Cofferdam combining steel pipe piles and Larsen steel sheet piles
Through the combination of inner steel pipe piles and outer steel pipe piles, the sealing device and adjustment structure are used to ensure the sealing of Larsen steel sheet piles, which solves the problem of deformation and gaps of cofferdams under water flow pressure, and improves waterproofing performance and construction safety and efficiency.
Patent Information
- Application Number
- CN202420062312.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-10
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2034-01-10
AI Technical Summary
The existing cofferdam combined with the Larsen steel sheet piles can easily cause the steel sheet pile to deform and form gaps when the water flow pressure is high, causing the water flow to penetrate into the cofferdam and affect construction.
The structure is adopted that combines inner steel pipe piles and outer steel pipe piles. Through the sealing device and adjustment structure, the sealing between Larsen steel sheet piles is ensured, deformation and gap formation is avoided, and construction safety and efficiency are improved through support plates and springboards. .
It effectively avoids water seepage into the cofferdam, improves the waterproof performance and construction safety of the cofferdam, and enhances construction efficiency.
Smart Images

Figure CN222044241U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of cofferdams, and in particular to a cofferdam combining steel pipe piles and Larsen steel sheet piles. Background Art
[0002] A cofferdam refers to a temporary retaining structure built during the construction of a water conservancy project. Its function is to prevent water and soil from entering the construction site of the building so that drainage can be drained within the cofferdam, foundation pits can be excavated, and buildings can be constructed.
[0003] The utility model patent with announcement number CN214784064U proposes a cofferdam combining steel pipe piles and Larsen steel sheet piles, including Larsen steel sheet piles, a clay filling layer, tension bolts and a steel waist beam; the Larsen steel sheet piles are arranged on both sides of the cofferdam, and the Larsen steel sheet piles on the same side are arranged in sequence; a clay filling layer is arranged in the middle of the Larsen steel sheet piles on both sides; the steel waist beam is arranged on both sides of the cofferdam and fixedly installed on the upper part of the Larsen steel sheet piles, fixing a row of Larsen steel sheet piles on the same side in series; the tension bolts are connected to the steel waist beam to fix the steel waist beams on both sides together; it also includes a clamp and a steel pipe pile; the clamp is installed on the steel waist beam; the steel pipe piles are vertically arranged on both sides of the cofferdam, the upper part of which is fixed on the clamp, and the bottom extends downward and exceeds the bottom of the Larsen steel sheet pile.
[0004] The above structure is connected to each other by Larsen steel sheet piles to form a cofferdam. When the water pressure is large, the steel sheet piles are easily deformed, resulting in gaps between two adjacent steel sheet piles, so that water seeps into the cofferdam and affects the construction. Utility Model Content
[0005] The utility model aims to solve or at least alleviate the problem that in the existing structure, Larsen steel sheet piles are connected to each other to form a cofferdam, and when the water pressure is large, the steel sheet piles are easily deformed, resulting in a gap between two adjacent steel sheet piles, so that water penetrates into the cofferdam and affects the construction.
[0006] In order to achieve the above purpose, the utility model adopts the following technical solutions:
[0007] The cofferdam combined with steel pipe piles and Larsen steel sheet piles comprises a plurality of Larsen steel sheet pile bodies connected to each other to form an annular structure, sealing devices are arranged at both ends of the Larsen steel sheet pile body, a plurality of clamping and fixing structures are arranged on both sides of the Larsen steel sheet pile body, the bottom end of the clamping and fixing structure is inserted into the foundation, and an adjustment structure is arranged between the top ends of the clamping and fixing structures, the clamping and fixing structures comprise a plurality of inner steel pipe pile bodies arranged inside the Larsen steel sheet pile body and a plurality of outer steel pipe pile bodies arranged outside the Larsen steel sheet pile body, and the plurality of inner steel pipe piles are arranged inside the Larsen steel sheet pile body. The main body and the plurality of outer steel pipe pile bodies are alternately staggered and distributed, the side walls of the inner steel pipe pile body and the outer steel pipe pile body are both in contact with the Larsen steel sheet pile body, the adjustment structure includes a fixing bolt fixedly connected to the top of the inner steel pipe pile body and the outer steel pipe pile body, the adjacent sides of the fixing bolts at the top of the inner steel pipe pile body and the outer steel pipe pile body are fixedly connected with a threaded rod, the adjacent ends of the two threaded rods are sleeved with the same sleeve, the internal threads at both ends of the sleeve are in opposite directions, and the sleeve is screwed to the threaded rod through the internal thread.
[0008] By adopting the above technical scheme, when using, the user first selects a suitable number of Larsen steel sheet pile bodies according to the size of the construction site, and connects multiple Larsen steel sheet pile bodies to form a circular cofferdam structure. Then, the user can plug multiple inner steel pipe pile bodies and outer steel pipe pile bodies that are alternately staggered on the foundation on both sides of the Larsen steel sheet pile body. After installation, the user rotates the casing. Since the internal threads at both ends of the casing are in opposite directions, the two threaded rods can move toward each other along the inner cavity of the casing under the push of the internal threads, thereby pulling the inner steel pipe pile body and the outer steel pipe pile body toward each other to stably clamp the Larsen steel sheet pile body, so that the sealing strip fits tightly in the inner cavity of the card slot, and the connection between the Larsen steel sheet pile bodies is sealed, so as to avoid the problem that the existing cofferdam structure is prone to deformation of the steel sheet pile when the water pressure is large, resulting in a gap between two adjacent steel sheet piles, thereby causing water to penetrate into the cofferdam and affect the construction.
[0009] Optionally, the Larsen steel sheet pile body has a U-shaped structure, and both end sides of the Larsen steel sheet pile body extend outward to form a slot, and adjacent Larsen steel sheet pile bodies are connected to each other through the slot.
[0010] By adopting the above technical solution, multiple Larsen steel sheet pile bodies are set, and the multiple Larsen steel sheet pile bodies are connected by card slots, which makes it convenient for construction personnel to select an appropriate number of Larsen steel sheet pile bodies according to the size of the construction site and splice them to form a cofferdam structure, making it more convenient for users to use.
[0011] Optionally, the sealing device is two sealing strips fixedly connected to the Larsen steel sheet pile body, the cross-section of the sealing strip is a semicircular structure, the sealing strip is embedded in the inner cavity of the slot and fits tightly with the inner wall of the slot.
[0012] By adopting the above technical solution, when two adjacent Larsen steel sheet pile bodies are connected, the sealing strip is embedded in the inner cavity of the slot and fits against the inner wall of the slot. The sealing strip is used to seal the connection between the two adjacent Larsen steel sheet pile bodies, thereby improving the waterproof performance of the overall cofferdam structure.
[0013] Optionally, the inner steel pipe pile body and the outer steel pipe pile body are identical in size and shape, the inner steel pipe pile body is a rectangular columnar structure, the top height of the inner steel pipe pile body is flush with the top height of the Larsen steel sheet pile body, and the length of the bottom of the inner steel pipe pile body inserted into the foundation is not less than two meters.
[0014] By adopting the above technical solution, an inner steel pipe pile body and an outer steel pipe pile body are provided to support and limit the Larsen steel sheet pile body from both sides, and the length of the inner steel pipe pile body buried inside the foundation is set longer, which can greatly improve the supporting performance of the inner steel pipe pile body.
[0015] Optionally, a support plate is fixedly connected to the side wall of the inner steel pipe pile body away from the Larsen steel sheet pile body, and the support plate is in a U-shaped structure. There are multiple support plates, and the multiple support plates are equidistantly distributed along the height direction of the inner steel pipe pile body.
[0016] By adopting the above technical solution, a support plate is provided for supporting, and a plurality of support plates are equidistantly arranged along the height direction of the inner steel pipe pile body, so that users can select a support plate of appropriate height for use according to their own needs.
[0017] Optionally, a transverse springboard and a vertical springboard are provided between the two opposing support plates, the transverse springboard and the vertical springboard are perpendicular to each other, and both ends of the transverse springboard and the vertical springboard are overlapped in the inner cavity of the support plates.
[0018] By adopting the above technical solution, a horizontal springboard and a vertical springboard are set up and overlapped on the support plate, so that construction workers can stand on the horizontal springboard and the vertical springboard to carry out construction, which is convenient for the workers to carry out construction.
[0019] Optionally, grooves are provided at the connection between adjacent sides of the horizontal springboard and the vertical springboard, the depth of the grooves is equal to half the thickness of the horizontal springboard and the vertical springboard, and the horizontal springboard and the vertical springboard are clamped together through the grooves.
[0020] By adopting the above technical solution, the upper surfaces of the horizontal springboard and the vertical springboard are flush after installation, and the formation of bulges on the horizontal springboard is avoided as much as possible, which may easily trip construction workers and cause safety hazards.
[0021] In summary, the beneficial effects of this application are as follows:
[0022] 1. The present application adopts the coordination arrangement between the inner steel pipe pile body, the outer steel pipe pile body, the sealing strip, the threaded rod and the casing. The inner steel pipe pile body and the outer steel pipe pile body are respectively arranged on both sides of the Larsen steel sheet pile body. The adjacent inner steel pipe pile bodies and the top ends of the outer steel pipe piles are fixed by the threaded rod and the casing. The sealing strip is tightly pressed into the inner cavity of the card slot to seal the connection between the Larsen steel sheet pile bodies, so as to avoid the problem that the existing cofferdam structure is prone to deformation of the steel sheet piles when the water pressure is large, resulting in the formation of gaps between two adjacent steel sheet piles, thereby causing water to penetrate into the cofferdam and affect the construction.
[0023] 2. Support plates are provided between the inner steel pipe pile bodies, and a platform formed by the staggered horizontal and vertical springboards is overlapped between the two opposite support plates. Users can stand on the platform during construction, which is not only safer, but also can avoid interference from silt and groundwater, greatly improving construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is an overall top view of this application;
[0025] Figure 2 It is a schematic diagram of the connection structure of the support plate and the horizontal springboard of the present application;
[0026] Figure 3 This is a schematic diagram of the connection structure between the Larsen steel sheet pile body and the sealing strip of the present application;
[0027] Figure 4 It is a schematic diagram of the connection of the adjustment structure of this application.
[0028] Explanation of the reference numerals: 1. Larsen steel sheet pile body; 2. Slot; 3. Sealing strip; 4. Inner steel pipe pile body; 5. Outer steel pipe pile body; 6. Fixing bolt; 7. Threaded rod; 8. Casing; 9. Support plate; 10. Horizontal springboard; 11. Vertical springboard; 12. Groove. DETAILED DESCRIPTION
[0029] The following is combined with Figure 1-4 This application is described in further detail.
[0030] See also Figure 1-3The cofferdam combining steel pipe piles and Larsen steel sheet piles includes a plurality of Larsen steel sheet pile bodies 1 connected to each other to form a ring structure. The Larsen steel sheet pile bodies 1 form a ring structure to block the river water outside, thereby forming a cofferdam.
[0031] Sealing devices are provided at both ends of the Larsen steel sheet pile body 1. The sealing devices are arranged at the connection of adjacent Larsen steel sheet pile bodies 1 to seal the connection of the Larsen steel sheet pile bodies 1 to avoid water leakage at the connection as much as possible.
[0032] Both sides of the Larsen steel sheet pile body 1 are provided with multiple clamping and fixing structures. The bottom ends of the clamping and fixing structures are inserted into the foundation, and adjustment structures are provided between the top ends of the clamping and fixing structures. The adjustment structures are provided to adjust the spacing between the clamping and fixing structures for user convenience.
[0033] The clamping and fixing structure includes a plurality of inner steel pipe pile bodies 4 arranged inside the Larsen steel sheet pile body 1 and a plurality of outer steel pipe pile bodies 5 arranged outside the Larsen steel sheet pile body 1 , and the plurality of inner steel pipe pile bodies 4 and the plurality of outer steel pipe pile bodies 5 are alternately staggered.
[0034] The side walls of the inner steel pipe pile body 4 and the outer steel pipe pile body 5 are both in contact with the Larsen steel sheet pile body 1 , and are used to squeeze two adjacent Larsen steel sheet pile bodies 1 toward each other from both sides, thereby improving the stability of the connection between the adjacent Larsen steel sheet pile bodies 1 .
[0035] The adjustment structure includes a fixing bolt 6 fixedly connected to the top of the inner steel pipe pile body 4 and the outer steel pipe pile body 5. The adjacent sides of the fixing bolts 6 at the top of the inner steel pipe pile body 4 and the outer steel pipe pile body 5 are fixedly connected with threaded rods 7. The adjacent ends of the two threaded rods 7 are sleeved with the same sleeve 8. The internal threads at both ends of the sleeve 8 are in opposite directions. The sleeve 8 is screwed to the threaded rod 7 through the internal threads. When the user rotates the threaded rod 7, due to the opposite directions of the internal threads at both ends of the sleeve 8, the two threaded rods 7 can be moved toward each other along the inner cavity of the sleeve 8 under the pushing action of the internal threads, thereby pulling the inner steel pipe pile body 4 and the outer steel pipe pile body 5 toward each other to stably clamp the Larsen steel sheet pile body 1.
[0036] Reference Figure 3 The Larsen steel sheet pile body 1 is in a U-shaped structure, and both ends of the Larsen steel sheet pile body 1 extend outward to form a slot 2, and adjacent Larsen steel sheet pile bodies 1 are connected by the slot 2. A plurality of Larsen steel sheet pile bodies 1 are provided, and the plurality of Larsen steel sheet pile bodies 1 are connected by the slot 2, so that construction personnel can select a suitable number of Larsen steel sheet pile bodies 1 according to the size of the construction site to form a cofferdam structure, making it more convenient for users to use.
[0037] Reference Figure 1 and Figure 3The sealing device is a sealing strip 3 fixedly connected on both sides of the Larsen steel sheet pile body 1. The cross section of the sealing strip 3 is a semicircular structure. The sealing strip 3 is embedded in the inner cavity of the card slot 2 and fits tightly with the inner wall of the card slot 2. When two adjacent Larsen steel sheet pile bodies 1 are connected, the sealing strip 3 is just embedded in the inner cavity of the card slot 2 and fits with the inner wall of the card slot 2. The connection between the two adjacent Larsen steel sheet pile bodies 1 is sealed by the sealing strip 3, thereby improving the waterproof performance of the overall cofferdam structure.
[0038] Reference Figure 2 The inner steel pipe pile body 4 and the outer steel pipe pile body 5 are of the same size and shape. The inner steel pipe pile body 4 is a rectangular columnar structure. The top height of the inner steel pipe pile body 4 is flush with the top height of the Larsen steel sheet pile body 1. The bottom of the inner steel pipe pile body 4 is inserted into the foundation for a length of not less than two meters. The inner steel pipe pile body 4 and the outer steel pipe pile body 5 are provided to support and limit the Larsen steel sheet pile body 1 from both sides. The inner steel pipe pile body 4 is buried in the foundation for a longer length, which can greatly improve the support performance of the inner steel pipe pile body 4.
[0039] Reference Figure 3 A support plate 9 is fixedly connected to the side wall of the inner steel pipe pile body 4 away from the Larsen steel sheet pile body 1. The support plate 9 is a U-shaped structure. There are multiple support plates 9, and the multiple support plates 9 are equidistantly distributed along the height direction of the inner steel pipe pile body 4. The support plate 9 is set to perform a supporting function. The multiple support plates 9 are equidistantly arranged along the height direction of the inner steel pipe pile body 4, so that users can select a support plate 9 of a suitable height for use according to their own needs.
[0040] Reference Figure 1 and Figure 2 A horizontal springboard 10 and a vertical springboard 11 are arranged between the two opposing support plates 9. The horizontal springboard 10 and the vertical springboard 11 are perpendicular to each other, and both ends of the horizontal springboard 10 and the vertical springboard 11 are overlapped in the inner cavity of the support plate 9. The horizontal springboard 10 and the vertical springboard 11 are arranged and overlapped on the support plate 9, so that construction workers can stand on the horizontal springboard 10 and the vertical springboard 11 to carry out construction, which is convenient for workers to carry out construction.
[0041] Reference Figure 3 A groove 12 is provided at the connection of the adjacent side of the horizontal springboard 10 and the vertical springboard 11. The depth of the groove 12 is equal to half the thickness of the horizontal springboard 10 and the vertical springboard 11. The horizontal springboard 10 and the vertical springboard 11 are connected by the groove 12. The height of the upper surface of the horizontal springboard 10 and the vertical springboard 11 is flush after installation, and the formation of a bulge on the horizontal springboard 10 is avoided as much as possible, which may easily trip the construction workers and cause safety hazards.
[0042] The implementation principle of the present application is as follows: when in use, the user first selects a suitable number of Larsen steel sheet pile bodies 1 according to the size of the construction site, and connects multiple Larsen steel sheet pile bodies 1 to form a circular cofferdam structure. Then, the user can plug multiple inner steel pipe pile bodies 4 and outer steel pipe pile bodies 5 that are alternately staggered and distributed on the foundation on both sides of the Larsen steel sheet pile body 1. After installation, the user rotates the sleeve 8. Since the internal threads at both ends of the sleeve 8 are in opposite directions, the two threaded rods 7 can be moved toward each other along the inner cavity of the sleeve 8 under the pushing action of the internal threads, thereby pulling the inner steel pipe pile body 4 and the outer steel pipe pile body 5 toward each other to stably clamp the Larsen steel sheet pile body 1, so that the sealing strip 3 fits tightly in the inner cavity of the card slot 2, and the connection between the Larsen steel sheet pile bodies 1 is sealed, so as to avoid the existing cofferdam structure as much as possible. When the water flow pressure is large, the steel sheet piles are easily deformed, resulting in a gap between two adjacent steel sheet piles, so that water flows into the cofferdam and affect the construction.
[0043] The above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A cofferdam combining steel pipe piles and Larsen steel sheet piles, comprising a plurality of Larsen steel sheet pile bodies (1) connected to each other to form an annular structure, wherein sealing devices are provided at both ends of the Larsen steel sheet pile body (1), and a plurality of clamping and fixing structures are provided on both sides of the Larsen steel sheet pile body (1), wherein the bottom ends of the clamping and fixing structures are inserted into the inside of the foundation, and adjustment structures are provided between the top ends of the clamping and fixing structures, and wherein: The clamping and fixing structure comprises a plurality of inner steel pipe pile bodies (4) arranged on the inner side of the Larsen steel sheet pile body (1) and a plurality of outer steel pipe pile bodies (5) arranged on the outer side of the Larsen steel sheet pile body (1). The plurality of inner steel pipe pile bodies (4) and the plurality of outer steel pipe pile bodies (5) are alternately staggered and distributed. The side walls of the inner steel pipe pile bodies (4) and the outer steel pipe pile bodies (5) are both in contact with the Larsen steel sheet pile body (1). The adjusting structure comprises a fixing bolt (6) fixedly connected to the top ends of the inner steel pipe pile bodies (4) and the outer steel pipe pile bodies (5). The fixing bolts (6) at the top ends of the inner steel pipe pile bodies (4) and the outer steel pipe pile bodies (5) are both fixedly connected to threaded rods (7). The adjacent ends of the two threaded rods (7) are sleeved with the same sleeve (8). The inner threads at both ends of the sleeve (8) are in opposite directions. The sleeve (8) is screwed to the threaded rod (7) through the inner threads.
2. The cofferdam combining steel pipe piles and Larsen steel sheet piles according to claim 1 is characterized in that: The Larsen steel sheet pile body (1) is in a U-shaped structure, and both end sides of the Larsen steel sheet pile body (1) extend outwards to form a clamping groove (2), and adjacent Larsen steel sheet pile bodies (1) are clamped together via the clamping groove (2).
3. The cofferdam combining steel pipe piles and Larsen steel sheet piles according to claim 2 is characterized in that: The sealing device is two sealing strips (3) fixedly connected to the Larsen steel sheet pile body (1), the cross section of the sealing strip (3) is a semicircular structure, the sealing strip (3) is embedded in the inner cavity of the slot (2) and fits tightly with the inner wall of the slot (2).
4. The cofferdam combined with steel pipe piles and Larsen steel sheet piles according to claim 1 is characterized in that: The inner steel pipe pile body (4) and the outer steel pipe pile body (5) are of the same size and shape. The inner steel pipe pile body (4) is in a rectangular columnar structure. The top height of the inner steel pipe pile body (4) is flush with the top height of the Larsen steel sheet pile body (1). The length of the bottom of the inner steel pipe pile body (4) inserted into the foundation is not less than two meters.
5. The cofferdam combining steel pipe piles and Larsen steel sheet piles according to claim 1 is characterized in that: A support plate (9) is fixedly connected to a side wall of the inner steel pipe pile body (4) away from the Larsen steel sheet pile body (1); the support plate (9) is in a U-shaped structure; there are a plurality of support plates (9), and the plurality of support plates (9) are equidistantly distributed along the height direction of the inner steel pipe pile body (4).
6. The cofferdam combined with steel pipe piles and Larsen steel sheet piles according to claim 5 is characterized in that: A transverse springboard (10) and a vertical springboard (11) are provided between the two opposing support plates (9); the transverse springboard (10) and the vertical springboard (11) are perpendicular to each other, and both ends of the transverse springboard (10) and the vertical springboard (11) are overlapped in the inner cavity of the support plates (9).
7. The cofferdam combined with steel pipe piles and Larsen steel sheet piles according to claim 6 is characterized in that: A groove (12) is provided at the connection between the adjacent sides of the transverse springboard (10) and the vertical springboard (11), the depth of the groove (12) being equal to half the thickness of the transverse springboard (10) and the vertical springboard (11), and the transverse springboard (10) and the vertical springboard (11) are connected to each other via the groove (12).
Citation Information
Cited By
Deep and long steel sheet pile cofferdam structure
CN120739142A