029] The pads 102 and anti-collision pads 101 are respectively arranged on the arc plate 104 and the top pressure plate 103, so that when the arc plate 104 touches the chamfered arc of the box beam, it can avoid damaging the box beam, and at the same time increase the friction force, thereby increasing the stability during the lifting process. The top pressure plate 103 that touches the filling plate side will also touch it through the anti-collision pad 101, so that the transportation process of the hoisted box beam can achieve the greatest protection effect, thereby achieving a good transportation effect for the box beam, convenient and fast, and can minimize the damage to the beam body, which can be widely promoted in the prefabrication process of centralized beam factories.
[0030] According to the above technical solution, the working steps of this solution are summarized and sorted out:
[0031] Step 1: After the box girder is tensioned on the pedestal and ready for transportation to the site,
[0032] Step 2: Drive the beam transport vehicle to the designated location of the box beam to be transported;
[0033] Step 3: The beam transporter will use the gantry crane to transport the lifting wire rope roughly to the right place;
[0034] Step 4: The two gantry cranes can be used to tie the lifting ropes in the two sets of stainless steel lifting rings 3, and then the gantry cranes can be lowered to drive the lifting ropes to drive the two sets of plywood 1 to descend to the upper sides of the box beam respectively; then the plywood 1 will touch the two sides of the box beam through the inclined surface at the lower end, so that the plywood 2 can be pushed to the two ends to unfold, and as the plywood 2 is continuously driven to descend, the plywood 1 can be put on both sides of the outer surface of the box beam, and the top pressure plate 103 will not be pushed by the box beam, so that the top pressure plate 103 can touch the box beam, and in the process of the plywood 1 moving towards the center, the plywood 1 will drive the arc plate 104 to touch the chamfered arc of the box beam, and The curved plate 104 will fit tightly within the chamfer arc, and then the gantry crane can be started to reel in the lifting rope to pull up the clamping plate 1. In the process of pulling up the clamping plate 1, the wire rope will be tightened into a straight line due to the pulling force, and the wire rope in a straight line will drive the two sets of control arms 2 to be in the center, so that the clamping plate 1 can always be kept in a closed clamping state until the two gantry cranes lift the box beam to the beam transport vehicle. As the lifting wire rope continues to descend, the lifting wire rope will be loosened, allowing the staff to push the control arm 2 to both ends to expand the clamping of the clamping plate 1 on the box beam, and then the unloaded box beam can be tied up, and the support measures are in place;
[0035] Step 5: Transport it to the beam storage area, lift it in the same way, unload it, and place the beam on the beam storage pedestal.
[0036] In summary: it makes it more stable during the lifting process, can minimize the damage to the beam body, and is not easy to loosen and fall off. The lifting process of the box beam eliminates the need for rope binding, thereby increasing work efficiency.
[0037] Parts not involved in the present invention are the same as the prior art or can be implemented by the prior art. Although the embodiments of the present invention have been shown and described, it is understood by those skilled in the art that various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principles and spirit of the present invention, and the scope of the present invention is defined by the attached claims and their equivalents.
Claims
1. A finished beam transport protection device, characterized in that: include: A protection component for protecting a finished box girder, the protection component comprising a clamping plate (1), a control arm (2) being fixedly mounted on the upper surface of the clamping plate (1), an arc-shaped plate (104) being fixedly mounted inside the clamping plate (1), a top pressure plate (103) being arranged at the end of the arc-shaped plate (104), and the top pressure plate (103) being in a planar shape.
2. A finished beam transport protection device according to claim 1, characterized in that: The control arm (2) is tilted to one side, so that the two groups of clamps (1) are connected to form a clamp by rotation through the control arm (2).
3. A finished beam transport protection device according to claim 2, characterized in that: A threaded hole (201) is provided on the upper surface of the control arm (2), and a stainless steel lifting ring (3) is installed in the inner thread of the threaded hole (201).
4. A finished beam transport protection device according to claim 1, characterized in that: The arc surface of the arc plate (104) is consistent with and fits the chamfer radius of the finished box beam.
5. A finished beam transport protection device according to claim 4, characterized in that: A gasket (102) is fixedly mounted on the arc surface of the arc plate (104), and the gasket (102) is made of strip-shaped rubber material.
6. A finished beam transport protection device according to any one of claims 1 to 5, characterized in that: An anti-collision pad (101) is fixedly mounted on one end of the top pressure plate (103), and the anti-collision pad (101) is made of block-shaped rubber material. The top pressure plate (103) can be pressed against one side of the planar filling plate through the anti-collision pad (101).